Sei sulla pagina 1di 10

TECHNICAL FEATURE

This article was published in ASHRAE Journal, December 2017. Copyright 2017 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed
electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal, visit www.ashrae.org.

Commissioning Chilled
Water TES Tank Systems
BY ROSS MONTGOMERY, P.E., BEAP, BEMP, CPMP, HBDP, FELLOW ASHRAE

Chilled water thermal energy storage systems (TES) have been used successfully in
district cooling systems for decades. According to the 2016 ASHRAE Handbook—HVAC
Systems and Equipment,1 thermal storage systems “remove heat from or add heat to a
storage medium for use at another time.” These TES systems can come in the form of
ice or cold-water storage. This article focuses on the commissioning of systems and the
sequence of operations for individual school project chiller plants and cold water ther-
mal energy storage systems using a large storage tank (Photo 1), performed on a large
group of individual educational facilities over the course of 2012 – 17. The sequences and
commissioning tasks have been refined over time to improve the final deliverables and
performance to the facilities.
The capacity design of the TES system used is tai- in the early 1980s, when ASHRAE started to develop
lored to the individual needs of the facility itself. In its Guideline 0 and Guideline 1 on commissioning, and
general, an example design for one school would be later its ANSI/ASHRAE/IES Standard 202, Commissioning
an air-cooled chiller plant consisting of two 400 ton Process for Buildings and Systems, buildings can now be pro-
(1407 kW) chillers operating at 42°F (5.6°C) to 56°F fessionally commissioned by third-party independent
(13.3°C) supply/return temperatures, chiller and charge commissioning providers.
primary flows at 1,370 gpm (86 L/s), discharge primary Benefits of cold-water storage include:
flows at 1,500 gpm (95 L/s) and secondary flows up to •• Shifting loads and kW demand from peak- to non-
3,000 gpm (189 L/s). The thermal storage tank capacity peak times (in both summer and winter) allow for par-
is 4,800 ton-hours (16 880 kWh) and holds 600,000 gal- ticipating utility incentive payments and discounts and
lons (2.3 million L) of treated water. In some projects, current utility rebates, relative to thermal water storage;
water-cooled chillers with cooling towers were also •• Discounts and rebates from participating utility(s)
used. reduce costs of new equipment purchases;
Building commissioning in its early days was per- •• If a time-of-use (TOU) rate is available from the
formed by its consulting engineer designer and their utility company, energy cost savings can be obtained by
staff as a part of continuing design services. Starting operating the chiller equipment in a central plant more

Ross D. Montgomery, P.E., is president and owner of Quality Systems and Technology Inc., a commissioning provider company based out of Parrish, Fla.

32 A S H R A E J O U R N A L   a s h r a e . o r g   D E C E M B E R 2 0 17
TECHNICAL FEATURE 

during the off-peak periods, and reducing the energy PHOTO 1   Typical thermal storage tank.
consumption during peak periods;
•• Increased energy efficiency of chiller equipment by
operating them at night in cooler ambient conditions
(cooler nighttime condensing water temperatures);
•• Reduced sizes of required HVAC and electric equip-

PHOTO CREDIT: COLLIER COUNTY (Fla.) PUBLIC SCHOOLS


ment/devices in some cases;
•• Increased operating flexibility and scheduling;
•• Backup capabilities and extra capacity to the facility
in case of equipment malfunction or failure;
•• Assistance to integrate renewables into systems; and
•• Dual-purpose fire protection water supply.

Construction Commissioning Process


Commissioning can begin at predesign, design, or
during construction. This article will focus on the efforts protocols for the field testing phase, and helps familiar-
taken during construction commissioning. At the begin- ize the commissioning provider with the project opera-
ning of any construction commissioning project, it is tions and personnel.
vital to make sure the owner’s project requirements Before the actual functional performance testing
(OPR), in the case of new construction, or current facil- begins, ensure all start-ups, check-out, testing, adjust-
ity requirements (CFR), in the case of existing buildings, ing and balancing, and contractor punch list repairs
are monitored and followed while performing the stan- have been made. On major equipment, it is vital that
dardized commissioning tasks for new construction, as manufacturer-certified start-up representatives per-
outlined and discussed in detail in ANSI/ASHRAE/IES form the start-up, calibration, and setup per the design
Standard 202-2013.2 Those steps can be summarized as: parameters. Precommissioning checklists are required
•• Initiating the commissioning process; to be filled out and signed by the contractor to ensure
•• Writing the commissioning plan; that compliance with the procedures and commission-
•• Reviewing the design and construction documents; ing process is met.
•• Creating and working with the commissioning Functional performance testing for these systems is
team; subdivided into the following sections and subsections:
•• Performing commissioning submittal review;
•• Performing construction observation and testing; Thermal Energy Storage Tank
•• Performing the functional performance testing; •• Checking the exterior of the tank area for security,
•• Maintaining the issues documentation and resolu- a fence, a ladder, overflow drain, piping attributes, con-
tion logs; nections, and supports installed properly, etc.
•• Observing the training process including using •• BAS control panels installed correctly with fiber op-
the systems manual and record documents as training tic communication (because of surge protection require-
materials; ments), supported for wind damage, conduits installed
•• Monitoring post occupancy operations; and with proper supports and wiring, etc.
•• Writing the final commissioning report. •• Internal tank temperature array installed and
Special attention should be paid to the following items. reading (typically one to two sensors per foot of vertical
The commissioning plan is a good opportunity to height).
inform the commissioning team about what the expec- •• Tank level sensor installed and operating.
tations, goals and objectives are for the project; and, •• Tank fill valve installed and operating to maintain
reviewing the submittals and making site visits during proper fill level and not overflowing.
the construction phase near completion allows for more •• Check the tank control valves/actuators that feed
accurately preparing functional performance testing cold and warm water to the tank. Make sure valves are

D E C E M B E R 2 0 17   a s h r a e . o r g   A S H R A E J O U R N A L 33
TECHNICAL FEATURE 

able to close tight and not leak-by. their automatic condition.


•• Signage is on all equipment and control devices. •• Test failure and switchover modes for pumps and
•• Verify expectations of design parameters, and re- VFDs, and the manual bypass for VFDs.
port discrepancies on issues log. •• Ensure that record drawing piping and flow dia-
grams are displayed in the chiller plant for use by facility
Chilled Water Plant personnel.
•• Request and review start-up reports and hydronic •• Test the complete chiller mode process, which
test reports for all piping and major equipment. includes the timing of the valves opening and closing,
•• Chiller is programmed with correct setup informa- valve positions, pumps/VFDs turning on and off, VFD
tion, setpoints, and start-up completed by the manufac- speeds and chillers energizing/staging on and off.
turer’s technical representative. •• Test the complete discharge mode process, which
•• Chiller coils and external parts are undamaged and includes the timing of the valves opening and closing,
in operational condition. valve positions, pumps/VFDs turning on and off, VFD
•• Cooling tower components and safety devices (vi- speeds and chillers energizing/staging on and off.
bration, overflow, etc.) are installed and operating. •• Test the complete charge mode process, which
•• Ensure all chiller plant components and piping are includes the timing of the valves opening and closing,
identified, supported, insulated and labeled per the valve positions, pumps/VFDs turning on and off, VFD
design and record documents. speeds and chillers energizing/staging on and off.
•• Inspect and verify that flow switch and differential •• Test the complete off-mode process, which brings
pressure transducers across chiller barrels are installed the facility to a complete stop and verifies that all devices
and operating. stop and open/close to their off-mode positions.
•• Test chiller-related temperatures and pressure read- •• Verify expectations of design parameters, and re-
ings with testing, adjusting and balancing (TAB) contrac- port discrepancies on the issues log.
tor gauges and local gauges to ensure they all agree.
•• Inspect and verify ambient shutdown of chiller Building Automation and Control Systems (BACS)
systems. •• Panels are completely installed per the design docu-
•• Test manual and automatic chiller plant shutdown ments and communicating on the network; controllers
processes. If emergency power sources are used, test on and control devices included in the design are installed
generator. in the project.
•• Verify proper start-up and TAB have been complet- •• Licensing agreements for all proprietary and intel-
ed on chiller plant for included VFDs, condenser fans, lectual properties and software required to operate the
cooling towers, chiller and condenser flows and differ- control systems, subsystems and integrated subsystems
ential pressures, setpoints, etc. are installed and assigned to the owner.
•• Verify proper start-up and TAB have been complet- •• Integrations to all associated ancillary equipment
ed on primary and secondary pumps, condenser pumps, such as chillers, VFDs, boilers, cooling towers, DX sys-
VFD operations, VFD minimum and maximum speeds tems, etc., are installed and operating seamlessly.
and limits, pump flows and differential pressures, set- •• Graphics are complete, impressive, populated with
points, building differential pressure readings, etc. the appropriate points and working.
•• Test and record flow meter readings and compare •• Time schedules are programmed and operating
against TAB readings and design requirements. equipment and building systems as designed.
•• Inspect and verify that makeup water systems, •• Control panels, control devices, conduit, wiring,
pressure relief, air bleeds and vents, pot feeder, chemi- cables and J-boxes are identified, supported and fas-
cal treatment system, and expansion tank devices are tened securely and labeled as depicted on the design and
installed and operating. record drawings.
•• Inspect and verify that control systems are installed, •• Point-to-point check out, calibrations and verifica-
programmed, checked-out, calibrated, and operating tions are made to ensure parts and devices are provided
the systems per the design document requirements in per the design documents. Sequence of operations are

34 A S H R A E J O U R N A L   a s h r a e . o r g   D E C E M B E R 2 0 17
TECHNICAL FEATURE 

verified as programmed per the design documents. chiller operation, but the projects depicted in this article
•• Verify expectations of design parameters and result- do not use this option in their design and OPR. The intent
ing building and equipment performance. of this example sequence is to suggest approximate val-
Making sure that the record documents and as-builts ues of variables that can be fine-tuned, or adjusted in the
are representative of the installation is vital. The train- field, under specific job to job conditions.
ing of the owner’s staff should use the most up-to-date
operation and maintenance manuals, as-builts, systems Plant Sequencing: Chiller Mode
manuals and record documents delivered by creden- The chiller mode is a straightforward primary (PP-1, 2,
tialed and experienced instructors for the mechanical 3)/secondary (SP-1, 2) with valved bypass (V 4.1) chiller
equipment and control systems. plant using state-of-the-art variable frequency drive
(VFD) pumping systems on both the primary and sec-
Utility Incentive Programs for TES Systems ondary pumps.
The utility and the owner have agreed to a time-of-use The chiller mode executes a primary-secondary design
(TOU) tariff payment energy rate plan that provides for scenario for the facility during normal school session
cooling kW demand load shifts of the TES system. The and administration working hours.
sequence of operation follows the winter and summer In the chiller mode, the tank is isolated, and the plant
utility modes for demand management, and its control operates as a primary-secondary chilled water plant.
is programmed into controllers so owner and utility can When the chiller mode is started, there is a series of
both benefit from an agreement to share advantages valves installed and positioned to force this situation as
from the program offered by the utility. In the case of follows relative to Figure 1: V-1, V-2 are closed; V-5, V-6,
this Florida utility, it offers a rebate of approximately V-3.1 are opened; V 4.1 can be modulated.
$625/kW of demand that is shifted from peak time to the The control system controls the operation of the chiller
non-peak time, as first estimated at the time of design, plant based on an optimal start/stop program or manual
and then proven by functional performance testing by command from the operator’s station. Chillers and their
the commissioning provider at the time of start-up and primary/secondary pumps are rotated weekly via lead-
commissioning. lag control and rotation.
The winter and summer schedule for this utility On a start command from the BACS, the chilled water
follows: plant shall be enabled and its corresponding secondary
•• On-Peak: Nov. 1 through March 31: Monday through loop campus chilled water pump starts. After campus
Friday from 6 a.m. to 10 a.m. and 6 p.m. to 10 p.m., loop flow is proven via the differential pressure trans-
excluding Thanksgiving Day, Christmas Day and New mitters, the lead chiller two-way isolation valve shall
Year’s Day. open. After a two-minute delay, the chilled water pri-
•• On-Peak: April 1 through Oct. 31: Monday through mary pump is energized. After flow is proven through
Friday from 12 p.m. to 9 p.m., excluding Memorial Day, the chiller flow switch, the lead chiller is enabled.
Independence Day and Labor Day. While the lead chiller operates, the bypass valve can be
•• Off-Peak: all other hours. modulated to ensure that the maximum flow rate to
one chiller is not exceeded. The lead chiller continues to
Example of Sequence of Operation operate until the return water temperature rises above
Commissioning the operation of the building chilled 56°F (13.3°C) and the lead chiller is loaded above 80% for
water production systems includes the chiller mode, more than 10 minutes. If this condition is met, the lag
which services the building directly, and then the charge chiller will start (the bypass valve will then close). Both
and discharge modes, which involve the use of a thermal chillers will continue to operate until the return water
storage tank. In some designs, it is possible to use the temperature reaches 50°F (10°C) for more than 15 min-
charge, discharge and chiller modes simultaneously in utes, when the lag chiller will then be stopped.
times of emergency or special conditions. Some project If the lead chiller fails to start, the next scheduled
designs involve shifting kW demand and loads by using lag chiller is enabled using the same sequence, and an
the thermal storage system output in conjunction with the alarm will be logged.

D E C E M B E R 2 0 17   a s h r a e . o r g   A S H R A E J O U R N A L 35
TECHNICAL FEATURE 

FIGURE 1   Chiller mode.

V-1 Closed
Tank; 600,000 Gallons V-5 Open
4,800 Ton-Hours
FM (CH-1)

Level
Sensor Chiller 1 (ON)
Chiller 2 (ON) Primary Pumps
PP-1,2,3 (ON)
V-6 Open

DIAGRAM CREDITS: WWW.SMARTDRAW.COM


FM (CH-2) FM (Bypass) CHWR
V-2 Closed
V-4.1 MOD Secondary Pumps SP-1,2 (ON)
FM (Tank)

V-3.1 Open
Makeup Valve = Open
FM (CHWS) CHWS

The chiller primary pump speed shall be controlled algorithm:


by operating the primary pump VFD between a range •• Increase pump speed as required by increasing
of 50 Hz to 60 Hz, which corresponds within the pressure setpoint in increments of 0.25 psi (1.7 kPa),
acceptable chiller flow rate, as verified during the TAB whenever any AHU control valve is 100% open;
process, with minimum speed settings set at the VFD •• Continue to check system every 15 minutes; and
parameters. This plant shows a third primary chilled •• As AHU valves begin to close, the reverse shall occur.
water pump, which acts as a standby pump that auto- The commissioning of the makeup water system
matically engages upon a primary Pump-1 or 2 failure. depends on the design that it takes on; sometimes the
Chiller differential pressure transmitters verify that incoming 40 psi (276 kPa) to 75 psi (517 kPa) street pres-
flows do not drop below the minimum flows for each sure has one separate part of the main leg that feeds
chiller. directly into an automatic tank fill valve (preferred),
When primary loop flow exceeds secondary loop flow, a and others have the entire main after the pressure-relief
bidirectional flow meter in its decoupler piping indicates valve (PRV) splitting off into branch legs going to the
forward (positive) flow through the decoupler piping. tank, and then separately going into the chilled water
When secondary loop flow exceeds primary loop flow, a system; design should include the provisions of pressure
bidirectional flow meter in its decoupler piping indicates gauges and ports for the visual and functional tests. A
reverse (negative) flow through the decoupler piping. makeup water control valve that provides makeup water
The secondary pump is controlled via its variable to the chilled water system is only allowed to open dur-
speed drive (VFD) as required to maintain the maxi- ing chiller mode. In all other modes, the valve is com-
mum building system water differential pressure set- manded closed. A similar makeup control valve can be
point at 18 psi (124 kPa); differential pressure sensor(s) provided that feeds the thermal storage tank, which can
are located near the end of the piping loop. The second- be regulated during certain modes. However, a direct
ary pumps are operated on a lead-lag basis, and their feed is acceptable as well. The tank feed pressure is typi-
changeover/rotation from lead to lag is programmed to cally left at city water line pressure.
be changed weekly. If the lead pump fails, the lag pump Also vital is inspecting and documenting the expan-
will start, and an alarm is generated if failure conditions sion tank and its operation; design should include
occur. In some projects, dual VFDs were used, which providing pressure gauges and ports for the visual and
automatically switch to the alternate VFD upon a fault recording of its operating parameters. Remembering
condition. that water is not a compressible fluid, the expansion or
The automatically switched secondary pump con- compression tank serves both thermal and hydraulic
trol loop setpoint will reset based on the following functions. Its thermal function allows the volumetric

36 A S H R A E J O U R N A L   a s h r a e . o r g   D E C E M B E R 2 0 17
TECHNICAL FEATURE 

expansion of its water to expand/contract on tempera- FIGURE 2   Thermocline example.


ture change. Its hydraulic function is to act as a single Stratified Tank
reference pressure point in the system. Typically, the
expansion tank is supplied with a pre-charge of 12 psi Warm
60°F
(83 kPa), but depending on the size (height) of the build-
ing, and height of the thermal storage tank, this “pre-
Thermocline
charge” may need adjustment; the design parameters
should include the settings for the makeup water system
that can be used to perform these functional perfor-
Cold
mance tests.

CREDIT: U.S. DOE


40°F

Plant Sequencing: Storage Tank Discharge Mode (Full Shift)


In the discharge mode of the storage tank, cold water
is drawn from the bottom of the tank, and warm water be slow-acting to ensure that the thermocline is not
is returned to the top of the tank, at the design flow disrupted. The chillers and their primary pumps are
rate of the diffusers (low enough not to interrupt the turned off.
thermocline). After a short time period to allow the valves to achieve
The horizontal thermocline (boundary layer between their position, the lead secondary pump is started, and
the upper and lower regions of the tank), Figure 2, devel- the building is provided cooling per its facility time
ops in the tank because of the carefully engineered flow schedule. The lag secondary pump shall cycle on as
rates, diffuser and tank design such that as the water needed to maintain its differential pressure setpoint.
flows in and out of the tank, and the temperatures inside A level sensor located at the top of the tank monitors
the tank do not mix and remain one relative tempera- the water level of the tank, and a simple float valve con-
ture on each side of the thermocline. nected to city water pressure maintains a prescribed
The discharge mode is activated during the period level to keep the water levels above the top manifolds of
of time dictated by the TOU utility rate. When the the internal piping and top diffuser. Alarms should be
discharge mode is started, there is a series of valves generated by the BACS systems if the tank level is out of
installed and positioned to force this situation as follows its normal operating range.
relative to Figure 3: Valves V-1, V-2, V-3.1 are opened; V As the tank discharges its load to the facility, the effects
4.1 can modulate; V-5 and V-6 are closed. Valves should of the thermocline can be seen by the values of the

FIGURE 3   Discharge mode.

V-1 Open V-5 Closed


Tank; 600,000 Gallons
4,800 Ton-Hours FM (CH-1)

Level
Sensor Chiller 1 (OFF)
Chiller 2 (OFF) Primary Pumps
PP-1,2,3 (OFF)
V-6 Closed

FM (CH-2) FM (Bypass) CHWR


DIAGRAM CREDITS: WWW.SMARTDRAW.COM

V-2 Open
V-4.1 MOD Secondary Pumps SP-1,2 (ON)
FM (Tank)

V-3.1 Open
Makeup Valve = Closed
FM (CHWS) CHWS

D E C E M B E R 2 0 17   a s h r a e . o r g   A S H R A E J O U R N A L 37
TECHNICAL FEATURE 

FIGURE 4   Charge mode.

V-1 Open V-5 Open


Tank; 600,000 Gallons
4,800 Ton-Hours FM (CH-1)

Level
Sensor Chiller 1 (ON)
Chiller 2 (ON) Primary Pumps
PP-1,2,3 (ON)
V-6 Open

DIAGRAM CREDITS: WWW.SMARTDRAW.COM


FM (CH-2) FM (Bypass) CHWR
V-2 Open V-4.1 Closed
Secondary Pumps SP-1,2 (OFF)
FM (Tank)

V-3.1 Closed
Makeup Valve = Closed
FM (CHWS) CHWS

temperature sensors at the top levels of the tank as they After a short time period to allow the valves to
will begin to rise gradually. achieve their position, the two primary pumps are
At rare times during any given year during a started (the third primary pump is a failure standby),
discharge mode process, if the load required over- and after flow is proven, the two chillers are started
comes the ability of the tank’s ton-hours to sup- and operated to provide chilled water at a supply
ply the needs of the facility, the discharge mode setpoint of 42°F (5.6°C) to the tanks, on their time
will “run out of cold water.” This situation may schedule. The time schedule will continue to oper-
be caused by equipment malfunctions, overnight ate the chillers in charge mode until its time runs out
power outages, control system failures or just or until the tank temperature sensors terminate the
human error; in any case, at those times decision charge mode when they sense that the tank is fully
makers would need to weigh the costs of violating charged. The control program looks at tank sensors
the peak-time utility agreement, and incurring typically located at 1 ft (0.3 m) to 2 ft (0.6) vertical
a resultant penalty (if any) and start the chiller intervals in the tank to determine its capacity; when
mode, or wait out the loss of cold water available it determines that a) the time schedule has expired,
from the tank until it can be charged in the next or b) the tank temperature vertical immersion sen-
cycle. sors are at 42°F (5.6°C) throughout, it will decide the
tank is “full” and shut down charge mode. (Note: the
Plant Sequencing: Storage Tank Charge Mode BACS program ignores outlier tank sensors that may
In the charge mode (Figure 4), cold water is fed to the be defective or out of range, reading ±25°F [±13.9°C]
bottom of the tank and warm water is drawn from the from a base of 42°F [5.6°C].)
top of the tank. Figure 5 shows the internal piping of the There is a safeguard control algorithm programmed
tank; one entry pipe feeds the water upward to the top into the control logic that does not allow a charge
of the tank, and the other entry pipe feeds water down- mode to replay more than once, unless the TES system
ward to the bottom of the tank. Care must be taken to has undergone at least one mode change to discharge
ensure the maximum flow rates are designed correctly mode in between; this is to avoid over-cycling of the
and set up carefully by the TAB professional so the integ- charge mode too much in one day.
rity of the thermocline is maintained.
When the charge mode is started, there is a series of Lessons Learned
valves installed and positioned to force this situation This is a short list of some of the lessons learned from
as follows: V-1, V-2, V-5, V-6 are opened; V-3.1, V 4.1 are issues that were encountered during the commissioning
closed. of chilled water thermal energy storage systems.

38 A S H R A E J O U R N A L   a s h r a e . o r g   D E C E M B E R 2 0 17
TECHNICAL FEATURE 

FIGURE 5  Internal piping of thermal storage tank with side entrance of supply and return piping. PHOTO 2   Entry pipes at even entry levels.

PHOTO CREDIT: COLLIER COUNTY (Fla.) PUBLIC SCHOOLS


CREDIT: CROM CORPORATION
PHOTO 3   Entry pipes at offset entry levels.

PHOTO CREDIT: COLLIER COUNTY (Fla.) PUBLIC SCHOOLS


During installation of the tank, language translation problems,
we have encountered on a few occa- the tank design/construction was
sions that the contractor had piped done by one designer/contractor,
the tank backwards, in that the two while the HVAC was done by a dif-
pipes going to the tank were piped ferent designer/contractor, and the
in the reverse order than required. integration of the two designs were
It was an easy error to make, sometimes not well coordinated.
because the language the tank Many times, equipment arrives
people use in their drawings and from the factory and is not always of this problem. Another idea to
the language that HVAC designers configured as illustrated on a typi- help make the tank demarcation
use is different, making it confus- cal generic piping schematic, and clearer is to mark the top of the
ing. “Supply and return” or “inlet the actual factory-installed piping tank piping and valve V-1 as “warm
and outlet” demarcations take on or markings are not checked in the inlet/outlet,” and the bottom of the
different meanings depending on field before it is final-connected and tank piping and valve V-2 as “cold
if you are talking about charge or started up. inlet/outlet.” In any case, when this
discharge modes, so it is an easy In later tank designs, the owner “backwards piping” happens, the
mistake to make. paid significant extra money to have tank will not work, in that it will
Also, a disconnect sometimes the tank designer offset the pipe not stratify correctly, and the pipes
existed between the office of entering and leaving profiles (as must be reversed to make the overall
the designer and contractor and shown in Photos 2 and 3). This cre- system work most effectively and
their respective field operations. ated the need for additional/unique as-designed.
Sometimes, the originally issued infrastructure on the interior of the Another issue found was the
design and final approved submittal tanks for supporting the incoming chronic overflow of the tank water
documents, and the later-developed pipes that were located at different level over time, which ended up
field working and installation draw- elevations that explicitly demon- being caused by incorrect setting
ings being used for actual fabrica- strate which pipe goes to the top of the pressure-relief valve (PRV)
tion, were two entirely different- of the tank and which goes to the for the makeup of the chilled water
looking “level of detail” documents. bottom of the tank; this modifica- system. Typically, in a normal chilled
Compounding the jargon and tion helped reduce the occurrence water plant project, the pressure

D E C E M B E R 2 0 17   a s h r a e . o r g   A S H R A E J O U R N A L 39
TECHNICAL FEATURE

setting of the PRV may go unnoticed as a critical setup best practice for design engineers to locate these on their
process. However, for a thermal storage tank project, design drawings in the proper locations to ensure the
it became apparent that the over-pressurization of information they provide is the most accurate we can
the makeup chilled water system was causing a small get. Flow meters need to have the required straight pipe
incremental burst of water into the tank over time as before and after to achieve accurate readings; bypass
tank valves V-1 and 2 opened. This small incremental flow meters in short pipe segments need to not be not
burst of makeup water (that overcame the effects of back be one flow meter in the short bypass pipe but two flow
pressure relative to the height of the tank) eventually meters, one in the supply and one in the return. Then,
made its way to the tank overflow as a constant small math can be used to subtract the difference to get the
drip. That constant drip, over time, added up to a loss of bypass flow; specifying one flow meter in a short pipe
wasted water, including its associated water treatment. that is nonfunctional is not useful.
By setting the makeup water PRV setpoint at a value less Differential pressure transducers showing analog
than the height of the tank (calibrated in psi), this situ- pressure readings across the chiller barrels provide vital
ation was cured. This makes it vital to have a monitored information for monitoring and maintaining the integ-
water meter on the makeup water supply, and an alarm rity of the chilled water delivery systems of the thermal
control point that indicates when an overflow condition storage systems through their differing modes of opera-
is sensed at the overflow drain pipe. tion. Differential pressure helps troubleshoot chiller
Flow meters are a vital part of the thermal storage proj- flow problems as well as degrading of chiller barrel heat
ect; they give us vital information for both control and transfer due to a variety of tube fouling issues.
energy monitoring. The proper location for these meters As-builts? Record drawings? O&M documents?
is paramount for their accuracy and functionality. It is a Whatever they are named, relevant to the mechanical
systems, who checks them and who verifies that they are
correct and includes all the changes made in the field
during construction and fabrication? This is an impor-
tant question. Commissioning requires that the provi-
sion of these documents is facilitated by the commis-
sioning provider; but, who makes sure they are validated
and real for the benefit of the owner and end-user? The
Available in standard and commissioning provider needs to facilitate the valida-
tion of these vital documents so the owner has current
custom sizes, call or email us for
and accurate record documents and maintenance and
a quote today! operation information to properly maintain the facility
with their own staff, or provide them to outside repair
companies as needed.
Owner training helps ensure the systems provided
are turned over in such a way that the owner can oper-
ate and maintain them per the manufacturer’s rec-
ommended best practices and in their most efficient
manner. The commissioning provider should facilitate
and ensure that the training sessions are planned
with a comprehensive schedule of topics, agenda, and
published times, populated with all of the appropriate
owner’s staff and personnel, and make sure the trainers
are credentialed and knowledgeable about the subject
Visit us in booth #6616 matter they are training about.
www.rotorsource.com Thermal storage often involves mandates from the
utility not to operate large kW demand equipment such

40 ASHRAE JOURNAL ashrae.org D E C E M B E R 2 0 17


TECHNICAL FEATURE 

as chillers and pumps during peak times. Sometimes The experience gained and lessons learned that were
during normal daily business, third-party service accumulated over the five-year span of these individual
mechanics, and even in-house employees who are not projects during the commissioning process provided
knowledgeable of these policies, will sometimes start valuable information that contributed to continuous
up the equipment to provide service. When this hap- improvement and quality of the delivery of the HVAC
pens, the peak kW demand rate agreement is violated and TES systems at these facilities. Information and
for the entire month and can result in a penalty. Making feedback provided to the designers from the commis-
facility managers aware and knowledgeable of these sioning documentation and effective post-occupancy
policies and penalties is vital. Providing signage at all communications after each construction cycle led to
major equipment locations can help prevent this from improved techniques, sequences and designs each time.
happening. Precommissioning tasks were vital when used on these
The EMS/BACS should monitor and record the tem- TES projects to identify early problems and issues that
perature and energy operational characteristics of the would potentially impact a timely substantial comple-
thermal energy storage systems, both at the chiller plant tion. A good example was that precommissioning could
and at the tank. A Btu energy meter uses the tank flow troubleshoot incorrect piping of the thermal energy
meter and tank supply and leaving temperature sen- storage tank by scrutinizing the fabrication/installa-
sors to calculate ton-hours produced during the charge tion field drawings, and by pre-functionally testing
and discharge modes. These values are displayed on the the sequence of operation on the completed piping/
graphic display, and trended. It should have the abil- hydronic systems once they were initially installed.
ity to alarm the owner if any failures happen overnight When problems or deficiencies were found, they could
or on the weekend so the owner can decide what they be reported and repaired early with less impact on the
need to do to overcome the failure or problems long completion schedule.
before they need the tank’s chilled water deliverable. It was typical to discover issues during the functional
These Btu meters can inform the owner when the use of performance testing phase of the commissioning pro-
the chillers and thermal storage systems are operating cess. The resolution of these issues, and the interaction
efficiently. during the training and close-out process with the com-
Because thermal storage projects make chilled water missioning team members, ensured that all the TES
at night and on weekends, noise from the chiller plant commissioned equipment, systems and assemblies were
can sometimes become an issue if the building is located furnished, installed and able to be operated to meet the
near a residential neighborhood. Consideration should OPR and design documents. The training and presenta-
be given to specifying lower noise emitting equipment, tion of accurate systems manuals to the owner’s O&M
and to perform sound tests as a part of the commission- staff ensured that the facilities were self-sustaining dur-
ing final performance testing protocols to document ing and after the warranty period.
noise levels at the plant and property lines. The commissioning process described here for the
We found a few VFDs operating their mechanical HVAC and TES systems was used to ensure that the
equipment at a greater speed than 60 Hz to make their designers and contractors were fully accountable for
specified performance; while this may be within the the quantity and quality of their work. The commission-
motor’s capacity, it is a not a best practice to burden the ing team used established means, methods and tools
downstream devices with the additional stresses that the to execute, document and test the projects’ specified
additional speed creates. sequences and provided twhe equipment and systems so
it achieved the goals and objectives of the OPR through-
Conclusions out the delivery of the project.
Chilled water thermal energy storage systems continue
to be an effective method to achieve the goals and objec- References
tives of providing efficient and cost-effective cooling to 1.  2016 ASHRAE Handbook—HVAC Systems and Equipment, Chap. 13,
“Hydronic Heating and Cooling” and Chap. 51, “Thermal Storage.”
their facilities. This is especially apparent when util- 2. ANSI/ASHRAE/IES Standard 202-2013, Commissioning Process for
ity incentives and special time-of-use rates were used. Buildings and Systems.”

D E C E M B E R 2 0 17   a s h r a e . o r g   A S H R A E J O U R N A L 41

Potrebbero piacerti anche