WORK PLAN FOR FIRST THREE MONTH

WORK PLAN FOR FIRST 3 MONTH

SEISMIC VULNERABILITY ASSESSMENT OF ALL THE EXISTING BRIDGES AT THE SITE

Work Scope for this three Month:


1) Collection of existing bridge data
2) Preparation of as built drawing of bridges
3) Micro-tremor test for evaluation of pier stiffness degradation
4) Collection of data for ground motion corresponding to 100 YRP,500YRP,1000YRP
and 2500YRP Earthquake from seismological team
5) Performance studies of bridges for above ground motions.

Selection Bridge Sites

Collection of Existing Bridge

If Not
Available

Preparation of Numerical Model


Pier Section capacity is known as Preparation of As Built Drawing
Reinforcement is known

Evaluation of Pier Stiffness degradation with


Micro-tremor Test

Check for Bridge bearing existing life span


Required Information from Seismological
Study team

Evaluation of Remaining Life span of Bridge


{ Non-Seismic Case}

Use of Site Specific Ground motion data


100 YRP Earthquake
500 YRP Earthquake
1000 YRP Earthquake
2500 YRP Earthquake
Evaluation of seismic Performance of bridge
for different level of Ground Shaking

R.K.Mallik
PhD. Candidate
WORK PLAN FOR FIRST THREE MONTH

Team Required:
Team for collecting as built information of bridges
1 No of Civil Engineer, 2 Overseer
Team for microtremor test:
1 Structural Engineer, 1 Civil Engineer, 1 Overseer, 1 helper
Equipment for micro-tremor test

Team for Seismic performance analysis


Team leader
1 Structural Engineer

Team Leader: Prof Gokarna Motra


Structural Engineer: R.K.Mallik
Civil Engineer: Deepndra Kandel
Civil overseer: Gajendra Jaiswaal

R.K.Mallik
PhD. Candidate