Sei sulla pagina 1di 41

Norms SN

No.
B-1 1.00 Earthwork in excavation in soft soil including hauling disposal of soil upto distance of 30m and lift upto 1.5 m (Rate per 1 Cu.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 0.800 800.00 640.00 640.00
2.00 Cost including 3% for tools and plants 19.20
Sub-total 659.20
15% Contractor Overhead 98.88
Grand Total 758.08
Per Unit Rate
758.08 Rs

H-15 1.00 Flat Brick Soling Works (Rate per 10 Sq.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,000.00 500.00 500.00
unskilled md 1.000 800.00 800.00 800.00
2.00 Material - -
Brick Nos 396.000 14.70 5,821.20 5,821.20
SAND cum 0.710 1,250.00 887.50 887.50
-
Sub-total 8,008.70
15% Contractor Overhead 1,201.31
Grand Total 9,210.01
Per Unit Rate
921.00 Rs
0.0253
Notes: Brick size 230x110x55 so number
of brick for 1 sq m = 396 nos 39.5256917

Plain cement concrete(PCC) in 1:2:4 ratio for foundations and flooring with approved quality of cement,sand and machine
crushed stone aggregate including supply of materials,mixing,laying,curing the work at least 7 days etc all complete as per
D-1 1 approved drawing specification and instruction of site engineer.( Rate Analysis: 1Cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,000.000 1,000.000 1,000.000
Unskilled Labour md 4.000 800.000 3,200.000 3,200.000
2 Material - -
Cement MT 0.320 16,500.000 5,280.000 5,280.000
40mm Aggregate Cum 0.520 1,680.000 873.600 873.600
20mm Aggregate Cum 0.220 1,750.000 385.000 385.000
10mm Aggregate Cum 0.110 1,800.000 198.000 198.000
Sand Cum 0.445 1,800.000 801.000 801.000
Water Ltr 150.000 0.180 27.000 27.000
Sub-total 11,764.600
15% Contractor Overhead 1,764.690
Grand Total 13,529.290
Per Unit Rate
13,529.29 Rs

D-4 1.00 PCC for RCC Works (1:1:2) by Using Mixture including Material.( Rate Analysis: 1Cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,000.00 500.00 500.00
Unskilled md 3.500 800.00 2,800.00 2,800.00
2.00 Material - -
Cement MT 0.610 16,500.00 10,065.00 10,065.00
40mm-aggregrate Cum 0.640 1,680.00 1,075.20 1,075.20
20mm-aggregrate cum 0.210 1,750.00 367.50 367.50
Sand Cum 0.425 1,800.00 765.00 765.00
water ltr 300.000 0.18 54.00 54.00
Diesel ltr 3.000 95.00 285.00 285.00
Petrol ltr 0.100 110.00 11.00 11.00
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 8,160.00 4,896.00 4,896.00
Vibrator hr 0.250 8,160.00 2,040.00 2,040.00
Sub-total 22,858.70
15% Contractor Overhead 3,428.81
Grand Total 26,287.51
Per Unit Rate
26,287.51 Rs

D-9 1.00 Steel Reinforcement bar of fe 500 grade including supplying, straightening, cleaning, cutting, binding & fixing in position with
annealed tying binding wire
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 12.000 1,000.00 12,000.00 12,000.00
Unskilled md 12.000 800.00 9,600.00 9,600.00
2.00 Material - -
MS Bar MT 1.100 80,000.00 88,000.00 88,000.00
Binding Wire Kg 10.000 105.00 1,050.00 1,050.00
Sub-total 110,650.00
15% Contractor Overhead 16,597.50
Grand Total 127,247.50
Per Unit Rate
127,247.50 Rs
E-1 1.00 Ply Formwork for Column (Rate per 10 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 1.574 1,000.00 1,574.00 1,574.00
Unskilled md 2.361 800.00 1,888.80 1,888.80
2.00 Material - -
19mm-ply board sqm 0.693 1,053.45 730.04 730.04
Local Wood cum 0.019 3,200.00 60.80 60.80
Tron Prop Pipe Nos 0.540 1,940.00 1,047.60 1,047.60
Nail kg 2.500 105.00 262.50 262.50
Sub-total 5,563.74
15% Contractor Overhead 834.56
Grand Total 6,398.30
Per Unit Rate
639.83 Rs
E-5 1.00 Ply Formwork for Beam (Rate per 10 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 2.670 1,000.00 2,670.00 2,670.00
Unskilled md 4.000 800.00 3,200.00 3,200.00
2.00 Material - -
19mm-ply board sqm 1.650 1,053.45 1,738.19 1,738.19
Local Wood cum 0.040 3,200.00 128.00 128.00
Tron Prop Pipe Nos 0.400 1,940.00 776.00 776.00
Nail kg 2.500 105.00 262.50 262.50
Sub-total 8,774.69
15% Contractor Overhead 1,316.20
Grand Total 10,090.89
Per Unit Rate
1,009.09 Rs
E-6 1.00 Ply Formwork (Rate per 100 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 17.200 1,000.00 17,200.00 17,200.00
Unskilled md 25.700 800.00 20,560.00 20,560.00
2.00 Material - -
19mm-ply board sqm 16.500 1,053.45 17,381.85 17,381.85
Local Wood cum 0.230 3,200.00 736.00 736.00
Iron Prop Pipe Nos 4.400 1,940.00 8,536.00 8,536.00
Nail kg 25.000 105.00 2,625.00 2,625.00
Sub-total 67,038.85
15% Contractor Overhead 10,055.83
Grand Total 77,094.68
Per Unit Rate
770.95 Rs

Good quality local chimney made Brickwork in 1:4 C/S mortar upto Ground Floor in perfect line level finish including supply
of materials,wetting the bricks,racking the joints and curing the work for at least 7 days all complete as per approved drawing
C-2 1 ,specification and instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 1.500 1,000.000 1,500.000 1,500.000
Unskilled md 2.200 800.000 1,760.000 1,760.000
Unskilled md 0.200 800.000 160.000 160.000
2 Material - -
brick no 520.000 14.700 7,644.000 7,644.000
cement MT 0.100 16,500.000 1,650.000 1,650.000
river sand cum 0.280 1,800.000 504.000 504.000
water lt 130.000 0.180 23.400 23.400
extra material 3%of Labour cost 48.000
Sub-total 13,289.400
15% Contractor Overhead 1,993.410
Grand Total 15,282.810
Per Unit Rate
15,282.81 Rs
Note : Brick size 230x110x55= 520 nos
required for 1 cum

2200 1 Iron Works with Red Oxide paint (Rate Analysis: 1 ton)
DoR S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
Norms
a Labour Cost
Technication 1.000 1,003.000 1,003.000 1,003.000
skilled md 2.000 1,000.000 2,000.000 2,000.000
simiskilled 2.000 750.000 1,500.000 1,500.000
Unskilled md 2.000 800.000 1,600.000 1,600.000
b Material - -
all type iron angle kg 1,100.000 145.000 159,500.000 159,500.000
Paint 5% of cost of material 7,975.000
drill bit, gas electrode 5% 7,975.000
nut bolt,revit 3% 4,785.000
c Equipment
crane hr 1.000 4,598.000 4,598.000 4,598.000
formwork
4 formwork and staging upto 5 m 25% of (a+b+c) 47,734.000
Sub-total 238,670.000
15% Contractor Overhead 35,800.500
Grand Total 274,470.500
Per Unit Rate
274.47 Rs

B-2 1.00 Earth back Filling


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 0.500 800.00 400.00 400.00
2.00 Material - -
Water Ltr 5.000 0.18 0.90 0.90
Sub-total 400.90
15% Contractor Overhead 60.14
Grand Total 461.04
Per Unit Rate
461.04 Rs

Elastocrete cementitious elastomeric water proofing coating 2 components capacity per kg 6 sq.ft for 2 coat (Rate Analysis:
K-7 1 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Material
Elastocrete cementitious elastomeric water
sqm 1.000 559.520 559.520 559.520
proofing material
Sub-total 559.520
15% Contractor Overhead 83.928
Grand Total 643.448
Per Unit Rate
643.45 Rs

J-5 b,c 1 2 coats of ready made enamel paint of approved colour over properly sanded surface all complete (Rate Analysis: 100 sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 9.000 1,000.000 9,000.000 9,000.000
Unskilled md 5.000 800.000 4,000.000 4,000.000
2 Material - -
Enamel Paint lt 16.000 550.000 8,800.000 8,800.000
Sub-total 21,800.000
15% Contractor Overhead 3,270.000
Grand Total 25,070.000
Per Unit Rate
250.70 Rs

Supplying and applying 4.5X20mm steel Grill with 12X12 solid core square rod all complete as per approved drawing
M-3 1 ,specification and instruction of site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 0.700 1,000.000 700.000 700.000
Unskilled Labour md 0.600 800.000 480.000 480.000
2 Material - -
Iron works for Grill kg 28.240 155.000 4,377.200 4,377.200
Iron Rod kg 215.000 81.000 17,415.000 17,415.000
Sub-total 22,972.200
15% Contractor Overhead 3,445.830
Grand Total 26,418.030
Per Unit Rate
2,641.80 Rs

Supplying and fitting 0.5mm CGI colour sheet for Roof all complete as per approved drawing ,specification and instruction of
F-1 1 site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.100 1,000.000 1,100.000 1,100.000
Unskilled Labour md 1.250 800.000 1,000.000 1,000.000
2 Material - -
CGI Sheet (0.5 mm (24 Guage)) sqm 12.000 511.700 6,140.400 6,140.400
8mm nut bolt no 30.000 41.667 1,250.000 1,250.000
J-hook no 25.000 11.790 294.750 294.750
Bitumen washer no 55.000 1.000 55.000 55.000
Sub-total 9,840.150
15% Contractor Overhead 1,476.023
Grand Total 11,316.173
Per Unit Rate
1,131.62 Rs

Providing and fixing Single Panel Swing Door of aluminium section in naturally anodized or black anodized/powder coated
color Section size (102*45*1.5 mm) fitted with 5 mm clear glass or 9 mm both side laminated board (excluding the cost of
1 handle).(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

2 Material - -
Aluminium swing door sqm 1.000 8,995.360 8,995.360 8,995.360
Sub-total 8,995.360
15% Contractor Overhead 1,349.304
Grand Total 10,344.664
Per Unit Rate
10,344.66 Rs

Providing and fixing 2 or 3 Panel Sliding window of aluminium section in naturally anodized or black anodized/powder coated
color, Section size (87*56*1.2 mm) fitted with 5 mm clear glass without fly mesh shutter (Window size 6'*5' or average area 30
1 Sq. feet per window).(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

2 Material - -

Aluminium sliding window without ventilator sqm 1.000 6,875.120 6,875.120 6,875.120

Sub-total 6,875.120
15% Contractor Overhead 1,031.268
Grand Total 7,906.388
Per Unit Rate
7,906.39 Rs

Plain cement Concrete (PCC)(38mm) in 1:2:4ratio for foundations and flooring with approved quality of cement, sand and
machine crushed stone aggregate including supply of materials,mixing, laying, curing the work at least 7 days etc all
H-1 1 complete as per approved drawing, Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.250 1,000.000 1,250.000 1,250.000
Unskilled md 2.000 800.000 1,600.000 1,600.000
2 Material - -
cement sqm 0.130 16,500.000 2,145.000 2,145.000
sand cum 0.180 1,800.000 324.000 324.000
12mm aggregate cum 0.360 1,800.000 648.000 648.000
Sub-total 5,967.000
15% Contractor Overhead 895.050
Grand Total 6,862.050
Per Unit Rate
686.21 Rs

3mm punning in 1:1 ratio for flooring with approved quality of cement, sand including supply of materials,mixing, laying,
curing the work at least 7 days etc all complete as per approved drawing, Specification and instruction of site engineer..(Rate
H-20 1 Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,000.000 1,000.000 1,000.000
Unskilled md 1.000 800.000 800.000 800.000
2 Material - -
cement MT 0.053 16,500.000 877.800 877.800 0.0532
Sub-total 2,677.800
15% Contractor Overhead 401.670
Grand Total 3,079.470
Per Unit Rate
307.95 Rs

Supplying and SolingStone in proper line and level with sand filling all complete as per approved drawing, Specification and
C-10 1 instruction of site engineer.(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Unskilled md 1.500 800.000 1,200.000 1,200.000
2 Material - -
Block stone cum 1.000 2,224.530 2,224.530 2,224.530
Bond stone cum 0.200 2,224.530 444.906 444.906
Sub-total 3,869.436
15% Contractor Overhead 580.415
Grand Total 4,449.851
Per Unit Rate
4,449.85 Rs

Stone Masonary Work in 1:6 C/S mortar in perfect line level finish including supply of materials, wetting the bricks, racking
the joints and curing the work for at least 7 days all complete as per approved drawing, Specification and instruction of site
C-6 1 engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Skilled md 1.500 1,000.000 1,500.000 1,500.000
Unskilled md 5.000 800.000 4,000.000 4,000.000
2 Material - -
cement MT 0.106 16,500.000 1,749.000 1,749.000
sand cum 0.470 1,800.000 846.000 846.000
water ltr 70.000 0.180 12.600 12.600
Block stone cum 1.000 2,224.530 2,224.530 2,224.530
Bond stone cum 0.100 2,224.530 222.453 222.453
Sub-total 10,554.583
15% Contractor Overhead 1,583.187
Grand Total 12,137.770
Per Unit Rate
12,137.77 Rs

Good quality local chimney made Brickwork in 1:4 C/S mortar in superstructure in perfect line level finish including supply of
materials,wetting the bricks,racking the joints and curing the work for at least 7 days all complete as per approved drawing
C-2 1 ,specification and instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.500 1,000.000 1,500.000 1,500.000
Unskilled md 2.200 800.000 1,760.000 1,760.000
Unskilled md 0.700 800.000 560.000 560.000
2 Material - -
brick no 520.000 14.700 7,644.000 7,644.000
cement MT 0.100 16,500.000 1,650.000 1,650.000
river sand cum 0.280 1,800.000 504.000 504.000
water lt 130.000 0.180 23.400 23.400
extra material 3%of Labour cost 168.000
Sub-total 13,641.400
15% Contractor Overhead 2,046.210
Grand Total 15,687.610
Per Unit Rate
15,687.61 Rs

Well seasoned salwood chaukhats for openable doo with good finish of approved quality incuding supply of materials, fixing
in postion with necessary M.S. hold fasts all complet as per approved drawing, Specification and instruction of site engineer..
G-1 1 (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 34.000 1,000.000 34,000.000 34,000.000
Unskilled Labour md 3.400 800.000 2,720.000 2,720.000
2 Material - -
Agrakh cum 1.100 220,687.500 242,756.250 242,756.250
Hold fast no 92.000 18.000 1,656.000 1,656.000
( Steel Screw nail 35mm) no 184.000 4.110 756.240 756.240
Sub-total 281,888.490
15% Contractor Overhead 42,283.274
Grand Total 324,171.764
Per Unit Rate
324,171.76 Rs

Making and fitting / fixing Plywood Panel door shutter of 38 x 100 mm size sal wood frame with 8 mm thick commercial ply on
midle and 4mm thick teak ply on both sides including supply of materials, all necessary hardware fitting all complete as per
G-9 1 approved drawing, Specification and instruction of site engineer.(Rate Analysis: 2.245sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 9.000 1,000.000 9,000.000 9,000.000
Unskilled Labour md 0.900 800.000 720.000 720.000
2 Material - -
sal wood cum 0.035 220,687.500 7,635.788 7,635.788
8mm commercial ply sqm 1.899 860.800 1,634.659 1,634.659
4mm teak ply sqm 3.798 645.600 2,451.989 2,451.989
listing rm 14.868 52.480 780.273 780.273
gum ls 60.000 60.000
100mm kabja no 3.000 36.000 108.000 108.000
150mm chaskeni no 2.000 73.000 -
mortis lock(normal) no 1.000 625.000 625.000 625.000
nail ls 45.000 45.000
Sub-total 23,060.708
15% Contractor Overhead 3,459.106
Grand Total 26,519.814
Per Unit Rate
11,812.83 Rs

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio on wall of good finish including supply of materials,
racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing, Specification
I-1 1 and instruction of site engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,000.000 12,000.000 12,000.000
Unskilled Labour md 16.000 800.000 12,800.000 12,800.000
2 Material - -
Cement MT 0.538 16,500.000 8,877.000 8,877.000
sand cum 1.460 1,800.000 2,628.000 2,628.000
Sub-total 36,305.000
15% Contractor Overhead 5,445.750
Grand Total 41,750.750
Per Unit Rate
417.51 Rs

Supplying & applying Cement putty on plastered surface all complete as per approved drawing, Specification and instruction
I-17 1 of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,000.000 1,000.000 1,000.000
Unskilled Labour md 1.000 800.000 800.000 800.000
2 Material - -
white putting kg 10.640 60.000 638.400 638.400
Sub-total 2,438.400
15% Contractor Overhead 365.760
Grand Total 2,804.160
Per Unit Rate
280.42 Rs

Supplying & applying 2 coats Emulsion painting in Internal Room of approved colour with one coat of primer Painting over
porperly cleaned surface at outside of building all complete as per approved drawing, Specification and instruction of site
J-5 1 engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,000.000 12,000.000 12,000.000
Unskilled Labour md 8.000 800.000 6,400.000 6,400.000
2 Material - -
Astar ltr 8.100 300.000 2,430.000 2,430.000
emulsion paint ltr 16.000 600.000 9,600.000 9,600.000
Sub-total 30,430.000
15% Contractor Overhead 4,564.500
Grand Total 34,994.500
Per Unit Rate
349.95 Rs

Supplying & applying 2 coats of weather paint at outside of Building of approved colour with one coat of primer Painting over
porperly cleaned surface at outside of building all complete as per approved drawing, Specification and instruction of site
J-26 1 engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 5.800 1,000.000 5,800.000 5,800.000
Unskilled Labour md 5.800 800.000 4,640.000 4,640.000
2 Material - -
Astar ltr 8.000 300.000 2,400.000 2,400.000
weathercoat ltr 16.000 612.000 9,792.000 9,792.000
Sub-total 22,632.000
15% Contractor Overhead 3,394.800
Grand Total 26,026.800
Per Unit Rate
260.27 Rs

supplying & Laying Supplying & laying Porcelain Non Glazed tile (1:4) on Toilet fixing in proper shape & size all complete as
H-6 1 per approved drawing, Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 13.000 1,000.000 13,000.000 13,000.000
Unskilled Labour md 4.500 800.000 3,600.000 3,600.000
2 Material - -
Cement MT 0.056 16,500.000 924.000 924.000
sand cum 0.152 1,800.000 273.600 273.600
white cement kg 3.228 60.000 193.680 193.680
porcelain non glazed tile sqm 11.000 798.400 8,782.400 8,782.400
Sub-total 26,773.680
15% Contractor Overhead 4,016.052
Grand Total 30,789.732
Per Unit Rate
3,078.97 Rs

Sand filling including supply of filling materials, watering, ramming etc. all complete as per approved drawing, Specification
B-3 1 and instruction of site engineer.(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Unskilled md 0.700 800.000 560.000 560.000
2 Material - -
sand cum 1.100 1,800.000 1,980.000 1,980.000
water ltr 5.000 0.180 0.900 0.900
Sub-total 2,540.900
15% Contractor Overhead 381.135
Grand Total 2,922.035
Per Unit Rate
2,922.04 Rs

D-4 1.00 PCC for RCC Works M25 (1:1:2) by Using Mixture including Material

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,000.00 500.00 500.00
Unskilled md 3.500 800.00 2,800.00 2,800.00
2.00 Material - -
Cement MT 0.610 16,500.00 10,065.00 10,065.00
40mm-aggregrate Cum 0.640 1,680.00 1,075.20 1,075.20
20mm-aggregrate cum 0.210 1,750.00 367.50 367.50
Sand Cum 0.425 1,800.00 765.00 765.00
water ltr 300.000 0.18 54.00 54.00
Diesel ltr 3.000 95.00 285.00 285.00
Petrol ltr 0.100 110.00 11.00 11.00
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 8,160.00 4,896.00 4,896.00
Vibrator hr 0.250 8,160.00 2,040.00 2,040.00
Sub-total 22,858.70
15% Contractor Overhead 3,428.81
Grand Total 26,287.51
Per Unit Rate
26,287.51 Rs
C-2 b 1.00 Brickworks (1:41) C/S motar
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 1.500 1,000.00 1,500.00 1,500.00
Unskilled md 2.500 800.00 2,000.00 2,000.00
2.00 Material - -
Brick Nos 520.000 14.70 7,644.00 7,644.00
Cement Mt 0.100 16,500.00 1,650.00 1,650.00
Sand cum 0.280 1,800.00 504.00 504.00
Water ltr 130.000 0.18 23.40 23.40
Sub-total 13,321.40
15% Contractor Overhead 1,998.21
Grand Total 15,319.61
Per Unit Rate
15,319.61 Rs
Note : Brick size 230x110x55= 520 nos
required for 1 cum

Supplying and Laying of 12.5mm thick cement sand plaster in (1:3) ratio on wall of good finish including supply of materials,
racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing, Specification
I-1 1 and instruction of site engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,000.000 12,000.000 12,000.000
Unskilled Labour md 16.000 800.000 12,800.000 12,800.000
2 Material - -
Cement MT 0.625 16,500.000 10,312.500 10,312.500
sand cum 1.280 1,800.000 2,304.000 2,304.000
Sub-total 37,416.500
15% Contractor Overhead 5,612.475
Grand Total 43,028.975
Per Unit Rate
430.29 Rs

I-1 1 16mm Marble Finishing


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 2.000 1,000.000 2,000.000 2,000.000
Unskilled Labour md 8.000 800.000 6,400.000 6,400.000
2 Material - -
Cement MT 0.130 16,500.000 2,145.000 2,145.000
sand cum 0.183 1,800.000 329.400 329.400
16mm marbel cum 11.000 1,883.000 20,713.000 20,713.000
Oxalic Acid kg 0.370 118.000 43.660 43.660
Mainn polish kg 0.118 345.000 40.710 40.710
Tarpentain lt 0.538 208.000 111.904 111.904
Carbondam stone 120.000 120.000
-
3 Marble polish manpower md 13.500 700.000 9,450.000 9,450.000
Sub-total 41,353.674
15% Contractor Overhead 6,203.051
Grand Total 47,556.725
Per Unit Rate
4,755.67 Rs

Providing and fixing Structural Glazing of aluminum section in natural or color anodized/powder coated color Section size
(60x75+13x1.6 mm) fitted with 5 mm color glass .
1 (average panel area 6.00 Sq.ft.)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Structure Glazing cum 1.000 6,843.360 6,843.360 6,843.360


Sub-total 6,843.360
15% Contractor Overhead 1,026.504
Grand Total 7,869.864
Per Unit Rate
7,869.86 Rs

B-1 1 Earthwork in excavation from 0.8cum capacity Hydraulic Excavator


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Diesel ltr 0.125 95.000 11.856 11.856


Excavator 0.8 cum capacity hr 0.010 3,150.000 32.760 32.760

Sub-total 44.616
15% Contractor Overhead 6.692
Grand Total 51.308
Per Unit Rate
51.31 Rs

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio on ceiling of good finish including supply of
materials, racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing,
Specification and instruction of site engineer.(Rate Analysis: 100sqm)
I-1 1
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 12.000 1,000.000 12,000.000 12,000.000 20
Unskilled md 20.000 800.000 16,000.000 16,000.000
2 Material - -
sand cum 1.460 1,800.000 2,628.000 2,628.000
cement MT 0.538 16,500.000 8,877.000 8,877.000
Sub-total 39,505.000
15% Contractor Overhead 5,925.750
Grand Total 45,430.750
Per Unit Rate
454.31 Rs

A-4 1 Surface dressing and filling hole (Rate Analysis: 1sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled md 0.010 800.000 8.000 8.000
Sub-total 8.000
15% Contractor Overhead 1.200
Grand Total 9.200
Per Unit Rate
9.20 Rs

Filling with 15-150mm broken brick all complete as per approved drawing, Specification and instruction of site engineer.(Rate
H-19 1 Analysis: 10cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 10.000 1,000.000 10,000.000 10,000.000
2 Material - -
broken brick cum 11.000 6,000.000 66,000.000 66,000.000
Sub-total 76,000.000
15% Contractor Overhead 11,400.000
Grand Total 87,400.000
Per Unit Rate
8,740.00 Rs

Supplying & applying spiral steel ladder 4'-6"dia black pipe all complete as per approved drawing, Specification and
M-5 1 instruction of site engineer.
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
spiral staircase rm 1.000 10,004.000 10,004.000 10,004.000
Sub-total 10,004.000
15% Contractor Overhead 1,500.600
Grand Total 11,504.600
Per Unit Rate
11,504.60 Rs

Supplying & applying iron benches all complete as per approved drawing, Specification and instruction of site engineer.
(Rate Analysis: 1no)
Level Qty Unit Rate Amount Total Amount Remarks
labour cost for iron works
Skilled 0.35 Md 1000.00 350.00 350.00
Unskilled 0.45 Md 800.00 360.00 360.00
Material
iron (40x40x2.6) 49.932 Kg 70.00 3495.24 3495.24
12mm iron strips 0.509 Kg 70.00 35.61 35.61
Paints 0.25 lit 550.00 137.50 137.50
Sub Total (M) 4378.35
15% Contractor Overhead 656.752
Grand Total 5,035.100
Per Unit Rate
5,035.10 Rs

supplying & Laying 16mm marble in 12.5mm 1:3 cement mortar in proper shape & size all complete as per approved
H-35 1 drawing, Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 14.000 1,000.000 14,000.000 14,000.000
Unskilled Labour md 12.000 800.000 9,600.000 9,600.000
2 Material - -
Cement MT 0.063 16,500.000 1,039.500 1,039.500
sand cum 0.128 1,800.000 230.400 230.400
main polish kg 0.118 450.000 53.100 53.100
turpentile lt 0.538 150.000 80.700 80.700
oxalic acid kg 0.370 280.000 103.600 103.600
16mm marble sqm 11.000 3,881.120 42,692.320 42,692.320
carborundum ls 120.000 120.000
Sub-total 67,919.620
15% Contractor Overhead 10,187.943
Grand Total 78,107.563
Per Unit Rate
7,810.76 Rs

Plain cement concrete(PCC) in 1:3:6 ratio for foundations and flooring with approved quality of cement,sand and machine
crushed stone aggregate including supply of materials,mixing,laying,curing the work at least 7 days etc all complete as per
D-1 1 approved drawing specification and instruction of site engineer.( Rate Analysis: 1Cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,000.000 1,000.000 1,000.000
Unskilled Labour md 4.000 800.000 3,200.000 3,200.000
2 Material - -
Cement MT 0.220 16,500.000 3,630.000 3,630.000
40mm Aggregate Cum 0.650 1,680.000 1,092.000 1,092.000
20mm Aggregate Cum 0.240 1,750.000 420.000 420.000
Sand Cum 0.470 1,800.000 846.000 846.000
Water Ltr 120.000 0.180 21.600 21.600
Sub-total 10,209.600
15% Contractor Overhead 1,531.440
Grand Total 11,741.040
Per Unit Rate
11,741.04 Rs
D-4 1.00 PCC for RCC Works (1:1.5:3) by Using Mixture including Material.( Rate Analysis: 1Cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,000.00 500.00 500.00
Unskilled md 3.500 800.00 2,800.00 2,800.00
2.00 Material - -
Cement MT 0.400 16,500.00 6,600.00 6,600.00
40mm-aggregrate Cum 0.570 1,680.00 957.60 957.60
20mm-aggregrate cum 0.290 1,750.00 507.50 507.50
Sand Cum 0.425 1,800.00 765.00 765.00
water ltr 200.000 0.18 36.00 36.00
Diesel ltr 3.000 95.00 285.00 285.00
Petrol ltr 0.100 110.00 11.00 11.00
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 8,160.00 4,896.00 4,896.00
Vibrator hr 0.250 8,160.00 2,040.00 2,040.00
Sub-total 19,398.10
15% Contractor Overhead 2,909.72
Grand Total 22,307.82
Per Unit Rate
22,307.82 Rs

Providing and fixing Structural Glazing of aluminum section in natural or color anodized/powder coated color Section size
(60x50+13x1.3 mm) fitted with 5 mm color glass. (average panel area 6.00 Sq.ft.) all complete as per approved drawing,
G-21 1 Specification and instruction of site engineer.( Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Material
structural glazing sqm 1.000 5,896.480 5,896.480 5,896.480
Sub-total 5,896.480
15% Contractor Overhead 884.472
Grand Total 6,780.952
Per Unit Rate
6,780.95 Rs
Providing and fixing Aluminium partition with 5 mm thick glass and 9 mm thick laminated board of section (101 x45x1.1) all
1 complete as per approved drawing, Specification and instruction of site engineer.( Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Material
aluminium partition sqm 1.000 4,745.160 4,745.160 4,745.160
Sub-total 4,745.160
15% Contractor Overhead 711.774
Grand Total 5,456.934
Per Unit Rate
5,456.93 Rs

Supplying & applying Panipatti on plastered surface all complete as per approved drawing, Specification and instruction of
I-15 1 site engineer.( Rate Analysis: 1 rm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 0.025 1,000.000 25.000 25.000
Unskilled Labour md 0.010 800.000 8.000 8.000
2 Material - -
Cement MT 0.007 16,500.000 115.500 115.500
sand cum 0.004 1,800.000 7.200 7.200
waterproofing lt 0.100 275.000 27.500 27.500
Sub-total 183.200
15% Contractor Overhead 27.480
Grand Total 210.680
Per Unit Rate
210.68 Rs

sallo planks with good finish of approved quality incuding supply of materials, fixing in postion with necessary M.S. hold
1 fasts all complet as per approved drawing, Specification and instruction of site engineer..(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 34.000 1,000.000 34,000.000 34,000.000
Unskilled Labour md 3.400 800.000 2,720.000 2,720.000
2 Material - -
local wood cum 1.100 3,200.000 3,520.000 3,520.000
Hold fast no 92.000 18.000 1,656.000 1,656.000
( Steel Screw nail 35mm) no 184.000 4.110 756.240 756.240
Sub-total 42,652.240
15% Contractor Overhead 6,397.836
Grand Total 49,050.076
Per Unit Rate
49,050.08 Rs

Supply and installation of 500 Gauge plastic sheet for damp proofing all complete work as per approved drawing
K-4 1 ,specification and instruction of site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 0.600 1,000.000 600.000 600.000
Unskilled Labour md 0.600 800.000 480.000 480.000
2 Material - -
polythene sheet 500 gauge sqm 11.000 31.000 341.000 341.000
Sub-total 1,421.000
15% Contractor Overhead 213.150
Grand Total 1,634.150
Per Unit Rate
163.42 Rs

Supplying and applying 4.5X20mm steel Grill with 12X12 solid core square rod all complete as per approved drawing
M-3 1 ,specification and instruction of site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 0.700 1,000.000 700.000 700.000
Unskilled Labour md 0.600 800.000 480.000 480.000
2 Material - -
Iron works for Grill kg 28.240 155.000 4,377.200 4,377.200
Iron Rod kg 215.000 70.000 15,050.000 15,050.000
Sub-total 20,607.200
15% Contractor Overhead 3,091.080
Grand Total 23,698.280
Per Unit Rate
2,369.83 Rs

Supplying and applying 100mm PVC pipe on floor for Ventilation all complete as per approved drawing ,specification and
1 instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 0.17 1,000.000 170.000 170.000
Unskilled Labour md 0.20 800.000 160.000 160.000
2 Material
110 mm dia. PVC pipe 6 kg/cm2. rm 1.000 452.000
Jointing material setc. ls 25.000 25.000
Sub-total 355.000
15% Contractor Overhead 53.250
Grand Total 408.250
Per Unit Rate
408.25 Rs

Cement base Prefabricated shera, thai, gypsum, everest solid wall panel non asbestos including 1.1 mm thick GI channel
(50x25x20) mm with necessary accessories and fitting charge in Partition wall all (75mm thick ) complete as per approved
1 drawing, Specification and instruction of site engineer.
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Material - -
Prefab panel for partition wall sqm 1.000 3,148.740 3,148.740 3,148.740
Sub-total 3,148.740
15% Contractor Overhead 472.311
Grand Total 3,621.051
Per Unit Rate
3,621.05 Rs
Spplying & applying 40mm thk vetrified tile all complete as per approved drawing, Specification and instruction of site
H-30 1 engineer.(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.3 1,000.000 1,300.000 1,300.000
Unskillled md 0.45 800.000 360.000 360.000
2 Material - -
cement Mt 0.015 16,500.000 247.500 247.500
sand cum 0.050 1,800.000 90.000 90.000
vetrified clay sqm 1.100 1,000.680 1,100.748 1,100.748
Sub-total 3,098.248
15% Contractor Overhead 464.737
Grand Total 3,562.985
Per Unit Rate
3,562.99 Rs

for staircase:Supplying & applying 38 mm dia stainless steel handrail pipe with 38mm dia stainless steel vertical post at 2m
interval with two layers of 25mm dia stainless steel member in between handrail and floor all complete as per approved
M-15 1 drawing, Specification and instruction of site engineer.(Rate Analysis: 9.15sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 7.78 1,000.000 7,780.000 7,780.000
Unskillled md 11.35 800.000 9,080.000 9,080.000
2 Material - -
38mm steel pipe m 15.490 549.450 8,510.981 8,510.981
25mm steel pipe m 20.000 243.000 4,860.000 4,860.000
gas welding 500.000 500.000
Sub-total 30,730.981
15% Contractor Overhead 4,609.647
Grand Total 35,340.628
Per Unit Rate
3,862.36 Rs
Norms Page no 52-53

Norms Page no 97
Norms Page no 66-75

Norms Page no 75
Norms Page no 75-78
Norms Page no 75
17.1

0.00050868
Norms Page no 66-75

Norms Page no 75
DISTRICT RATE
SN Item Name District Rate UNIT Remarks
A Labour
1 Skilled 1,000.00 man/day
2 semi-Skilled 915.00 man/day
3 Unskilled 800.00 man/day
4 Technician 830.00 man/day
B Material
1 Brick 14.70 no
2 Sand 1,800.00 cum
2' sand for soling 1,250.00 cum
3 Cement 16,500.00 MT
4 40 mm Aggregate 1680 cum
5 20 mm Aggregate 1750 cum
6 10 mm Aggregate 1800 cum
7 Water 0.18 lt
8 TMT Rod 80,000.00 MT
9 Gi Binding Wire 105.00 KG
10 19mm Ply Board 1053.4455 sqm
11 12 mm Ply board 698.6007 sqm
12 Local Wood 3,200.00 cum sthaniya sallo
13 Iron Bolt for Formworks 250.00 KG
14 Nails 105.00 KG

15 Iron Prop Pipe 1,940.00 no per kg=Rs 88 (5.03


kg/m)
16 All Type Iron Angle 145.00 KG
17 Red Oxide Paint 390.00 LT
Elastocrete cementitious
18 elastomeric water proofing 559.52 sqm
material
19 Enamel Paint 550.00 lt
20 Astar 300.00 lt
21 Iron works for Grill 155.00 KG
22 iron square pipe 70.00 KG
23 Iron Rod 81.00 KG
CGI Sheet (0.5 mm (24
24 511.70 SQM
Guage))
25 8mm nut Bolt 250.00 KG
26 8mm nut Bolt 41.67 no 1kg=6no
27 J hook 165.06 KG
28 J hook 11.79 NO 1kg=14no
29 Bitumen Washer 1.00 NO
30 ( Steel Screw nail 35mm) 4.11 no

31 Aluminium door swing type 8,995.36 sqm

Aluminium sliding window


32 6,875.12 sqm 6875.118
without ventilator

33 Block stone 2,224.53 sqm


34 Bond stone 2,224.53 sqm
35 Agrakh 220,687.50 cum
36 Hold fast 18.00 no
37 8mm commercial ply 860.8 sqm
38 4mm teak ply 645.60 sqm
39 listing 52.48 rm
40 100mm kabja 36.00 no
41 150mm chaskeni 73.00 no
42 mortis lock(normal) 625.00 no
43 emulsion paint 600.00 ltr
44 weathercoat 612.00 ltr
45 porcelain non glazed tile 798.40 sqm
46 white putting 60.00 kg
47 diesel 95.00 lt
48 petrol 110.00 lt
49 vibrator 8,160.00 per day
50 mixer 8,160.00 per day
51 broken brick 6,000.00 cum
52 main polish 450.00 kg
53 turpentile 150.00 lt
54 oxalic acid 280.00 kg
55 waterproofing 275.00 lt
56 16mm marble 3,881.12 sqm
57 25mm steel pipe 243 m
58 38mm steel pipe 549.45 m

59 collapsable gate inclusive


fitting 4,435.50 sqm
60 iron gate 16 gauge inclusive
fitting 6,994.00 sqm
61 10 SWGG chain link 2"x2''
mesh size 517.00 sqm
62 spiral staircase 10,004.00 no
63
polythene sheet 500 gauge 31.00 sqm
64 pvc pipe 110mm dia 452.00 sqm
65 prefab panel 3,148.74 sqm
66 vetrified clay 1,000.68 sqm
Sn Description Rate
Earthwork in excavation in medium soil including hauling disposal of soil
1.00 upto distance of 30m and lift upto 1.5 m
758.08
supplying and soling local flat brick in proper line and level with sand filling
2.00 all complete as per approved drawing,specification and instruction of site
engineer.
921.00
Plain cement concrete(PCC) in 1:2:4 ratio for foundations and flooring
with approved quality of cement,sand and machine crushed stone
3.00 aggregate including supply of materials,mixing,laying,curing the work at
least 7 days etc all complete as per approved drawing specification and
instruction of site engineer.
13,529.29
Plain cement concrete(PCC) in 1:3:6 ratio for foundations and flooring
with approved quality of cement,sand and machine crushed stone
4.00 aggregate including supply of materials,mixing,laying,curing the work at 11,741.04
least 7 days etc all complete as per approved drawing specification and
instruction of site engineer.

Plain Cement Concrete(PCC) for RCC works M25 (1:1:2) for


slab/lintels/columns/beams with approved quality of cement,sand and
5.00 machine crushed stone aggregate including supply of
materials,mixing,laying,curing the work at least 7 days etc all complete as
per approved drawing specification and instruction of site engineer.
26,287.51
Plain Cement Concrete(PCC) for RCC works M20 (1:1.5:3) for
slab/lintels/columns/beams with approved quality of cement,sand and
6.00 machine crushed stone aggregate including supply of
materials,mixing,laying,curing the work at least 7 days etc all complete as
per approved drawing specification and instruction of site engineer.
22,307.82

TMT steel reinforcement bar of Fe 500 grade including


supplying,straightening,cleaning,cutting,binding and fixing in position with
7.00 annealed tying binding wire all complete as per approved drawing
specification and instruction of site engineer
127,247.50
Formwork,for Column with 19mm thick waterproof ply board and steel
post for all works necessary propping,scaffolding,staging,supporting
8.00 inclusive of wedging and cutting holes for utilization till the support if fully
unyielding nett all complete as per approved drawing ,specification and
instruction of site engineer. 639.83
Formwork,for Beam with 19mm thick waterproof ply board and steel post
for all works necessary propping,scaffolding,staging,supporting inclusive
9.00 of wedging and cutting holes for utilization till the support if fully unyielding
nett all complete as per approved drawing ,specification and instruction of
site engineer. 1,009.09
Formwork,for Slab with 15mm thick waterproof ply board and steel post
for all works necessary propping,scaffolding,staging,supporting inclusive
10.00 of wedging and cutting holes for utilization till the support if fully unyielding
nett all complete as per approved drawing ,specification and instruction of
site engineer. 770.95
Good quality local chimney made Brickwork in 1:4 C/S mortar upto
Ground Floor in perfect line level finish including supply of
11.00 materials,wetting the bricks,racking the joints and curing the work for at
least 7 days all complete as per approved drawing ,specification and
instruction of site engineer. 15,282.81
Good quality local chimney made Brickwork in 1:4 C/S mortar in
Superstructure in perfect line level finish including supply of materails,
12.00 wetting the bricks, racking the joints and curing the work for at least 7
days all complete as per approved drawing, Specification and instruction
of site engineer. 15,687.61

Supplying and fitting of Iron Works with Red Oxide paint as per approved
13.00 drawing ,specification and instruction of site engineer.
274.47

Earth filling of Excavated surface in 150 mm thick layer watering ,ramming


14.00 including supply of filling materials within 10m distance all complete as
per approved drawing ,specification and instruction of site engineer.
461.04
Elastocrete cementitious elastomeric water proofing coating 2
components capacity per kg 6 sq.ft for 2 coat including supplying and
15.00 applying all complete work as per approved drawing ,specification and
instruction of site engineer. 643.45

Supplying and applying 2 coats of ready made enamel paint of approved


colour over 1 coat of primer Painting over properly sanded surface all
16.00 complete as per approved drawing ,specification and instruction of site
engineer.
250.70
Supplying and applying 4.5X20mm steel Grill with 12X12 solid core
17.00 square rod all complete as per approved drawing ,specification and
instruction of site engineer.
2,641.80

Supplying and fitting 0.5mm CGI colour sheet for Roof all complete as per
18.00 approved drawing ,specification and instruction of site engineer.
1,131.62
Providing and fixing Single Panel Swing Door of aluminium section in
naturally anodized or black anodized/powder coated color Section size
19.00 (102*45*1.5 mm) fitted with 5 mm clear glass or 9 mm both side laminated
board (excluding the cost of handle). 10,344.66

Providing and fixing 2 or 3 Panel Sliding window of aluminium section in


naturally anodized or black anodized/powder coated color, Section size
20.00 (87*56*1.2 mm) fitted with 5 mm clear glass without fly mesh shutter
(Window size 6'*5' or average area 30 Sq. feet per window).
7,906.39
Plain cement Concrete (PCC)(38mm) in 1:2:4ratio for foundations and
flooring with approved quality of cement, sand and machine crushed
21.00 stone aggregate including supply of materials,mixing, laying, curing the
work at least 7 days etc all complete as per approved drawing,
Specification and instruction of site engineer. 686.21

3mm punning in 1:1 ratio for flooring with approved quality of cement,
sand including supply of materials,mixing, laying, curing the work at least
22.00 7 days etc all complete as per approved drawing, Specification and
instruction of site engineer.
307.95
Supplying and SolingStone in proper line and level with sand filling all
23.00 complete as per approved drawing, Specification and instruction of site
engineer. 4,449.85

Stone Masonary Work in 1:6 C/S mortar in perfect line level finish
including supply of materials, wetting the bricks, racking the joints and
24.00 curing the work for at least 7 days all complete as per approved drawing,
Specification and instruction of site engineer.
12,137.77
Well seasoned salwood chaukhats for openable doo with good finish of
approved quality incuding supply of materials, fixing in postion with
25.00 necessary M.S. hold fasts all complet as per approved drawing,
Specification and instruction of site engineer.
324,171.76
Making and fitting / fixing Plywood Panel door shutter of 38 x 100 mm size
sal wood frame with 8 mm thick commercial ply on midle and 4mm thick
26.00 teak ply on both sides including supply of materials, all necessary
hardware fitting all complete as per approved drawing, Specification and
instruction of site engineer. 11,812.83

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio
on ceiling of good finish including supply of materials, racking the joint,
27.00 wetting of surfaces & curing the work at least 7days all complete as per 454.31
approved drawing, Specification and instruction of site engineer.

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio
on wall of good finish including supply of materials, racking the joint,
28.00 wetting of surfaces & curing the work at least 7days all complete as per
approved drawing, Specification and instruction of site engineer.
417.51

Supplying & applying Cement putty on plastered surface all complete as


29.00 per approved drawing, Specification and instruction of site engineer.
280.42
Supplying & applying 2 coats Emulsion painting in Internal Room of
approved colour with one coat of primer Painting over porperly cleaned
30.00 surface at outside of building all complete as per approved drawing,
Specification and instruction of site engineer.
349.95
Supplying & applying 2 coats of weather paint at outside of Building of
approved colour with one coat of primer Painting over porperly cleaned
31.00 surface at outside of building all complete as per approved drawing,
Specification and instruction of site engineer. 260.27

supplying & Laying Supplying & laying Porcelain Non Glazed tile on Toilet
32.00 fixing in proper shape & size all complete as per approved drawing,
Specification and instruction of site engineer.
3,078.97

Sand filling including supply of filling materials, watering, ramming etc. all
33.00 complete as per approved drawing, Specification and instruction of site
engineer.
2,922.04
34.00 Surface dressing and filling hole 9.20
Supplying & fitting benches(1.5X0.6X0.75) all complete as per approved
35.00 drawing, Specification and instruction of site engineer.
5,035.10
Supplying & applying grass for Picnic spot portion(dubo) all complete as
36.00 per approved drawing, Specification and instruction of site engineer.
322.80
Filling with 15-150mm broken brick all complete as per approved
37.00 drawing, Specification and instruction of site engineer. 8,740.00

Supplying & applying spiral steel ladder 4'-6"dia black pipe all complete
38.00 as per approved drawing, Specification and instruction of site engineer. 11,504.60
supplying & Laying 16mm marble in 12.5mm 1:3 cement mortar in proper
39.00 shape & size all complete as per approved drawing, Specification and 7,810.76
instruction of site engineer.(Rate Analysis: 10sqm)

Providing and fixing Structural Glazing of aluminum section in natural or


color anodized/powder coated color Section size (60x50+13x1.3 mm)
40.00 fitted with 5 mm color glass. (average panel area 6.00 Sq.ft.) all complete 6,780.95
as per approved drawing, Specification and instruction of site engineer.

Providing and fixing Aluminium partition with 5 mm thick glass and 9 mm


41.00 thick laminated board of section (101 x45x1.1) all complete as per 5,456.93
approved drawing, Specification and instruction of site engineer.

Supplying & applying 3mm thick skirting on plastered surface all complete
42.00 as per approved drawing, Specification and instruction of site engineer
210.68
supplying & Laying 10 SWGG chain link 2"x2'' mesh size in proper shape
43.00 & size all complete as per approved drawing, Specification and
instruction of site engineer 517.00
sallo planks with good finish of approved quality incuding supply of
materials, fixing in postion with necessary M.S. hold fasts all complet as
44.00 per approved drawing, Specification and instruction of site engineer.
49,050.08
Supply and installation of 500 Gauge plastic sheet for damp proofing all
45.00 complete work as per approved drawing ,specification and instruction of
site engineer. 163.42
Supplying and applying 4.5X20mm steel Grill with 12X12 solid core
46.00 square rod all complete as per approved drawing ,specification and
instruction of site engineer. 2,369.83
Cement base Prefabricated shera, thai, gypsum, everest solid wall panel
non asbestos including 1.1 mm thick GI channel (50x25x20) mm with
47.00 necessary accessories and fitting charge in Partition wall all (75mm thick )
complete as per approved drawing, Specification and instruction of site
engineer. 3,621.05
Spplying & applying 40mm thk vetrified tile all complete as per approved
48.00 drawing, Specification and instruction of site engineer. 3,562.99

Supplying and applying 100mm PVC pipe on floor for Ventilation all
49.00 complete as per approved drawing ,specification and instruction of site
engineer 408.25
for staircase:Supplying & applying 38 mm dia stainless steel handrail pipe
with 38mm dia stainless steel vertical post at 2m interval with two layers of
50.00 25mm dia stainless steel member in between handrail and floor all 3,862.36
complete as per approved drawing, Specification and instruction of site
engineer.

Potrebbero piacerti anche