Productivity Benchmarks for Constructions Activities

Sr. Output per day in


no Activity Location India Gang size

1 BBM work 1st floor 240 sq ft 1 M,1 M.C,1F.C.


2 BBM work 5th floor 200 sq ft 1 M,1 M.C,1F.C.
3 BBM work 9th floor 200 sq ft 1 M,1 M.C,1F.C.
4 Ext. Plaster 1st floor 150 sq ft 1 M,1 M.C,1F.C.
5 Ext. Plaster 5th floor 140 sq ft 1 M,1 M.C,1F.C.
6 Ext. Plaster 9th floor 100 sq ft 1 M,1 M.C,1F.C.
7 Int. Plaster 1st floor 160 sq ft 1 M,1 M.C,1F.C.
8 Int. Plaster 5th floor 150 sq ft 1 M,1 M.C,1F.C.
9 Int. Plaster 9th floor 140 sq ft 1 M,1 M.C,1F.C.
10 Door Frame Fixing 1st floor 4 nos 1 M,1 M.C
11 Door Frame Fixing 5th floor 4 nos 1 M,1 M.C
12 Door Frame Fixing 9th floor 4 nos 1 M,1 M.C
13 Window Fixing 1st floor 72 sq ft 1 M,1 M.C
14 Window Fixing 5th floor 72 sq ft 1 M,1 M.C
15 Window Fixing 9th floor 72 sq ft 1 M,1 M.C
16 Excavation G floor 150 cft 1 M.C, 1 F.C
1 C,1 F,2 M.C, 1M,2
17 Piling Foundation G floor 1 no H
1 C,1 F,2 M.C, 1M,2
18 Isolated Footing G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
19 Raft Foundation G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
20 Retaining Wall G floor 125 cft H
1 C,1 F,2 M.C, 1M,2
21 Ramp G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
22 Column G floor 80 cft H
1 C,1 F,2 M.C, 1M,2
23 Beam G floor 80 cft H
1 C,1 F,2 M.C, 1M,2
24 Slab G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
25 Podium Footing G floor 1 no H
1 C,1 F,2 M.C, 1M,2
26 Podium column G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
27 Podium Beam G floor 100 cft H
1 C,1 F,2 M.C, 1M,2
28 Podium Slab G floor 150 cft H
1 C,1 F,2 M.C, 1M,2
29 RCC Slab 1st floor 150 cft H
Sr. Output per day in
no Activity Location India Gang size
1 C,1 F,2 M.C, 1M,2
30 RCC Slab 5th floor 150 cft H
1 C,1 F,2 M.C, 1M,2
31 RCC Slab 9th floor 150 cft H
1 C,1 F,2 M.C, 1M,2
32 RCC Column 1st floor 100 cft H
1 C,1 F,2 M.C, 1M,2
33 RCC Column 5th floor 100 cft H
1 C,1 F,2 M.C, 1M,2
34 RCC Column 9th floor 100 cft H
1 C,1 F,2 M.C, 1M,2
35 RCC Beam 1st floor 100 cft H
1 C,1 F,2 M.C, 1M,2
36 RCC Beam 5th floor 100 cft H
1 C,1 F,2 M.C, 1M,2
37 RCC Beam 9th floor 100 cft H
1 C,1 F,2 M.C, 1M,2
38 RCC Staircase 1st floor 75 cft H
1 C,1 F,2 M.C, 1M,2
39 RCC Staircase 5th floor 75 cft H
1 C,1 F,2 M.C, 1M,2
40 RCC Staircase 9th floor 75 cft H
1 C,1 F,2 M.C, 1M,2
41 RCC Lift shaft 1st floor 100 cft H
1 C,1 F,2 M.C, 1M,2
42 RCC Lift shaft 5th floor 100 cft H
1 C,1 F,2 M.C, 1M,2
43 RCC Lift shaft 9th floor 100 cft H

44 Fixing Glass
Cutting track 220sft 1 M, 1 MC
Fixing Glass 120sft 1 M, 1 MC

45 Installation of down take pipe


60ft( 2",1.5",4") 1 M, 4 MC
4" fire fighting 60'

46 Installation of rising main


50ft( 1.5") 1 M, 4 MC

47 Plumbing
Cutting 1 No. toilet including 1 M, 1 MC
G.I Pipe fitting 1 No. toilet 2 M, 2 MC
Waterproofing 1 No. toilet 1 M, 1 MC
Bottom Tile 100 sq.ft. 1 M, 2 MC
Dado Tile fixing 50sft 1 M, 1 MC
Sr. Output per day in
no Activity Location India Gang size

Sanitary ware fixing 1 No. toilet 1 M, 1 MC

C.P.Fitting 1 M, 1 MC
48 Terrace Waterproofing
Brick laying 4.0 Brass 2M,3 MC,3 FC
Finishing of surface 4.0 Brass 2M,3 MC
49 Excavation
1 no.of M/C+4
Excavation in Hard Rock 150 m³ dumper
1 no.of M/C+4
Excavation In Soft Rock 300m³ dumper
50 R.M.C Plant
120-130m³ 2 ope., 11MC
51 Swimming Pool
1 no.of MC+4
Excavation in Hard Rock 150m³ dumper
1 no.of MC+4
Excavation In Soft Rock 300m³ dumper
52 Concreting
1000sft con. 9" thick
Con.P.C.C By Mixer wall 2M, 10 MC, 4FC
Con .Bottom slab 1000sft con.6"thick 2M, 10 MC, 4FC
R.C.C.Pardi 200sft .6"thick
Tiling 50sft 1 M, 1 MC
53 Steel work
R.C.C.Paradi Binding 200sft 1M, 2 MC
Slab 400sft 1M, 2 MC
54 Carpenter
Shuttering Pardi 100 sft 2M, 3 MC

Index:
1. M: Mason
2. MC: Male Coolie
3. FC: Female Coolie
4. C: Carpenter
5. F: Fitter
6. H: Helper