July 20-27, 2020

WEEKLY ACCOMPLISHMENT REPORT

PROPOSED 2000cu.m STEEL BOLTED TANK FOR BUENAVISTA WATER


DISTRICT
LOCATION: BUENAVISTA, AGUSAN DEL NORTE

HEALTH STATUS
PREPARED BY: JAYSON R. HANGAD, PROJECT ENGINEER OK
MANPOWER: ROBERTO B. LIM FOREMAN OK
ROEL A. LIM SR. SKILLED OK

ROEL B. LIM JR. SKILLED OK


REMON B. LIM SKILLED OK

SAFE MANHOURS: 320 man-hours

ACTIVITIES:

JULY 20, 2020; MONDAY


 SITE INSPECTION FOR THE LOCATION OF THE WATER TANK
 FIRST MEETING OF THE GSSC PROJECT ENGINEER AND BWD ENGINEERS
 INTERVIEW AT RHU OFFICE PRIOR FOR RAPID TEST
 MOBILIZATION OF QUALITES SOLUTIONS & TECHNOLOGIES INC. (QSTI) FOR SOIL INVESTIGATION
 SET UP OF THE MACHINE/MATERIALS FOR SOIL INVESTIGATION
 STAKING AND ESTABLISHING LAYOUT FOR TANK FOUNDATION (PRELIMINARY)

JULY 21, 2020; TUESDAY


 RAPID TESTING
 SOIL INVESTIGATION AT PROJECT LOCATION IS ON PROGRESS.
 PURCHASING MATERIALS TO BE USE FOR STAKING AND ESTABLISHING PERIMETER LAYOUT FOR
TANK FOUNDATION
JULY 22, 2020; WEDNESDAY
 SOIL INVESTIGATION AT PROJECT LOCATION IS ON PROGRESS.
 STAKING AND ESTABLISHING PERIMETER LAYOUT FOR TANK FOUNDATION AND THE PERIMETER
FOR TECHNICAL FACILITIES AND ENGINEER’S OFFICE
 PURCHASING PVC PIPE FOR 50mm THK. AND 75mm THK. (EXPOSED FROM GROUND) FOR
CONCRETE COVER.

JULY 23, 2020; THURSDAY


 BUENAVISTA WATER DISTRICT GM AND ENGINEER’S SITE VISIT
 SOIL INVESTIGATION AT PROJECT LOCATION IS COMPLETED
 STAKING AND ESTABLISHING PERIMETER LAYOUT FOR TANK FOUNDATION IS COMPLETED
 EXCAVATION FOR THE FOUNDATION AND FOOTING TIE BEAM FOR TECHNICAL FACILITIES AND
ENGINEER’S OFFICE IS ON PRORESS
 MAKING 50mm AND 75mm (EXPOSED FROM GROUND) FOR CONCRETE COVER IS ON PROGRESS

JULY 24, 2020; FRIDAY


 EXCAVATION FOR THE FOUNDATION AND FOOTING TIE BEAM FOR TECHNICAL FACILITIES AND
ENGINEER’S OFFICE IS ON PRORESS
 MAKING 50mm AND 75mm (EXPOSED FROM GROUND) FOR CONCRETE COVER IS ON PROGRESS

JULY 25, 2020; SATURDAY


 EXCAVATION FOR THE FOUNDATION AND FOOTING TIE BEAM FOR TECHNICAL FACILITIES AND
ENGINEER’S OFFICE IS ON PRORESS
 MAKING 50mm AND 75mm (EXPOSED FROM GROUND) FOR CONCRETE COVER IS ON PROGRESS

JULY 26, 2020; SUNDAY


 EXCAVATION FOR THE FOUNDATION AND FOOTING TIE BEAM FOR TECHNICAL FACILITIES AND
ENGINEER’S OFFICE IS COMPLETED
 PURCHASING MATERIALS FOR TECHNICAL FACILITIES AND ENGINEER’S OFFICE
 PUTTING OF GRAVEL BIDS FOR THE FOUNDATION AND FOOTING TIE BEAM PRIOR FOR
INSTALLATION OF MATTING AND FOOTING TIE BEAM REINFORCEMENT FOR TECHNICAL
FACILITIES AND ENGINEER’S OFFICE
 MAKING 50mm AND 75mm (EXPOSED FROM GROUND) FOR CONCRETE COVER IS ON PROGRESS
 SITE INSPECTION WITH THE HEAVY EQUIPMENT (BACKHOE) OWNER PRIOR FOR EXCAVATION

JULY 27, 2020; MONDAY


 REBAR INSTALLATION FOR FOUNDATION, COLUMN AND FOOTING TIE BEAM IS ON PROGRESS
 MAKING OF FORMWORKS FOR COLUMN AND FOOTING TIE BEAM IS ON PROGRESS
 MAKING 50mm AND 75mm (EXPOSED FROM GROUND) FOR CONCRETE COVER IS ON PROGRESS
PHOTO DOCUMENTATION:

JULY 20, 2020 (MONDAY)

JULY 21, 2020 (TUESDAY)


JULY 22, 2020 (WEDNESDAY)
JULY 23, 2020 (THURSDAY)
JULY 24-25, 2020 (FRIDAY-SATURDAY)
JULY 26-27, 2020 (SUNDAY-MONDAY)