1 Scope.................................................................. 2
2 Applicable Documents........................................ 3
3 Instructions…...................................................... 4
4 Responsibilities................................................. 14
1 Scope
This procedure provides detailed guidelines and establishes responsibilities for project
information collection, preparation and submittal of Project Closeout Reports.
1.1 Purpose
1.2 Application
1.2.1 Abbreviated Project Closeout Reports (phase-wise) are mandatory for all
BIs (A, B, C and C1-type projects) with an ER value of $10 million or
greater and less than $50 million. These reports, as a minimum, shall
contain the deliverables covered under Section 3.2.1 and the completed
checklist in Exhibit II.
1.2.2 Full Project Closeout Reports (phase-wise) are mandatory for all BIs
with an ER value of $50 million or greater. These reports shall contain
all deliverables covered under Section 3.2.
1.2.3 Projects with an ER value of $100 million or greater shall conduct After
Action Review (AAR) meetings in conjunction with Lessons Learned
Collection sessions in accordance with Section 3.2.6 and to be held at:
1) Project Proposal completion
2) Mechanical Completion
Exception:
Project closeout reports are waived for Maintain Potential and Third-party projects.
1.3 Timing
Page 2 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 3 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
2 Applicable Documents
The requirements contained in the following documents and forms apply, to the extent
specified in this procedure.
General Instructions
GI-0002.710 Mechanical Completion and Performance
Acceptance of Facilities
GI-0020.520-1 Instructions for Preparing a Project Change Request
GI-0020.700 Post Project Appraisals
GI-0202.301 Definition of Property, Plant and Equipment
Accounts in the General Ledger
Other Documents
Cost & Scheduling Manual
AIM-201 Financial Close-Out of Capital/Non-Capital Projects
3 Instructions
The reports shall be submitted using the Project Closeout Reports Repository
(PClRR). However, in exceptional circumstances and with prior approval from
the Project Execution Optimization Division (PEOD), the reports can be
submitted on CD-ROM or USB flash drive to the General Supervisor, Project
Page 4 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Along with each report, a completed Project Closeout Report Checklist (Exhibit II),
signed by the Project Leader/Manager is required. Project Closeout Reports shall
contain deliverables prepared in accordance with the following guidelines which are
also referenced in Exhibit II:
Page 5 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
3.2.1.4 List of approved scope changes. For each item, this list shall
include a concise description of the scope change, the business
or technical justification for the change, and any cost and
schedule impact as a result of the change.
Page 6 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
3.2.1.7 Log of approved Change Orders for each contract. The log
shall include a concise description of each change, the
standardized reason for the change (see change order
supplement, SAP transaction), and any cost and schedule
impact of the change order.
Page 7 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
3.2.1.13 Average Project Safety Index from contract award to final MCC.
Page 8 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
3.2.2.2 Planned and actual costs and man-hours information for each
Contractor (including engineering contractors) involved in the
project. All costs and man-hours associated with change orders,
manufacturer bid equalization, commissioning assistance,
surplus material, stand by time/delay costs, incidental services,
or any other payments incurred by the contractor toward the
execution of the contract should also be accounted for.
3.2.2.3 All other miscellaneous costs not identified above that may
include:
a. Saudi Aramco construction equipment, such as rented,
leased and chartered vehicles, aircraft, marine and
construction equipment.
b. Miscellaneous direct costs such as living and
transportation expenses IK and OOK, miscellaneous
invoiced costs, SAO inspection costs, start-up/
commissioning costs, vendor representatives, employee
business assignments outside SAO, SEC power, etc.
c. Prorates, miscellaneous reallocated costs and other indirect
costs such as engineering and construction overhead.
3.2.3.1 Planned and actual key milestone dates for the following
phases, should they apply. Include reasons for variances where
planned and actual milestone dates differ:
a. FEL 1 (Business Case) and FEL 2 (Study and Design
Basis Scoping Paper) milestones:
i. Approved Business Case (except C1-type projects)
Page 9 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 10 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
vi. On-stream
3.2.4 Materials
Page 11 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
3.2.5 General
3.2.5.1 Waivers log if applicable. The waivers log contains the approved
waivers (see SAEP-302) that allow non-compliance to the
Mandatory Saudi Aramco Engineering Requirements (MSAERs).
It also indicates when waivers are obtained (i.e., DBSP, Project
Proposal, Detailed Design, Construction, after the fact, etc.)
Page 12 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
The purpose of these meetings is to identify and record lessons learned that
could be used to improve the planning and execution of future projects.
Page 13 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 14 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
4 Responsibilities
Closeout-related activities during the project life cycle are addressed or performed by
several stakeholders from different organizations and the following are their
responsibilities:
4.1 Project Leader is responsible for submission of the Project Closeout Report
required at DBSP completion.
4.4 Design Manager, Southern Area Projects Department (SAPD) is responsible for
maintaining the Design Deficiencies Database and associated activities specified
in Section 3.2.1.5.
4.5 All key stakeholders and concerned departments that participated in the project
planning and execution and provided support to the integrated project team(s)
are required to:
a. Ensure that the invited participants attend the AAR meetings
b. Provide such data and information as may be required to fulfill the
requirements of this procedure and prepare the Project Closeout Reports
Revision Summary
2 July 2014 Major revision.
11 December 2014 Editorial revision to revise Project Sponsor definition and repair broken hyperlinks.
Page 15 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Cover Page
BI No. ------------------------------
BI Title -----------------------------
Department--------------------------
Page 16 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Index
I. Deliverables Checklist (duly filled-in and signed)
II. Summary
1. BI and Department Representatives
2. Project Execution Plan(s)
3. ATP- Capital Efficiency Requirements (if applicable)
4. Scope Change(s)
5. Design Deficiencies
6. Project Change Request(s)
7. Change Order(s) Log
8. Achievements and Successes
9. Major Issues
10. Value Improvements Practices
11. Performance Evaluation Report(s)
12. Project Quality Index and Log of NCRs
13. Project Safety Index
14. Final Reports
III. Cost and Manhours
1. Construction Agency
2. Contractor(s)
3. Miscellaneous Costs
IV. Schedule and Staffing Profile
1. Milestone Dates
2. Schedules
3. Histograms
V. Material
1. Material Costs
2. Purchase Orders
3. Quantities
VI. General
1. Waivers
2. Permits and License Agreements
3. Project Records
4. Project Photos
VII. After Action Review Meetings Minutes
Note: Progressive project closeout reports are to be assembled as per above index and each report shall only
address the requirements of specific milestones indicated in the Project Closeout Reports’ Checklist
(Exhibit-I). Please indicate NA for above item(s) that are not applicable to the respective project closeout
report.
Page 17 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
BI Title: BI No.
Please write N.A. to indicate Not Applicable or an Completely Legend:
100%
integer number (with no decimals) from 0 to 100 in Submitted Design Basis Scoping
each % complete cell with fill color representing the Partially 0% < X Paper: DBSP
actual status of each section. Additionally, in the Submitted <100% Project Proposal: PP
Remarks column cite the reasons for Partially/Not Not Submitted 0% Detailed Design: DD
submitted submittals and provide target dates for re- Mech Completion: MC
Not Applicable N.A.
submittals. On-stream: OS
Required at:
D %
Ref.
Description B P D M O Complet Remarks
Section
S P D C S e
P
3.2 - Report Preparation and Compilation of Submittals
Prepare, compile, and submit
a x x x x x
progressive Project Closeout Report.
Include this completed checklist
b (signed by the Project x x x x x
Leader/Manager)
3.2.1 – Project Summary
3.2.1.1 Provide the Name and Login ID of the following:
a Project Leader/Manager x x x x x
b Department Manager x x x x x
c BI Primary Contact/Representative x x x x x
Provide approved Project Execution
3.2.1.2 x x x
Plans (including Rev Log).
3.2.1.3 Provide the following ATP Capital Efficiency-required deliverables:
a Opportunity Statement x
b Sponsor Nomination x
Due Diligence Report (for A & B type
c
projects)
x
List of approved Deliverable Waiver
d
Requests
x x
e Project Charter x x
f Operational Readiness Plan x x x
g Target Setting (except C1-type projects) x
Assurance Reviews Reports including
h
Peer Review Reports, as applicable
x x
i Gate Outcome Report x x
j Description of Final Execution KPIs x
Benchmarking Reports (Internal and/or
k
External)
x x
Page 18 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 19 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 20 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 21 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 22 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 23 of 24
Document Responsibility: Project Management Office Department SAEP-329
Issue Date: 11 December 2014
Next Planned Update: 2 July 2019 Project Closeout Reports
Page 24 of 24