Sei sulla pagina 1di 10

SHEAR CONNECTOR REQUIREMENTS FOR EMBEDDED STEEL SECTIONS

By Charles W. Roeder,1 Member, ASCE, Robert Chmielowski,2 Associate Member, ASCE,


and Colin B. Brown,3 Honorary Member, ASCE

ABSTRACT: The paper evaluates bond stress and shear connector requirements in encased steel structures,
which are sometimes known as steel reinforced concrete (SRC). Bond stress is important to the behavior of
SRC elements, and shear connectors are required if the bond stress demand exceeds that capacity. Past research
on bond stress is summarized and analyzed. An experimental study is described and evaluated. The results show
that the size of the encased section and the length of the bond affect the bond capacity. Confining reinforcement
has little impact upon the bond stress capacity, but increased confinement increases the post slip resistance. The
bond stress is distributed exponentially under service load but more uniformly after initial slip. Cyclic loading
results in deterioration of bond stress for loads greater than the slip initiation load. Shear connectors combined
Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

with natural bond stress may produce smaller load transfer than bond stress acting alone, and loads should be
transferred entirely either by bond or by mechanical methods. Design recommendations for bond stress and
shear connectors are developed for serviceability and ultimate load limit states.

INTRODUCTION ness to help resist loads and assure serviceability of the struc-
ture, based on their past observations of building performance
Steel sections have been encased in reinforced concrete col-
umns and walls for many buildings. This composite construc- rather than extensive calculations or predictions of behavior.
tion is sometimes known as steel reinforced concrete (SRC). Today the manner of use of SRC is actually based upon
SRC components provide larger strength and stiffness than construction sequence, since the steel frame must be erected
steel or reinforced concrete construction at minimal cost. before the concrete is placed. As a consequence, SRC con-
These benefits require stress transfer between the steel and struction takes a limited number of forms in U.S. practice. In
concrete encasement, which may be accomplished by either some situations the steel frame is first erected as a normal
natural bond stress or shear connectors. Shear connectors are braced or moment frame, and selected columns then encased
expensive, and at present there are no rational rules for deter- in concrete to increase their strength and stiffness. In others,
mining when and where they are required. This paper sum- entire bays of the steel framing are encased within an SRC
marizes a research study into the bond stress achieved with shear wall where the steel sections serve as longitudinal wall
SRC construction and the requirements for shear connector reinforcement. Stress transfer between the encased steel sec-
design. The focus of this work is seismic design, but the con- tion and the surrounding concrete is necessary to develop com-
clusions from this paper are useful for other applications. posite action and achieve the full stiffness and resistance of
This paper reviews the use of SRC construction in the the SRC element. If the steel is to serve as tensile reinforce-
United States, and then discusses the effect of shear stress (or ment for the composite element, then either bond stress must
bond stress) transfer on the composite behavior of SRC com- develop the tensile capacity of the steel or shear connectors
ponents. This leads to an evaluation of past research performed must be provided. Some SRC buildings have had many shear
on the bond stress issues throughout the world. The bond stress connectors attached to the steel sections, while other buildings
permitted by building codes in the U.S., Europe, and Japan rely entirely on natural bond between the steel and concrete.
are compared and noted. The gist of an experimental study, Prototype structural designs to the general seismic provi-
which addresses several important issues previously raised and sions of the Uniform Building Code (UBC) were completed
expands the existing data base, is then presented. The accu- for concentrically braced frames with composite columns and
mulated results are evaluated, and recommendations are made mixed steel frames with SRC shear walls. Static, dynamic re-
regarding bond stress and shear connector requirements for sponse spectra, and time history computer analyses were per-
embedded steel sections for various performance levels in U.S. formed (Emoto 1996) for these prototype structures; they
practice. showed the locations of critical bond stress demand, and es-
timated these local values. The bond stress demand varies
BACKGROUND — BOND STRESS DEMAND widely for different structural systems and different locations
Virtually all major steel buildings constructed before 1960 within the systems.
involved a form of SRC construction. These buildings were Maximum bond stress demand is greatest in braced frames
designed as bare steel frames, but the entire frame and its with SRC columns and in SRC shear wall systems. In braced
connections were encased in concrete for fire protection. The frames, axial forces in the braces transfer substantial vertical
bare frame was designed to resist gravity and modest lateral force components to the SRC column at each brace-beam-
loads. However, engineers used the added strength and stiff- column joint, and large bond stress demand is required to dis-
tribute the force between the steel and concrete. The column
1
Prof. of Civ. Engrg., Univ. of Washington, Seattle, WA 98195-2700. base of a braced frame and the column base for longitudinal
2
Former Res. Asst., Dept. of Civ. Engrg., Univ. of Washington, Seattle, edge reinforcement of a shear wall are locations where bond
WA. stress demands are usually the largest. These SRC elements
3
Prof. Emeritus, Dept. of Civ. Engrg., Univ. of Washington, Seattle,
WA, and Courtesy Prof. of Civ. Engrg., Oregon State Univ., Corvalis, must often transfer their entire tensile capacity to the foun-
OR 97331-2301. dation within a short distance near these points. These dis-
Note. Associate Editor: C. Dale Buckner. Discussion open until July tinctions between bond stress demands at various locations are
1, 1999. To extend the closing date one month, a written request must important because natural bond stress may be used at locations
be filed with the ASCE Manager of Journals. The manuscript for this where the demand is smaller than the available bond stress
paper was submitted for review and possible publication on April 9, 1998.
This paper is part of the Journal of Structural Engineering, Vol. 125, capacity. The goal of this paper is to establish the bond stress
No. 2, February, 1999. 䉷ASCE, ISSN 0733-9445/99/0002-0142 – 0151/ capacity that can be reliably achieved so that shear connectors
$8.00 ⫹ $.50 per page. Paper No. 18089. can be located where demands exceed this capacity.
142 / JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999

J. Struct. Eng. 1999.125:142-151.


LITERATURE REVIEW — BOND STRESS CAPACITY
Past research considered the bond stress capacity of rein-
forcing bars embedded in concrete. Only the earlier studies on
nondeformed reinforcement are relevant to SRC applications,
and care must be used in interpreting these since they did not
always include mill scale, paint and corrosion, or other surface
conditions that may effect the bond stress capacity of steel
shapes.
Many studies (Bryson and Mathey 1962; Hawkins 1973;
Roeder 1984; Hamdan and Hunaiti 1991; Wium and Lebet
1991, 1992) have addressed the bond stress capacity of SRC
composite columns with push-out tests like that illustrated in
Fig. 1. In this test, the load is applied to the exposed steel at
the top of the specimen, and the reaction is provided solely
Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

through the concrete at the base. The bond stress capacity is


commonly evaluated as the maximum average bond stress,
which is the maximum load transferred between the steel and
concrete, divided by the total surface area of steel section em-
bedded within the concrete. Other studies have employed the
short column test, where the load is applied to the exposed
steel at the top of the column but where the reaction is pro-
vided to both the concrete and steel at the base of the speci-
men. In a short column test, as in a real column, the relative
slip between the concrete and steel is limited to a portion of
the column length, because the bottom part of the column has FIG. 1. Typical Push-Out Test
full composite behavior provided by compatibility of the
strains in the steel and concrete. The maximum average bond Later push-out tests (Hamdan and Hunaiti 1991) examined the
stress for short column tests must be based only on the load effects of the concrete strength, surface condition, and tie re-
that is transferred from the steel to the concrete, rather than inforcement on the maximum average bond stress. The study
on the maximum load. suggested that concrete strength had no effect but that adding
The earliest push-out testing (Bryson and Mathey 1962) tie reinforcement to specimens with sandblasted steel surfaces
studied the effect of the surface condition of the steel on the increased the maximum average bond stress.
bond stress capacity. The steel sections were either freshly Other researchers (Wium and Lebet 1992) performed both
sandblasted, sandblasted and allowed to rust, or left with nor- short column and push-out tests. They postulated that bond
mal rust and mill scale. Sections that were sandblasted or sand- stress can be separated into two stages. The first stage occurs
blasted and allowed to rust developed larger maximum average prior to complete slip and is governed by adhesion or chemical
bond stresses than those with mill scale. Once the steel core bonding between the cement paste and the steel. The second
slipped relative to the concrete encasement, the post slip bond stage occurs after complete slip and is characterized as a
stress was similar for all surface conditions. They postulated purely frictional phenomenon. The tests showed that an in-
that the bond stress was primarily developed on the flange crease in flange cover from 50 mm to 150 mm (2 – 6 in.) in-
surfaces. A later study (Hawkins 1973) examined the position creased the force transfer after chemical debonding by 50%.
of casting and relative size of reinforcement. Specimens cast Increasing the amount of hoop reinforcement increased the
in the horizontal position had smaller bond capacity than those bond stress capacity somewhat. Steel sections that were small
cast in the vertical position. This was attributed to the segre- relative to the concrete encasement had significantly larger
gation of aggregate and accumulation of water under the lower maximum average bond stress, but concrete shrinkage was
flange of the horizontal steel section. The amount of confining found to reduce the bond stress capacity slightly.
reinforcement did not consistently affect the bond stress ca-
pacity prior to significant slip, but an increase in confining DESIGN VALUES USED FOR BOND STRESS
reinforcement increased the bond resistance after slip. The size CAPACITY
of the steel section had no effect on the bond behavior for
specimens, provided that the ratio of the embedment length to While SRC construction has been used in numerous build-
the steel core depth was the same for all specimens. ings, there is very little guidance for design in the United
Another study (Roeder 1984) considered the distribution of States. The American Concrete Institute Specification (ACI
bond stress over the member length. Strain gauges were placed 1995) recognizes the use of SRC columns, but requires that
along the length of each specimen. The bond stress was found shear transfer between the steel and concrete be based entirely
to vary exponentially under service loads, but the distribution on direct bearing. No allowance is made for natural bond be-
was nearly uniform as the specimen approached its maximum tween the steel and concrete. The American Institute of Steel
capacity. Relative slip was observed and attributed to cracks Construction LRFD Specification (AISC 1994) permits the use
developing in the concrete matrix along the concrete/steel in- of SRC construction in both beams and columns. The AISC
terface. These results were qualitatively the same as those ob- provisions for columns require that all shear transfer be ac-
tained on embedded plain steel rods under axial loading complished by direct bearing. However, the AISC specification
(Womersley 1927) and torsion (Brown 1966). It was postu- permits SRC beams with natural bond stress but no shear con-
lated by Roeder that the specimen is permanently damaged by nector requirements.
the onset of cracking, and that load levels higher than the While the U.S. practice is not well defined, other countries
initial slip load should be avoided for cyclic loading. These have established explicit design standards for SRC construc-
tests suggested that the bond stress capacity increased with the tion. The European countries have established EUROCODE4
concrete strength. However, later studies (Hamdan and Hunaiti (EUROCODE 1990), which permits the use of natural bond
1991; Wium and Lebet 1992) disagreed with this observation. of 0.5 MPa (75 psi) over the entire perimeter of the section
JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999 / 143

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 2. Effect of Concrete Strength and Surface Condition on Maximum Average Bond Stress

FIG. 3. Effect of Relative Length of Specimen on Maximum Average Bond Stress

for a length equal to the maximum dimension of the cross There is considerable scatter in the data, and no discernible
section. The Japanese provisions permit the use of bond stress trend with respect to the effect of concrete strength on the
of 0.2 f⬘c but not more than 0.45 MPa (64 psi) over the length bond stress capacity. Past research has reported that sandblast-
of the member. Clearly these specifications illustrate signifi- ing significantly increases bond stress capacity over that
cant differences from U.S. specifications. achieved with normal mill-scale surfaces, bug Fig. 2 shows
that, on average, sandblasting has relatively little effect on the
EVALUATION OF PAST RESEARCH RESULTS bond stress capacity. The averages are about the same for both
mill scale and blast cleaned surfaces, although the largest and
Past research provides consistent results when any one study lowest values are clearly attained with the blast-cleaned sur-
is independently considered, but reveals contradictions when faces.
studies are compared. As a result, an analysis of all past test Past research (Roeder 1984; Wium and Lebet 1991) shows
data was made to better understand trends. Data from more that the bond stress is distributed exponentially before slip.
than 120 previous SRC bond stress experiments were identi- After slip, friction between the steel and concrete provides
fied, tabulated, and included in this evaluation. Fig. 2 shows some bond stress capacity, but past work has also indicated
the maximum average bond stress for all push-out tests as a that this frictional resistance must deteriorate as slip increases.
function of concrete strength, except for those studies which As noted earlier, bond stress capacity is commonly evaluated
were designed to minimize bond on some part of the section. as a maximum average — as if the transferred load is uniformly
144 / JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 4. Effect of Relative Size of Steel Section on Maximum Average Bond Stress

TABLE 1. Summary of Test Specimens and Results


Ratio of
Maximum post slip Maximum Maximum
Interface load load to average local bond
Test Reinforcing length Steel Concrete capacity maximum bond stress stress
specimen arrangement (mm) size encasement (KN) Test type load (MPa) (MPa)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 Spiral 1,060 W10 ⫻ 45 500 mm Dia. 1,876.6 Concentric 0.592 1.378 2.646
2 Spiral 1,060 W10 ⫻ 45 500 mm Dia. 1,716.4 Concentric 0.633 1.261 2.394
3 Pattern II 600 W10 ⫻ 45 450 ⫻ 450 mm 841.5 Concentric 0.699 1.082 1.516
4 Pattern II 600 W10 ⫻ 45 450 ⫻ 450 mm 853.1 Concentric with 0.735 1.082 3.036
10 cycles at
80%
5 Pattern II 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,608.2 Concentric 0.747 1.185 2.498
6 Pattern II 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,648.3 Concentric 0.788 1.199 1.898
7 Pattern II 1,524 W10 ⫻ 45 450 ⫻ 450 mm 2,231.7 Concentric 0.696 1.123 3.307
8 Pattern II 1,525 W10 ⫻ 45 450 ⫻ 450 mm 2,055.9 Concentric with 0.688 1.033 2.183
10 cycles at
60%
9 ACI Minimum 1,060 W10 ⫻ 22 450 ⫻ 450 mm 966.1 Concentric 0.552 0.854 3.218
10 ACI Minimum 1,060 W10 ⫻ 22 450 ⫻ 450 mm 999.0 Concentric with 0.552 0.903 1.817
10 cycles at
35%
11 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,453.4 Concentric 0.683 1.061 2.401
12 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,393.3 Concentric 0.556 0.992 2.713
13 ACI Minimum 1,060 W10 ⫻ 77 450 ⫻ 450 mm 1,535.7 Concentric 0.571 0.951 1.521
14 ACI Minimum 1,060 W10 ⫻ 77 450 ⫻ 450 mm 1,429.8 Concentric 0.604 0.888 3.163
15 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,312.7 Concentric with 4 0.50 NA NA
shear connec-
tors
16 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,246.0 Concentric with 8 0.40 NA NA
shear connec-
tors
17 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,269.1 75 mm eccentric- 0.61 NA 4.479
ity
18 ACI Minimum 1,060 W10 ⫻ 45 450 ⫻ 450 mm 1,024.39 150 mm eccen- 0.72 NA 3.727
tricity

distributed over the entire contact surface area of the specimen. of the deterioration noted as slip progresses. Fig. 3 shows sub-
As a consequence, the maximum average bond stress must be stantial scatter in the measured data, but the maximum average
significantly smaller than the maximum local bond stress ob- bond stress is lower for specimens that are relatively long com-
served with the exponential distribution. Further, the maxi- pared with the dimensions of the specimen. Past research
mum average bond stress should be somewhat smaller with (Wium and Lebet 1992) indicates that increasing the concrete
specimens in which the interface length is very long relative area, relative to the area of the steel, increases the maximum
to the cross section dimensions of the steel section, because average bond stress. This observation is verified in Fig. 4.
JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999 / 145

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 5. Reinforcement Details for Test Specimens: (a) ACI Minimum; (b) Second Pattern; (c) Spiral Reinforcement

mm, and 1524 mm (24, 42, and 60 in.) were used. Specimens
15 and 16 had two and four 12.7 mm (0.5 in.) shear connec-
tors, respectively, welded to both outer flange faces of the steel
core, as depicted in Fig. 6. The shear connectors were 54 mm
(2.125 in.) in length to minimize interaction between the shear
connectors and the confining steel. The connectors were
welded by a commercial installation company and had a min-
imum tensile strength of 60 ksi.
Past research (Wium and Lebet 1991) suggested that the
concrete cover of the flanges affected the bond stress capacity.
To avoid this effect, the minimum clear cover was held con-
stant at approximately 100 mm (4 in.) for these tests. The
encasement was 450 mm (18 in.) square for all specimens with
normal tie reinforcement, and 500 mm in diameter (20 in.) on
specimens with spiral reinforcement. The steel shapes were
blast cleaned to remove mill scale, and the steel surface was
treated with the degreaser Trisodium Phosphate prior to cast-
ing of concrete.
FIG. 6. Shear Connectors on Specimens 15 and 16 Gauges were installed on each steel core to measure the
strain along the length of the steel/concrete interface. Fig. 7
EXPERIMENTAL PROGRAM illustrates one typical strain gauge spacing. The longitudinal
strain gauges were placed at close intervals near the top of the
As experimental program (Chmielowski 1997) of 18 push- specimen, since the bond stress is initially exponentially (Roe-
out tests examined the effect of the size of steel core relative der 1984) distributed, with the greatest bond stress value and
to the encasing concrete, the confinement, the interface length, most rapid variation near the top. This bond stress results in
eccentric loading, and the interaction of shear connectors with a change in axial load. The axial load, the rate of change in
the bond stress capacity. Table 1 summarizes the test speci- the axial load and the bond stress distribution needed to pro-
mens and test results. duce the change in axial load are estimated from strain mea-
Fourteen of the specimens were tested as identical pairs so surements along the specimen length. It has been suggested
that the variability in test results and the effect of cyclic load- (Bryson and Mathey 1962) that the bond stress is primarily
ing could be examined. Three different reinforcement arrange- developed on the flanges of the section. Therefore the strain
ments were selected to examine the effect of confinement on gauges were placed on the inside of the flanges as shown in
the bond stress capacity. The first arrangement approximated the figure, thus maintaining the critical contact surface area on
minimum ACI requirements with #3 ties at 200 mm (8 in.) the outside of the flanges. The gauges were protected by a
and eight #6 longitudinal bars [Fig. 5(a)]. The second arrange- waterproof coating, and a light 18 mm (3.4 in.) steel channel
ment used #3 ties in both square and octagonal patterns at 100 was placed over the gauges and wiring to isolate them from
mm (4 in.) with fourteen #6 longitudinal [Fig. 5(b)]. The final the concrete. The channel was lubricated to prevent develop-
arrangement used #3 spiral reinforcing with a 75 mm (3 in.) ment of extra bond stress capacity.
pitch and twelve #6 longitudinal bars [Fig. 5(c)]. The steel Standard commercial formwork was used for the specimens,
sections were W10⫻22, W10⫻45, and W10⫻77 sections and and a special plywood insert provided a 38 mm (1.5 in.) gap
three embedment lengths of the steel sections of 600 mm, 1060 between the bottom of the steel and the supporting base, as
146 / JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999

J. Struct. Eng. 1999.125:142-151.


and they were cured in the same manner as the test specimens.
These cylinders showed a concrete strength of 36.5 MPa
(5,300 psi) for Specimens 5, 6, 11, 13, and 14 and 29.6 MPa
(4,300 psi) for other specimens. Tensile coupons from the steel
sections and rebar segments were cut (Chmielowski 1997) to
obtain yield and tensile strength. Yield stresses were higher
than 306 MPa (44.4 ksi) in all cases, and therefore inelastic
deformation of the steel did not contribute to the test results.
The tests were conducted after the specimens had cured for
at least 28 days. The load was applied concentrically to the
first 16 specimens by a 10.4 MN (2,400 kip) hydraulic test
machine, through a swivel and a machined steel plate, as
shown in Fig. 1. Specimens 17 and 18 had a deliberate eccen-
tricity to induce a combined axial load and bending moment.
Each specimen was placed in the testing machine and was
Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

plumbed and leveled. A layer of hydrostone was placed be-


neath the specimen to provide uniform support and to distrib-
ute the load from the column base to the test machine. The
load was monitored using a calibrated linear variable differ-
ential transformer (LVDT) installed in the test machine. The
slip of the steel core with respect to the concrete encasement
was recorded by potentiometers attached to each flange of the
steel section. Voltage readings from the strain gauges, poten-
tiometers, and LVDT were recorded using a Hewlett Packard
FIG. 7. Typical Strain Gauge Placement computer and data acquisition system. The voltages were con-
verted into strain, bond stress, load, and displacement, and
depicted in Fig. 1. This gap allowed a large amount of slip critical data were displayed and plotted and monitored during
before the steel reacted on the base of the test machine. Tie the test.
wire was used to prevent shifting of components during cast-
ing. Ready mix concrete with 9 mm (3/8 in.) pea gravel and EXPERIMENTAL RESULTS
a superplasticizer were used. The design slump, water/cement The tests were carried out over a period of three weeks.
ratio, and concrete strength was 175 mm (7 in.), 0.33, and 35 Each specimen was loaded to displacements well beyond com-
MPa (5,000 psi), respectively. The concrete arrived with a plete slip. Certain individual test results are shown in Table 1.
slump of 115 mm (4.5 in.). Five specimens (5, 6, 11, 13, and The maximum average bond stress, as described earlier, was
14) used the original concrete, but additional superplasticizer calculated by dividing the maximum load by the total interface
was added to enhance the concrete workability of the remain- area. The maximum value of local bond stress is that calcu-
ing specimens. lated from the strain gauge measurements recorded at any level
The specimens were cast in the upright position. Concrete during the test.
was placed in three layers, and each layer was vibrated. After Fig. 8 shows a typical force deflection (or slip) curve. The
casting, the specimens were covered with moist burlap and specimens had virtually no slip for loads up to 25 – 40% of the
plastic, and they were moistened regularly to facilitate curing. maximum load capacity. However, local slip began at the top
Twenty-four cylinders were cast to provide concrete strength, of the specimen for loads above this threshold and then prop-

FIG. 8. Typical Force Deflection Curve

JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999 / 147

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 9. Typical Force Distribution for Different Load Levels

agated down the specimen with increasing load. The maximum curacy because they are determined from small differences in
load and maximum average bond stress were achieved when strains in adjacent gauges, and the limited resolution of each
the total slip at the top of the specimen was approximately 0.5 strain gauge plays a larger role in the determination of bond
mm. After the maximum load was achieved, the slip proceeded stress distribution than for the axial force distribution. Nev-
rapidly over the entire specimen length with reduced load ca- ertheless, these local bond stress measurements provide un-
pacity at increasing slip. The proportion of this reduced load derstanding of the bond stress capacity.
and the maximum load capacity at their maximum slip of each Specimens 10, 8, and 4 were subjected to cyclic loading. In
specimen are stated in Table 1; the reduction is generally larger these tests, the specimens were loaded to 35, 60, and 80% of
for specimens with less confining reinforcement. All speci- the expected axial capacity, respectively, and then unloaded
mens were loaded to a total slip of approximately 15 to 20 and reloaded for 10 cycles to examine the effect of cyclic
mm (0.6 – 0.8 in.). inelastic behavior. These three load levels were selected as
The measured longitudinal strains were directly transformed representing significantly different levels of behavior. The 35%
to axial forces in the steel section by the application of uniaxial loading results in cycling at the threshold of slip propagation.
stress state and elastic stress-strain relationship. Fig. 9 shows At this load, slight local slip is possible with only a short
typical distributions of the force in the steel at locations along penetration into the specimen. Examination of the behavior
the embedded length at 25, 75, and 100% of the maximum achieved by this specimen suggests that there is no significant
load. The distribution was nearly exponential over a length of change in the bond stress behavior under cyclic loading. The
approximately two times the depth of the steel section for all ultimate load achieved was somewhat larger than the resis-
specimens at loads of 25 – 50% of the maximum capacity. Prior tance achieved in Specimen 9, the companion, uncycled spec-
to significant slip, an intermediate zone of nearly constant imen. Specimens 4 and 8 were cycled at 80% and 60% of the
force distribution was noted. The strain in the steel and con- maximum load, respectively. These loads are well above the
crete are equal, and no bond stress transfer occurs in this in- slip initiation load. At 60% loading, slip was expected over a
termediate region, because composite action is fully devel- length greater than the depth of the steel section, and, at 80%
oped. This intermediate region is shorter for short specimens loading, slip should propagate over most of the specimen
and longer for long specimens, but the exponential variation length. Comparison of the measured strains in the first cycle
is nearly identical regardless of the specimen length. Finally, to subsequent cycles indicate significant deterioration in the
another short region of bond stress transfer occurs at the bot- bond stress behavior with loading cycles at high initial load
tom of the specimen, where the total load of the specimen states. The deterioration did not always result in a large re-
exists in the concrete. duction on the ultimate load capacity, but there were large
The distribution of force in the steel section approaches a changes in local behavior. This observation indicates that serv-
linear variation, as shown in Fig. 9, as the load approaches its iceable behavior under cyclic loading can be assured only if
maximum value. A truly linear variation is never quite the load cycles are kept at or below the threshold load for
achieved, particularly for the longer specimens, because of de- local slip.
terioration caused by the local interface slip. Specimen 15 and 16 had shear connectors welded to each
The bond stress between the steel and concrete causes the flange of the steel section, as illustrated in Fig. 6. The tests
change in force distribution, and bond stress depends upon the were designed to examine the manner in which bond stress
derivative or rate of change of the curves in Fig. 9. Fig. 10 and shear connectors work together in transferring forces be-
shows typical bond stress distribution curves; the distribution tween the steel and the concrete. Specimens 15 and 16 were
is nearly exponential for loads below slip and approaches a directly comparable to Specimens 11 and 12. The addition of
constant value at loads approaching the maximum. The max- shear connectors resulted in a loss in total resistance, reduced
imum bond stress obtained from these strain gauge measure- ductility, and greater deterioration in resistance after slip com-
ments are given in Table 1. The local bond stresses obtained pared with the behavior of Specimens 11 and 12, as can be
from strain gauge measurements have limitations in their ac- seen in Table 1. In both specimens, shear connectors caused
148 / JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 10. Typical Measure Bond Stress Distribution

significant spalling of the concrete, and some shear connectors Confinement of concrete did not have a dramatic effect on
fractured in the heat affected metal outside of the weld. The the maximum average bond stress, but it affected the post-slip
loads attained by these specimens were larger than the capacity deterioration. Cracking patterns were observed on the concrete
expected with the shear connectors acting alone. The length surface before and during testing. Specimens with large
of the shear connectors was limited to keep them within the amounts of confining steel developed more cracking due to
area of the concrete, and they were not long enough to guar- shrinkage prior to testing, but less cracking during testing. The
antee their full force development. The data showed that shear stiffness of the confinement steel prevented the concrete from
connectors require local deformation to achieve their resis- shrinking and thus induced local concrete cracking during cur-
tance, and this deformation disrupts the conditions required to ing. During loading, the confinement steel restrained further
develop bond stress. The flange cover was approximately 100 crack opening and improved the postslip performance. Spec-
mm, but it is plausible that greater cover with longer con- imens with little confining steel has few shrinkage cracks, but
nectors would have improved the interaction of the shear con- cracks under loading appeared to grow more quickly. The lo-
nectors with the bond stress. Care must be exercised in draw- cation of cracking suggested that the flanges of the encased
ing conclusions from only two tests. However, these surprising section act as wedges which split the concrete under increased
results suggest that force transfer should be developed by bond load. These observations suggest that minimum confinement
stress alone or shear connectors alone rather than a combina- is necessary to assure satisfactory postslip behavior, but that
tion of the two transfer mechanisms. large amounts of confining steel are not needed to achieve
Specimens 17 and 18 were loaded eccentrically and are good bond performance.
comparable to the concentrically loaded Specimens 11 and 12.
The ultimate axial load capacity of Specimens 17 and 18 are APPLICATION OF RESEARCH RESULTS TO
lower than those for Specimens 11 and 12, and this dominance PRACTICE
could suggest that bond stress is reduced by eccentric loading.
However, this conclusion would be misleading. Eccentric Bond stress demand was described earlier in this paper. This
loading places large bond stress demand on one flange while demand is variable and important, but it must be compared to
reducing the demand (and even reversing the direction of the the bond stress capacity. Experimental research has considered
demand) on the other flange. As a consequence, the actual the capacity that can be achieved with SRC construction and
bond stress capacity is dramatically increased under combined indicates that, in engineering design for safety, serviceability,
bending and compression rather than decreased. This is illus- and economy, two criteria for deciding on the appropriateness
trated by comparing the maximum local bond stress values of using shear connectors are
obtained from strain gauge readings where the eccentrically
loaded specimens had maximum local bond stress values • That shear connectors should not be used where the nat-
50 – 100% larger than those for concentrically loaded speci- ural bond stress capacity exceeds the bond stress demand
mens. Also, the force-deflection behavior showed that eccen- • That shear connectors must be employed where the de-
trically loaded specimens delayed the initiation of significant mand exceeds the capacity
slip. That is, the load associated with progression of local slip,
as illustrated in Fig. 8, was a significantly larger load with The demand can be determined by analysis for each struc-
eccentrically loaded specimens than for concentrically loaded tural design; however, a method is needed for translating ex-
specimens. Finally, it is noted that none of these tests involve perimental results into a reliable estimate of bond stress
yielding of the steel, but the eccentrically loaded test speci- capacity. A multivariable linear regression analysis was per-
mens are closer to yielding than any of the other specimens. formed for all push-out test data, and the L/d and As /At ratios
The combined stress ratios are at 80 – 90% of yielding for both were primary variables which affect the bond stress capacity.
of the eccentric load tests, and so local yielding due to residual Here L and d are the length and depth of the steel section, and
stress may have had some effect. As and At are the areas of the steel section to the total cross
JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999 / 149

J. Struct. Eng. 1999.125:142-151.


Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

FIG. 11. Comparison of Prediction Resistance with Measured Resistance

of the data, and permits bond stress estimates for higher or


lower confidence levels.
The maximum load that can be transferred by bond stress
depends on the bond stress capacity, the perimeter of the en-
cased section, and the bond length. It is tempting to use the
longest bond length, but this will not necessarily produce the
largest load transfer capacity. An optimization of the maximum
load capacity computed from (2) found that the maximum ca-
pacity will occur when
L/dcritical = 3.22 ⫺ 24.519␳ (3)
Thus, this ratio should be used in (2) when columns have a
longer length than the critical length defined in (3). In practice,
nearly all columns will use this critical length for defining their
bond stress capacity, and therefore (3) can be introduced into
(2) for these practical applications. Then,
FIG. 12. Proposed Bond Stress Evaluation Models fB2␴ = 1.256 ⫺ 9.554␳ (in MPa) (4)

section of the composite member. The results of this regression The dimensionless parameter, ␳, is limited in practice to num-
analysis indicate that bers such as 0.02, 0.04, or 0.06. For these values of ␳, the
bond stress capacity will be 1.06, 0.87, and 0.68 MPa (154,
fBR = 2.91 ⫺ 0.300(L/d) ⫺ 14.97␳ (in MPa) (1) 126, and 99 psi), respectively, applied over the total perimeter
of the cross section for the length defined by (3). These esti-
Here ␳ = As /At ratio. The maximum average bond stress is mates of bond stress capacities are larger than the bond stress
used in this statistical derivation, and fBR is a mean expected values permitted by Japanese and European codes. It is rea-
value. It is desirable to design for a more reliable estimated sonable to compare these estimates to past test results. Fig. 11
bond stress, and so (1) was reduced by 2 standard deviations compares predictions by (2) with the actual experimental load
to obtain capacity. The length used in the prediction was the shorter of
fB2␴ = 2.5119 ⫺ 0.3900(L/d) ⫺ 19.1168␳ (in MPa) (2) the critical length provided by (3) or the actual length of the
test specimen. The predicted resistance is divided by the total
Eq. (2) provides an estimated confidence of 97.7% that the load capacity of the specimen and plotted as a function of the
true average bond stress will be larger than the value given in concrete strength in Fig. 11. Considerable scatter persists in
the equation, and as a result it is more conservative and suit- the results, but it can be seen that all but three specimens have
able for engineering applications. Eq. (2) indicates that no resulted below the predicted values (below the 1.0 line) and
bond is available when the L/d ratio is greater than approxi- that the predicted strength is a conservative estimate.
mately 6 or when ␳ is greater than 0.125. Nor is any bond At the ultimate load performance level, this bond stress can
stress available when both of the ratios are moderately large be uniformly distributed over the perimeter of the section and
but below the above limits. It should be noted that there is a length equal to the lesser of either the column length or the
considerable scatter in the data, and fB2␴ is reduced signifi- length defined by (3). Fig. 12 shows this recommended uni-
cantly by that scatter. There are two standard deviations be- form distribution of bond stress capacity. Engineers have in-
tween Eq. (1) and (2). Therefore, comparison of these equa- creasing concern for the performance of structures under re-
tions shows a measure of the standard deviation or variance peated loading and their serviceability limit states. The tests
150 / JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999

J. Struct. Eng. 1999.125:142-151.


reported show evidence of interface deterioration when cyclic methods and not by any combination of the two. The obser-
loading is applied after initial slip between the steel and con- vations regarding shear connectors and natural bond stress are
crete. Thus, at the serviceability performance level, it is pro- important and surprising. Further studies of this phenomenon
posed that a triangular bond stress distribution be used over a are recommended to establish the mechanics of the interaction.
length equal to two times the depth of the encased sections. Tests performed on two eccentrically loaded specimens re-
Fig. 12 also shows this serviceability requirement. The maxi- sulted in lower ultimate load capacities, but bond stresses that
mum average bond stress defined in (2) is also used for the were significantly greater than specimens loaded concentri-
serviceability limit state, because it leads to a conservative cally.
estimate of serviceability behavior. The maximum local bond The experimental results are combined with results from
stress at condition of initiation of slip is invariably larger than past research, and these are used to establish a rational pro-
the average value. Further, the information needed to compute posal for a design method, which is provided in the previous
local bond stress is missing from most of the past results, and section.
the use of the maximum average bond stress permits the use
of a larger data base and provides greater confidence in the ACKNOWLEDGMENTS
result. It should be emphasized that the bond stress check is This work was funded by the National Science Foundation under a
Downloaded from ascelibrary.org by Universite De Liege on 06/19/13. Copyright ASCE. For personal use only; all rights reserved.

only needed for the axial load transfer; bending appears to Grant CMS-9520233, ‘‘Design Requirements for Shear Connectors in En-
develop a binding action that enhances the local bond stress cased Steel (SRC) and Concrete Filled Tube (CF T) Construction.’’ Dr.
S. C. Liu is the NSF Program Manager for this research. The financial
capacity. Finally, there is evidence that shear connectors do
support is greatly appreciated. Cheryl Burwell and Daniel Morrow pro-
not work well with natural bond stress, and therefore it is vided great help with this research through an NSF Research Experience
recommended that the design for axial load transfer be accom- for Undergraduates supplemental grant. They helped the project signifi-
plished entirely by bond stress or entirely by shear connectors, cantly, and this is greatly appreciated.
rather than a combination of the two.
APPENDIX I. REFERENCES
SUMMARY AND CONCLUSIONS ACI Committee 318. (1995). ‘‘Building code requirements for structural
concrete.’’ ACI 318-95, American Concrete Institute, Farmington Hills,
This paper examines the bond stress transfer between steel Mich.
and concrete in SRC elements. Shear stress must be transferred ACI Committee 318. (1995). ‘‘Commentary.’’ ACI 318R-95, American
between the steel and concrete if the composite members are Concrete Inst., Farmington Hills, Mich.
to perform as desired. Analysis of prototype structures show AIJ. (1991). AIJ standards for structural calculation of steel reinforced
that the critical locations for bond stress demand are the at- concrete structures. Architectural Institute of Japan, Shiba, Japan.
AISC. (1994). Manual of steel construction: Load and resistance factor
tachment of SRC shear walls and SRC columns of braced design, 2nd Ed., American Institute of Steel Construction, Chicago,
frames to the foundation. However, brace-beam-column con- Illinois.
nections in braced frames also have significant demand be- Brown, C. B. (1966). ‘‘Bond failure between steel and concrete.’’ J. of
cause of the vertical component of force transferred by the the Franklin Inst., 282(5), 271 – 290.
brace. Bryson, J. O., and Mathey, R. G. (1962). ‘‘Surface condition effect on
bond strength of steel beams embedded in concrete.’’ J. Am. Concrete
More than 120 SRC bond stress tests and the results of Inst., 59(3), 397 – 405.
experiments described in this paper were evaluated to deter- Chmielowski, R. A. (1997). ‘‘Force transfer in steel columns encased in
mine factors that affect the bond stress capacity. This evalua- concrete,’’ MS thesis, University of Washington, Seattle, Wash.
tion shows considerable scatter in the test results, but the rel- Emoto, J. (1996). ‘‘Bond shear demand in composite concrete and steel
ative size of the encased steel section compared with the members,’’ MS thesis, University of Washington, Seattle, Wash.
concrete encasement, the thickness of the concrete cover, and EUROCODE No. 4. (1990). Design of composite steel and concrete
structures. Part 1: General rules for buildings. Commission of Euro-
the length of the bond stress region were all deemed to affect pean Communities, Luxembourg.
the bond stress capacity. Individual previous studies have sug- Hamdan, M., and Hunaiti, Y. (1991). ‘‘Factors affecting bond strength in
gested that the surface condition of the steel affected the bond composite columns.’’ Proc., 3rd Int. Conf. on Steel-Concrete Compos-
stress capacity, but this trend is less clear when all the avail- ite Structures, Association for International Cooperation and Research
able results are considered. Nevertheless, it is still recom- in Steel-Concrete Composites, Fukuoka, Japan, 213 – 218.
Hawkins, N. M. (1973). ‘‘Strength of concrete encased steel beams.’’ Civ.
mended that bond stress be employed only with blast cleaned Engrg. Trans. Inst. of Engrgs., CE15(1), (2), 39 – 46.
surface. The bond stress capacity does not appear to be related Roeder, C. W. (1984). ‘‘Bond stress in embedded steel shapes in con-
to the strength of the concrete. crete.’’ Composite and Mixed Construction, Proceedings of the U.S./
An experimental program was performed to address bond Japan Joint Seminar, Charles W. Roeder, Ed., New York, 277 – 240.
stress capacity in SRC elements. These tests provided supple- Wium, J. A., and Lebet, J. P. (1991). Composite columns: Force transfer
mental information that was combined with past research re- from steel section to concrete encasement. Ecole Polytechnique Fed-
erale, Lausanne, Switzerland.
sults. The experimental work showed that the confining rein- Wium, J. A., and Lebet, J. P. (1992). Force transfer in composite columns
forcement had little impact upon the maximum average bond consisting of embedded HEB 300 and HEB 400 sections. Ecole Poly-
stress, but that increased confinement increased the postslip technique Federale, Lausanne, Switzerland.
resistance. These experiments supported observations that the Womersley, W. D. (1927). ‘‘Bond between concrete and steel.’’ Concrete
bond stress is distributed exponentially over length under ser- and Constr. Engrg., 22(2), 153 – 159.
vice load, and the distribution approaches a uniform value for APPENDIX II. NOTATION
loads approaching the maximum capacity. Cyclic load tests
show no deterioration if cyclic loads were less than the slip The following symbols are used in this paper:
initiation load, and this initiation load is about 40% of the As =area of steel section;
maximum load capacity. Interface deterioration is significant At =area of total cross section of composite member;
for loads larger than the slip initiation load. d =depth of steel section;
Tests performed on two specimens with shear connectors fBR =average bond stress capacity from regression analysis;
suggested that they induce local deformations and stress con- fB2␴ =average bond stress capacity with two standard deviations
centrations into the concrete encasement, which then acceler- or 97.7% confidence level;
ates the deterioration of bond due to cracking along the inter- f ⬘c = strength of concrete;
face. Thus, it is recommended that, in design, either the loads L = length of steel section or bond stress interface length; and
be transferred entirely by bond or entirely by mechanical ␳ = As /At.

JOURNAL OF STRUCTURAL ENGINEERING / FEBRUARY 1999 / 151

J. Struct. Eng. 1999.125:142-151.

Potrebbero piacerti anche