Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
This article was published in ASHRAE Journal, December 2017. Copyright 2017 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed
electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal, visit www.ashrae.org.
Commissioning Chilled
Water TES Tank Systems
BY ROSS MONTGOMERY, P.E., BEAP, BEMP, CPMP, HBDP, FELLOW ASHRAE
Chilled water thermal energy storage systems (TES) have been used successfully in
district cooling systems for decades. According to the 2016 ASHRAE Handbook—HVAC
Systems and Equipment,1 thermal storage systems “remove heat from or add heat to a
storage medium for use at another time.” These TES systems can come in the form of
ice or cold-water storage. This article focuses on the commissioning of systems and the
sequence of operations for individual school project chiller plants and cold water ther-
mal energy storage systems using a large storage tank (Photo 1), performed on a large
group of individual educational facilities over the course of 2012 – 17. The sequences and
commissioning tasks have been refined over time to improve the final deliverables and
performance to the facilities.
The capacity design of the TES system used is tai- in the early 1980s, when ASHRAE started to develop
lored to the individual needs of the facility itself. In its Guideline 0 and Guideline 1 on commissioning, and
general, an example design for one school would be later its ANSI/ASHRAE/IES Standard 202, Commissioning
an air-cooled chiller plant consisting of two 400 ton Process for Buildings and Systems, buildings can now be pro-
(1407 kW) chillers operating at 42°F (5.6°C) to 56°F fessionally commissioned by third-party independent
(13.3°C) supply/return temperatures, chiller and charge commissioning providers.
primary flows at 1,370 gpm (86 L/s), discharge primary Benefits of cold-water storage include:
flows at 1,500 gpm (95 L/s) and secondary flows up to •• Shifting loads and kW demand from peak- to non-
3,000 gpm (189 L/s). The thermal storage tank capacity peak times (in both summer and winter) allow for par-
is 4,800 ton-hours (16 880 kWh) and holds 600,000 gal- ticipating utility incentive payments and discounts and
lons (2.3 million L) of treated water. In some projects, current utility rebates, relative to thermal water storage;
water-cooled chillers with cooling towers were also •• Discounts and rebates from participating utility(s)
used. reduce costs of new equipment purchases;
Building commissioning in its early days was per- •• If a time-of-use (TOU) rate is available from the
formed by its consulting engineer designer and their utility company, energy cost savings can be obtained by
staff as a part of continuing design services. Starting operating the chiller equipment in a central plant more
Ross D. Montgomery, P.E., is president and owner of Quality Systems and Technology Inc., a commissioning provider company based out of Parrish, Fla.
32 A S H R A E J O U R N A L a s h r a e . o r g D E C E M B E R 2 0 17
TECHNICAL FEATURE
during the off-peak periods, and reducing the energy PHOTO 1 Typical thermal storage tank.
consumption during peak periods;
•• Increased energy efficiency of chiller equipment by
operating them at night in cooler ambient conditions
(cooler nighttime condensing water temperatures);
•• Reduced sizes of required HVAC and electric equip-
D E C E M B E R 2 0 17 a s h r a e . o r g A S H R A E J O U R N A L 33
TECHNICAL FEATURE
34 A S H R A E J O U R N A L a s h r a e . o r g D E C E M B E R 2 0 17
TECHNICAL FEATURE
verified as programmed per the design documents. chiller operation, but the projects depicted in this article
•• Verify expectations of design parameters and result- do not use this option in their design and OPR. The intent
ing building and equipment performance. of this example sequence is to suggest approximate val-
Making sure that the record documents and as-builts ues of variables that can be fine-tuned, or adjusted in the
are representative of the installation is vital. The train- field, under specific job to job conditions.
ing of the owner’s staff should use the most up-to-date
operation and maintenance manuals, as-builts, systems Plant Sequencing: Chiller Mode
manuals and record documents delivered by creden- The chiller mode is a straightforward primary (PP-1, 2,
tialed and experienced instructors for the mechanical 3)/secondary (SP-1, 2) with valved bypass (V 4.1) chiller
equipment and control systems. plant using state-of-the-art variable frequency drive
(VFD) pumping systems on both the primary and sec-
Utility Incentive Programs for TES Systems ondary pumps.
The utility and the owner have agreed to a time-of-use The chiller mode executes a primary-secondary design
(TOU) tariff payment energy rate plan that provides for scenario for the facility during normal school session
cooling kW demand load shifts of the TES system. The and administration working hours.
sequence of operation follows the winter and summer In the chiller mode, the tank is isolated, and the plant
utility modes for demand management, and its control operates as a primary-secondary chilled water plant.
is programmed into controllers so owner and utility can When the chiller mode is started, there is a series of
both benefit from an agreement to share advantages valves installed and positioned to force this situation as
from the program offered by the utility. In the case of follows relative to Figure 1: V-1, V-2 are closed; V-5, V-6,
this Florida utility, it offers a rebate of approximately V-3.1 are opened; V 4.1 can be modulated.
$625/kW of demand that is shifted from peak time to the The control system controls the operation of the chiller
non-peak time, as first estimated at the time of design, plant based on an optimal start/stop program or manual
and then proven by functional performance testing by command from the operator’s station. Chillers and their
the commissioning provider at the time of start-up and primary/secondary pumps are rotated weekly via lead-
commissioning. lag control and rotation.
The winter and summer schedule for this utility On a start command from the BACS, the chilled water
follows: plant shall be enabled and its corresponding secondary
•• On-Peak: Nov. 1 through March 31: Monday through loop campus chilled water pump starts. After campus
Friday from 6 a.m. to 10 a.m. and 6 p.m. to 10 p.m., loop flow is proven via the differential pressure trans-
excluding Thanksgiving Day, Christmas Day and New mitters, the lead chiller two-way isolation valve shall
Year’s Day. open. After a two-minute delay, the chilled water pri-
•• On-Peak: April 1 through Oct. 31: Monday through mary pump is energized. After flow is proven through
Friday from 12 p.m. to 9 p.m., excluding Memorial Day, the chiller flow switch, the lead chiller is enabled.
Independence Day and Labor Day. While the lead chiller operates, the bypass valve can be
•• Off-Peak: all other hours. modulated to ensure that the maximum flow rate to
one chiller is not exceeded. The lead chiller continues to
Example of Sequence of Operation operate until the return water temperature rises above
Commissioning the operation of the building chilled 56°F (13.3°C) and the lead chiller is loaded above 80% for
water production systems includes the chiller mode, more than 10 minutes. If this condition is met, the lag
which services the building directly, and then the charge chiller will start (the bypass valve will then close). Both
and discharge modes, which involve the use of a thermal chillers will continue to operate until the return water
storage tank. In some designs, it is possible to use the temperature reaches 50°F (10°C) for more than 15 min-
charge, discharge and chiller modes simultaneously in utes, when the lag chiller will then be stopped.
times of emergency or special conditions. Some project If the lead chiller fails to start, the next scheduled
designs involve shifting kW demand and loads by using lag chiller is enabled using the same sequence, and an
the thermal storage system output in conjunction with the alarm will be logged.
D E C E M B E R 2 0 17 a s h r a e . o r g A S H R A E J O U R N A L 35
TECHNICAL FEATURE
V-1 Closed
Tank; 600,000 Gallons V-5 Open
4,800 Ton-Hours
FM (CH-1)
Level
Sensor Chiller 1 (ON)
Chiller 2 (ON) Primary Pumps
PP-1,2,3 (ON)
V-6 Open
V-3.1 Open
Makeup Valve = Open
FM (CHWS) CHWS
36 A S H R A E J O U R N A L a s h r a e . o r g D E C E M B E R 2 0 17
TECHNICAL FEATURE
Level
Sensor Chiller 1 (OFF)
Chiller 2 (OFF) Primary Pumps
PP-1,2,3 (OFF)
V-6 Closed
V-2 Open
V-4.1 MOD Secondary Pumps SP-1,2 (ON)
FM (Tank)
V-3.1 Open
Makeup Valve = Closed
FM (CHWS) CHWS
D E C E M B E R 2 0 17 a s h r a e . o r g A S H R A E J O U R N A L 37
TECHNICAL FEATURE
Level
Sensor Chiller 1 (ON)
Chiller 2 (ON) Primary Pumps
PP-1,2,3 (ON)
V-6 Open
V-3.1 Closed
Makeup Valve = Closed
FM (CHWS) CHWS
temperature sensors at the top levels of the tank as they After a short time period to allow the valves to
will begin to rise gradually. achieve their position, the two primary pumps are
At rare times during any given year during a started (the third primary pump is a failure standby),
discharge mode process, if the load required over- and after flow is proven, the two chillers are started
comes the ability of the tank’s ton-hours to sup- and operated to provide chilled water at a supply
ply the needs of the facility, the discharge mode setpoint of 42°F (5.6°C) to the tanks, on their time
will “run out of cold water.” This situation may schedule. The time schedule will continue to oper-
be caused by equipment malfunctions, overnight ate the chillers in charge mode until its time runs out
power outages, control system failures or just or until the tank temperature sensors terminate the
human error; in any case, at those times decision charge mode when they sense that the tank is fully
makers would need to weigh the costs of violating charged. The control program looks at tank sensors
the peak-time utility agreement, and incurring typically located at 1 ft (0.3 m) to 2 ft (0.6) vertical
a resultant penalty (if any) and start the chiller intervals in the tank to determine its capacity; when
mode, or wait out the loss of cold water available it determines that a) the time schedule has expired,
from the tank until it can be charged in the next or b) the tank temperature vertical immersion sen-
cycle. sors are at 42°F (5.6°C) throughout, it will decide the
tank is “full” and shut down charge mode. (Note: the
Plant Sequencing: Storage Tank Charge Mode BACS program ignores outlier tank sensors that may
In the charge mode (Figure 4), cold water is fed to the be defective or out of range, reading ±25°F [±13.9°C]
bottom of the tank and warm water is drawn from the from a base of 42°F [5.6°C].)
top of the tank. Figure 5 shows the internal piping of the There is a safeguard control algorithm programmed
tank; one entry pipe feeds the water upward to the top into the control logic that does not allow a charge
of the tank, and the other entry pipe feeds water down- mode to replay more than once, unless the TES system
ward to the bottom of the tank. Care must be taken to has undergone at least one mode change to discharge
ensure the maximum flow rates are designed correctly mode in between; this is to avoid over-cycling of the
and set up carefully by the TAB professional so the integ- charge mode too much in one day.
rity of the thermocline is maintained.
When the charge mode is started, there is a series of Lessons Learned
valves installed and positioned to force this situation This is a short list of some of the lessons learned from
as follows: V-1, V-2, V-5, V-6 are opened; V-3.1, V 4.1 are issues that were encountered during the commissioning
closed. of chilled water thermal energy storage systems.
38 A S H R A E J O U R N A L a s h r a e . o r g D E C E M B E R 2 0 17
TECHNICAL FEATURE
FIGURE 5 Internal piping of thermal storage tank with side entrance of supply and return piping. PHOTO 2 Entry pipes at even entry levels.
D E C E M B E R 2 0 17 a s h r a e . o r g A S H R A E J O U R N A L 39
TECHNICAL FEATURE
setting of the PRV may go unnoticed as a critical setup best practice for design engineers to locate these on their
process. However, for a thermal storage tank project, design drawings in the proper locations to ensure the
it became apparent that the over-pressurization of information they provide is the most accurate we can
the makeup chilled water system was causing a small get. Flow meters need to have the required straight pipe
incremental burst of water into the tank over time as before and after to achieve accurate readings; bypass
tank valves V-1 and 2 opened. This small incremental flow meters in short pipe segments need to not be not
burst of makeup water (that overcame the effects of back be one flow meter in the short bypass pipe but two flow
pressure relative to the height of the tank) eventually meters, one in the supply and one in the return. Then,
made its way to the tank overflow as a constant small math can be used to subtract the difference to get the
drip. That constant drip, over time, added up to a loss of bypass flow; specifying one flow meter in a short pipe
wasted water, including its associated water treatment. that is nonfunctional is not useful.
By setting the makeup water PRV setpoint at a value less Differential pressure transducers showing analog
than the height of the tank (calibrated in psi), this situ- pressure readings across the chiller barrels provide vital
ation was cured. This makes it vital to have a monitored information for monitoring and maintaining the integ-
water meter on the makeup water supply, and an alarm rity of the chilled water delivery systems of the thermal
control point that indicates when an overflow condition storage systems through their differing modes of opera-
is sensed at the overflow drain pipe. tion. Differential pressure helps troubleshoot chiller
Flow meters are a vital part of the thermal storage proj- flow problems as well as degrading of chiller barrel heat
ect; they give us vital information for both control and transfer due to a variety of tube fouling issues.
energy monitoring. The proper location for these meters As-builts? Record drawings? O&M documents?
is paramount for their accuracy and functionality. It is a Whatever they are named, relevant to the mechanical
systems, who checks them and who verifies that they are
correct and includes all the changes made in the field
during construction and fabrication? This is an impor-
tant question. Commissioning requires that the provi-
sion of these documents is facilitated by the commis-
sioning provider; but, who makes sure they are validated
and real for the benefit of the owner and end-user? The
Available in standard and commissioning provider needs to facilitate the valida-
tion of these vital documents so the owner has current
custom sizes, call or email us for
and accurate record documents and maintenance and
a quote today! operation information to properly maintain the facility
with their own staff, or provide them to outside repair
companies as needed.
Owner training helps ensure the systems provided
are turned over in such a way that the owner can oper-
ate and maintain them per the manufacturer’s rec-
ommended best practices and in their most efficient
manner. The commissioning provider should facilitate
and ensure that the training sessions are planned
with a comprehensive schedule of topics, agenda, and
published times, populated with all of the appropriate
owner’s staff and personnel, and make sure the trainers
are credentialed and knowledgeable about the subject
Visit us in booth #6616 matter they are training about.
www.rotorsource.com Thermal storage often involves mandates from the
utility not to operate large kW demand equipment such
as chillers and pumps during peak times. Sometimes The experience gained and lessons learned that were
during normal daily business, third-party service accumulated over the five-year span of these individual
mechanics, and even in-house employees who are not projects during the commissioning process provided
knowledgeable of these policies, will sometimes start valuable information that contributed to continuous
up the equipment to provide service. When this hap- improvement and quality of the delivery of the HVAC
pens, the peak kW demand rate agreement is violated and TES systems at these facilities. Information and
for the entire month and can result in a penalty. Making feedback provided to the designers from the commis-
facility managers aware and knowledgeable of these sioning documentation and effective post-occupancy
policies and penalties is vital. Providing signage at all communications after each construction cycle led to
major equipment locations can help prevent this from improved techniques, sequences and designs each time.
happening. Precommissioning tasks were vital when used on these
The EMS/BACS should monitor and record the tem- TES projects to identify early problems and issues that
perature and energy operational characteristics of the would potentially impact a timely substantial comple-
thermal energy storage systems, both at the chiller plant tion. A good example was that precommissioning could
and at the tank. A Btu energy meter uses the tank flow troubleshoot incorrect piping of the thermal energy
meter and tank supply and leaving temperature sen- storage tank by scrutinizing the fabrication/installa-
sors to calculate ton-hours produced during the charge tion field drawings, and by pre-functionally testing
and discharge modes. These values are displayed on the the sequence of operation on the completed piping/
graphic display, and trended. It should have the abil- hydronic systems once they were initially installed.
ity to alarm the owner if any failures happen overnight When problems or deficiencies were found, they could
or on the weekend so the owner can decide what they be reported and repaired early with less impact on the
need to do to overcome the failure or problems long completion schedule.
before they need the tank’s chilled water deliverable. It was typical to discover issues during the functional
These Btu meters can inform the owner when the use of performance testing phase of the commissioning pro-
the chillers and thermal storage systems are operating cess. The resolution of these issues, and the interaction
efficiently. during the training and close-out process with the com-
Because thermal storage projects make chilled water missioning team members, ensured that all the TES
at night and on weekends, noise from the chiller plant commissioned equipment, systems and assemblies were
can sometimes become an issue if the building is located furnished, installed and able to be operated to meet the
near a residential neighborhood. Consideration should OPR and design documents. The training and presenta-
be given to specifying lower noise emitting equipment, tion of accurate systems manuals to the owner’s O&M
and to perform sound tests as a part of the commission- staff ensured that the facilities were self-sustaining dur-
ing final performance testing protocols to document ing and after the warranty period.
noise levels at the plant and property lines. The commissioning process described here for the
We found a few VFDs operating their mechanical HVAC and TES systems was used to ensure that the
equipment at a greater speed than 60 Hz to make their designers and contractors were fully accountable for
specified performance; while this may be within the the quantity and quality of their work. The commission-
motor’s capacity, it is a not a best practice to burden the ing team used established means, methods and tools
downstream devices with the additional stresses that the to execute, document and test the projects’ specified
additional speed creates. sequences and provided twhe equipment and systems so
it achieved the goals and objectives of the OPR through-
Conclusions out the delivery of the project.
Chilled water thermal energy storage systems continue
to be an effective method to achieve the goals and objec- References
tives of providing efficient and cost-effective cooling to 1. 2016 ASHRAE Handbook—HVAC Systems and Equipment, Chap. 13,
“Hydronic Heating and Cooling” and Chap. 51, “Thermal Storage.”
their facilities. This is especially apparent when util- 2. ANSI/ASHRAE/IES Standard 202-2013, Commissioning Process for
ity incentives and special time-of-use rates were used. Buildings and Systems.”
D E C E M B E R 2 0 17 a s h r a e . o r g A S H R A E J O U R N A L 41