***** ANALYSIS OF RATE *****

PProviding and laying cement concrete work 1:1:2 (1 cement: 1 sand: 2 graded stone aggregate 20 mm nominal size) and curing complete excluding cost of from work
and reinforcement for reinforced concrete work (Arches upto floor two level) (DETAIL OF COST FOR 26.73 CUM)

S.No. Description of item Qty. Rate Unit Amount


A) MATERIAL:-
C.Cncrete 1:1:2 (RCC)
1 x1/2 x 22/7x 6.30x 9.00x 0.30 26.73 Cum 26.73 7656.60 CUM 204660.92
Total 204660.92 1)
B) LABOUR:-
EXTRA FOR LAYING C.CONC. IN RCC WORK
BELDAR 0.10 320.83 EACH 32.08
BHISTI 0.20 320.83 EACH 64.17
MASON(G-1) 0.04 374.50 EACH 14.98
MASON(G-II) 0.04 374.50 EACH 14.98
MATE 0.04 320.83 EACH 12.83
BELDAR FOR EXTRA LIFTING THE MATERIAL 0.17 320.83 EACH 54.54
Total 193.58
COST FOR LAYING 26.73 CUM 26.73 193.58 CUM 5174.39 2)
EXTRA FOR LAYING C.CONC. OVER CURVED SURFACE
KM 5.00 374.50 EACH 1872.50
KM 5.00 374.50 EACH 1872.50
0.00 4.45 320.83 EACH 1427.69
0.00 1.50 320.83 EACH 481.25

SANDRIES LS 40.42
Total 5694.36 3)
Total (1 to 3 ) 215529.67
ADD 1.5 % FOR WATER CHARGES EXCEPT THE COST OF CEMENT 10868.75 163.03
Total 221908.73
ADD 10 % CP & 5 % O.H.C.EXCEPT THE COST OF CEMENT 17247.81 2587.17
Total 224495.90
COST FOR 26.73 CUM 224495.90
COST FOR ONE CUM 8398.65
Say Rs. 8398.60
Add Labour Cess @ 1.00 % 0n Rs.= 8398.60 (+ ) Rs. 1007.80
9406.40
Add GST @ 12.00 % 0n Rs.= 8398.60 (+ ) Rs. 83.99
G.Total Rs.= 9490.39
Say Rs. 9490.40

Executive Engineer,
Jal Sahkti Vibhag Arki