Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
: Page 1 of 11
Revision : 0
Issued : May 2002
IMPORTANT:
The information contained herein is the proprietary property of UE CONSTRUCTION SDN BHD.
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 11
Revision : 0
Issued : May 2002
1.0 SCOPE
2.0 MATERIALS
3.1 The following is a list of equipment to be used. However, the actual number
of units would depend on the works involved.
a) Survey equipment
b) Excavator / backhoe
c) Cranes
d) Vibrator
e) Compressor / jack hammers
METHOD STATEMENT Page No. : Page 4 of 11
Revision : 0
Issued : May 2002
f) Welding set
g) Gas cutting set
h) Bar cutter
i) Bar bending machine
3.2 All plants and machinery will be with valid documents or license.
4.1.1.1 Piles shall be exposed to 75mm below cut off level. The level shall
then be marked on exposed bored piles.
4.1.1.2 Bored piles shall then be hacked using pneumatic breaker up to the
pile cut-off level or up to required lap length whichever is greater.
4.2.1.2 Circular steel mould of 900mm and 1500mm dia. shall be used for
abutment and pier column respectively.
4.2.1.3 The position and verticality of the moulds shall be checked for
accuracy and tolerance before concreting.
4.2.1.4 Concreting shall be carried out using crane and bucket. The lift of
concreting shall be approximately 2.0m.
4.3.3.5 The side formwork for piercap shall be stripped after 12 hours
of concreting. Bottom formwork and staging shall be removed after 7-
10 days provided concrete has attained 2/3 of 28-day strength.
4.3.3.8 Having exposed and hacked the piles to cut-off level, 75mm
thick lean concrete shall be laid followed by the above sequence.
4.4.1 As shown in the drawings, dowel bar and rubber strips shall be
provided abutment caps and pier caps respectively using approved
materials.
4.9.7.3 The top levels of concrete shall be marked along the side
formworks. Steel rods indicating the deck level shall also be
provided at suitable spacing covering the entire deck slab area.
4.9.8.4 Wooden formwork shall be used for casting of kerb and cable
trench.
4.9.9.2 After lean concrete has been laid, reinforcement bars and side
formworks shall be fixed according to drawings.
Testing shall follow the procedure laid out in the Project Inspection & Test
Plan.
6.1 Work will be carried out according to the Project Safety Plan.
6.2 Tool box meeting will be carried out on construction area at regular
interval to ensure compliance with the Safety Plan and familiarity with
accident and emergency procedures.
6.4 Provide PPE to all workers including safety helmet, safety shoe, vest,
ear protector, etc.
METHOD STATEMENT Page No. : Page 8 of 11
Revision : 0
Issued : May 2002
6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when
working in the vicinity of existing road if required.
6.9 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.
Not applicable.
9.0 DOCUMENTATION
APPENDIX A
METHOD STATEMENT Page No. : Page 10 of 11
Revision : 0
Issued : May 2002
APPENDIX B
METHOD STATEMENT Page No. : Page 11 of 11
Revision : 0
Issued : May 2002
APPENDIX C