Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1996,67,404-412
Abstract: A model clarifier was designed using conventional methods for the
surface calculation and an alternative pathway for the determination of the
height and constructed accordingly. In addition, a new approach was used to
evaluate the necessary scraper speed in comparison to full-scale clarifiers. Scaling
effects were taken into account. The model clarifier was first tested by tracer
experiments. Conductivity measurements were used for the clarification zone,
whereas the thickening zone was tested using pyrene as an organic tracer com-
pound. Finally, the behaviour of the model clarifier was compared with a full-
scale settler. The results indicated that operation of the model clarifier was
representative of full-scale behaviour, except for severe overloads. Hence, the
small-scale clarifier qualified as a model for small-scale studies and could be
installed on large-scale plants to monitor more transparently plant performance
and sludge behaviour
Key words : activated sludge, secondary clarifier, design, down scaling, tracer
testing, sludge blanket height measurements
image.4 For example, the emuent suspended solids con- determination of the cross-sectional surface needed for a
tribute a substantial part to the chemical oxygen certain flow, the height of the clarifier, construction of
demand (COD) and nutrient ~ o n t e n t .The~ small-scale inlet and outlet and the scraper speed.
clarifier should simulate the full-scale clarifier as well as
possible and provide equivalent results. 2.1 Surface
There are few references regarding the design of
small-scale settlers. Some authors have mentioned the Five conventional methods were compared for their
importance of wall- and bridging effect^.^^' These phe- ability for use as small-scale clarifiers, namely emuent
nomena occur during the determination of the sludge and thickening criteria,” STORA design criterion,”
volume index (SVI).8-’1 This problem can be tackled solids flux theory,’O ATV-design” and WRC-design.”
more rigorously using the dimensionless characteristics Imposing a fixed volume for the small clarifier of 10
of the flow dm3, and using general values for the design parameters
The obvious way to verify the hydraulics is using (which differ from method to method), only the solids
tracer e~periments.’~’’~ The flow in the clarification flux theory produced unrealistic results. The other
zone must be smooth enough to prevent turbulence methods indicated very similar designs (Fig. 2). A sensi-
effects from obstructing flocculation of sludge flocs.” tivity analysis was carried out for the methods towards
On the other hand, slow mixing is essential for an the parameters (data not shown). The outcome demon-
enhanced floc formation.I6 No dead zones should occur strated that the final design was particularly sensitive to
in the thickening zone, since this can lead to rising the expected flows and inlet concentration. This shows
sludge.’’ the importance of a careful analysis of the particular
In this paper, five design methods for circular full- situation before constructing a plant. Obviously,
scale clarifiers have been compared for their applicabil- method-specific parameters are also important, but
ity to small-scale clarifiers. Special attention was given without exception their influence is an order of magni-
to important aspects such as scraper speed and down- tude less. Normally, it is not common practice to design
scaling side effects. The design was then subjected to full-scale secondary clarifiers starting from an imposed
tracer experiments. Finally, the model clarifier was com- volume. However, when there are no other constraints
pared with a full-scale clarifier for a period of several imposed, this is the most convenient procedure for
weeks. pilot- and laboratory-scale designs.
The design parameters for a circular clarifier are sum- Several of the design techniques refer to a way to decide
marized in Fig. 1. The clarifier receives an input Q the minimum clarifier height for a certain hydraulic
+ Qr, the emuent flow is Q - Q, and an underflow Q, load. However, these methods cannot be used since they
+ Q, is withdrawn continuously. Qris a fraction r of Q, require minimum values of 2 m and more. Hence, an
alternative procedure was used.I6 Assuming that the
r normally ranging between 0-25 and 1.5.” From this
underflow, a certain flow Q, is taken to compensate for clarification and thickening zone are independent from
the growth of the biomass. If Q, is expressed as w Q, - each other, the clarifier height can be calculated as the
then w is generally a factor of 10 smaller than r.I8 Scra-
pers are provided to collect the sludge in the central
underflow outlet. The design exercise comprised the
Q + Q.
-8 E
I
v)
02
01
0.00
1 2 3 4 5
Design method
Fig. 2. The surface area of the circular clarifier as calculated
1 with the different design methods. 1, Emuent and thickening
Q, Q, * criteria; 2, STORA; 3, solids flux; 4, Abwassertechnische
Fig. 1. Design parameters for a circular clarifier. Vereinigung (ATV);5, water research centre (WRC).
406 K . Grijspeerdt, H . Bogaert, W . Verstraete
sum of the height of the clarification and thickening following expression can be deduced :
zones of the clarifier, respectively. The design variables
are the retention time in the clarification zone (z,) and
the thickening zone (zbs). The retention time for a spe- (5)
cific zone can be calculated as the volume of that zone
divided by the flow rate. The left-hand side represents the power number N , ,
The height of the clarification zone is: and the right-hand side contains a Reynolds and a
Froude number:
H, =
Q(1 - 47,
A TR P
N, = ___ = C ReXFrY
N3D:p
Values for z, can be found in the 1 iteratu re.l~A~value
~
of at least 1 h is sufficient. When there is no vortex formation due to the scraping
The height in the thickening zone ( H , ) is: action, y can be set equal to zero. This is certainly the
case in secondary clarifiers, where the scraping is very
H2 =
+
Q(l r)Xz,, SVI slow. In practice, x generally has the value - l . 2 3 By
A480 comparing the power input per unit area for two stir-
ring devices, the final result is obtained:
The factor (SVI/480) originates from a correlation for
the mean sludge blanket concentration given by
STORA.’
The choice of zbs is governed by two conflicting phe- Equation (7) expresses the fact that the tip speed must
nomena. The thickening should be as pronounced as be the same for both systems, independent of the scale
po~sible,’~ but anoxic or anaerobic conditions must be and should not exceed 5 mm s-’.”
avoided.’5,’7 Values found in the literature range from
0.7 to 5 h.’5,23 2.5 Additional criteria
' Recycle
n
Measurement
data logging
I
V Q,
Under Flow)
Fig. 4. The experimental arrangement for the tracer tests of the clarification zone.
408 K . Grijspeerdt, H . Bogaert, W . Verstraete
4
The mean residence time z.
The variance 0'.
The ratio of these two parameters is a measure for the 7
width of the peak.j5
The Peclet number, a dimensionless characteristic
7-
evolving from zero for a completely mixed vessel to E
m2
infinity for a plug flow system: z
k
2
Pe = -1
Q
lt
The ratio of z to the theoretical residence time leads 0
.. 0
to the percentage of the clarifier volume effectively 0 1 2 3 4
Primary clarifier i: II
Fig. 7. Schematic overview of the WWTP of Ninove and the parallel installation of the small-scale clarifier. (I. Flon IIIC.ISIIIC
merit; ......, control line.
410 K . Grijspeerdt, H . Bogaert, W . Verstraete
recycle flow rate (w < 0.01) and the error introduced by 0.75 m h-', except for some instantaneous peak load-
not taking the waste into account was negligible. These ings, lasting not longer than a few minutes. These peak
flow rates were sent to two peristaltic pumps (Watson- loadings happened during the whole measuring period,
Marlow, UK) by the computer. The input position of but did not influence the sludge interface for both clari-
the small-scale clarifier was located at the lowest posi- fiers.
tion, 20 cm up from the bottom, corresponding with the During period 2, a substantial amount of rainfall
inlet position of the full-scale clarifier. occurred, resulting in an overloading of the clarifiers.
This experimental set-up enabled continuous mea- Although the small-scale clarifier followed the trend, the
surement of the sludge blanket height in the two clari- sludge blanket level rose too soon, indicating a higher
fiers parallel to each other. Comparing the dynamic sensitivity of the small-scale clarifier towards high
behaviour of the blanket demonstrated whether the loading rates (> 1 m h-I). The correlation between the
small-scale clarifier was sufficiently representative of the two signals is good (r2 = 0.82), but there is an offset
full-scale settler. Also, limitations on the representation during the rise of the blanket. When situations like this
are important, i.e. what operating conditions show a occur, care has to be taken in interpreting data gener-
significantly different blanket movement. ated with the small-scale clarifier.
Figure 8 summarizes the data collected over more Period 3 can be classified as a transition phase
than a month. The gaps in the data are due to elec- between well and badly settling sludge. Again, the
tricity failures. The sludge blanket levels are not indi- small-scale measurement correlated well with the full-
cated in absolute numbers, but as percentages of the scale signal. At the end of this period, the sludge level
total height. There was good general correlation rose quite drastically. This was due to an onset of fila-
between both clarifiers over a broad working range. mentous bulking, causing SVI values of more than 500.
When considering the whole time span of the experi- The rise of the sludge level was followed well by the
ment, the correlation between the two line series is 0.95. small clarifier (r2 = 0-91).
However, this global result should be refined. The total In the last period, the sludge continued to bulk,
experimental time can be subdivided in four periods. causing regular wash-out of sludge. The sludge blanket
In period 1, the clarifiers were not greatly loaded and was not clearly defined here, causing the blanket meter
the sludge settled quite well (SVI = 100-150 cm3 g-I), on the full-scale clarifier to drift away. This was verified
with correlation between the two satisfactory by manual measurements. The settlometer, however,
(r2 = 0.65), despite the relatively high amount of mea- consistently pointed to very high sludge levels, which
surement noise present. The operating conditions could was consistent with visual observations. Consequently,
be described as the normal situation in a WWTP. The the correlation between the two measurements was the
surface loading rate of the clarifiers was not higher than lowest of all ptriods (r2 = 0.52).
A
I I
7 600 - I
c I
m 400 - I
-
Q
E
200
o !
- I
l
I
I I
I
I I
+? 300 - I
I I
I
I
C
m 200-
2
E I
0 -
loo
--f4
Period 1 I
I d
Period2 LI Period3
I
I
I
/ + I T Period
J 4Y
I
Computing, 2nd edn. Cambridge University Press, tion measurement for activated sludge using pyrene as a
London, 1992. tracer element. Enuiron. Technol., 16 (1995) 483-8.
34. Froment, G. F. & Bischoff, K. B., Chemical Reactor 37. Vanrolleghem, P. A., Van Der Schueren, D., Krikilion, G.,
Analysis and Design, 2nd edn. Wiley, New York, 1990. Grijspeerdt, K., Willems, P. & Verstraete, W., On-line
35. Walpole, R. E. & Myers, R. H., Probability and Statistics quantification of settling properties with in-sensor-experi-
for Engineers and Scientists. The Macmillan Company, ments in an automated settlometer. Wat. Sci. Tech., 331)
New York, 1972. (1996), 37-51.
36. Grijspeerdt, K. & Verstraete, W., Residence time distribu-