Sei sulla pagina 1di 73

ACT.

VOLUME VOLUME
ACCOMULATED CONCRETE CON. VOL. BOQ FW&REBAR
OCT 16-30 2019 GF-RD GF-RD
5Ksi
STAIR 24 314.223156844 343 314.2231568443

8.5Ksi
COLUMN 157.6 1631.448 1583 2888.98

8.5Ksi
SHEARWALL 88 1631.448 1680 2938.208
50

5Ksi
RW 0 1863.19 1698 1863.19

6Ksi
SLAB/BEAMS & GIRDERS 803 4533.44 7215 11752.33

6Ksi/8.5Ksi
LINK BEAM 2.4 121.1784 123 235.668

PRECAST 132.25 3035.798 (meter)

CHB WALL(MASONRY) 111.99 6530 sqm 150MM CHB


8335 sqm 100MM CHB

CHB (PLASTERING 275 24206 sqm

RUBBED CONCRETE
Column 13.17 10,816.15 7694 sqm
Retaining Wall 13.17 3,212.03 3203 sqm
RC Wall 13.17 12,724.80 12948 sqm
Ramp sqm
Drop Wall 13.17 2,656.00 2504 sqm
Sides of Beams 13.17 30,976.23 22959 sqm
Smooth Formed Concrete, Rubbed Finish 13.17 34,875.00 19246 sqm

WHEEL GUARD 5 355.00 pcs

CEMENT CONCRETE CURB 37 1788 sqm

TOTAL VOLUME 1075 CU.M.


1715.24
50

2938.208
1631.448
FW&REB.
BOQ %WT ACCOM.
CONCRETE FW&REBAR

343 7.638% 7.64% FW & REBAR

2414 10.073% 6.627% 1564.577 2378.297

CONRETE
3110 5.394% 1.702%

1880.647
3544.747
0.000% 0.00%

12857 11.130% 7.43% 11.130%

1.98% 1.02% MM^2


TOTAL ARE 1,682,478,110.00 1,682.48
4.356% 211.595121 TOTAL ARE 1,481,645,810.00 1,481.65

1.7150% ACCOMPLIS 127,439,801.00


0.00% ACCOMPLIS 98,466,691.90
252.37
1.14% 6.65% 222.25

to date previous 93.35% 42.40%


0.122% 1,139.00 1,139.00
0.410% 1,885.17 1,850.16
0.103% 436.53 357.01 79
0.496% 13.1666666666667
0.496% 2,915.15 2,915.15
0.043% 4,847.87 4,847.87
0.038% 939.27 939.27

1.41%

2.07%

#REF!
FLOOR LEVEL SHEARWALL
ACTUAL ESTIMATE
FOUNDATION/UNDERGROUND 4.1 89.544
BASEMENT 5 3.5 76.44
BASEMENT 4 3.5 76.44
BASEMENT 3 3.5 76.44
BASEMENT 2 3.5 76.44
BASEMENT 1 4.75 103.74
GROUND FLOOR 5.05 110.292
2ND FLOOR 3.2 69.888
3RD FLOOR 3.2 69.888
4TH FLOOR 3.2 69.888
5TH FLOOR 3.2 69.888
6TH FLOOR 3.2 69.888
7TH FLOOR 3.2 69.888
8TH FLOOR 7.6 165.984
9TH FLOOR 4 87.36
10TH FLOOR 4 87.36
11TH FLOOR 4 87.36
12TH FLOOR 4 87.36
14TH FLOOR 1631.448 4 87.36
15TH FLOOR 4 4 87.36
16TH FLOOR 4 4 87.36
17TH FLOOR 4 4 87.36
18TH FLOOR 4 4 87.36
19TH FLOOR 4 4 87.36
20TH FLOOR 5.5 120.12
21ST FLOOR 4 87.36
22ND FLOOR 4 87.36
23RD FLOOR 4 87.36
24TH FLOOR 1 4 58.24
25TH FLOOR 4 58.24
26TH FLOOR 4 58.24
27TH FLOOR 4 58.24
28TH FLOOR 4 58.24
29TH FLOOR 4 58.24
30TH FLOOR 4 58.24
31ST FLOOR 5.5 80.08
32RD 2
33ROOF APEX (partially) 2938.208
TOTAL CONCRETE VOLUME
BEAMS &
GIRDERS/ RETAININ SLAB ON GRADE STAIRS
SHEARWALL SUSPENDED LINK BEAM G WALL
SLABS

3110 11752.33 235.668 1863.19 314.22315684


0

8.5 3091.42
7 3654.41
6 7218.89 121.1784
5 4533.44 114.4896 1863.19 314.22315684

SLAB ON GRADE WHEEL GUARD


M^2 TOTAL 336
ACCOMPLISHED 77 1
WT% 22.92% 1
92.43% 1
91.40% 1
7.57% 1
8.60% 1
1
1
1
1
1
1

WT% 3.226% 16.67%

RETAINING WALL
3.5
3.5
3.5
3.5
5.5
1.25 6.02%
20.75
93.98%

LINK BEAM W
6-10TH F LB1 600
LB2 600

LB1 TOTAL GF-21F


LB2 TOTAl GF-21F

LB1 TOTAL 22-31F


LB2 TOTAl 22-31F

7K 24TH FLOOR #VALUE!


6K 17TH FLOOR
LINK BEAM
4.1 FOUNDATION/UNDERGROUND
3.5 BASEMENT 5
3.5 BASEMENT 4
3.5 BASEMENT 3
3.5 BASEMENT 2
4.75 BASEMENT 1
5.05 GROUND FLOOR 8.6556
3.2 2ND FLOOR 8.6556
3.2 3RD FLOOR 8.6556
3.2 4TH FLOOR 8.6556
3.2 5TH FLOOR 8.6556
3.2 6TH FLOOR 8.6556
3.2 7TH FLOOR 8.6556
7.6 8TH FLOOR 8.6556
4 9TH FLOOR 8.6556
4 10TH FLOOR 8.6556
4 11TH FLOOR 8.6556
4 12TH FLOOR 8.6556
4 14TH FLOOR 8.6556
4 15TH FLOOR 8.6556
4 16TH FLOOR 8.6556
4 17TH FLOOR 8.6556
4 18TH FLOOR 8.6556
4 19TH FLOOR 8.6556
5.5 20TH FLOOR 8.6556
4 21ST FLOOR 8.6556
4 22ND FLOOR 6.2556
4 23RD FLOOR 6.2556
4 24TH FLOOR 6.2556
4 25TH FLOOR 6.2556
4 26TH FLOOR 6.2556
4 27TH FLOOR 6.2556
4 28TH FLOOR 6.2556
4 29TH FLOOR 6.2556
4 30TH FLOOR 6.2556
5.5 31ST FLOOR 6.2556
2 32RD 6.2556

241.9236
COLUMN

2888.98

2075.26
813.72

WHEEL GUARD ACCOMPLISHED carlift


B5 10 34 37 27
B4 26 30 33
B3 26 30 33
B2 15 30 33
B1 26 11 26
GF
F2 15 22
F3 31 31
F4 31 31
F5 31 31
F6 31 31
F7 31 31
F8 16 1 16
77 302 355

90 7.188
0.253521 5.4
1,478,749,285.21
22,003,424.18
18,816,374.70

D V PRECAST WALL
800 1.2 CU.M 2.5M 4X
900 1.9278 CU.M 3.57M 2X FOUNDATION/UNDERGRO
BASEMENT 5
BASEMENT 4
4.8 8.6556 BASEMENT 3
3.8556 BASEMENT 2
BASEMENT 1
2.4 6.2556 GF
3.8556 F2
F3
F4
F5
0 F6
0.032258 F7
F8
F9
LINK BEAM F10
LB1 LB2 F11
A1 1 F12
A2 1 2 F14
A3 1 0 F15
A4 1 0 F16
F17
1 F18
1 F19
1 F20
1 F21
1 2 F22
1 F23
F24
F25
F26
F27
F28
F29
F30
F31
32RD
33ROOF APEX (partially)
RUBBED CONCRETE

ITEM TOTAL AREA APPLICABLE (sq.m) LAST BILLED

Column 10,816.15 sq.m 649.81 96.8045425 553.0054575 5.11%


Retaining Wall 3,212.03 sq.m 916.31 210.227364 706.0826365 21.98%
Girders & Beams 30,976.23 sq.m 1,349.62 274.139636 1,075.48 3.47%
Ceilings/ Soffits 34,875.00 sq.m 2,718.89 671.34375 2,047.55 5.87%
Shear Wall 12,724.80 sq.m 18.03

Column 10,816.15 217.08 260.56


Retaining Wall 3,212.03 536.36 300.88
Shear Wall 12,724.80
Sides of Beams 30,976.23 336.38 199.59 479.01
Ceilings 34,875.00 1,119.45 40.14 869.66
1,478.75 221.81
22.00 3.30
18.82 2.82

215.69

167.833

4.1
3.5
3.5 117.7005
3.5 3.877%
3.5
4.75
5.05
3.2 67.568 10.385 4.68 6.26 5.66 9.58
3.2 100.265 10.385 2.34 6.26 5.66 9.6
3.2 100.265 10.385 2.34 6.26 5.66 9.6
3.2 100.265 10.385 2.34 6.26 5.66 9.6
3.2 100.265 10.385 2.34 6.26 5.66 9.6
3.2 100.265 10.385 2.34 6.26 5.66 9.6
7.6 84.305 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
5.5 70.845 10.385 2.34 6.26 5.66 9.6
4 70.845 10.385 2.34 6.26 5.66 9.6
4 111.23 10.38 3.01 6.26 5.66 6.55
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
4 143.33 36.13 16.96 37.1 9.89 6.65
5.5 143.33 36.13 16.96 37.1 9.89 6.65
2 131.26 131.26

3035.798
TO DATE 10-Jan

867.58 2.91% 1,139.00 Column


1462.18 23.54% 1,850.16 Retaining Wall
2032.28 3.09% 357.01 Shear Wall
3991.99 5.58% 2,915.15 Sides of Beams
60.94 0.48% 4,847.87 Ceilings
939.27 Walls
14.07 233.83 142.04 867.58
425.54 199.4 1,462.18
60.94 60.94
117.76 456.25 57.28 359.91 26.1 2,032.28
74.88 751.8 190.68 513.48 431.9 3,991.99
10.03 4.79 6.273 9.91
9.3 4.16 9.58 10.52 10.03 4.79 2.13 5.6 9.91
9.3 4.16 9.58 10.52 10.03 4.79 2.13 5.6 9.91
9.3 4.16 9.58 10.52 10.03 4.79 2.13 5.6 9.91
9.3 4.16 9.58 10.52 10.03 4.79 2.13 5.6 9.91
9.3 4.16 9.58 10.52 10.03 4.79 2.13 5.6 9.91
9.3 4.16 10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
6.8 6.87 5.71 16.68 6.71 10.03 4.79 6.27 5.6
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
10.03 4.79 6.27 5.6 9.91
APPROXIMATE AREA

10,816.15 7694 0.11


3,212.03 3203 0.58
13,085.60 12948 0.03
31,178.80 1634 0.09
35,970.18 870 0.13
2,655.62 22959 0.35
19246
to date
48.65
74
39.52
16.74
18.84
14.34
30
48
28.215
18.693
13.98
31.14

382.118
9.91
LOCATION TOTAL VOLUME UNIT
FOUNDATION/UNDERGROUND
BEAMS & GIRDERS 27.15 cu.m
RETAINING WALL 185.81 cu.m
UNDER TANKS - WALL 320.3 cu.m
UNDER TANKS - SLAB 292.22 cu.m
BASEMENT 5
BEAMS & GIRDERS 27.15 cu.m
COLUMNS 176.72 cu.m
SLAB 190.87 cu.m
RETAINING WALL 223.35 cu.m
SHEARWALL 158.63 cu.m
BASEMENT 4
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 190.87 cu.m
RETAINING WALL 272.13 cu.m
SHEARWALL 158.63 cu.m
BASEMENT 3
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 190.87 cu.m
RETAINING WALL 272.13 cu.m
SHEARWALL 158.63 cu.m
BASEMENT 2
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 190.87 cu.m
RETAINING WALL 272.13 cu.m
SHEARWALL 158.63 cu.m
BASEMENT 1
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 190.87 cu.m
RETAINING WALL 317.34 cu.m
SHEARWALL 215.59 cu.m
GROUND FLOOR
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 335.13 cu.m
SHEARWALL 228.89 cu.m
2ND FLOOR
BEAMS & GIRDERS 176.72 cu.m
COLUMNS 176.72 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
3RD FLOOR
BEAMS & GIRDERS 189.16 cu.m
COLUMNS 70.34 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
4TH FLOOR
BEAMS & GIRDERS 189.16 cu.m
COLUMNS 70.34 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
5TH FLOOR
BEAMS & GIRDERS 189.16 cu.m
COLUMNS 64.96 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
6TH FLOOR
BEAMS & GIRDERS 189.16 cu.m
COLUMNS 64.96 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
7TH FLOOR
BEAMS & GIRDERS 189.16 cu.m
COLUMNS 64.96 cu.m
SLAB 174.23 cu.m
SHEARWALL 145.04 cu.m
8TH FLOOR
BEAMS & GIRDERS 200.5 cu.m
COLUMNS 153.22 cu.m
SLAB 179.01 cu.m
SHEARWALL 145.04 cu.m
9TH FLOOR
BEAMS & GIRDERS 188.74 cu.m
COLUMNS 80.64 cu.m
SLAB 174.23 cu.m
SHEARWALL 271.94 cu.m
10TH FLOOR
BEAMS & GIRDERS 190.5 cu.m
COLUMNS 67.2 cu.m
SLAB 174.23 cu.m
SHEARWALL 181.3 cu.m
11TH FLOOR
BEAMS & GIRDERS 190.5 cu.m
COLUMNS 67.2 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
12TH FLOOR
BEAMS & GIRDERS 190.5 cu.m
COLUMNS 67.2 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
14TH FLOOR
BEAMS & GIRDERS 188.47 cu.m
COLUMNS 67.2 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
15TH FLOOR
BEAMS & GIRDERS 188.47 cu.m
COLUMNS 67.2 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
16TH FLOOR
BEAMS & GIRDERS 188.47 cu.m
COLUMNS 67.2 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
17TH FLOOR
BEAMS & GIRDERS 183.29 cu.m
COLUMNS 60.48 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
18TH FLOOR
BEAMS & GIRDERS 183.29 cu.m
COLUMNS 60.48 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
19TH FLOOR
BEAMS & GIRDERS 183.29 cu.m
COLUMNS 60.48 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
20TH FLOOR
BEAMS & GIRDERS 183.29 cu.m
COLUMNS 60.48 cu.m
SLAB 166.56 cu.m
SHEARWALL 181.3 cu.m
21ST FLOOR
BEAMS & GIRDERS 185.59 cu.m
COLUMNS 83.16 cu.m
SLAB 168.94 cu.m
SHEARWALL 181.3 cu.m
22ND FLOOR
BEAMS & GIRDERS 181.11 cu.m
COLUMNS 37.84 cu.m
SLAB 156.92 cu.m
SHEARWALL 249.28 cu.m
23RD FLOOR
BEAMS & GIRDERS 126.37 cu.m
COLUMNS 35.84 cu.m
SLAB 111.13 cu.m
SHEARWALL 181.3 cu.m
24TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 35.84 cu.m
SLAB 108.93 cu.m
SHEARWALL 776.79 cu.m
25TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 35.84 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
26TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 35.84 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
27TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 35.84 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
28TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 31.36 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
29TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 31.36 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
30TH FLOOR
BEAMS & GIRDERS 122.19 cu.m
COLUMNS 31.36 cu.m
SLAB 108.93 cu.m
SHEARWALL 159.72 cu.m
31ST FLOOR
BEAMS & GIRDERS 122.18 cu.m
COLUMNS 43.12 cu.m
SLAB 108.93 cu.m
SHEARWALL 219.62 cu.m
TOTAL 23250.33

ITEM No. FLOOR LEVEL FOOTING COLUMNS


1 FOUNDATION 650.96
2 B5 596.68
3 B4 10.08
4 B3 248.64
5 B2 240.96
6 B1 240.96
7 GF 240.96
8 2F 308.48
9 3F 308.48
10 4F 308.48
11 5F 293.12
12 6F 293.12
13 7F 293.12
14 8F 693.12
15 9F 364.84
16 10F 326.4
17 11F 326.4
18 12F 326.4
19 14F 326.4
20 15F 326.4
21 16F 326.4
22 17F 307.2
23 18F 307.2
24 19F 307.2
25 20F 307.2
26 21F 422.4
27 22F 208
28 23F 192
29 24F 192
30 25F 192
31 26F 192
32 27F 192
33 28F 179.2
34 29F 179.2
35 30F 179.2
36 31F 246.4

FLOOR LEVEL AREA REBAR GRADE 60 REBAR GRADE 40


FOUNDATION 3392.338 460768.561 13120.8
BASEMENT 5 1779.8963 128735.561849819 25532.7204813492
BASEMENT 4 1779.8963 128735.561849819 25532.7204813492
BASEMENT 3 1779.8963 128735.561849819 25532.7204813492
BASEMENT 2 1779.8963 128735.561849819 25532.7204813492
BASEMENT 1 1779.8963 128735.561849819 25532.7204813492
GROUND FLOOR 1779.8963 128735.561849819 25532.7204813492
2ND FLOOR 1484.75757 107388.896749053 21298.9374815697
3RD FLOOR 1484.75757 107388.896749053 21298.9374815697
4TH FLOOR 1484.75757 107388.896749053 21298.9374815697
5TH FLOOR 1484.75757 107388.896749053 21298.9374815697
6TH FLOOR 1484.75757 107388.896749053 21298.9374815697
7TH FLOOR 1484.75757 107388.896749053 21298.9374815697
8TH FLOOR 1484.75757 107388.896749053 21298.9374815697
9TH FLOOR 1484.75757 107388.896749053 21298.9374815697
10TH FLOOR 1484.75757 107388.896749053 21298.9374815697
11TH FLOOR 1484.75757 107388.896749053 21298.9374815697
12TH FLOOR 1484.75757 107388.896749053 21298.9374815697
14TH FLOOR 1484.75757 107388.896749053 21298.9374815697
15TH FLOOR 1484.75757 107388.896749053 21298.9374815697
16TH FLOOR 1484.75757 107388.896749053 21298.9374815697
17TH FLOOR 1484.75757 107388.896749053 21298.9374815697
18TH FLOOR 1484.75757 107388.896749053 21298.9374815697
19TH FLOOR 1484.75757 107388.896749053 21298.9374815697
20TH FLOOR 1484.75757 107388.896749053 21298.9374815697
21ST FLOOR 1484.75757 107388.896749053 21298.9374815697
22ND FLOOR 1484.75757 107388.896749053 21298.9374815697
23RD FLOOR 980.5454 70920.4592358867 14065.9832921012
24TH FLOOR 980.5454 70920.4592358867 14065.9832921012
25TH FLOOR 980.5454 70920.4592358867 14065.9832921012
26TH FLOOR 980.5454 70920.4592358867 14065.9832921012
27TH FLOOR 980.5454 70920.4592358867 14065.9832921012
28TH FLOOR 980.5454 70920.4592358867 14065.9832921012
29TH FLOOR 980.5454 70920.4592358867 14065.9832921012
30TH FLOOR 980.5454 70920.4592358867 14065.9832921012
31ST FLOOR 980.5454 70920.4592358867 14065.9832921012
ROOFDECK 980.5454 70920.4592358867 14065.9832921012
Total 53572.3212000001
FORMWORKS UNIT DESIGN(psi) BAGS OF CEMENT VOLUME POURED

231 sq.m 6000 psi 23.00cu.m


sq.m 5000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 6000 psi 825.48 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 1542.89 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 8500 psi 776.72 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 8500 psi 975.07 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 8500 psi 975.07 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 8500 psi 975.07 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 8500 psi 1077.24 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 917.46 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 672.71 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 578.77 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 578.77 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 573.39 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 573.39 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 573.39 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 677.77 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 715.55 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 613.23 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 605.56 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 605.56 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 8500 psi 603.53 23.00cu.m
23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 6000 psi 23.00cu.m
sq.m 7000 psi 603.53 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 603.53 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 591.63 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 591.63 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 591.63 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 591.63 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 618.99 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 625.15 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 454.64 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 1043.75 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 426.68 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 426.68 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 426.68 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 422.2 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 422.2 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 422.2 23.00cu.m
23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 23.00cu.m
sq.m 5000 psi 23.00cu.m
sq.m 7000 psi 493.85 23.00cu.m

HORIZONTAL
SHEARWALL RETAINING WALL FTB/GIRDER/BEAM/SLAB TOTAL CSA(sq.m)
607.5 336.33 1594.79
362.38 604.73 2208.7 3772.49
335.72 604.73 2208.7 3159.23
335.72 604.73 2208.7 3397.79
335.72 705.2 2208.7 3490.58
335.72 883.59 2511.44 3971.71
455.62 2200.1 2896.68
484.4 2139.07 2931.95
306.94 2139.07 2754.49
306.94 2139.07 2754.49
306.94 2139.07 2739.13
306.94 2139.07 2739.13
306.94 2139.07 2739.13
306.94 2127.65 3127.71
306.94 2066.95 2738.73
575.52 2073.11 2975.03
383.68 2073.11 2783.19
383.68 2073.11 2783.19
383.68 2070.57 2780.65
383.68 2070.57 2780.65
383.68 2070.57 2780.65
372.61 2063.85 2743.66
383.68 2063.85 2754.73
383.68 2063.85 2754.73
383.68 2063.85 2754.73
383.68 2087.05 2893.13
383.68 1981.05 2572.73
412.45 1404.56 2009.01
383.68 1361.05 1936.73
306.96 1361.05 1860.01
306.96 1361.05 1860.01
306.96 1361.05 1860.01
306.96 1361.05 1847.21
306.96 1361.05 1847.21
306.96 1361.05 1847.21
306.96 1358.97 1912.33
95144.83

TOTAL / FLOOR SLAB REBAR


473889.361 6.33% 9.83%
154268.2823312 3.32% 3.20%
154268.2823312 3.32% 3.20%
154268.2823312 3.32% 3.20%
154268.2823312 3.32% 3.20%
154268.2823312 3.32% 3.20%
154268.2823312 3.32% 3.20%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
128687.8342306 2.77% 2.67%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
84986.44252799 1.83% 1.76%
4823120.164879
WT1.% WT OVERALL% UNIT

84.71% 6.33% 1 UG/FOUNDATION 825.48


12.38% 3.32% 2 B5 776.72
7.18% 3.32% 3 B4 975.07
7.87% 3.32% 4 B3 975.07 TOTAL QUANTITY (BO
5 B2 975.07 REBAR
84.71% 3.32% 6 B1 1077.24 5,117,018.00
13.01% 3.32% 7 GF 917.46
12.05% 2.77% 8 2F 672.71
10.30% 2.77% 9 3F 578.77
14.50% 2.77% 10 4F 578.77
11 5F 573.39
13.01% 2.77% 12 6F 573.39
13.01% 2.77% 13 7F 573.39
12.05% 2.77% 14 8F 677.77
8.45% 2.77% 15 9F 715.55
14.50% 2.77% 16 10F 613.23
17 11F 605.56
13.01% 2.77% 18 12F 605.56
13.01% 2.77% 19 14F 603.53
12.05% 2.77% 20 15F 603.53
8.45% 2.77% 21 16F 603.53
14.50% 2.77% 22 17F 591.63
23 18F 591.63
13.01% 2.77% 24 19F 591.63
13.01% 2.77% 25 20F 591.63
12.05% 2.77% 26 21F 618.99
8.45% 2.77% 27 22F 625.15
14.50% 1.83% 28 23F 454.64
29 24F 1043.75
13.01% 1.83% 30 25F 426.68
13.01% 1.83% 31 26F 426.68
12.05% 1.83% 32 27F 426.68
7.25% 1.83% 33 28F 422.2
10.67% 1.83% 34 29F 422.2
35 30F 422.2
13.01% 1.83% 36 31F 493.85
13.01% 1.83% RD
6.86% 0.00% 23250.33
10.05% 100.00%
13.01% 0.00%
13.01% 0.00%

15.86% 0.00%

12.16% 0.00%
32.70% 0.00%
13.20% 0.00%
15.86% 0.00%

12.16% 0.00%
32.70% 0.00%
13.20% 0.00%
15.86% 0.00%

12.16% 0.00%
35.41% 0.00%
13.20% 0.00%
15.86% 0.00%

12.16% 0.00%
35.41% 0.00%
13.20% 0.00%
15.86% 0.00%

12.16% 0.00%
35.41% 0.00%
13.20% 0.00%
15.86% 0.00%

11.47% 0.00%
15.01% 0.00%
12.85% 0.00%
15.86% 0.00%

12.19% 0.00%
28.52% 0.00%
13.20% 0.00%
8.46% 0.00%

12.07% 0.00%
34.23% 0.00%
13.20% 0.00%
12.69% 0.00%
12.07% 0.00%
34.23% 0.00%
13.81% 0.00%
12.69% 0.00%

12.07% 0.00%
34.23% 0.00%
13.81% 0.00%
12.69% 0.00%

12.20% 0.00%
34.23% 0.00%
13.81% 0.00%
12.69% 0.00%

12.20% 0.00%
34.23% 0.00%
13.81% 0.00%
12.69% 0.00%

12.20% 0.00%
34.23% 0.00%
13.81% 0.00%
12.69% 0.00%

12.55% 0.00%
38.03% 0.00%
13.81% 0.00%
12.69% 0.00%

12.55% 0.00%
38.03% 0.00%
13.81% 0.00%
12.69% 0.00%

12.55% 0.00%
38.03% 0.00%
13.81% 0.00%
12.69% 0.00%

12.55% 0.00%
38.03% 0.00%
13.81% 0.00%
12.69% 0.00%
12.39% 0.00%
27.66% 0.00%
13.61% 0.00%
12.69% 0.00%

12.70% 0.00%
60.78% 0.00%
14.66% 0.00%
9.23% 0.00%

18.20% 0.00%
64.17% 0.00%
20.70% 0.00%
12.69% 0.00%

18.82% 0.00%
64.17% 0.00%
21.11% 0.00%
2.96% 0.00%

18.82% 0.00%
64.17% 0.00%
21.11% 0.00%
14.40% 0.00%

18.82% 0.00%
64.17% 0.00%
21.11% 0.00%
14.40% 0.00%

18.82% 0.00%
64.17% 0.00%
21.11% 0.00%
14.40% 0.00%

18.82% 0.00%
73.34% 0.00%
21.11% 0.00%
14.40% 0.00%

18.82% 0.00%
73.34% 0.00%
21.11% 0.00%
14.40% 0.00%
18.82% 0.00%
73.34% 0.00%
21.11% 0.00%
14.40% 0.00%

18.82% 0.00%
53.34% 0.00%
21.11% 0.00%
10.47% 0.00%

true total??? SHEARWALL HEIGHT


1594.79 5.2
3772.49 3.5
3159.23 3.5
3397.79 3.5
3490.57 3.5
3971.71 4.75
2896.68 5.05
2931.95 3.2
4893.56 3.2
4893.56 3.2
4878.2 3.2
4878.2 3.2
4878.2 3.2
5255.37 3.2
4805.65 6
5048.14 4
4856.3 4
4856.3 4
4851.22 4
4851.22 4
4851.22 4
4807.51 4
4818.59 4
4818.59 4
4818.59 4
4980.19 4
4553.79 5.5
3413.56 4
3297.78 4
3221.06 4
3221.06 4
3221.06 4
3208.26 4
3208.26 4
3208.26 4
3271.3 5.5
147080.21

FE STAIR VOLUME COMPUTAIONS CONCRETE VOLUME


LENGTH
FES-1
B5 B4 16413 1.225 150 3.01588875
B4 B3 16524 1.225 150 3.036285
B3 B2 16855 1.225 150 3.09710625
B2 B1 1828200.00% 1.225 150 3.3593175
B1 GF 27862 1.225 150 5.1196425
GF 2F 28634 1.225 150 5.2614975
2F F3 16925 1.225 150 3.10996875
F3 F4 16770 1.225 150 3.0814875
F4 F5 16860 1.225 150 3.098025
F5 F6 16705 1.225 150 3.06954375
F6 F7 16685 1.225 150 3.06586875
F7 F8 16670 1.225 150 3.0631125
F8 F9 29314 1.225 150 5.3864475
F9 F10 17205 1.225 150 3.16141875
F10 F11 17119 1.225 150 3.14561625
F11 F12 17168 1.225 150 3.15462
F12 F14 17073 1.225 150 3.13716375
F14 F15 17122 1.225 150 3.1461675
F15 F16 17157 1.225 150 3.15259875
F16 F17 17122 1.225 150 3.1461675
F17 F18 17065 1.225 150 3.13569375
F18 F19 17165 1.225 150 3.15406875
F19 F20 17142 1.225 150 3.1498425
F20 F21 18830 1.225 150 3.4600125
F21 F22 27742 1.225 150 5.0975925
F22 F23 16714 1.225 150 3.0711975
F23 F24 13568 1.225 150 2.49312
F24 F25 13902 1.225 150 2.5544925
F25 F26 13734 1.225 150 2.5236225
F26 F27 13720 1.225 150 2.52105
F27 F28 13795 1.225 150 2.53483125
F28 F29 13775 1.225 150 2.53115625
F29 F30 13747 1.225 150 2.52601125
F30 F31 13329 1.225 150 2.44920375
F31 F32 110.00983875
F32 F33

BOQ
OPEN LOBBY STAIR
HIEGHT WIDTH LENGTH RISE
B5 B4 2 1200 2150
B4 B3 2 1200 2150
B3 B2 2 1200 2150
B2 B1 2 1200 2150
B1 GF 2 1200 2150
GF 2F 1.6 1200 2150
2F F3 1.6 1200 2150
F3 F4 1.6 1200 2150
F4 F5 1.6 1200 2150
F5 F6 1.6 1200 2150
F6 F7 1.6 1200 2150
F7 F8 1.6 1200 2150
F8 F9 1.6 1200 2150
F9 F10
F10 F11
F11 F12
F12 F14
F14 F15
F15 F16
F16 F17
F17 F18
F18 F19
F19 F20
F20 F21
F21 F22
F22 F23
F23 F24
F24 F25
F25 F26
F26 F27
F27 F28
F28 F29
F29 F30
F30 F31
F31 F32
F32 F33
DESIGNATION
UG/FOUNDATION
B5
B4
B3
TOTAL QUANTITY (BOQ) B2
CONCRETE FORMWORKS con. fw rebar B1
24,193.00 128,293.00 26.27% 23.18% 29.02% GF
2F
23,076.10 147,080.21 V H 3F
38.00% 26.73% 4F
5F
23.18% 20.14% 6F
7F
8F
9F
10F
11F
12F
14F
6522.11 435.12 15F
29.923% 16F
17F
18F
19F
20F
21F
22F
23F
24F
25F
26F
27F
28F
29F
30F
31F
RD

TOTAL
ETE VOLUME

FES-2 TOTAL TOTAL STAIR VOLUME


3.01588875 6.0317775 13.2782
3.036285 6.07257 13.31899
3.09710625 6.1942125 13.44063
3.3593175 6.718635 13.96506
5.1196425 10.239285 17.48571
5.2614975 10.522995 17.76942
3.10996875 6.2199375 13.46636
3.0814875 6.162975 13.4094
3.098025 6.19605 13.44247
3.06954375 6.1390875 13.38551
3.06586875 6.1317375 13.37816
3.0631125 6.126225 13.37265
5.3864475 10.772895 18.01932
3.16141875 6.3228375 6.322838
3.14561625 6.2912325 6.291233
3.15462 6.30924 6.30924
3.13716375 6.2743275 6.274328
3.1461675 6.292335 6.292335
3.15259875 6.3051975 6.305198
3.1461675 6.292335 6.292335
3.13569375 6.2713875 6.271388
3.15406875 6.3081375 6.308138
3.1498425 6.299685 6.299685
3.4600125 6.920025 6.920025
5.0975925 10.195185 10.19519
3.0711975 6.142395 6.142395
2.49312 4.98624 4.98624
2.5544925 5.108985 5.108985
2.5236225 5.047245 5.047245
2.52105 5.0421 5.0421
2.53483125 5.0696625 5.069663
2.53115625 5.0623125 5.062313
2.52601125 5.0520225 5.052023
2.44920375 4.8984075 4.898408
220.0196775
314.2232

CU.M.
343 cu.m 122.9803

RUN VOLUME
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022
7.246421488022

94.20348

0.0324
SHEAR WALL(CONCRETE/FW/REBAR) SW% SUSPENDED SLAB(CON.) S-SLAB(CON.)%
5.20 m 3.60% 3392.338 6.33%
3.50 m 2.42% 1779.8963 3.32%
3.50 m 2.42% 1779.8963 3.32%
3.50 m 2.42% 1779.8963 3.32%
3.50 m 2.42% 1779.8963 3.32%
4.75 m 3.29% 1779.8963 3.32%
5.05 m 3.50% 1779.8963 3.32%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
3.20 m 2.22% 1484.75757 2.77%
6.00 m 4.16% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
4.00 m 2.77% 1484.75757 2.77%
5.50 m 3.81% 1484.75757 2.77%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
4.00 m 2.77% 980.5454 1.83%
5.50 m 3.81% 980.5454 1.83%
980.5454 1.83%

144.40 m 53572.3212000001 100.00%


SUSPENDED SLAB (FW) S-SLAB(FW) S-SLAB (REBAR) S-SLAB (REBAR)%
1594.79 1.66% 473889.361 9.83%
3772.49 3.92% 154268.2823312 3.20%
3159.23 3.29% 154268.2823312 3.20%
3397.79 3.53% 154268.2823312 3.20%
3490.58 3.63% 154268.2823312 3.20%
3971.71 4.13% 154268.2823312 3.20%
2896.68 3.01% 154268.2823312 3.20%
2931.95 3.05% 128687.8342306 2.67%
2754.49 2.87% 128687.8342306 2.67%
2754.49 2.87% 128687.8342306 2.67%
2739.13 2.85% 128687.8342306 2.67%
2739.13 2.85% 128687.8342306 2.67%
2739.13 2.85% 128687.8342306 2.67%
3127.71 3.25% 128687.8342306 2.67%
2738.73 2.85% 128687.8342306 2.67%
2975.03 3.09% 128687.8342306 2.67%
2783.19 2.90% 128687.8342306 2.67%
2783.19 2.90% 128687.8342306 2.67%
2780.65 2.89% 128687.8342306 2.67%
2780.65 2.89% 128687.8342306 2.67%
2780.65 2.89% 128687.8342306 2.67%
2743.66 2.85% 128687.8342306 2.67%
2754.73 2.87% 128687.8342306 2.67%
2754.73 2.87% 128687.8342306 2.67%
2754.73 2.87% 128687.8342306 2.67%
2893.13 3.01% 128687.8342306 2.67%
2572.73 2.68% 128687.8342306 2.67%
2009.01 2.09% 84986.44252799 1.76%
1936.73 2.01% 84986.44252799 1.76%
1860.01 1.93% 84986.44252799 1.76%
1860.01 1.93% 84986.44252799 1.76%
1860.01 1.93% 84986.44252799 1.76%
1847.21 1.92% 84986.44252799 1.76%
1847.21 1.92% 84986.44252799 1.76%
1847.21 1.92% 84986.44252799 1.76%
1912.33 1.99% 84986.44252799 1.76%
980.5454 1.02% 84986.44252799 1.76%

96125.3754 100.00% 4823120.164879 100.00%


COLUMN(CON.) COLUMN(CON.)% COLUMN(FW) COLUMN(FW%) DESIGNATION
141.512 5.79% 596.68 5.19% UG/FOUNDATION
85.75 3.51% 362.6 3.16% B5
85.75 3.51% 362.6 3.16% B4
81.83 3.35% 351.4 3.06% B3
111.055 4.54% 476.9 4.15% B2
147.294 6.02% 632.52 5.51% B1
70.336 2.88% 308.48 2.69% GF
70.336 2.88% 308.48 2.69% 2F
70.336 2.88% 308.48 2.69% 3F
64.96 2.66% 293.12 2.55% 4F
64.96 2.66% 293.12 2.55% 5F
64.96 2.66% 293.12 2.55% 6F
64.96 2.66% 293.12 2.55% 7F
64.96 2.66% 293.12 2.55% 8F
153.216 6.27% 693.12 6.03% 9F
80.64 3.30% 364.8 3.18% 10F
67.2 2.75% 326.4 2.84% 11F
67.2 2.75% 326.4 2.84% 12F
67.2 2.75% 326.4 2.84% 14F
67.2 2.75% 326.4 2.84% 15F
67.2 2.75% 326.4 2.84% 16F
67.2 2.75% 326.4 2.84% 17F
60.48 2.47% 307.2 2.67% 18F
60.48 2.47% 307.2 2.67% 19F
60.48 2.47% 307.2 2.67% 20F
83.16 3.40% 422.4 3.68% 21F
37.84 1.55% 208 1.81% 22F
35.84 1.47% 192 1.67% 23F
35.84 1.47% 192 1.67% 24F
35.84 1.47% 192 1.67% 25F
35.84 1.47% 192 1.67% 26F
35.84 1.47% 192 1.67% 27F
31.36 1.28% 179.2 1.56% 28F
31.36 1.28% 179.2 1.56% 29F
31.36 1.28% 179.2 1.56% 30F
43.12 1.76% 246.4 2.15% 31F
RD

2444.895 100.00% 11486.06 100.00%


DESIGNATION BEAM(CONC.) BEAM(CONC.%)
UG/FOUNDATION 27.15 0.47%
27.15 0.47%
176.72 3.05%
176.72 3.05%
176.72 3.05%
176.72 3.05%
176.72 3.05% 16.20%
176.72 3.05%
189.16 3.27%
189.16 3.27%
189.16 3.27%
189.16 3.27%
189.16 3.27%
200.5 3.46%
188.74 3.26%
190.5 3.29%
190.5 3.29%
190.5 3.29%
188.47 3.25%
188.47 3.25%
188.47 3.25%
183.29 3.17%
183.29 3.17%
183.29 3.17%
183.29 3.17%
185.59 3.21%
181.11 3.13%
126.37 2.18%
122.19 2.11%
122.19 2.11%
122.19 2.11%
122.19 2.11%
122.19 2.11%
122.19 2.11%
122.19 2.11%
122.18 2.11%

5790.31 100.00%
RETAINING
RETAINING
WALL CON. WALL %
POURED SUSPENDED SLAB COLUMNS BEAMS/GIRDERS
FLOOR LEVEL
UG/FOUNDATION
B5
B4
B3
B2
B1
GF
2F
3F
4F
5F
6F
7F
8F
9F
10F
11F
12F
14F
15F
16F
17F
18F
19F
20F
21F
22F
23F
24F
25F
26F
27F
28F
29F
30F
31F
RD
COLUMN(ACT.) HEIGHT(M)
SHEARWALL
137.76 4.1
6000 psi 70.56 3.5
5000 psi 3.5
8500 psi 3.5
7000 psi 3.5
4.75
5.05
3.2
3.2
3.2
3.2
3.2
1564.577 3.2
7.6
4
110 1578.5352 4
6899.52 1880.6472 4
1.594% 3820.79 36.79% 4
slab & beams 6ksi 7218.89 59.900% 4
4
SW8.5KSI 1777.4256 4
totAL ALL 3362.4216 7218.89 4
4
c 1070.0882568 4
COCNCRETE FOR 8.5KSI 1464.988 fw&r 1744.81538592 4
FW & REBAR TOTAL ALL COL. 2278.708 508.4469432 5.5
166.28018592 4
4
53.76 4
SHEARWALL SURFACE AREA 53.76 4
53.76 4
SW2A&2B 7.188 23.0016 53.76 4
SW1&3 5.4 17.28 53.76 4
53.76 4
53.76 4
73.92 5.5
SHEARWALL 2
ACTUAL ESTIMATE
4.1 89.544
3.5 76.44
3.5 76.44
3.5 76.44
3.5 76.44
4.75 103.74
5.05 110.292
3.2 69.888
3.2 69.888
3.2 69.888
3.2 69.888
3.2 69.888
3.2 69.888
7.6 165.984
4 87.36
4 87.36
4 87.36
4 87.36
1631.448 4 87.36
4 4 87.36
4 4 87.36
4 4 87.36
4 4 87.36
4 4 87.36
5.5 120.12
4 87.36
4 87.36
4 87.36
1 4 58.24
4 58.24
4 58.24
4 58.24
4 58.24
4 58.24
4 58.24
5.5 80.08
2
2938.208
2 2 2 1 1 1
COLUMN
C1 C2 C3 C4 C5 C6
FOUNDATION 0.98 1.05 0.98 0.98 0.98 1.19
BASEMENT 0.98 1.05 0.98 0.91 1.12 1.05
2ND FLOOR 0.91 0.91 0.91 0.91 0.98 0.98
5TH FLOOR 0.84 0.84 0.84 0.84 0.91 0.91
8TH FLOOR 0.84 0.84 0.84 0.84 0.84 0.84
10TH FLOOR 0.7 0.7 0.7 0.7 0.7 0.7
15TH FLOOR 0.7 0.7 0.7 0.7 0.7 0.7
17TH FLOOR 0.63 0.63 0.63 0.63 0.63 0.63
20TH FLOOR 0.63 0.63 0.63 0.63 0.63 0.63

0.63 0.63 0.63 0.63 0.63 0.63


0.63 0.63 0.63 0.63 0.63 0.63
CONCRETE VOLUME(CU.M.)

BEAMS & SLAB/BEAMS/


FLOOR LEVEL SLABS COLUMNS SHEARWALL
GIRDERS GIRDERS
FOUNDATION/UNDERGROUND 27.15 292.22 319.37 99.589 103.2216
BASEMENT 5 27.15 190.87 218.02 81.83 88.116
BASEMENT 4 176.72 190.87 367.59 81.83 88.116
BASEMENT 3 176.72 190.87 367.59 81.83 88.116
BASEMENT 2 176.72 190.87 367.59 81.83 88.116
BASEMENT 1 176.72 190.87 367.59 111.055 119.586
GROUND FLOOR 176.72 335.13 511.85 118.069 127.1388
2ND FLOOR 176.72 174.23 350.95 70.336 80.5632
3RD FLOOR 189.16 174.23 363.39 70.336 80.5632
4TH FLOOR 189.16 174.23 363.39 70.336 80.5632
5TH FLOOR 189.16 174.23 363.39 64.96 80.5632
6TH FLOOR 189.16 174.23 363.39 64.96 80.5632
7TH FLOOR 189.16 174.23 363.39 64.96 80.5632
8TH FLOOR 200.5 179.01 379.51 153.216 191.3376
9TH FLOOR 188.74 174.23 362.97 80.64 100.704
10TH FLOOR 190.5 174.23 364.73 67.2 100.704
11TH FLOOR 190.5 166.56 357.06 67.2 100.704
12TH FLOOR 190.5 166.56 357.06 67.2 100.704
14TH FLOOR 188.47 166.56 355.03 67.2 100.704
15TH FLOOR 188.47 166.56 355.03 67.2 100.704
16TH FLOOR 188.47 166.56 355.03 67.2 100.704
17TH FLOOR 183.29 166.56 349.85 60.48 100.704
18TH FLOOR 183.29 166.56 349.85 60.48 100.704
19TH FLOOR 183.29 166.56 349.85 60.48 100.704
20TH FLOOR 183.29 166.56 349.85 60.48 100.704
21ST FLOOR 185.59 168.94 354.53 83.16 138.468
22ND FLOOR 181.11 156.92 338.03 37.84 100.704
23RD FLOOR 126.37 111.13 237.5 35.84 79.104
24TH FLOOR 122.19 108.93 231.12 35.84 79.104
25TH FLOOR 122.19 108.93 231.12 35.84 79.104
26TH FLOOR 122.19 108.93 231.12 35.84 79.104
27TH FLOOR 122.19 108.93 231.12 35.84 79.104
28TH FLOOR 122.19 108.93 231.12 31.36 79.104
29TH FLOOR 122.19 108.93 231.12 31.36 79.104
30TH FLOOR 122.19 108.93 231.12 31.36 79.104
31ST FLOOR 122.18 108.93 231.11 43.12 108.768
32RD 69.234
33ROOF APEX (partially)
5790.31 5962.02 11752.33 2378.297 3534.8772

total cubic of concrete


CAST-IN-PLACE CONCRETE

Reinforced Concrete, 1000PSI


To lean Concrete; 50mm thk 43 cu.m OSM 1808

Reinforced Concrete, 5000PSI


To Retaining Wall Footing 71 cu.m OSM 1808
To Retaining Wall 1698 cu.m OSM 1808
To Footings 1850 cu.m OSM 1808
To Slab on Grade 84 cu.m OSM 1808
To RC Wall 1015 cu.m OSM 1808
To Stair 343 cu.m OSM 1808
To Concrete Saddle 24 cu.m OSM 1808
To Davit Pedestal 8 cu.m OSM 1808
To Concrete Pads 11 cu.m OSM 1808
To STP & Underground Utilities 425 cu.m OSM 1808

Reinforced Concrete, 6000PSI


To Beams & Girders 3953 cu.m OSM 1808
To Link Beams 123 cu.m OSM 1808
To Suspended Slab 3262 cu.m OSM 1808

Reinforced Concrete, 7000PSI


To Column 831 cu.m OSM 1808
To Shearwall 1430 cu.m OSM 1808
To Beams & Girders 2249 cu.m OSM 1808
To Link Beams 117 cu.m OSM 1808
To Suspended Slab 3393 cu.m OSM 1808

Reinforced Concrete, 8500PSI


To Column 1583 cu.m OSM 1808
To Shearwall 1680 cu.m OSM 1808

SS 6655
SOG 84
1 2 3 1 3 1

C7 C8 C9 C10 C11 C12


1.05 1.05 1.05 0.98 0.98 0.98
0.98 0.98 1.05 0.91 0.91 0.91
0.91 0.91 0.91 0.91 0.91 0.91
0.84 0.84 0.84 0.84 0.84 0.84
0.84 0.84 0.84 0.84 0.84 0.84
0.7 0.7 0.7 0.7 0.7 0.7
0.7 0.7 0.7 0.7 0.7 0.7
0.63 0.63 0.63 0.63 0.63 0.63
0.63 0.63 0.63 0.63 0.63 0.63

0.63 0.63 0.63 0.63 0.63 0.63


0.63 0.63 0.63 0.63 0.63 0.63
WEIGHT %

RETAINING LINK BEAMS & SLAB/BEAMS/ SHEARWAL


STAIRS SLABS COLUMNS
WALL BEAM GIRDERS GIRDERS L
185.81 0.47% 4.90% 2.72% 4.19% 2.92%
320.3 13.2782 0.47% 3.20% 1.86% 3.44% 2.49%
223.35 13.31899 3.05% 3.20% 3.13% 3.44% 2.49%
272.13 13.44063 3.05% 3.20% 3.13% 3.44% 2.49%
272.13 13.96506 3.05% 3.20% 3.13% 3.44% 2.49%
272.13 17.48571 3.05% 3.20% 3.13% 4.67% 3.38%
317.34 8.6556 17.76942 3.05% 5.62% 4.36% 4.96% 3.60%
8.6556 13.46636 3.05% 2.92% 2.99% 2.96% 2.28%
8.6556 13.4094 3.27% 2.92% 3.09% 2.96% 2.28%
8.6556 13.44247 3.27% 2.92% 3.09% 2.96% 2.28%
8.6556 13.38551 3.27% 2.92% 3.09% 2.73% 2.28%
8.6556 13.37816 3.27% 2.92% 3.09% 2.73% 2.28%
8.6556 13.37265 3.27% 2.92% 3.09% 2.73% 2.28%
8.6556 18.01932 3.46% 3.00% 3.23% 6.44% 5.41%
8.6556 6.322838 3.26% 2.92% 3.09% 3.39% 2.85%
8.6556 6.291233 3.29% 2.92% 3.10% 2.83% 2.85%
8.6556 6.30924 3.29% 2.79% 3.04% 2.83% 2.85%
8.6556 6.274328 3.29% 2.79% 3.04% 2.83% 2.85%
8.6556 6.292335 3.25% 2.79% 3.02% 2.83% 2.85%
8.6556 6.305198 3.25% 2.79% 3.02% 2.83% 2.85%
8.6556 6.292335 3.25% 2.79% 3.02% 2.83% 2.85%
8.6556 6.271388 3.17% 2.79% 2.98% 2.54% 2.85%
8.6556 6.308138 3.17% 2.79% 2.98% 2.54% 2.85%
8.6556 6.299685 3.17% 2.79% 2.98% 2.54% 2.85%
8.6556 6.920025 3.17% 2.79% 2.98% 2.54% 2.85%
8.6556 10.19519 3.21% 2.83% 3.02% 3.50% 3.92%
6.2556 6.142395 3.13% 2.63% 2.88% 1.59% 2.85%
6.2556 4.98624 2.18% 1.86% 2.02% 1.51% 2.24%
6.2556 5.108985 2.11% 1.83% 1.97% 1.51% 2.24%
6.2556 5.047245 2.11% 1.83% 1.97% 1.51% 2.24%
6.2556 5.0421 2.11% 1.83% 1.97% 1.51% 2.24%
6.2556 5.069663 2.11% 1.83% 1.97% 1.51% 2.24%
6.2556 5.062313 2.11% 1.83% 1.97% 1.32% 2.24%
6.2556 5.052023 2.11% 1.83% 1.97% 1.32% 2.24%
6.2556 4.898408 2.11% 1.83% 1.97% 1.32% 2.24%
6.2556 2.11% 1.83% 1.97% 1.81% 3.08%

1863.19 235.668 314.2232 100.00% 100.00% 100.00% 100.00% 98.04%

19528.6942
LINK BEAM W D
6-10TH F LB1 600 800
LB2 600 900

1808 LB1 TOTAL GF-21F 4.8


LB2 TOTAl GF-21F 3.8556

1808 LB1 TOTAL 22-31F 2.4


1808 LB2 TOTAl 22-31F 3.8556
1808
1808
1808 BOQ
1808 7K 117 240 114.4896
1808 6K 123 121.1784
1808
1808
1808

1808
1808
1808

1808
1808
1808
1808
1808

1808
1808
2 1 1 24
COLUMN
C13 C14 C15 C1 C2 C3 C4 C5
0.98 0.98 0.98 1.96 2.1 1.96 0.98 0.98
0.91 0.91 0.91 1.96 2.1 1.96 0.91 1.12
0.91 0.91 0.91 1.82 1.82 1.82 0.91 0.98
0.84 0.84 0.84 1.68 1.68 1.68 0.84 0.91
0.84 0.84 0.84 1.68 1.68 1.68 0.84 0.84
0.7 0.7 0.7 1.4 1.4 1.4 0.7 0.7
0.7 0.7 0.7 1.4 1.4 1.4 0.7 0.7
0.63 0.63 0.63 1.26 1.26 1.26 0.63 0.63
0.63 0.63 0.63 1.26 1.26 1.26 0.63 0.63

0.63 0.63 0.63


0.63 0.63 0.63
RETAININ LINK
G WALL BEAM
9.97% FW & REBAR
17.19%
11.99%
14.61%
14.61%
14.61% CONRETE
17.03% 3.67% 8.5 Ksi
3.67% 7.0 Ksi
3.67% 6.0 Ksi
3.67% 5.0 Ksi
3.67%
3.67%
3.67%
3.67% 41.24%
3.67%
3.67%
3.67% 44.967%
3.67%
3.67%
3.67% 61.77%
3.67% 37.94%
3.67%
3.67%
3.67%
3.67% 335.552
3.67%
2.65%
2.65%
2.65% SLAB/BEAM COLUMN
2.65%
2.65% CONCRETE 62.417% 59.360% 65.32%
2.65% FW&REBAR 38.34% 42.97%
2.65% 0.37 2.70666666666667
2.65% 182.00 2.69
2.65% 64 2.67857142857143
2.65% 140
386.00
47.15%
100.00% 16.58%
36.27%
V
1.2 CU.M
1.9278 CU.M

8.6556

6.2556
C6 C7 C8 C9 C10
1.19 1.05 2.1 3.15 0.98
1.05 0.98 1.96 3.15 0.91
0.98 0.91 1.82 2.73 0.91
0.91 0.84 1.68 2.52 0.84
0.84 0.84 1.68 2.52 0.84
0.7 0.7 1.4 2.1 0.7
0.7 0.7 1.4 2.1 0.7
0.63 0.63 1.26 1.89 0.63
0.63 0.63 1.26 1.89 0.63
BEAMS
TOTAL &
CONCRETE VOLUME
GIRDERS/
SUSPENDED RETAININ SLAB ON
STAIRS COLUMN
SHEARWALL SLABS LINK BEAM G WALL GRADE

3362.4216 11752.33 235.668 1863.19 314.2232 2278.708

1777.4256 1464.988
1584.996 813.72
7218.89 121.1784
4533.44 114.4896 1863.19 314.2232

649.81
916.31
1,349.62
2,718.89
18.03
SW LB STAIR

80.92% 32.08% 41.208%


43.05% 16.50%
C11 C12 C13 C14 C15 AREA
2.94 0.98 1.96 0.98 0.98 24.29 77.728 3.2
2.73 0.91 1.82 0.91 0.91 23.38 128.59 5.5
2.73 0.91 1.82 0.91 0.91 21.98 87.92 4
2.52 0.84 1.68 0.84 0.84 20.3 40.6 2
2.52 0.84 1.68 0.84 0.84 20.16 70.56 3.5
2.1 0.7 1.4 0.7 0.7 16.8 0
2.1 0.7 1.4 0.7 0.7 16.8 0
1.89 0.63 1.26 0.63 0.63 15.12 0
1.89 0.63 1.26 0.63 0.63 15.12 0
ACTUAL bEAM&SLAB
GF
F2 213
F3 110
ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT
GENERAL PRELIMINARIES & ATTENDANCE FEE % AMOUNT % AMOUNT % AMOUNT

01000 DIVISION 01 - GENERAL REQUIREMENTS

A BILL OF QUANTITIES
B GENERAL PREAMBLES
C GENERAL PROVISIONS
C.1 Mobilization/Demobilization 1.00 lot 760,000.00 50.00% 380,000.00 0.00% - 50.00% 380,000.00
C.2 Site Survey including equipment 1.00 lot 200,000.00 18.88% 37,764.98 1.59% 3,177.06 20.47% 40,942.04
C.3.5 Crack Mapping (Provisional) 1.00 lot 1,000,000.00 0.00% - 0.00% - 0.00% -
C.3.6 Restoration of Cracks (Provisional) 1.00 lot 1,000,000.00 0.00% - 0.00% - 0.00% -
C.4 Permits, Bonds and Insurances 0.00%
C.4.1.3 Others 0.00%
Truck Passes 28.00 mos 965.00 27,020.00 25.26% 6,825.17 1.59% 429.22 26.85% 7,254.39
Road Usage Permit 28.00 mos 10,000.00 280,000.00 25.26% 70,727.10 1.59% 4,447.88 26.85% 75,174.98
OCAI 1.00 lot 7,250,000.00 7,250,000.00 100.00% 7,250,000.00 0.00% - 100.00% 7,250,000.00
Building Permit 1.00 lot 7,750,000.00 7,750,000.00 100.00% 7,750,000.00 0.00% - 100.00% 7,750,000.00
Occupancy Permit 1.00 lot 7,750,000.00 7,750,000.00 0.00% - 0.00% - 0.00% -
C.4.2.1 Surety Bond 1.00 lot 3,117,652.00 3,117,652.00 100.00% 3,117,652.00 0.00% - 100.00% 3,117,652.00
C.4.2.2 Performance Bond 1.00 lot 2,997,742.00 2,997,742.00 100.00% 2,997,742.00 0.00% - 100.00% 2,997,742.00
C.4.2.3 Guarantee Bond 1.00 lot 399,699.00 399,699.00 27.32% 109,197.77 0.00% - 27.32% 109,197.77
C.4.2.4 Employee's Accident Insurance and Employee's CGL 1.00 lot 1,978,510.00 1,978,510.00 8.05% 159,263.70 1.59% 31,429.20 9.64% 190,692.89
C.5 Health and Safety Requirements

The Contractor is to provide and enforce the wearing of efficient safety


helmets, and where necessary, face masks, eye goggles, ear protectors,
safety harnesses and other personal protection equipment for all
C.5.1 personnel. The Contractor shall submit for approval detailed proposals 200.00 pax 3,400.00 680,000.00 17.21% 117,028.00 0.00% - 17.21% 117,028.00
for emergency procedures and safety regulations. The Contractor shall
provide all Owner's representatives and consultants employed
necessary safety gadgets i.e. safety helmets, safety shoes, etc.

The Contractor shall be responsible for the safety of the people and
C.5.9 security on the jobsite and shall regularly report status to the Owner.

Steel Gate 2.00 set 150,000.00 300,000.00 0.00% - 0.00% - 0.00% -


Landing Pad 1.00 set 1,265,000.00 1,265,000.00 0.00% - 50.00% 632,500.00 50.00% 632,500.00
Vertical Deflector 9.00 set 360,000.00 3,240,000.00 0.00% - 55.56% 1,800,000.00 55.56% 1,800,000.00
Deflector 680.00 sq.m 2,065.00 1,404,200.00 0.00% - 0.00% - 0.00% -
Safety Net 199.00 sq.m 270.00 53,730.00 27.03% 14,523.22 27.03% 14,521.62 54.06% 29,044.84
Safety Railing 680.00 lm 545.00 370,600.00 20.00% 74,120.00 26.91% 99,735.00 46.91% 173,855.00
Pedestrian Canopy 136.00 sq.m 955.00 129,880.00 0.00% - 50.00% 64,940.00 50.00% 64,940.00
Road Canopy 168.00 sq.m 3,535.00 593,880.00 10.00% 59,388.00 40.00% 237,552.00 50.00% 296,940.00
C.6 Security Services 28.00 mo 337,430.00 9,448,040.00 25.26% 2,386,544.55 1.59% 150,084.81 26.85% 2,536,629.36
C.7.3 Drawings from Consultants 593.00 sheets 3,500.00 2,075,500.00 25.26% 524,264.63 1.59% 32,969.91 26.85% 557,234.54
C.8 As-Built Drawings 1.00 lot 200,000.00 200,000.00 0.00% - 0.00% - 0.00% -
C.10 Representation
The Contractor shall be responsible for all the refreshments and logistics
C.10.2 28.00 mos 15,000.00 420,000.00 25.26% 106,090.65 1.59% 6,671.82 26.85% 112,762.47
required during meetings, inspections and walk-thrus.

The Contractor shall be responsible for all the preparation works


inclusive of all the requirements, refreshments, etc. to all formal
C.10.3 ceremonies i.e. ground breaking, 1st concrete pouring, topping off, etc. 1.00 lot 60,000.00 60,000.00 0.00% - 0.00% - 0.00% -
as required by the owner. All cost incurred shall be to the Contractor's
account.

C.13 HouseKeeping
C.13.4.1 Garbage Disposal 28.00 mos 70,000.00 1,960,000.00 21.18% 415,041.00 3.57% 70,000.00 24.75% 485,041.00
C.13.4.2 Fumigation 28.00 mos 8,500.00 238,000.00 21.18% 50,397.84 3.57% 8,500.00 24.75% 58,897.84
C.14 Material Testing
C.14.1.1 Concrete 630.00 cyl 1,175.00 740,250.00 25.26% 186,984.78 1.59% 11,759.08 26.85% 198,743.86
C.14.1.2 Rebar 510.00 set 435.00 221,850.00 25.26% 56,038.60 1.59% 3,524.15 26.85% 59,562.75
C.16 Plant and Equipment
Tower Crane 2.00 unit 9,140,000.00 18,280,000.00 25.26% 4,617,469.27 1.59% 290,383.01 26.85% 4,907,852.28
Material Hoist 1.00 unit 1,990,000.00 1,990,000.00 0.00% - 0.00% - 0.00% -
Passenger Hoist 1.00 unit 3,299,600.00 3,299,600.00 0.00% - 0.00% - 0.00% -
Telescopic Crane 1.00 unit 470,000.00 470,000.00 50.00% 235,000.00 0.00% - 50.00% 235,000.00
Trucking 18.00 mos 176,800.00 3,182,400.00 25.26% 803,864.01 1.59% 50,553.33 26.85% 854,417.35
C.18 Dewatering 1.00 lot 1,170,000.00 1,170,000.00 100.00% 1,170,000.00 0.00% - 100.00% 1,170,000.00
C.20 Site Management
C.20.1.1 Technical and Support Staff 28.00 mos 1,430,200.00 40,045,600.00 25.26% 10,115,389.89 1.59% 636,135.78 26.85% 10,751,525.67
C.21 Temporary Facilities 0.00%
All temporary facilities should include conference room and site offices
C.21.1 1.00 set 4,586,744.00 4,586,744.00 50.00% 2,293,372.00 - 50.00% 2,293,372.00
for the Contractor. 0.00%
The Contractor shall provide and maintain adequate latrine utilities for
male and female project site personnel, workers, sub-contractors,
C.21.2 consultants, visitors and government personnel. Latrines shall be 28.00 mos 75,500.00 2,114,000.00 25.26% 533,989.61 1.59% 33,581.49 26.85% 567,571.10
properly disposed daily and should not impose hazard on the work site.
A separate latrine will be provided to the Owner.

C.21.3 The Contactor shall allow for holding area, perimeter fence, equipment 1.00 set 500,000.00 500,000.00 25.26% 126,298.39 7,942.64 26.85% 134,241.04
staging, wheel washing and other facilities needed by the Contractor.
1.59%
The Contactor shall allow temporary housing for workers, project staff
C.21.4 with bed and kitchen provisions. 28.00 mos 281,000.00 7,868,000.00 25.26% 1,987,431.52 124,985.42 26.85% 2,112,416.94
1.59%
The Contractor shall take full responsibility for all discussions, liaison
C.21.9 works etc. with the various authorities concerned in respect of -
restrictions for cartage of and loading and off-loading of materials and
plant for the works.
Office Staging Area 12.00 mos 95,000.00 1,140,000.00 25.26% 287,960.34 1.59% 18,109.23 26.85% 306,069.56
Labor Staging Area 28.00 mos 365,000.00 10,220,000.00 25.26% 2,581,539.16 1.59% 162,347.62 26.85% 2,743,886.78
MCPI Office Supplies 28.00 mos 115,655.00 3,238,340.00 25.26% 817,994.27 1.59% 51,441.95 26.85% 869,436.23
C.22 Temporary Utilities -
C.22.1 The Contactor shall allow for temporary power and lighting. 28.00 mos 486,450.00 13,620,600.00 25.26% 3,440,519.80 1.59% 216,367.12 26.85% 3,656,886.91
The Contractor shall allow for temporary water, drainage and sewer
C.22.2 utilities. 28.00 mos 175,000.00 4,900,000.00 25.26% 1,237,724.26 77,837.90 26.85% 1,315,562.15
1.59%
The Contactor shall allow for temporary telecommunications, fax,
C.22.3 internet services and the likes as required. 28.00 mos 13,500.00 378,000.00 25.26% 95,481.59 6,004.64 26.85% 101,486.23
1.59%
Temporary Light Fixtures & wirings 50.00 set 7,400.00 370,000.00 25.26% 93,460.82 1.59% 5,877.56 26.85% 99,338.37
C.23 Owner's Representative Office
C.23.1.1 Temporary Facilities for Owners Representative 1.00 lot 66,936.00 66,936.00 50.00% 33,468.00 0.00% - 50.00% 33,468.00
Male and Female Toilet w/ Shower Rooms and Common Toilet (Floor
C.23.1.2 1.00 137,192.00 137,192.00 50.00% 68,596.00 - 50.00% 68,596.00
and wall Ceramic tiles finish) lot 0.00%
C.23.1.3 Engineer's Quarters 1.00 lot 40,400.00 40,400.00 50.00% 20,200.00 0.00% - 50.00% 20,200.00
C.23.1.4 Office Equipment including Maintenance 1.00 lot 1,857,462.00 1,857,462.00 50.00% 928,731.00 0.00% - 50.00% 928,731.00
C.23.1.5 Kitchen Equipment 1.00 lot 93,509.00 93,509.00 50.00% 46,754.50 0.00% - 50.00% 46,754.50
C.23.1.6 Office Supplies incl. Ink for Printer 1.00 lot 1,056,381.00 1,056,381.00 6.09% 64,294.53 3.57% 37,727.89 9.66% 102,022.43
C.23.1.7 PPE's Equipment for Owners Representative 1.00 lot 114,764.00 114,764.00 51.39% 58,972.98 3.57% 4,098.71 54.96% 63,071.69
Standard PMS (28mos) 1.00 lot 1,184,430.00 1,184,430.00 21.18% 250,809.70 - 21.18% 250,809.70
C.25 Attendance Fee
C.25.1 1.00 lot 29,557,930.00 29,557,930.00 4.70% 1,389,222.71 - 4.70% 1,389,222.71
-
Division 01 - Preliminaries Carried to Summary: 209,393,841.00 28.26% 59,168,138.31 2.34% 4,895,636.05 30.59% 64,063,774.35

SITEWORKS

02000 DIVISION 02 - SITE CONSTRUCTION


Sand Filling including all necessary tools and equipment to complete the
B works 1,887.00 cu.m 1,105.00 2,085,135.00 13.50% 281,493.23 0.00% - 13.50% 281,493.23
ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT
E Backfill 1,753.00 cu.m 195.00 341,835.00 60.00% 205,101.00 0.00% - 60.00% 205,101.00
F Compaction 5,843.00 sq.m 156.00 911,508.00 60.00% 546,904.80 0.00% - 60.00% 546,904.80
Gravel Bedding 3,129.00 sq.m 247.00 772,863.00 93.35% 721,467.61 0.00% - 93.35% 721,467.61
02360 SOIL TREATMENT
D Reticulation Piping; PIXA Termx Replenishment System 10,031.00 sq.m 112.00 1,123,472.00 0.00% - 0.00% - 0.00% -

Division 02 - Site Construction Carried to Summary: 5,234,813.00 33.52% 1,754,966.64 0.00% - 33.52% 1,754,966.64

STRUCTURAL

03000 DIVISION 03 - CONCRETE

03110 STRUCTURAL CAST-IN PLACE CONCRETE FORMS

A To Footing 1,131.00 sq.m 809.00 914,979.00 100.00% 914,979.00 0.00% - 100.00% 914,979.00
B To FTB 136.00 sq.m 809.00 110,024.00 100.00% 110,024.00 0.00% - 100.00% 110,024.00
C To Suspended Slab 44,661.00 sq.m 809.00 36,130,749.00 37.11% 13,408,120.95 1.23% 444,290.40 38.34% 13,852,411.35
D To Beams 34,130.00 sq.m 809.00 27,611,170.00 33.97% 9,379,514.45 4.37% 1,206,518.09 38.34% 10,586,032.54
E To Shearwall 10,935.00 sq.m 809.00 8,846,415.00 36.52% 3,230,710.76 6.53% 577,837.49 43.05% 3,808,548.24
F To Column 11,329.00 sq.m 809.00 9,165,161.00 34.44% 3,156,481.45 8.53% 781,814.36 42.97% 3,938,295.81
G To Stairs 3,043.00 sq.m 809.00 2,461,787.00 0.00% - 41.21% 1,014,502.42 41.21% 1,014,502.42
H To Retaining Wall 7,644.00 sq.m 809.00 6,183,996.00 89.65% 5,543,643.21 0.00% - 89.65% 5,543,643.21
I To Retaining Wall Footing 145.00 sq.m 809.00 117,305.00 100.00% 117,305.00 0.00% - 100.00% 117,305.00
J To Slab On Grade 372.00 sq.m 809.00 300,948.00 80.00% 240,758.40 6.0% 18,056.88 86.00% 258,815.28
K To RC Wall (Including Underground Utilities) 13,334.00 sq.m 809.00 10,787,206.00 20.00% 2,157,441.20 0.00% - 20.00% 2,157,441.20
L To Link Beam 1,101.00 sq.m 809.00 890,709.00 16.12% 143,582.29 5.92% 52,701.15 22.04% 196,283.44
N To Davit Pedestal 61.00 sq.m 809.00 49,349.00 0.00% - 0.00% - 0.00% -
O To Concrete Saddle 162.00 sq.m 809.00 131,058.00 0.00% - 0.00% - 0.00% -
P To Concrete Pad 109.00 sq.m 809.00 88,181.00 0.00% - 0.00% - 0.00% -

TOTAL: (FORMWORKS) 103,789,037.00 37.00% 38,402,560.71 3.95% 4,095,720.78 40.95% 42,498,281.50

03200 CONCRETE REINFORCEMENT

To Footings
P 16mm dia. 3,645.00 kg 10 36,450.00 100.00% 36,450.00 0.00% - 100.00% 36,450.00
Q 20mm dia. 8,810.00 kg 10 88,100.00 100.00% 88,100.00 0.00% - 100.00% 88,100.00
R 25mm dia. 77,195.00 kg 10 771,950.00 100.00% 771,950.00 0.00% - 100.00% 771,950.00
S 28mm dia. 88,425.00 kg 10 884,250.00 100.00% 884,250.00 0.00% - 100.00% 884,250.00
T 32mm dia. 6,232.00 kg 10 62,320.00 100.00% 62,320.00 0.00% - 100.00% 62,320.00

To Footing Tie Beam


10mm dia. 1,622.00 kg 10 16,220.00 100.00% 16,220.00 0.00% - 100.00% 16,220.00
16mm dia. 6,700.00 kg 10 67,000.00 100.00% 67,000.00 0.00% - 100.00% 67,000.00
20mm dia. 23,110.00 kg 10 231,100.00 100.00% 231,100.00 0.00% - 100.00% 231,100.00

To Suspended Slab
V 10mm dia. 493,420.00 kg 10 4,934,200.00 40.91% 2,018,581.22 0.00% - 40.91% 2,018,581.22
W 12mm dia. 135,565.00 kg 10 1,355,650.00 40.91% 554,596.42 0.00% - 40.91% 554,596.42

To Beam & Girders


Y 10mm dia. 111,830.00 kg 10 1,118,300.00 34.77% 388,832.91 3.57% 39,919.66 38.34% 428,752.57
Z 12mm dia. 71,660.00 kg 10 716,600.00 34.77% 249,161.82 3.57% 25,580.28 38.34% 274,742.10
AA 16mm dia. 184,710.00 kg 10 1,847,100.00 34.77% 642,236.67 3.57% 65,935.45 38.34% 708,172.12
AB 20mm dia. 143,515.00 kg 10 1,435,150.00 34.77% 499,001.66 3.57% 51,230.18 38.34% 550,231.83
AC 25mm dia. 307,411.00 kg 10 3,074,110.00 34.77% 1,068,868.05 3.57% 109,735.70 38.34% 1,178,603.75
AD 28mm dia. 423,294.00 kg 10 4,232,940.00 34.77% 1,471,793.24 3.57% 151,102.16 38.34% 1,622,895.39
AE 32mm dia. 203,741.00 kg 10 2,037,410.00 34.77% 708,407.46 3.57% 72,728.89 38.34% 781,136.35

To Shearwall
AF 12mm dia. 117,850.00 kg 10 1,178,500.00 36.70% 432,509.50 6.35% 74,856.94 43.05% 507,366.44
AG 16mm dia. 259,840.00 kg 10 2,598,400.00 36.70% 953,612.80 6.35% 165,047.33 43.05% 1,118,660.13
AH 20mm dia. 24,677.00 kg 10 246,770.00 36.70% 90,564.59 6.35% 15,674.54 43.05% 106,239.13
AI 25mm dia. 138,522.00 kg 10 1,385,220.00 36.70% 508,375.74 6.35% 87,987.56 43.05% 596,363.30
AJ 28mm dia. 98,522.00 kg 10 985,220.00 36.70% 361,575.74 6.35% 62,580.02 43.05% 424,155.76
AK 32mm dia. 78,100.00 kg 10 781,000.00 36.70% 286,627.00 6.35% 49,608.21 43.05% 336,235.21

To Column
AL 12mm dia. 33,010.00 kg 10 330,100.00 34.30% 113,224.30 8.67% 28,620.61 42.97% 141,844.91
AM 16mm dia. 440,550.00 kg 10 4,405,500.00 34.30% 1,511,086.50 8.67% 381,969.41 42.97% 1,893,055.91
AO 25mm dia. 101,470.00 kg 10 1,014,700.00 34.30% 348,042.10 8.67% 87,977.38 42.97% 436,019.48
AP 28mm dia. 204,360.00 kg 10 2,043,600.00 34.30% 700,954.80 8.67% 177,185.95 42.97% 878,140.75
AQ 32mm dia. 300,448.00 kg 10 3,004,480.00 34.30% 1,030,536.64 8.67% 260,496.98 42.97% 1,291,033.62

To Link Beam
AR 16mm dia. 116,981.00 kg 10 1,169,810.00 22.35% 261,452.54 0.00% - 22.35% 261,452.54
AS 25mm dia. 159,021.00 kg 10 1,590,210.00 22.35% 355,411.94 0.00% - 22.35% 355,411.94
AT 28mm dia. 115,275.00 kg 10 1,152,750.00 22.35% 257,639.63 0.00% - 22.35% 257,639.63
AU 32mm dia. 50,326.00 kg 10 503,260.00 22.35% 112,478.61 0.00% - 22.35% 112,478.61

To Stairs
AV 10mm dia. 14,690.00 kg 10 146,900.00 25.58% 37,577.02 15.63% 22,960.47 41.21% 60,537.49
AW 12mm dia. 2,201.00 kg 10 22,010.00 25.58% 5,630.16 15.63% 3,440.16 41.21% 9,070.32
AX 16mm dia. 55,750.00 kg 10 557,500.00 25.58% 142,608.50 15.63% 87,137.25 41.21% 229,745.75

To Retaining Wall
12mm dia. 51,079.00 kg 10 510,790.00 100.00% 510,790.00 0.00% - 100.00% 510,790.00
16mm dia. 190,175.00 kg 10 1,901,750.00 100.00% 1,901,750.00 0.00% - 100.00% 1,901,750.00
20mm dia. 4,568.00 kg 10 45,680.00 100.00% 45,680.00 0.00% - 100.00% 45,680.00

To Retaining Wall Footing


AZ Rebar, Grade 60 (80kg/cu.m) 5,667.00 kg 10 56,670.00 100.00% 56,670.00 0.00% - 100.00% 56,670.00

To Slab on Fill
AW Rebar, Grade 60 (80kg/cu.m) 18,097.00 kg 10 180,970.00 85.00% 153,824.50 6.00% 10,858.20 91.00% 164,682.70

To RC Wall 0.00%
AX Rebar, Grade 40 155,582.00 kg 10 1,555,820.00 10.55% 164,139.01 0.00% - 10.55% 164,139.01

A Concrete Saddle
12mm dia. 955.00 kg 10 9,550.00 0.00% - 0.00% - 0.00% -
16mm dia. 783.00 kg 10 7,830.00 0.00% - 0.00% - 0.00% -

B Davit Pedestal - kg 10 n/a 0.00%

Davit Saddle
12mm dia. 1,788.00 kg 10 17,880.00 0.00% - 0.00% - 0.00% -
16mm dia. 1,984.00 kg 10 19,840.00 0.00% - 0.00% - 0.00% -

Concrete Pads
10mm dia. 375.00 kg 10 3,750.00 0.00% - 0.00% - 0.00% -
12mm dia. 591.00 kg 10 5,910.00 0.00% - 0.00% - 0.00% -
ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT

STP & Underground Utilities


10mm dia. 4,040.00 kg 10 40,400.00 94.00% 37,976.00 0.00% - 94.00% 37,976.00
12mm dia. 21,387.00 kg 10 213,870.00 94.00% 201,037.80 0.00% - 94.00% 201,037.80
16mm dia. 15,382.00 kg 10 153,820.00 94.00% 144,590.80 0.00% - 94.00% 144,590.80
20mm dia. 42,087.00 kg 10 420,870.00 94.00% 395,617.80 0.00% - 94.00% 395,617.80

TOTAL: (REBAR WORKS) 51,170,180.00 40.81% 20,880,853.44 3.97% 2,032,633.33 44.78% 22,913,486.76

03300 CAST-IN-PLACE CONCRETE

Reinforced Concrete, 1000PSI


C To lean Concrete; 50mm thk 43.00 cu.m 1,808.00 77,744.00 100.00% 77,744.00 0.00% - 100.00% 77,744.00

Reinforced Concrete, 5000PSI


D To Retaining Wall Footing 71.00 cu.m 1,808.00 128,368.00 100.00% 128,368.00 0.00% - 100.00% 128,368.00
E To Retaining Wall 1,698.00 cu.m 1,808.00 3,069,984.00 100.00% 3,069,984.00 0.00% - 100.00% 3,069,984.00
F To Footings 1,850.00 cu.m 1,808.00 3,344,800.00 100.00% 3,344,800.00 0.00% - 100.00% 3,344,800.00
G To Slab on Grade 84.00 cu.m 1,808.00 151,872.00 80.00% 121,497.60 11.00% 16,705.92 91.00% 138,203.52
H To RC Wall 1,015.00 cu.m 1,808.00 1,835,120.00 19.00% 348,672.80 0.00% - 19.00% 348,672.80
I To Stair 343.00 cu.m 1,808.00 620,144.00 12.79% 79,316.42 28.42% 176,232.91 41.21% 255,549.33
L To Concrete Saddle 24.00 cu.m 1,808.00 43,392.00 0.00% - 0.00% - 0.00% -
M To Davit Pedestal 8.00 cu.m 1,808.00 14,464.00 0.00% - 0.00% - 0.00% -
To Concrete Pads 11.00 cu.m 1,808.00 19,888.00 0.00% - 0.00% - 0.00% -
To STP & Underground Utilities 425.00 cu.m 1,808.00 768,400.00 92.00% 706,928.00 0.00% - 92.00% 706,928.00

Reinforced Concrete, 6000PSI


N To Beams & Girders 3,953.00 cu.m 1,808.00 7,147,024.00 51.00% 3,644,982.24 11.42% 815,966.25 62.42% 4,460,948.49
O To Link Beams 123.00 cu.m 1,808.00 222,384.00 20.00% 44,476.80 22.86% 50,830.63 42.86% 95,307.43
P To Suspended Slab 3,262.00 cu.m 1,808.00 5,897,696.00 55.45% 3,270,272.43 6.97% 410,884.66 62.42% 3,681,157.09

Reinforced Concrete, 7000PSI


Q To Column 831.00 cu.m 1,808.00 1,502,448.00 0.00% - 0.00% - 0.00% -
R To Shearwall 1,430.00 cu.m 1,808.00 2,585,440.00 0.00% - 0.00% - 0.00% -
S To Beams & Girders 2,249.00 cu.m 1,808.00 4,066,192.00 0.00% - 0.00% - 0.00% -
T To Link Beams 117.00 cu.m 1,808.00 211,536.00 0.00% - 0.00% - 0.00% -
U To Suspended Slab 3,393.00 cu.m 1,808.00 6,134,544.00 0.00% - 0.00% - 0.00% -
0.00%
Reinforced Concrete, 8500PSI 0.00%
V To Column 1,583.00 cu.m 1,808.00 2,862,064.00 48.78% 1,396,114.82 17% 473,347.53 65.32% 1,869,462.35
W To Shearwall 1,680.00 cu.m 1,808.00 3,037,440.00 50.49% 1,533,603.46 30% 924,311.54 80.92% 2,457,915.00
43,740,944.00 40.62% 17,766,760.56 6.56% 2,868,279.44 47.18% 20,635,040.01

03350 CONCRETE FINISHING


Rubbed Concrete Finish; including all necessary tools and equipment to
complete the works 11.65% 7.0%
X To Column 7,694.00 sq.m 192.00 1,477,248.00 8.45% 124,753.59 3.21% 47,380.17 11.65% 172,133.76
Y To Retaining Wall 3,203.00 sq.m 192.00 614,976.00 28.97% 178,127.80 23.53% 144,673.10 52.49% 322,800.90
Z To RC 12,948.00 sq.m 192.00 2,486,016.00 0.00% - 0.00% - 0.00% -
AA To Ramp 1,634.00 sq.m 192.00 313,728.00 0.00% - 0.00% - 0.00% -
AB To Drop Wall 870.00 sq.m 192.00 167,040.00 0.00% - 0.00% - 0.00% -
AC To Sides of Beams 22,959.00 sq.m 192.00 4,408,128.00 5.18% 228,120.62 1.79% 78,695.38 6.96% 306,816.00
AD To Smooth Formed Concrete, Rubbed Finish (Ceiling) 19,246.00 sq.m 396.00 7,621,416.00 9.51% 724,415.59 0.54% 40,774.58 10.04% 765,190.17
17,088,552.00 0.00% 1,255,417.61 1.82% 311,523.22 1.82% 311,523.22
TOTAL: (CONCRETING WORKS) 60,829,496.00 31.27% 19,022,178.17 5.23% 3,179,802.66 36.50% 20,946,563.23

03400 PRECAST CONCRETE


Supply and Installation of Precast Concrete; including all necessary tools,
equipment and fixing accessories to complete the works
AF Exterior Wall; 125mm thick 10,820.00 sq.m 4,137.00 44,762,340.00 0.00% - 2.35% 1,051,601.62 2.35% 1,051,601.62
AG Cement Concrete Curbs 1,788.00 m 336.00 600,768.00 0.00% - 11.23% 67,476.13 11.23% 67,476.13
AH Wheel Guards 355.00 no 840.00 298,200.00 14.69% 43,805.58 9.54% 28,448.28 24.23% 72,253.86
AI To ACP Concrete Framing 247.00 sq.m 4,137.00 1,021,839.00 0.00% - 0.00% - 0.00% -

TOTAL: (PRECAST) 46,683,147.00 0.09% 43,805.58 2.46% 1,147,526.03 2.55% 1,191,331.61

03500 CEMENTITIOUS DECKS AND UNDERLAYMENT

03530 CONCRETE TOPPING

Includes cellular concrete for floor construction, concrete toppings for


slabs and all necessary tools and equipment to complete the works

Concrete Topping; 50mm thick


AJ Concrete Topping, smooth trower finish 7,029.00 sq.m 336.00 2,361,744.00 0.00% - 0.00% - 0.00% -

Concrete Accessories
AQ Water Stop (2.5m) 4,579.00 m 325.00 1,488,175.00 0.00% - 0.00% - 0.00% -

G Polypropylene Fiber 10.00 cu.m 407.00 4,070.00 0.00% - 0.00% - 0.00% -

Countertop Structure 163.00 ln.m 8,064.00 1,314,432.00 0.00% - 0.00% - 0.00% -

TOTAL: (TOPPING) 5,168,421.00 0.00% - 0.00% - 0.00% -

DIVISION 03 - Concrete Carried to Summary: 267,640,281.00 0.00% - 0.00% - 0.00%

ARCHITECTURAL WORKS

04000 DIVISION 04 - MASONRY

04200 MASONRY UNITS

04220 CONCRETE MASONRY UNITS


100mm thick CHB Wall; including rebar, tie wire, grout, use of
A scaffolding and all necessary tools and fixing accessories to complete the 6,530.00 sq.m 2,278.00 14,875,340.00 0.75% 111,565.05 0.00% - 0.75% 111,565.05
works

150mm thick CHB Wall; including rebar, tie wire, grout, use of
B scaffolding and all necessary tools and fixing accessories to complete the 8,335.00 sq.m 2,423.00 20,195,705.00 6.62% 1,336,955.67 1.00% 201,957.05 7.62% 1,538,912.72
works

DIVISION 04 - Masonry Carried to Summary: 35,071,045.00 4.13% 1,448,520.72 0.58% 201,957.05 4.71% 1,650,477.77

05000 DIVISION 05 - METALS

05100 STRUCTURAL METAL FRAMING


A Elevator Hoisting Beam 1,099.00 kg 264.00 290,136.00 0.00% - 0.00% - 0.00% -

U Separator I Beam 10,567.00 kgs 264.00 2,789,688.00 0.00% - 0.00% - 0.00% -

Provisional Cost for Transformer Hoisting Beam (as per Bid Bulletin 33)
W Considered Fixed Exposed Type w/o trolley & hook 834.00 kg 264.00 220,176.00 0.00%
- 0.00% - 0.00% -
ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT

05500 METAL FABRICATIONS


C Steel Gates; Exterior 4.00 set/s 58,779.00 235,116.00 0.00% - 0.00% - 0.00% -

05510 METAL STAIRS AND LADDERS

Metal Stairs including all necessary tools, equipment and fixing


accessories to complete the works
D To Exterior Stairs (GF to Podium 1); as shown on drawing no. 17/A-1103 1.00 lot 957,284.00 957,284.00 0.00%
- 0.00% - 0.00% -

Ladder Rung including all necessary tools, equipment and fixing


accessories to complete the works
F To Underground Tanks 206.00 nr 2,160.00 444,960.00 0.00% - 0.00% - 0.00% -

X Manhole Cover 13.00 nr 66,000.00 858,000.00 0.00% - 0.00% - 0.00% -

05520 HANDRAILS AND RAILINGS

Wall Mounted Railings; 50mm dia. BI pipe including all necessary tools
and fixing accessories to complete the works
G To FE Stairs 913.00 m 2,280.00 2,081,640.00 0.00% - 0.00% - 0.00% -
H To Stairs 72.00 m 2,280.00 164,160.00 0.00% - 0.00% - 0.00% -

Floor Mounted Railings; 50mm dia. GI pipe including all necessary tools
and fixing accessories to complete the works
I To FE Stairs 513.00 m 3,600.00 1,846,800.00 0.00% - 0.00% - 0.00% -
J To Ramp 591.00 m 3,600.00 2,127,600.00 0.00% - 0.00% - 0.00% -
K To Stairs 60.00 m 3,600.00 216,000.00 0.00% - 0.00% - 0.00% -

Floor Mounted Railings; Stainless Steel including all necessary tools and
fixing accessories to complete the works
L To PWD Ramp; 38mm dia. 19.00 m 6,120.00 116,280.00 0.00% - 0.00% - 0.00% -
M To PWD Ramp; 50mm dia. 34.00 m 6,120.00 208,080.00 0.00% - 0.00% - 0.00% -

Guard Rail; 600mm High Stainless Steel including all necessary tools and 66.00 set/s 9,140.00 603,240.00 0.00%
fixing accessories to complete the works - 0.00% - 0.00% -

DIVISION 05 - Metals Carried to Summary: 13,159,160.00 0.00% - 0.00% - 0.00% -

07000 DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07100 DAMPROOFING AND WATERPROOFING

07160 CEMENTITIOUS AND REACTIVE WATERPROOFING


Supply and installtion of waterproofing including all fixing accessories,
use of tools and equipment, and all necessary items to complete the
works, all in accordance with the drawings and specifications

Crystalline Waterproofing, type WP-1A; Supply and application of 2-


A 1mm thick coats of concrete waterproofing by crystallization, including 5,201.00 sq.m 960.00 4,992,960.00 0.00%
all necessary tools and fixing accessories to complete the works - 0.00% - 0.00% -
Modified Bituminous Sheet Waterproofing (APP Modified Asphalt),
type WP-2A; Supply and installation of Flextorch Membrane including
B surface preparation and all necessary tools and fixing accessories to 1,935.00 sq.m 2088.00 4,040,280.00 0.00%
complete the works
- 0.00% - 0.00% -

Modified Bituminous Sheet Waterproofing (APP Modified Asphalt with


C root inhibitor), type WP-2B; Supply and installation of Unolastic with 2,626.00 sq.m 1032.00 2,710,032.00 0.00%
Anti-Root including surface preparation and all necessary tools and
fixing accessories to complete the works
- 0.00% - 0.00% -
Modified Polyurethane, type WP-3; Supply and installation of RPC-11
Polyaspartic (Non-Exposed Type) Waterproofing including surface
D preparation and all necessary tools and fixing accessories to complete 3,532.00 sq.m 1848.00 6,527,136.00 0.00%
the works
- 0.00% - 0.00% -
Polymer Modified Cement Waterproofing, type WP-4; Supply and
installation of R-23 Flex/Osmolastic AB waterproofing including surface
E 48.00 sq.m 576.00 27,648.00 0.00%
preparation and all necessary tools and fixing accessories to complete
the works
- 0.00% - 0.00% -
Traffic Coating, type WP-5; Supply ang installation of traffic coating
F including surface preparation and all necessary tools and fixing 2,930.00 sq.m 1080.00 3,164,400.00 0.00%
accessories to complete the works - 0.00% - 0.00% -

Integral Waterproofing
G To SOG (Basement 5 Slab) 84.00 cu.m 908.00 76,272.00 80.00% 61,017.60 0.00% - 80.00% 61,017.60
H To Retaining Wall 1,698.00 cu.m 908.00 1,541,784.00 100.00% 1,541,784.00 0.00% - 100.00% 1,541,784.00

Bentonite Waterproofing WP-6; Supply and installation of bentonite


waterproofing including surface preparation and all necessary tools and
fixing accessories to complete the works
I To Retaining Wall 3,617.00 sq.m 984.00 3,559,128.00 90.00% 3,203,215.20 0.00% - 90.00% 3,203,215.20
J To Underground Utilities 938.00 sq.m 984.00 922,992.00 90.00% 830,692.80 0.00% - 90.00% 830,692.80
5,636,709.60
07180 TRAFFIC COATING
Supply and application of traffic coating (Aliphatic Urethanes) paint
including all necessary tools to complete the works

Basement and Podium Parking


K To Parking Divider Strip 239.00 sq.m 438.00 104,682.00 0.00% - 0.00% - 0.00% -
L To Parking Slot Number 357.00 sq.m 438.00 156,366.00 0.00% - 0.00% - 0.00% -
M To Column 2,966.00 sq.m 438.00 1,299,108.00 0.00% - 0.00% - 0.00% -
N To Ramp Wall 2,286.00 sq.m 438.00 1,001,268.00 0.00% - 0.00% - 0.00% -
O To PWD Floor Strip 24.00 sq.m 438.00 10,512.00 0.00% - 0.00% - 0.00% -
P To Directional Arrows 46.00 sq.m 438.00 20,148.00 0.00% - 0.00% - 0.00% -
Q To PWD Markings 5.00 sq.m 438.00 2,190.00 0.00% - 0.00% - 0.00% -
R To Wheel Stop 393.00 sq.m 438.00 172,134.00 0.00% - 0.00% - 0.00% -
S Concrete Curb 65.00 sq.m 438.00 28,470.00 0.00% - 0.00% - 0.00% -
T To Floor Strips 208.00 sq.m 438.00 91,104.00 0.00% - 0.00% - 0.00% -

07200 THERMAL PROTECTION


Insulation applied for thermal protection, elastomeric finish system,
vapor retarders and barriers; including all necessary tools and
equipment to complete the works

Thermal Insulation
U To Genset Room 438.00 sq.m 615.00 269,370.00 0.00% - 0.00% - 0.00% -

07220 ROOF AND DECK INSULATION

V Extruded polystyrene foam-plastic board 1,541.00 sq.m 1879.00 2,895,539.00 0.00% - 0.00% - 0.00% -

07260 VAPOR RETARDERS


ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT
W Polyethylene Sheet (6mils thick) 1,789.00 sq.m 59.00 105,551.00 100.00% 105,551.00 0.00% - 100.00% 105,551.00

DIVISION 07 - Thermal and Moisture Protection Carried to Summary: 33,719,074.00 17.03% 5,742,260.60 0.00% - 17.03% 11,378,970.20

08000 DIVISION 08 - DOORS AND WINDOWS

08100 METAL DOORS

08110 STEEL DOORS AND FRAMES


Supply and installtion of steel doors including framing and all necessary
tools and fixing accessories to complete the works: hardware measured
separately

SD-01; 900mm x 2100mmH; Swing type single leaf steel door (120mins
A fire rating) 69.00 set/s 16,397.00 1,131,393.00 0.00%
- 0.00% - 0.00% -
SD-01A; 900mm x 2100mmH; Swing type single leaf steel door with
B 2.00 set/s 17,297.00 34,594.00 0.00%
view panel (120mins fire rating) - 0.00% - 0.00% -
SD-02; 900mm x 2100mmH; Single leaf door on steel frame (90mins fire
C 171.00 set/s 16,397.00 2,803,887.00 0.00%
rating) - 0.00% - 0.00% -
D SD-02A; 900mm x 2100mmH; Single leaf door on steel frame 1.00 set/s 16,397.00 16,397.00 0.00% - 0.00% - 0.00% -
E SD-03; 1600mm x 2100mmH; Double leaf steel door (90mins fire rating) 7.00 set/s 29,892.00 209,244.00 0.00%
- 0.00% - 0.00% -
F SD-04; 1600mm x 2100mmH; Double leaf steel door fully louvered 5.00 set/s 22,692.00 113,460.00 0.00% - 0.00% - 0.00% -
G SD-05; 920mm x 2100mmH; Double leaf steel door fully louvered 2.00 set/s 13,697.00 27,394.00 0.00% - 0.00% - 0.00% -
H SD-06; 1200mm x 2000mmH; Steel door fully louvered 116.00 set/s 28,092.00 3,258,672.00 0.00% - 0.00% - 0.00% -

08110 WOOD DOOR AND FRAMES


Supply and installation of wood doors including framing and all
necessary tools and fixing accessories to complete the works: hardware
measured separately
WD-01; 900mm x 2100mmH; Single leaf solid core wood door on wood
I 1.00 set/s 22,332.00 22,332.00 0.00%
frames - 0.00% - 0.00% -
WD-02; 900mm x 2100mmH; Single leaf hollow wood door w/ bottom
J 68.00 set/s 13,932.00 947,376.00 0.00%
louvers - 0.00% - 0.00% -
K WD-03; 600mm x 1800mmH; Single leaf wood door fully louvered 44.00 set/s 18,324.00 806,256.00 0.00% - 0.00% - 0.00% -

DIVISION 08 - Doors and Windows Carried to Summary: 9,371,005.00 0.00% - 0.00% - 0.00% -

09000 DIVISION 09 - FINISHES

09200 PLASTER AND GYPSUM BOARD

09220 PORTLAND CEMENT PLASTER


Cement Plaster Finish (25mm thick); including all necessary tools and
fixing accessories to complete the works
A To CHB Walls 24,206.00 sq.m 396.00 9,585,576.00 0.00% - 0.45% 42,899.47 0.45% 42,899.47

09250 GYPSUM BOARD


Regular Gypsum Board Ceiling (12mm thick); including metal furring
system and all necessary tools and fixing accessories to complete the
works
B To Interior Ceiling 2,899.00 sq.m 1,390.00 4,029,610.00 0.00% - 0.00% - 0.00% -
Access Oanel for Ceiling (CL-1) & (CL-2) 171.00 pcs 2,366.00 404,586.00 0.00% - 0.00% - 0.00% -

MR Gypsum Board Ceiling (12mm thick); including metal furring system


and all necessary tools and fixing accessories to complete the works
C To Interior Ceiling (Toilet) 980.00 sq.m 1,551.00 1,519,980.00 0.00% - 0.00% - 0.00% -

09300 TILE
Supply and installation of specified tile including mortar, grout,
adhesive, corner bead and all necessary tools and fixing accessories to
complete the works
D 600mm x 600xx Homogenous tile (polished); to floors 2,582.00 sq.m 1,798.00 4,642,436.00 0.00% - 0.00% - 0.00% -
E 600mm x 600xx Homogenous tile (polished); to walls 2,119.00 sq.m 1,798.00 3,809,962.00 0.00% - 0.00% - 0.00% -
F 600mm x 600xx Homogenous tile (matte); to floors 987.00 sq.m 1,798.00 1,774,626.00 0.00% - 0.00% - 0.00% -
600mm x 600mm Non-Skid Homogeneous Tiles (at Landscape Area, 243.00 sq.m 790.00 191,970.00 0.00%
OSM as per Response to Queries No. 8) - 0.00% - 0.00% -

09600 FLOORING
Supply and installation of flooring including all necessary tools and fixing
accessories to complete the works
K Concrete Paver Tiles, to floor 3,144.00 sq.m 1,082.00 3,401,808.00 0.00% - 0.00% - 0.00% -
L Resilient Sheet static control flooring 15.00 sq.m 2,508.00 37,620.00 0.00% - 0.00% - 0.00% -

09700 WALL FINISHES


Supply and installtion of specified wall finish including all necessary tools
and fixing accessories to complete the works
O Skimcoat 22,618.00 sq.m 420.00 9,499,560.00 0.00% - 0.00% - 0.00% -

Skirting
Q Resilient tile; Vinyl composition tile; 100mm high 40.00 m 588.00 23,520.00 0.00% - 0.00% - 0.00% -

09900 PAINTS AND COATINGS

09910 PAINTS
Latex paint, type PT-2, semi-gloss finish; including primer, sealer and all
necessary tools and fixing accessories to complete the works

Interior
R To Gypsum Board 3,879.00 sqm 313.00 1,214,127.00 0.00% - 0.00% - 0.00% -
S To Under Slab 19,391.00 sqm 313.00 6,069,383.00 0.00% - 0.00% - 0.00% -
T To CHB 12,855.00 sqm 313.00 4,023,615.00 0.00% - 0.00% - 0.00% -
U To Column 2,720.00 sqm 313.00 851,360.00 0.00% - 0.00% - 0.00% -
V To Precast 2,533.00 sqm 313.00 792,829.00 0.00% - 0.00% - 0.00% -
W To RC Wall (all concrete surfaces) 5,309.00 sqm 313.00 1,661,717.00 0.00% - 0.00% - 0.00% -
X To Drop Wall 98.00 sqm 313.00 30,674.00 0.00% - 0.00% - 0.00% -
Y To Sides of Beam 8,532.00 sqm 313.00 2,670,516.00 0.00% - 0.00% - 0.00% -
Z To Retaining Wall 5,123.00 sqm 313.00 1,603,499.00 0.00% - 0.00% - 0.00% -

Exterior
AA Precast 10,820.00 sqm 650.00 7,033,000.00 0.00% - 0.00% - 0.00% -
AB Column 1,828.00 sqm 650.00 1,188,200.00 0.00% - 0.00% - 0.00% -
AC Beams 3,423.00 sqm 650.00 2,224,950.00 0.00% - 0.00% - 0.00% -
AD Precast Parapet 193.00 sqm 650.00 125,450.00 0.00% - 0.00% - 0.00% -

Enamel paint, semi-gloss finish; including primer and all necessary tools
and fixing accessories to complete the works

A To Steel Doors and Jambs 1,564.00 sqm 728.00 1,138,592.00 0.00% - 0.00% - 0.00% -
B To Louvers (Aluminum Storm Louver) - - -
C To Column Guard 586.00 ln.m 413.00 242,018.00 0.00% - 0.00% - 0.00% -
D To FES Railings 2,061.00 ln.m 413.00 851,193.00 0.00% - 0.00% - 0.00% -
A To Wood Doors 356.00 sqm 1,059.00 377,004.00 0.00% - 0.00% - 0.00% -
ITEM WORK ITEM DESCRIPTION QUANTITY UNIT TOTAL UNIT COST TOTAL COST PHP PREVIOUS ACCOMPLISHMENT TO DATE ACCOMPLISHMENT ACCUMULATED
PHP/UNIT ACCOMPLISHMENT

09960 HIGH-PERFORMANCE COATINGS


E Epoxy Tank Lining (Chemical Resistant); to underground tanks 1,184.00 sq.m 960.00 1,136,640.00 0.00% - 0.00% - 0.00% -
F Epoxy Tank Lining (Food Grade); to underground tanks 727.00 sq.m 960.00 697,920.00 0.00% - 0.00% - 0.00% -

09980 COATINGS FOR CONCRETE AND MASONRY


G Floor Sealer 15,979.00 sq.m 612.00 9,779,148.00 0.00% - 0.00% - 0.00% -

M Straight to Finish for Leasable Areas 19,805.00 sq.m 336.00 6,654,480.00 0.00% - 0.00% - 0.00% -

DIVISION 09 - Finishes Carried to Summary: 89,287,569.00 0.00% - 0.05% 42,899.47 0.05% 42,899.47

10000 DIVISION 10 - SPECIALTIES

10150 COMPARTMENT AND CUBICLES

10165 PLASTIC LAMINATE TOILET COMPARTMENTS


Toilet Partition (per cubicle) 176.00 set/s 31,200.00 5,491,200.00 0.00% - 0.00% - 0.00% -

Urinal Partition
600mm x 1800mm High 68.00 set/s 14,400.00 979,200.00 0.00% - 0.00% - 0.00% -

10260 WALL AND CORNER GUARDS

Protective devices such as corner guards, bumper rails and guards for
wall surfaces; made of metal, plastic, rubber and other finish materials
Steel Column Guard; 75 x 75 x 900 x 10mm thk (painted) 651.00 set 2,151.00 1,400,301.00 0.00% - 0.00% - 0.00% -

10800 TOILET, BATH AND LAUNDRY ACCESSORIES


Tissue Holder 202.00 set/s 420.00 84,840.00 0.00% - 0.00% - 0.00% -
Robe Hook 202.00 set/s 1,200.00 242,400.00 0.00% - 0.00% - 0.00% -
Hand Dryer 68.00 set/s 1,200.00 81,600.00 0.00% - 0.00% - 0.00% -
Straight Grab Bar 35.00 set/s 1,200.00 42,000.00 0.00% - 0.00% - 0.00% -
L-Shaped Grab Bar 23.00 set/s 1,200.00 27,600.00 0.00% - 0.00% - 0.00% -
Soap Dispenser 112.00 set/s 420.00 47,040.00 0.00% - 0.00% - 0.00% -

08830 MIRROR
6mm thick mirror beyelled w/ 12mm thick backing including metal angle
bar mirror frame in bronzatto finish all necessary framing, tools and
fixing accessories to complete the works
1550mm x 900mmH 2.00 sq.m 5,511.00 11,022.00 0.00% - 0.00% - 0.00% -
2560mm x 900mmH 26.00 sq.m 5,511.00 143,286.00 0.00% - 0.00% - 0.00% -
2700mm x 900mmH 27.00 sq.m 5,511.00 148,797.00 0.00% - 0.00% - 0.00% -
3520mm x 900mmH 32.00 sq.m 5,511.00 176,352.00 0.00% - 0.00% - 0.00% -
3750mm x 900mmH 4.00 sq.m 5,511.00 22,044.00 0.00% - 0.00% - 0.00% -
4120mm x 900mmH 41.00 sq.m 5,511.00 225,951.00 0.00% - 0.00% - 0.00% -
600mm x 900mmH 1.00 sq.m 5,511.00 5,511.00 0.00% - 0.00% - 0.00% -
610mm x 900mmH 7.00 sq.m 5,511.00 38,577.00 0.00% - 0.00% - 0.00% -
750mm x 900mmH 7.00 sq.m 5,511.00 38,577.00 0.00% - 0.00% - 0.00% -
900mm x 900mmH 1.00 sq.m 5,511.00 5,511.00 0.00% - 0.00% - 0.00% -

DIVISION 10 - Specialties Carried to Summary: 9,211,809.00 0.00% - 0.00% - 0.00% -

12000 DIVISION 12 - FURNISHING

Casework

Toilet counter including stone countertop including all necessary


framing, tools and fixing accessories to complete the works
3045mm x 650mm 11.00 set/s 65,772.00 723,492.00 0.00% - 0.00% - 0.00% -
4125mm x 650mm 11.00 set/s 89,100.00 980,100.00 0.00% - 0.00% - 0.00% -
2700mm x 650mm 12.00 set/s 58,320.00 699,840.00 0.00% - 0.00% - 0.00% -
4120mm x 650mm 1.00 set/s 88,992.00 88,992.00 0.00% - 0.00% - 0.00% -
3550mm x 650mm 1.00 set/s 76,680.00 76,680.00 0.00% - 0.00% - 0.00% -
3575mm x 650mm 1.00 set/s 77,220.00 77,220.00 0.00% - 0.00% - 0.00% -
3575mm x 650mm 8.00 set/s 77,112.00 616,896.00 0.00% - 0.00% - 0.00% -
520mm x 650mm 23.00 set/s 11,232.00 258,336.00 0.00% - 0.00% - 0.00% -

Reception Counter including stone countertop including all necessary


framing, tools and fixing accessories to complete the works
Reception Table; 2500mm x 650mm x 1100mmH 2.00 set/s 120,000.00 240,000.00 0.00% - 0.00% - 0.00% -
Back Counter; 3700mm x 150mm x 3400mmH 1.00 set/s 96,000.00 96,000.00 0.00% - 0.00% - 0.00% -

DIVISION 12 - Furnishings Carried to Summary: 3,857,556.00 0.00% - 0.00% - 0.00% -

ARCHITECTURAL WORKS (DIVISION 04 - DIVISION 12) Carried to Summary: 193,677,218.00

CP-01 Gen. Construction Works (CSA) Carried to Summary: 675,946,153.00

ELECTRICAL WORKS
CP-01 - General Construction Works (ELECTRICAL) Carried to Summary: 40,935,699.00 1.73% 708,187.59 0.21% 85,437.05 1.94% 793,624.64

PLUMBING & SANITARY WORKS


Cp-01 - General Construction Works (Plumbing) Carried to Summary: 37,949,996.00 1.56% 591,764.15 0.56% 210,884.82 2.12% 802,648.97

FIRE PROTECTION WORKS


CP-01 - General Construction Works (Fire Protection) Carried to Summary: 35,168,152.00 2.10% 740,166.01 0.63% 220,938.95 2.73% 961,104.96
888 Cayetano Ave., C5 Ext. Diversion Road
Brgy. Palingon Tipas, Taguig City
Tel. 628-8228 / Fax 628-8221

PROJECT : NEXUS TOWER 1


LOCATION : Emerald Ave. & Ruby Road Ortigas Center, Pasig City
OWNER : ETON PROPERTIES PHILS. INC.
SUBJECT : TREE REMOVAL AND TREE SAMPLINGS BILLING (WAO No.1)
BILLING DATE : February 10, 2020

CONTRACT PREVIOUS TO DATE ACCUMULATED


ITEM NO. DESCRIPTION REMARKS
QUANTITY UNIT COST AMOUNT % WEIGHT % AMOUNT % AMOUNT % AMOUNT
1 CHANGE ORDER
Tree Removal and Tree Sampling ### % Php. 130,000.00 Php. 130,000.00 100.00 - 100.00% 130,000.00 100.00% 130,000.00
- -

GRAND TOTAL Php. 130,000.00 100.00 0.00% - 100.00% 130,000.000 100.00% 130,000.000

% ACCOMPLISHMENT 100.00%
AMOUNT OF ACCOMPLISHMENT 130,000.00

LESS 10% RETENTION 13,000.00


Prepared by: Evaluated:
ENGR. MARICAR T. DE ASIS GRAND TOTAL 117,000.00
DESIGN COORDINATOR, MCPI

Approved by:
ENGR. SIMEON JAMES D. VILLACRUSIS
ASSIST. DESIGN COORDINATOR, MCPI

Noted by:
ENGR. ROSTUM CAPILI
Project Manager, MCPI
888 Cayetano Ave., C5 Ext. Diversion Road
Brgy. Palingon Tipas, Taguig City
Tel. 628-8228 / Fax 628-8221

PROJECT : NEXUS TOWER 1


LOCATION : Emerald Ave. & Ruby Road Ortigas Center, Pasig City
OWNER : ETON PROPERTIES PHILS. INC.
SUBJECT : STP PARTITION BILLING (WAO No.2)
BILLING DATE : February 10, 2020

CONTRACT PREVIOUS TO DATE ACCUMULATED


ITEM NO. DESCRIPTION REMARKS
QUANTITY UNIT COST AMOUNT % WEIGHT % AMOUNT % AMOUNT % AMOUNT
1 CHANGE ORDER
STP Partition - Structural and Waterproofing Works 100.00 % Php. 90,518.39 Php. 90,518.39 100.00 - 100.00% 90,518.39 100.00% 90,518.39
- -

GRAND TOTAL Php. 90,518.39 100.00 0.00% - 100.00% 90,518.390 100.00% 90,518.390

% ACCOMPLISHMENT 100.00%
AMOUNT OF ACCOMPLISHMENT 90,518.39

LESS 10% RETENTION 9,051.84


Prepared by: Evaluated:
ENGR. MARICAR T. DE ASIS GRAND TOTAL 81,466.55
DESIGN COORDINATOR, MCPI

Approved by:
ENGR. SIMEON JAMES D. VILLACRUSIS
ASSIST. DESIGN COORDINATOR, MCPI

Noted by:
ENGR. ROSTUM CAPILI
Project Manager, MCPI

Potrebbero piacerti anche