RYG
SCHEDULED ACTUAL / EXPECTED STATUS
STATUS
PROCUREMENT LONG LEAD/CRITICAL ITEMS DELIVERY DELIVERY
Paint for Façade (Dulux Acratex) 30th Sep’16 27th Oct’16 Delivered
Steel Structures for Banquet Hall 22nd Oct’16 20th Jan’17 Delivery to site on 10th Feb’17
For Skylight Steel Structure: ETA 22nd
March’17. Expected delivery 31st Mar’17
Last delivery at 02nd May’17. Delivered
Steel Structures for Meeting Rooms 27th Jan’17 17th Feb’17 Arrived on site at 21st Feb’17.
Last Container to Site at 06th May’17. Delivered
Lift Equipment – First Shipment (Service Lifts) 1st Mar’07 22nd Feb’17 Shipped on 4th Feb. ETA 20th Feb’17
Revised: Delivered to site. Delivered
Lift Equipment – Second Shipment 1st Mar’07 31st Mar’17 PL (Confirmed to ship out on 31st
Mar’17)
Arrived at port on 5th Apr’17.
Custom clearance.
Arriving at site on 26th Apr’17. Delivered
Transformers & Switch Gear (5.5 Month lead-time) 25th Apr’17 15th August’17 Pending confirmation letter by YESC for
33kV – 0.4kV.
YESC approval acquired.
FAT completed.
Generators 09th Mar’17 03rd Apr’17 Custom Clearance in process. Delivered
Delivered at 1st Apr’17
Bus-duct 15th Nov’16 30th Apr’17 Shipped out on 18th May’17. Delivered
Arrived to port. Custom Clearance in
Process.
Feeders Feb’17 Depend on YESC.
Approval acquired. Road damage fees
will be paid shortly.
APQ to start work soonest possible.
Diesel Storage Tank Feb’17 22nd Mar’17 Delivered to site. Diesel
Storage
Permit to be
applied asap.
HT panels/cubical 25th Apr’17 Same as Transformers
LV main MSB (MSB Total) 13th Jan’17 14th March’17 *Waiting MIC Permit. Delivered
Delivered to site.
PROJECTED /
SCHEDULED PERCENT
ACTUAL START ACTUAL STATUS
COMPLETION COMPLETE
ACTIVITIES ONGOING FROM PREVIOUS WEEK COMPLETION
SL 1, 2 Structure Work 10th Mar’17 10th Apr’17 24th Jun’17> 4th Mary and
July’17 > 10th July > Gareth will
17th July’17 inspect
98% tomorrow
PL4 Structure – including brickwork 05th Apr’17 24th Jun’17>4th
July’17 >10th July> Level – 5
17th July’17 > 04th entrance wall
August’17 85% to redo.
Brickwork at Internal Façade – including plastering work 1st Apr’17 30th May’17 25th July’17 > 30th Rain header
July’17 95% remains
Wet Works in Guestrooms L1, L2 & L3 30th May’17 87%
Waterproofing in Guestrooms L1 & L3 (ST, SK, DT & DK) 30th Apr’17 10th May’17 17th May’17 87% *L1 is done
Sanitary Ware Installation – L3 (Shower Mixer & Mixing Valve) 02nd May’17 09th May’17 Prime Flux
needs to do
90% pressure test
Cable Laying in UG Cable Trench 30th July’17 15th July’17 15th Aug’17 5-days for
glazing
materials
30% carry-up.
Skylight Installation 26th May’17 2nd Jun’17 30th Jun’17 > 30th 90% Smoke Vent
July’17 > remains
QUALITY ISSUES
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
QA/QC meeting proposed at 2:00pm every Thursday *Senior management personnel & in-charge to attend QA/QC meeting.
- JECM, Primeflux, Kama, 29, Kanok CIMAC, Brickwork Contractors
Pre-Inspection Checklists *Pre-Inspection Checklists to return with status updates to Gareth Owen by 26 th
Jul’17 before 5:30.
MISCELLANEOUS ISSUES
TARGET
DESCRIPTION PROPOSED ACTION RESP. DATE
Housekeeping Day Every Saturday @ 9 AM: All contractors to provide TWO labors to PR office to clean one particular All contractors KIV
area every week led by PR Safety Officer
Mock-Up Inspection Completed on 02nd of March 2017 PR/ Kanok 10th Apr’17
Second inspection to be confirmed. All defects need to be resolved.
Underground Utilities All underground utilities to be completed in February for road and paving works. Primeflux 28th Feb’17
The activities are two weeks late according to current status.
Storm water drainage connections To be completed in early April in preparation for rain Primeflux April’17
Hot Works unsupervised All contractors to inform PR Safety and acquire Hot Work Permit for any hot work executed on-site. All Contractors KIV
Hot work without permit will be fined 100,000 MMK to any contractor.
AV Racks AV Racks not disturb the Kitchen Equipment. Definite location & dimension required. TBA
Overtime Works All contractors to resume overtime works to catch up project schedule All contractors KIV
Audit by Insurance Firm CHUBB, construction insurance firm is visiting site on 20 th
Jun’17 for auditing. PR 20th Jun’17
L1 & L2 Guestrooms Occupancy by KANOK All contractors to move storage materials out of guestrooms at L1 and L2 for Kanok to start fit-out All contractors KIV
works. If they have to work, clean up immediately after working and leave the space clean.
Unproductive Labor by JEC JEC labors seen sitting and sleeping on site for at least a week. JEC Closed
JEC to improve labor productivity.
All contractors to monitor worker productivity.
SK room electrical wiring To be completed by Friday (2nd Jun’17)
Water-tightness of Server Room Temporary Window, Raised Topping & Painting, Waterproofing above Roof Slab PR 15th Jun’17
Plumbing at Pre-function ceiling Primeflux to study ceiling plan and resolve the constructability of pre-function ceiling. Primeflux/PR 9th Jun’17
Ballroom Area Vacate the area by early July. All contractors 7th July’17
**All architectural works & MEP installation to be completed by 16 th August.
Gypsum Board Cutting in Guestrooms by another All contractors to notify PR to coordinate with Kanok for wall cuttings. All contractors
contractor other than Kanok
IT Rack Cabinet Ground floor – moved location to behind SL5/6. Have not A/C. PR-MEP KVS to RFI,
L2, L3 & L4 PR.