Sei sulla pagina 1di 10

International Journal of Construction Management

ISSN: 1562-3599 (Print) 2331-2327 (Online) Journal homepage: https://www.tandfonline.com/loi/tjcm20

Assessment of critical risk and success factors in


construction supply chain: a case of Pakistan

Muhammad Abas, Sikandar Bilal Khattak, Tufail Habib & Uroosa Nadir

To cite this article: Muhammad Abas, Sikandar Bilal Khattak, Tufail Habib & Uroosa Nadir (2020):
Assessment of critical risk and success factors in construction supply chain: a case of Pakistan,
International Journal of Construction Management

To link to this article: https://doi.org/10.1080/15623599.2020.1783597

Published online: 26 Jun 2020.

Submit your article to this journal

View related articles

View Crossmark data

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tjcm20
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT
https://doi.org/10.1080/15623599.2020.1783597

Assessment of critical risk and success factors in construction supply chain: a case
of Pakistan
Muhammad Abasa, Sikandar Bilal Khattaka, Tufail Habibb and Uroosa Nadirb
a
Department of Industrial Engineering, University of Engineering and Technology Peshawar, Pakistan; bDepartment of Industrial Engineering,
Jalozai Campus, University of Engineering and Technology Peshawar, Pakistan

ABSTRACT KEYWORDS
Assessment of critical risk and success factors is essential for successful execution of construction projects. Construction supply chain;
This paper aims to identify the critical risk and success factors that affect the performance of the supply risk factors; severity index;
chain in the construction projects of Pakistan. For this purpose, a methodology was developed to identify success factors
risk and success factors. A questionnaire was designed to obtain the opinions of contracting companies,
consulting firms, and project managers. Data were collected from 259 respondents and were analyzed
statistically. The results of this study identified the top five critical risk factors that were prioritized based
on the severity index. The most critical risk factors identified were, funding with a highest percentage of
93.89%, followed by shortage of material/equipment, cash flow, and bad weather. Among success factors,
the communication has the highest severity index of 93.23%, followed by trust with a supplier, risk alloca-
tion, problem-solving, and joint working. These factors were discussed with implications that affect and
impact the performance of the construction industry. The findings of this research can be used to guide
the improvements in the construction industry in Pakistan, and other terror hit countries.

Introduction material, machine, skilled labor, unskilled labor, or any other


requirement. These multi echelons make the supply chain the
The construction projects are usually hybrid (Meng 2012). The heart for successful project completion and client satisfaction.
execution of construction projects uses not only manufactured Figure 1 illustrates the supply chain interaction between different
goods but also energy and raw materials. Similar to other prod- stakeholders of a construction project.
ucts, a construction project quality is defined by the client (i.e. The concept of supply chain management originated from the
the satisfaction of customer), whereas project success is directly manufacturing industry (Vrijhoef and Koskela 2000). Toyota is
dependent on the project team. Concerning Gross Domestic one of the pioneers in applying the concept of Just in Time (JIT)
Product (GDP), the construction industry has a significant for the delivery system (Shingo 1988). It assures the right
impact on the national and global economy (Yun and Jung amount of supplies at the right time. It reduces inventory and
2017). According to Shahbaz Rana (2019) growth rate of streamlines the interaction of suppliers with the production line
Pakistan’s construction industry during 2017–2018 was 9.13%. (Vrijhoef and Koskela 2000). Due to its successful implementa-
The construction projects are not only labor extensive (Dlamini tion in the manufacturing sector, researchers adopted some of its
et al. 2019), but drives and support other manufacturing and ser- aspects in the construction sector as well (Akintoye and
vice units as well (Liu and Kim 2019). Fitzgerald 2000; Vrijhoef and Koskela 2000; Tennant and
In developing countries, the construction industry is the Fernie 2014).
second largest employer for both skilled and unskilled labors According to Kumaraswamy (1996), the primary objective of
(Goel et al. 2019). Roughly 30–35% of employment is directly or a supply chain within a construction project is to help the pro-
indirectly associated with the construction industry (Farooqui ject team in better utilization of resources and achieves schedul-
and Ahmed 2008). The job offered by the construction industry ing goals. Palaneeswaran et al. (2003) emphasized that a supply
is at all levels of society. A small change in the construction chain should benefit all the members by developing a good rela-
environment and procedures can impact the society at large, tionship between client, contractor, consultant, suppliers, and
especially the daily wage workers. sub-contractors. A good supply chain sustains effective commu-
Typically, a construction project involves a client, contractor, nication, integration, collaboration, and coordination between
consultant, and sub-contractors. A client initiates a construction stakeholders throughout the project (Segerstedt and Olofsson
project, by initiating ideas, arranging finances, and integrating 2010). According to Vrijhoef and Koskela (2000), success factors
the supply chain (Segerstedt and Olofsson 2010). A consultant for the supply chain are incentive-based contracting, and part-
provides feasibility plans and safeguards client specifications. A nering. Moreover, the flow of raw material, information, and
contractor transforms the resources into a physical entity and is cash flow are critical risk factors for project success (L€
onngren
hired by the client in consultation with all the stakeholders. The et al. 2010). Selection of suppliers, number of deliveries deter-
contractor may have tens of different sub-contractors depending mination, and resource allocation are critical aspects of the suc-
on the requirements. The selected sub-contractors could be for cessful supply chain (Deng et al. 2019). High fragmentation and

CONTACT Sikandar Bilal Khattak sikandarbilal@uetpeshawar.edu.pk


ß 2020 Informa UK Limited, trading as Taylor & Francis Group
2 M. ABAS ET AL.

Figure 1. Supply chain within a construction project.

dynamic nature complicate the construction supply chain government support, and lack of public awareness and know-
(Cheng et al. 2010). The application of information technology ledge. The integration of the construction supply chain as a busi-
in the construction supply chain improves resource utilization, ness process in the construction sector of Pakistan is still in
time, and logistics performance. Getuli et al. (2016) integrated infancy. Likewise, the adoption of technology such as informa-
building information modeling (BIM) with the construction sup- tion and communications systems and the Internet of Things
ply chain to improve the exchange of information during differ- (IoT) is very slow in the construction industry in Pakistan.
ent phases of the project. Previous literature, especially in the context of Pakistan, did not
Limited research is available regarding the supply chain prac- take into account the risk factors and their implications on suc-
tices in the construction industry in Pakistan. For instance, cess parameters. As these factors vary from region to region, lim-
Khattak et al. (2015) studied the risk factors affecting the supply ited research is available regarding the supply chain practices
chain environment of the construction industry of Khyber within the Pakistan construction environment. Thus, it motivated
Pukhtunkhwa (KPK), a province of Pakistan. They identified the authors to conduct a holistic study to identify the critical
that escalation of material prices, cash flow, terrorism, shortages risk and success factors that affect the performance of the supply
of material and equipment’s and funding are the most critical chain in the construction projects of Pakistan. The purpose of
risk factors affecting the performance of the construction supply this study is twofold, first to develop awareness among stake-
chain. However, success factors and perceptions of consultants holders, especially contractors and consultants, concerning the
are not discussed in their study. Furthermore, their study is lim- possibility of potential risk in a construction supply chain and
ited to only one province of Pakistan. Shahbaz et al. (2018), in second to give recommendations to reduce the occurrence of
their study, identified that supplier relationship, customer rela- risk factors in the construction supply chain.
tionship, and risk and reward sharing effect the construction
supply chain performance of Pakistan. However, their study is
limited to a stakeholder management approach and ignores the Literature review
aspect of contractors and consultants. In another study, Shahbaz
An adequate supply chain in the construction industry cannot be
et al. (2019) studied the impact of supply chain capabilities on
logistic efficiency for the construction projects. They concluded developed unless the success and risk factors are identified and
that collaboration with stakeholders and flexibility in terms of quantified. The following section discussed the literature related
cost, time, labor, and other vital decisions is efficient for the to success and risk factors:
logistic supply chain. According to Gabol and Siddiqui (2019),
the success of the construction supply chain in Pakistan is greatly Critical success factors of supply chain
affected by top management commitment, information sharing,
and mutual trust. Ahmed et al. (2019) identified the critical bar- Fearne and Hughes (1999) argued that the critical success factors
riers impeding the adoption of green supply chain management for the supply chain are the commitment of top management,
in construction sectors of developing countries (Including team skills, consultant skills, and the reliability of schedule and
Pakistan, India, Bangladesh, Qatar, Iran, Kuwait, Saudi Arabia, budget. Whipple and Frankel (2000) identified clear goals, trust,
Egypt, UAE, Yemen, Ghana, Somalia, and Argentina). The crit- good partnership, efficient leadership, committed human resour-
ical factors identified are insufficient policies, incentives, regula- ces. According to Power et al. (2001), continuous improvement,
tions, or a commitment by leaders or top management, relation with suppliers, computer-based technology, management
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 3

style, and utilization of technology are the success factors of an determined risk allocation in construction projects based on
agile supply chain. For managing an effective web-based supply three significant factors, which are the form of payment, risk
chain, the success factors are communication, training, educa- management, and the form of contract. Smith (1995) classified
tion, the commitment of top management, and reliability of the risk into five major groups, namely, economic risk, capability
computer hardware and software (Ngai et al. 2004). Chen and risk, physical factor risk, contractual and legal risks, and political
Paulraj (2004) in their study discussed that customer focus, and societal risks. Shukla et al. (2011) held an inadequate risk
uncertainty in the environment, information technology, supplier assessment responsible for inaccurate estimates.
relationship, integration of logistics, and support from top man- Construction organization, which intends to have a competi-
agement are critical success factors for the supply chain. Rao tive edge, needs to focus on continuous improvement.
Tummala et al. (2006) identified that information and communi- Continuous improvement is related to lean manufacturing.
cation technology, no blame culture, supplier relationship, and Project managers who intend to reduce wastage need to stream-
performance measurement are success factors of supply chain line the business chain (Meng 2012). To develop a continuous
assessment. The study by Hong et al. (2008) identified govern- improvement cycle, the problem-solving approach from each of
ment policies, costs, technology, relationships, and service qual- the participants is mandatory. Problem solving plays a vital role
ity. The critical factors affecting the performance of the supply in daily construction activities. Incentive mechanism is practiced
chain in the UAE construction industry are technical back- in construction to mitigate the performance problems (Bubshait
ground, customer needs, and company procedures (Albaloushi 2003). One cannot blame others for the sake of their own mis-
and Skitmore 2008). Wu and Weng (2010) implored that critical take. Additionally, suppliers could not be given the same status
factors to be considered when selecting a supplier are manage- and benefits if they fail to achieve targets. Incentives mechanism
ment capability, financial capability, price response, delivery for goods participants can boost the morale of all the suitable
time, quality management, and technological capability. suppliers (Peckiene et al. 2013; Chen et al. 2017).
Moreover, for a successful supply chain, partnering, trust, no The other studies identified on-time funding, law and regula-
blame culture, standardized data, and mutual objectives are the tion, rewards, expertise, skills, technical staff availability, good
key factors (Koh et al. 2011). Additionally, critical factors for the weather, and teamwork as success factors (Gunduz and Yahya
implementation of green supply chain management are; informa- 2015; Mashwama et al. 2017; Zakaria et al. 2017; Afolabi et al.
tion technology, support from government, awareness, manage- 2019; Ahmadabadi and Heravi 2019; Sfakianaki 2019).
ment commitment, trust, and procurement strategies (Luthra
et al. 2014). Luo et al. (2018) conclude that supply chain excel-
lence can be achieved through building trust, communication, Critical risk factor for supply chain
mutual objectives, continuous improvement, performance meas- According to Brindley (2004), the adoption of risk management
urement, no blame culture, and partnering. in the construction supply chain is beneficial to the organization
Gale and Luo (2004) mentioned that joint working and a that is looking for technological advancement and global compe-
joint venture are critical for the construction supply chain. Joint tition. Chopra and Sodhi (2004) identified that the risk factors
working not only shares responsibility but also provide the that disrupt supply chain are natural disasters, terrorism, com-
expertise required to complete a project. The key aspect of the munication infrastructure, delays in supplies, inaccurate fore-
joint venture is technology transfer (Chowdhury and Chowdhury casts, fluctuations in the exchange rate, and uncertainties in
2001). It is considered to be successful if the competitive position demand and supply. Liu and Wang (2011) argued that the sour-
of parent firms about technology and management improves ces of disruption of a collaborative supply chain are law and
(Scaringella and Burtschell 2017). A joint venture encourages regulation, labor strikes, technology inconsistencies, and lack of
acquisition and knowledge sharing (Min et al. 2005). Building communication. Zou and Couani (2012) analyzed the key risks
trust is a fundamental consideration in building a supply chain and their dissemination in the green supply chain. Their results
relationship (Khalfan et al. 2007). A firm cannot compete indi- show that the most common risk factors are lack of commitment
vidually but must collaborate with other members in a supply to supply chain and higher investment cost. Gosling et al. (2013)
chain (Kwon and Suh 2004). Trust develops excellent communi- reported that late specification changes, late deliveries, bad wea-
cation, reduces risk and uncertainty among participants (Ryciuk ther, and supplier bad performance are the most influential risk
2017). Trust and good relationship results in knowledge sharing, factors. According to Badea et al. (2014), ineffective supply chain
experience, mutual problem solving, and shared planning risk can cause delays, cost-overrun, and quality problems in con-
(Khalfan et al. 2007). Groznika and Trkman (2012) conclude struction projects. In their study, they identified 16 potential
that trust decreases the complexity of negotiations. Olanrewaju risks. Among them, competitive cost risk, delivery risk, procure-
et al. (2017) and Trkman and McCormack (2009) highlighted ment risk, material quality risk, and delay risk are the most crit-
inappropriate mutual objectives for creating the inabilities to rec- ical. Khattak et al. (2015) ranked the external risk factors based
ognize ownership and project goals. Meng (2010) reported that on the analytical hierarchy process (AHP) affecting the perform-
lack of communication results in rework, non-uniformity, uneth- ance of a construction supply chain. Among 19 risk factors, the
ical behavior, worker frustration, and onsite violence. Effective top five factors identified are an escalation of material prices, fol-
communication results in proper planning and scheduling of lowed by cash flow, terrorism, shortages of material and equip-
construction activities and ensures on-time availability of mater- ment, and funding. Darko et al. (2016) identified 11 potential
ial and labor (Meng 2010). critical risks and concluded that fluctuation in prices, instability
Pain and benefits sharing are the key factors in developing a of interest rates, shortages of material, and unexpected changes
robust and trustful supply chain (Andelin et al. 2015). All con- in demand are critical risks in the Ghana construction industry.
struction projects are prone to risk. The risks must be allocated Panova and Hilletofth (2018) concluded that delays in the supply
among parties in such a way that no party is at a disadvantage of material and other resources, overcapacity or deficiency ware-
(Meng 2010). The risk should be allocated to those contracting house, on-time loading, and shipment of goods are the possible
parties which can handle it effectively. Lam et al. (2007) risks in the supply chain.
4 M. ABAS ET AL.

The literature review discussed the issues and factors that Table 1. Identified factors.
affect the performance of a supply chain in construction projects. S. no Risk factors S. no Success factors
The significance of these factors varies depending upon the type 1 PC-1 preparation 1 Benefit shared
of project, project team, and region. It is crucial to identify the 2 Funding 2 Trust with supplier
3 Procurement unit of contractor 3 Communication
factors that impact the performance of a construction supply
4 Financial capability of contractor 4 Problem solving
chain and the knowledge to improve the construction industry 5 Management team of contractor 5 Risk allocation
of Pakistan. The present study aims to highlight critical risk and 6 Communication infrastructure 6 Continuous improvement
success factors that affect the performance of a construction sup- 7 Escalation of material prices 7 Incentive mechanism
8 Technical person availability 8 Pain and gain sharing
ply chain and to develop awareness among the construction 9 Cash flow 9 Performance measurement
practitioners to adopt successful supply chain practices. 10 Shortage of material/equipment 10 Joint working
The rest of this paper is organized as follows. Section 11 Low bid 11 No blame culture
‘Methodology’, includes pilot study, questionnaire design, and 12 Bad weather 12 Mutual objective
13 Bureaucracy and political influence
analysis methods. ‘Results’ section presents the data analysis 14 Terrorism
using various measures such as reliability analysis, agreement 15 Regulatory authority
analysis, and ranking of identified factors. Section ‘Discussion’ 16 Government policies
deals with the success and risk factors and their implications. 17 ISO certification
18 Inflation
Section ‘Limitations and Future Research’ provides the limita- 19 Law and order situation
tions of the proposed method. Section ‘Conclusions and
Recommendations’ presents the practical implication of the study
and concludes the paper. Respondent selection
Contractors, clients (owners), and consultants were the potential
respondents. Only those contractors and consultants were
Methodology
approached that were registered with the Pakistan engineering
The methodology used for the present study is discussed council (PEC). Information related to contractors and consul-
as follows: tants was retrieved from the PEC website (PEC. 2019). PEC
divides the contractors into eight different categories based on
the project cost limit. These categories are CA, CB, and C1–C6.
Pilot study Category CA is the highest category with no project cost limit,
For a pilot study, identified factors were analyzed and validated CB up to 4000 million (PKR), C1–C6 between 2500 and 25 mil-
through experienced professionals. A preliminary questionnaire lion (PKR). Total local contractors registered with PEC of all cat-
was designed based on identified risk and success factors affect- egories are 20593, with CA 195, CB 123, C1 353, C2–C6
ing the construction supply chain performance. For survey-based (1013–9075). Local consultants registered with PEC are 2021. To
maintain the uniformity among respondent’s perception, only
research (Hill 1998) suggested 10–30 respondents. So a total of
the professionals who have more than 5 years of experience in
15 project participants having experience of more than 20 years
construction projects were considered as potential respondents.
were interviewed. The respondents thoroughly reviewed the draft
Table 2 shows the respondent profile.
of the designed questionnaire in a head-on interview. The dur-
488 questionnaires were distributed. However, with a response
ation of the interview was dependent on the degree of discussion
rate of 53.07%, only 259 responses were received, as shown in
and time allocated by the respondents. The purpose of the pilot
Table 3. According to Dillman et al. (2014), with a ± 5% sam-
study was to test the relevancy and comprehensiveness of the pling error, and a 95% confidence interval, a minimum sample
questionnaire. As no significant reviews were received from size of 246 was enough. Table 3 shows the questionnaires distrib-
respondents. The designed questionnaire with minor changes uted and received from respondents of different categories and
was adopted for the study. The risk and success factors that were their response rates. As the average response rate is above 50%,
finalized are shown in Table 1. A total of 19 risk factors and 12 so it is adequately good, as suggested for a construction survey
success factors are considered in this research. by Black et al. (2000).

Questionnaire design Analysis method


The designed questionnaire is divided into three sections: The reliability and normality of collected data were analyzed
1. The first section dealt with respondents’ personal informa- through the Omega (xt) coefficient and the Shapiro–Wilk nor-
tion such as name, designation, organization, and email. mality test. Moreover, Kendall’s coefficient of concordance was
2. The second is concerned with the organization, such as type performed to analyze the level of agreement on the ranking of
of organization, annual work done, and the number of factors among different respondent groups. Finally, the top 5
qualified workers (at least a bachelor’s degree). most critical factors were ranked based on the severity index/
3. The third section lists the factors shown in Table 1. The relative importance index.
respondents were asked to give the significance score based
on a Likert scale from 1 to 9 (1 strongly disagree, 2–3 dis-
agree, 4–6 neither agree nor disagree, 7–8 agree and 9 Results and analysis
strongly agree).
Reliability analysis
Nine points Likert scale is a better option because it increases
reliability and provides sensitivity to sense small significant dif- The reliability test based on the Omega (xt) coefficient was per-
ferences (Tabish and Jha 2011). formed to check the internal consistency of the collected data.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 5

Table 2. Respondents profile.


Target respondents Respondent designation Years of experience Project executed
Contractors (CA, CB, C1) Directors 15–35 More than 100
Project Manager 10–30 Between 50 and 100
Owners Private 5–25
Public Government 5–30 More than 100
Consultants 10–35 More than 100

Table 3. Questionnaire distributed and response rate. where:


Target respondent category Questionnaire Average response rate (%) n X
X
Distributed Received W¼ Rj Þ2
Contractors j¼1
CA 90 47 52.22
CB 60 31 51.67 ‘m’ is the number of factors, ‘p’ is the number of respondent’s
C1 110 56 50.91 groups, and j is the factor 1, 2, 3 … m.
Owners Kendall’s coefficient of concordance K for the available data is
Private 50 27 54.00
Government 75 40 53.33
0.9312. Test hypothesis is needed to know whether the respond-
Consultants 103 58 56.31 ents of different groups agree or disagree on the ranking
488 259 53.07 of factors.
 Null hypothesis, H0¼There is disagreement among respond-
ents of different groups on the ranking of factors (means every
The test was developed by McDonald (1999) and provide good
respondent ranked the factors differently).
reliability estimation (Trizano-Hermosilla and Alvarado 2016).
 Alternate hypothesis, Ha¼There is agreement among
Omega coefficient is expressed as Equation 1:
respondents of different groups on the ranking of factors (means
P
ð kj Þ2 every respondent ranked the factors in the same order).
xt ¼ P 2 P (1) Chi-square (v2) approximation of the sampling distribution of
½ð kj Þ þ ð1  kj 2 Þ
K is calculated for testing the hypothesis using Equation 3.
where kj is loading of item j, kj2 commonality of item j.
The value of the Omega (xt) coefficient varies between 0 and v2 ¼ gðm  1ÞK (3)
1. The acceptable range of xt is 0.7, while 0.9 and higher where g is the number of groups.
values provide high reliability (McDonald 1999). The xt calcu- The test statistics computed for Kendall’s coefficient of con-
lated for the data collected from contractors is 0.916, consul- cordance is shown in Table 4. As P value is less than the alpha
tants is 0.923, and owners is 0.908, while the combined xt is value of 0.05, so we reject the null hypothesis (H0) in favor of
0.903, so this shows that the data is highly reliable and suit- the alternate hypothesis (Ha). It is concluded that there is a sig-
able for further analysis. nificant level of agreement among respondents of different
groups on how they rank the factors.
Normality test
Ranking of factors
As the sample size of the collected data is less than 2000, so
the Shapiro–Wilk normality test is performed to check the The risk and success factors were ranked according to the sever-
normality (Royston 1982). For the normality of the data, sig- ity index (SI)/relative importance index. According to Le-Hoai
nificance values must be higher than 0.05. The results revealed et al. (2008), Rooshdi et al. (2018), Kamal et al. (2019), severity
that the significance value for each factor is less than 0.05, index is a more suitable method to prioritize indicators/factors
showing that the collected data is not normally distributed. So rated based on the Likert scale. The severity index is calculated
it concludes that non-parametric/distribution-free tests are through Equation 4.
suitable for further analysis. P9
x f
i i i
Severity index ð%Þ ¼  100 (4)
9N
Agreement analysis
where
Questionnaires were received from respondents of different xi ¼ weight assigned to ith response, i ¼ 1,2,3,4,5,6,7,8,9
organizations of different categories (contractors, clients, and fi ¼frequency of ith response,
consultants). A conflicting opinion about the ranking of critical N¼total number of responses,
risk and success factors of a construction supply chain might 9 is the highest point on the Likert scale.
exist. Therefore, agreement analysis needs to be performed to Table 5 shows factors, their SI percentage and ranking.
analyze the extent of agreement among respondents. Kendall’s The most critical risk factors identified are funding (93.89%),
coefficient of concordance test (non-parametric test) is one of followed by a shortage of material/equipment (90.05%), cash
the preferred methods to evaluate agreement in comparison to flow (89.78%), and bad weather (89.05%). ISO certification
other methods such as Cohn’s kappa (Ahmed et al. 2007). (50.34%) and PC-1 preparation (59.33%) are on the lower side.
Kendall’s coefficient of concordance values varies between zero Among success factors the communication has the highest sever-
and one and can be calculated from Equation 2: ity index of 93.23%, subsequently trust with a supplier (92.16%),
risk allocation (91.56%), problem solving (90.67%) and joint
12W 3p2 mðm1Þ2
K¼ (2) working (90.12%), whereas benefits sharing (79.56%) and mutual
p2 mðm1Þ2 objective (80.88) have a low ranking.
6 M. ABAS ET AL.

Discussion issues and should prepare a remedial plan. Additionally, the pro-
ject manager should be aware of how the accounting department
Critical risk factors
collects and report cashflow. The supply chain finance system
With a severity index value 93.89%, funding is the most critical can ensure excellent performance (Ali et al. 2019).
risk factor in a construction supply chain. Late funding, create With a severity index of 89.25%, terrorism is the fourth most
financial problems. This finding agrees with Xie et al. (2019), critical risk factor. According to Blackhurst et al. (2005), it dis-
who suggested that shortening the payment period accelerate the rupts the supply chain activities and affects the performance of
flow of fund and reduces the financial burden on contractors. construction projects. Terrorism and terrorist attacks can lead to
According to respondents, the decisive reasons for late funding site closure. Moreover, it can interrupt the supply and transpor-
are poor communication, late approval of invoices, poor financial tation of material, equipment, and staff. The contractors need to
management, and economic instability. To mitigate late funding accurately calculate the safety stock and be in constant liaison
problems, the contractor should study the financial stability of with government and security agencies to ensure the provision
their clients and their performance on funds payment. and safety of workers, material, and equipment.
With a severity index of 90.05%, the second most critical risk Unusual weather is the fifth most significant risk factor (with
is the shortage of materials and equipment. This finding coin- a severity index of 89.05%). J€ uttner et al. (2003), also implores
cides with Chapman (2001) and Darko et al. (2016), who argued weather to be a critical risk factor. Extreme weather such as
that a shortage of material and equipment is the primary source floods, hurricanes, and storms can disrupt worksite and are also
of disruption in a construction supply chain and causes signifi- responsible for late deliveries of material and utilities
cant delays. The core materials for construction are cement, steel, (Christopher and Lee 2004; Wedawatta et al. 2010). Construction
bricks, and sand. Their shortage leads to a stoppage of work, companies can monitor weather conditions of the region by
which causes delays and affects the supply chain. To avoid such incorporating private weather forecast service. Furthermore, the
problems, contractors need to incorporate inventory manage- project manager is required to keep in view the risks associated
ment guidelines. Request the quotes from multiple suppliers to with adverse weather when making a project schedule. A con-
get reasonable prices. Perform daily supervision of material to struction project that depends on dry weather conditions such as
avoid pilferages and stock out. Make an adequate estimation of roads and foundations are significantly affected when too many
material. Introduce the information-sharing system to share wet days occur. Hence, it is essential to introduce a risk manage-
inventory and demand data with suppliers for a quick response. ment system to avoid delays.
Many construction firms face a problem in the supply chain
due to poor cash flow. Cash flow is the third most critical risk
factor, having a severity index of 89.78%. This finding concurs Critical success risk factors
with Blackhurst et al. (2005), who proposed that poor cash flow
are responsible for delays in construction projects and disrupt Communication with a severity index of 93.23% is the most crit-
the supply chain performance. Respondents suggest that poor ical success factor. This finding corroborates with Love et al.
cash flow occurs because of late payment from clients, poor (2004), Luo et al. (2018), who identified that a successful supply
communication, error in estimation, and poor performance by chain in construction projects is not possible without effective
the procurement team. The contractors need to understand these communication. It is considered to be an indispensable aspect of
a construction supply chain. The suppliers and managers fail to
Table 4. Kendall’s coefficient of concordance results. communicate changes or other relevant information on time. For
Test statistics a successful supply chain, communication needs to effective and
Sample size 259
efficient among all stakeholders. The integration of technology
Kendall’s K 0.9312 can effectively reduce the communication gap.
Chi-square 1197 With a severity index of 92.16%, trust with the supplier is the
Degree of freedom 30 second most significant success factor. Kwon and Suh (2004),
P value 0.001
Ryciuk (2017), Luo et al. (2018) suggest that developing trust

Table 5. Ranking of risk and success factors based on severity index.


Risk factors Severity index (%) Rank Success factors Severity index (%) Rank
PC-1 preparation 59.33 18 Benefit shared 79.56 12
Funding 93.89 1 Trust with supplier 92.16 2
Procurement unit of contractor 78.45 15 Communication 93.23 1
Financial capability of contractor 80.01 13 Problem solving 90.67 4
Management team of contractor 81.56 12 Risk allocation 91.56 3
Communication infrastructure 83.61 8 Continuous improvement 81.48 10
Escalation of material prices 87.23 6 Incentive mechanism 82.15 9
Technical person availability 85.63 7 Pain and gain sharing 85.56 6
Cash flow 89.78 3 Performance measurement 85.17 7
Shortage of material/equipment 90.05 2 Joint working 90.12 5
Low bid 75.21 16 No blame culture 82.56 8
Bad weather 89.05 5 Mutual objective 80.88 11
Bureaucracy and political influence 82.32 10
Terrorism 89.25 4
Regulatory authority 79.81 14
Government policies 72.91 17
Iso certification 50.34 19
Inflation 82.45 9
Law and order situation 81.79 11
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 7

with a supplier is considered to be necessary for a successful sup- contractors and consultants registered with the Pakistan
ply chain. The respondents implore that due to mistrust, neither Engineering Council (PEC) is not considered in the present study.
the project manager nor the supplier offers any favor or cost–be- Further research could investigate their views by comparing them
nefit. Participants fail to blend their expertise to help each other. with the views of local contractors and consultants. Future studies
Effective communication with suppliers is a crucial parameter can develop a model or framework for the construction supply
for developing trust. Regular discussion sessions with suppliers chain in Pakistan by considering the identified critical factors.
can provide acme and grab their apprehensions and uncertainties Also, comparative studies can be carried out with other countries.
as they happen during the life cycle of a project. Moreover, case studies can be conducted to analyze how these fac-
Risk allocation with a severity index of 91.56% is the third tors impacted the performance of projects during different phases.
most significant success factor. This finding matches with Meng
(2012), who concluded that risk allocation is one of the critical
Conclusions and recommendations
construction supply chain factors. Due to fragmentation, a con-
struction supply chain is more prone to risk. A risk management The present study aimed to identify critical risk factors affecting
team can integrate suppliers with other parties and educate them the construction supply chain, which has a direct impact on the
about possible risks during the project. A review of the last project successful execution of projects. The purpose of this study was to
to answer a question regarding the type of risks, effect of those develop awareness among stakeholders, especially contractors
risks, responsible party, and probability of those risks in the cur- and consultants, concerning the possibility of potential risk in a
rent project can help in preventive and predictive measures. construction supply chain. For this reason, risk and success fac-
Problem solving with a severity index of 90.67% is the fourth tors were identified based on literature and were finalized after
most critical success factor. Problems start with minor issues, and consultation with professionals. The results in the study show
if it is overlooked or remains unsolved, it can lead to major dis- that the most critical risk factors are funding that is 93.89%, fol-
putes and challenging to solve (Jones et al. 2003; Meng 2012). A lowed by shortage of material/equipment that is 90.05%, cash
construction project is prone to different problems. The strategies flow is 89.78%, bad weather is 89.05%, while the ISO certification
for practical problem-solving needs to identify the problem, its ori- is 50.34% and PC-1 preparation is 59.33% having lowest signifi-
gination, nature, level of severity, and then search for possible solu- cance rank. Among success factors, communication has the high-
tions. The problems need to be adequately documented, so it can est severity index of 93.23%, subsequently trust with the supplier
be used to resolve future problems on time effectively. Moreover, is 92.16%, risk allocation is 91.56%, problem solving is 90.67%,
creating a culture of continuous improvement reduces problems. and joint working is 90.12%, whereas benefit-sharing is 79.56%
With a severity index of 90.12%, joint working is the fifth and mutual objective is 80.88% having low significance ranking.
most significant success factor. Meng (2012) argues that joint For effective implementation of the supply chain, the identified
working provides clear guidelines for mutual objectives. Joint factors are required to be considered during the decision-mak-
working is the collaboration between partners that may be short ing process.
term or long term depending on the level of their relationship. The following recommendations can be made to reduce the
For continuity of project without delays, long term partnership is occurrence of risk factors in the construction supply chain:
essential. Joint working is possible in the presence of mutual
trust, no blame culture, and pain and gain sharing.  To mitigate late funding problems, the contractor must
In synopsis, the construction supply chain is affected by sev- study the financial stability of their clients and their per-
eral factors. However, due to budget and other constraints, one formance on funds payments.
cannot target or improve all these factors. The significant success  To avoid a shortage of materials, contractors need to have
and risk factors identified in this research can be a starting point inventory management systems.
to develop an effective and robust construction supply chain for  To avoid supply disruption due to terrorist activities, the
developing countries like Pakistan. contractors need to be in constant liaison with government
and security agencies to ensure safety to workers, material,
and equipment.
Practical implications  To reduce the risks associated with bad weather, the project
manager must consider the weather conditions in their
Identification of risk and success factors in the construction sup- schedules by incorporating weather forecast services.
ply chain is the most critical step for supply chain managers.  Establish effective communication with suppliers to
The purpose of this study is to develop guidelines that may be develop trust.
useful for the identification of supply chain risk and success fac-  Regular discussion with suppliers highlights the uncertainties
tors for the Pakistan construction industry. From a practical per- as they happen during the life cycle of a project.
spective, construction practitioners should focus on the most  A risk management team can integrate suppliers with other
critical risk and success factors identified in this study. This parties and educate them about possible risks during the
study will support construction practitioners in executing supply project. A review of the previous project, especially the risk
chain activities proficiently and thereby shall improve the per- factors, can support the current project to have preventive
formance and productivity of construction projects. Finally, and corrective actions.
awareness about the importance of these factors leads to a suc-  A useful problem-solving strategy should be practiced to
cessful implementation of the construction supply chain. identify the problem, its origin, and search for possible solu-
tions. Documentation of the problems and their mitigation
Limitations and future research is necessary for continuous improvement.

Although 259 responses were considered enough for the present Disclosure statement
study. The number could be increased for extensive analysis to
get more in-depth analysis. The perspective of foreign No potential conflict of interest was reported by the authors.
8 M. ABAS ET AL.

References Gale A, Luo J. 2004. Factors affecting construction joint ventures in China.
Int J Project Manage. 22(1):33–42.
Afolabi A, Ibem E, Aduwo E, Tunji-Olayeni P, Oluwunmi O. 2019. Critical Getuli V, Ventura SM, Capone P, Ciribini AL. 2016. A BIM-based construc-
success factors (CSFs) for e-procurement adoption in the Nigerian con- tion supply chain framework for monitoring progress and coordination of
struction industry. Buildings. 9(2):47. site activities. Proc Eng. 164:542–549.
Ahmadabadi AA, Heravi G. 2019. The effect of critical success factors on Goel A, Ganesh LS, Kaur A. 2019. Deductive content analysis of research on
project success in public–private partnership projects: a case study of sustainable construction in India: current progress and future directions. J
highway projects in Iran. Transp Policy. 73:152–161. Clean Prod. 226:142–158.
Ahmed F, Capretz LF, Sheikh SA. 2007. Institutionalization of software prod- Gosling J, Naim M, Towill D. 2013. Identifying and categorizing the sources
uct line: an empirical investigation of key organizational factors. J Syst of uncertainty in construction supply chains. J Constr Eng Manage.
Softw. 80(6):836–849. 139(1):102–110.
Ahmed M, Thaheem MJ, Maqsoom A. 2019. Barriers and opportunities to Groznika A, Trkman P. 2012. Current issues and challenges of supply chain
greening the construction supply chain management: cause-driven imple- management. Econ Res. 25(4):1101–1112.
mentation strategies for developing countries. Benchmarking. Int J. 27(3): Gunduz M, Yahya AMA. 2015. Analysis of project success factors in con-
1211–1237. struction industry. Technol Econ Develop Econ. 24(1):67–80.
Akintoye A, Fitzgerald E. 2000. A survey of current cost estimating practices Hill R. 1998. What sample size is ‘enough’ in internet survey research.
in the UK. Construct Manage Econ. 18(2):161–172. Interpers Comput Technol. 6(3–4):1–12.
Albaloushi H, Skitmore M. 2008. Supply chain management in the UAE con- Hong JY, Suh EH, Hou LY. 2008. Identifying the factors influencing the per-
struction industry. Int J Construct Manage. 8(1):53–71. formance of reverse supply chains (RSC). Int J Sustain Eng. 1(3):173–187.
Ali Z, Gongbing B, Mehreen A. 2019. Predicting supply chain effectiveness Jones D, Savage D, Westgate R. 2003. Partnering and collaborative working:
through supply chain finance: evidence from small and medium enter- law and industry practice. London: LLP.
prises. IJLM. 30(2):488–505. J€
uttner U, Peck H, Christopher M. 2003. Supply chain risk management: out-
Andelin M, Karhu J, Junnila S. 2015. Creating shared value in a construction lining an agenda for future research. Int J Logist Res Appl. 6(4):197–210.
project: a case study. Proc Econ Finance. 21:446–453. Kamal A, Abas M, Khan D, Waqas Azfar R. 2019. Risk factors influencing
Badea A, Prostean G, Goncalves G, Allaoui H. 2014. Assessing risk factors in the building projects in Pakistan: from perspective of contractors, clients
collaborative supply chain with the analytic hierarchy process (AHP). and consultants. Int J Construct Manage. 1–17. DOI: 10.1080/15623599.
Procedia-Soc Behav Sci. 124(1):114–123. 2019.1683693.
Black C, Akintoye A, Fitzgerald E. 2000. An analysis of success factors and Khalfan MM, McDermott P, Swan W. 2007. Building trust in construction
benefits of partnering in construction. Int J Project Manage. 18(6): projects. Supp Chain Manage. 12(6):385–391.
423–434. Khattak SB, Abas M, Maqsood S, Omair M, Nawaz R, Ul Haq I. 2015. Vol.
Blackhurst J, Craighead CW, Elkins D, Handfield RB. 2005. An empirically 20(6), Identification and evaluation of risk factors affecting the supply
derived agenda of critical research issues for managing supply-chain dis- chain environment of construction industry of Khyber Pukhtunkhwa
ruptions. Int J Prod Res. 43(19):4067–4081. (KPK). University of Engineering and Technology (UET) Taxila, Pakistan.
Brindley C. 2004. Supply chain risk. Aldershot, United Kingdom: Ashgate Koh SL, Gunasekaran A, Goodman T. 2011. Drivers, barriers and critical suc-
Publishing. cess factors for ERPII implementation in supply chains: a critical analysis.
Bubshait AA. 2003. Incentive/disincentive contracts and its effects on indus-
J Strat Inform Syst. 20(4):385–402.
trial projects. Int J Project Manage. 21(1):63–70. Kumaraswamy MM. 1996. Contractor evaluation and selection: a Hong Kong
Chapman RJ. 2001. The controlling influences on effective risk identification
perspective. Build Environ. 31(3):273–282.
and assessment for construction design management. Int J Project
Kwon I-WG, Suh T. 2004. Factors affecting the level of trust and commit-
Manage. 19(3):147–160.
ment in supply chain relationships. J Supply Chain Manage. 40(2):4–14.
Chen IJ, Paulraj A. 2004. Understanding supply chain management: critical
Lam KC, Wang D, Lee PTK, Tsang YT. 2007. Modelling risk allocation deci-
research and a theoretical framework. Int J Prod Res. 42(1):131–163.
sion in construction contracts. Int J Project Manage. 25(5):485–493.
Chen Z, Tang J, Wan J, Chen Y. 2017. Promotion incentives for local offi-
Le-Hoai L, Lee YD, Lee JY. 2008. Delay and cost overruns in Vietnam large
cials and the expansion of urban construction land in China: using the
construction projects: a comparison with other selected countries. KSCE J
Yangtze river delta as a case study. Land Use Policy. 63:214–225.
Civ Eng. 12(6):367–377.
Cheng JC, Law KH, Bjornsson H, Jones A, Sriram R. 2010. A service oriented
Liu Y, Kim D. 2019. Understanding of servicification trends in China
framework for construction supply chain integration. Autom Constr.
through analysis of interindustry network structure. In INFORMS
19(2):245–260.
Chopra S, Sodhi MS. 2004. Managing risk to avoid supply chain breakdown. International Conference on Service Science. Cham: Springer; p. 55–64.
MIT Sloan Manage Rev. 46(1):53–62. Liu Y, Wang S. 2011. Research on collaborative management in supply chain
Chowdhury IR, Chowdhury PR. 2001. A theory of joint venture life-cycles. crisis. Vol. 10, 3rd International Conference on Environmental Science
Int J Indus Organ. 19(3–4):319–343. and Information Application Technology, Procedia Environmental
Christopher M, Lee H. 2004. Mitigating supply chain risk through improved Sciences; p. 141–146.
confidence. Int J Phys Distrib Logist Manage. 34(5):388–396. L€
onngren H-M, Rosenkranz C, Kolbe H. 2010. Aggregated construction sup-
Darko A, Owusu-Manu DG, P€arn E, Edwards DJ. 2016. Identifying potential ply chains: success factors in implementation of strategic partnerships.
critical risks in the construction supply chain: an empirical study in Supp Chain Manage 15(5):404–411.
Ghana, Mindanao. J Sci Technol. 14:79–100. Love PE, Irani Z, Edwards DJ. 2004. A seamless supply chain management
Deng Y, Gan VJ, Das M, Cheng JC, Anumba C. 2019. Integrating 4D BIM model for construction. Supp Chain Manage. 9(1):43–56.
and GIS for construction supply chain management. J Constr Eng Luo W, Shi Y, Venkatesh VG. 2018. Exploring the factors of achieving supply
Manage. 145(4):04019016. chain excellence: a New Zealand perspective. Prod Plan Control. 29(8):
Dillman DA, Smyth JD, Christian LM. 2014. Internet, phone, mail, and 655–667.
mixed-mode surveys: the tailored design method. New York: John Wiley Luthra S, Qadri MA, Garg D, Haleem A. 2014. Identification of critical suc-
& Sons. cess factors to achieve high green supply chain management performances
Dlamini B, Oshodi OS, Aigbavboa C, Thwala WD. 2019. Work–life balance in Indian automobile industry. IJLSM. 18(2):170–199.
practices in the construction industry of Swaziland. In: Construction Mashwama N, Aigbavboa C, Thwala D. 2017. An assessment of the critical
industry development board postgraduate research conference. Cham: success factor for the reduction of cost of poor quality in construction
Springer; p. 82–89. projects in Swaziland. Proc Eng. 196:447–453.
Farooqui R, Ahmed S. 2008. Assessment of Pakistani construction industry: McDonald RP. 1999. Test theory: a unified treatment. Mahwah, NJ:
current performance and the way forward. J Adv Perform Inform Value. Lawrence Erlbaum Associates, Inc.; p. 142–145.
1(1):51–72. Meng X. 2010. Assessment framework for construction supply chain relation-
Fearne A, Hughes D. 1999. Success factors in the fresh produce supply chain: ships: development and evaluation. Int J Project Manage. 28(7):695–707.
insights from the UK. Supp Chain Manage. 4(3):120–131. Meng X. 2012. The effect of relationship management on project perform-
Gabol MS, Siddiqui DA. 2019. The factors impacting the success of supply ance in construction. Int J Project Manage. 30(2):188–198.
chain management in the construction industry of Pakistan. Available at Min S, Roath AS, Daugherty PJ, Genchev SE, Chen H, Arndt AD, Glenn
SSRN: https://ssrn.com/abstract=3382200. or http://dx.doi.org/10.2139/ Richey R. 2005. Supply chain collaboration: what’s happening? Int J Logist
ssrn.3382200. Manage. 16(2):237–256.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 9

Ngai EWT, Cheng TCE, Ho SSM. 2004. Critical success factors of web-based Shahbaz MS, Soomro MA, Bhatti NUK, Soomro Z, Jamali MZ. 2019. The
supply-chain management systems: an exploratory study. Prod Plan impact of supply chain capabilities on logistic efficiency for the construc-
Control. 15(6):622–630. tion projects. Civ Eng J. 5(6):1249–1256.
Olanrewaju A, Yeow Tan S, Kwan LF. 2017. Roles of communication on per- Shingo S. 1988. Non-stock production: the Shingo system of continuous
formance of the construction sector. Proc Eng. 196:763–770. improvement. Boca Raton: CRC Press.
Palaneeswaran E, Kumaraswamy M, Rahman M, Ng T. 2003. Curing con- Shukla RK, Garg D, Agarwal A. 2011. Understanding of supply chain: a lit-
genital construction industry disorders through relationally integrated sup- erature review. Int J Eng Sci Technol. 3(3):2059–2072.
ply chains. Build Environ. 38(4):571–582. Smith NJ, editor. 1995. Project cost estimating. Vol. 6. London: Thomas
Panova Y, Hilletofth P. 2018. Managing supply chain risks and delays in con- Telford Ltd.
struction project. Indus Manage Data Syst. 118(7):1413–1431. Tabish SZS, Jha KN. 2011. Identification and evaluation of success factors for
PEC. 2019. List of constructor/operator firms and consultant firms. Retrieved
public construction projects. Construct Manage Econ. 29(8):809–823.
July 31, 2019. https://verification.pec.org.pk/COFirmList., https://verifica-
Tennant S, Fernie S. 2014. Theory to practice: a typology of supply chain
tion.pec.org.pk/ConsultList.
Peckiene A, Komarovska A, Ustinovicius L. 2013. Overview of risk allocation management in construction. Int J Construct Manage. 14(1):56–66.
between construction parties. Proc Eng. 57:889–894. Trizano-Hermosilla I, Alvarado JM. 2016. Best alternatives to Cronbach’s
Power DJ, Sohal AS, Rahman S-U. 2001. Critical success factors in Agile sup- alpha reliability in realistic conditions: congeneric and asymmetrical meas-
ply chain management: an empirical study. Int J Phys Distrib Logist urements. Front Psychol. 7:769.
Manage. 31(4):247–265. Trkman P, McCormack K. 2009. Supply chain risk in turbulent environ-
Rana S. 2019. Economic growth rate revised downward. THE EXPRESS ments—a conceptual model for managing supply chain network risk. Int J
TRIBUNE, February 8. Prod Econ. 119(2):247–258.
Rao Tummala VM, Phillips CL, Johnson M. 2006. Assessing supply chain Vrijhoef R, Koskela L. 2000. The four roles of supply chain management in
management success factors: a case study. Supp Chain Manage. 11(2): construction. Eur J Purchas Supply Manage. 6(3–4):169–178.
179–192. Wedawatta G, Ingirige B, Amaratunga D. 2010. Building up resilience of con-
Rooshdi RRRM, Majid MZA, Sahamir SR, Ismail NAA. 2018. Relative struction sector SMEs and their supply chains to extreme weather events.
importance index of sustainable design and construction activities criteria Int J Strategic Prop Manage. 14(4):362–375.
for green highway. Chem Eng Trans. 63:151–156. Whipple JM, Frankel R. 2000. Strategic alliance success factors. J Supply
Royston JP. 1982. An extension of Shapiro and Wilk’s W test for normality Chain Manage. 36(3):21–28.
to large samples. Appl Stat. 31(2):115–124 Wu M-Y, Weng Y-C. 2010. A study of supplier selection factors for high-
Ryciuk U. 2017. Identification of factors related to trust formation in con- tech industries in the supply chain. Tot Q Manage. 21(4):391–413.
struction supply chains. Proc Eng. 182:627–634. Yun S, Jung W. 2017. Benchmarking sustainability practices use throughout
Scaringella L, Burtschell F. 2017. The challenges of radical innovation in
industrial construction project delivery. Sustainability. 9(6):1007.
Iran: Knowledge transfer and absorptive capacity highlights—evidence
Xie H, Zheng J, Zhang Y, Li H. 2019. Effects of payment delays at two links
from a joint venture in the construction sector. Technol Forecast Soc
Change. 122:151–169. in payment chains on the progress of construction projects: system
Segerstedt A, Olofsson T. 2010. Supply chains in the construction industry. dynamic modeling and simulation. Sustainability. 11(15):4115.
Supp Chain Manage. 15(5):347–353. Zakaria SF, Zin RM, Mohamad I, Balubaid S, Mydin SH, Mohd Rahim ER.
Sfakianaki E. 2019. Critical success factors for sustainable construction: a lit- 2017. Critical success factors in infrastructure projects. In: AIP
erature review. Manage Environ Q. 30(1):176–196. Conference Proceedings, Vol. 1903, No. 1. Palembang, Indonesia: AIP
Shahbaz MS, Chandio AF, Oad M, Ahmed A. 2018. Stakeholders’ manage- Publishing LLC; p. 070017. DOI: 10.1063/1.5011586.
ment approaches in construction supply chain: A new perspective of Zou PX, Couani P. 2012. Managing risks in green building supply chain.
Stakeholder’s theory. IJSCET. 9(2):16–25. Architect Eng Design Manage. 8(2):143–158.

Potrebbero piacerti anche