Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Table 1 : Test voltages for high voltage test 2.2.5 The UPS unit is to be monitored and audible and
on static convertors visual alarm is to be given in a normally attended location
for:
Um • power supply failure (voltage and frequency) to the con-
-= U
------- Test voltage
2 nected load
V
in V (1) • earth fault
U 60 600 • operation of battery protective device
60 < U 90 900 • when the battery is being discharged
2 U + 1000 • when the bypass is in operation for on-line UPS units.
90 < U
(at least 2000)
(1) Um: highest crest value to be expected between any 2.3 Location
pair of terminals.
2.3.1 The UPS unit is to be suitably located for use in an
2 Requirements for uninterruptible emergency.
power system (UPS) units as
2.3.2 UPS units utilising valve regulated sealed batteries
alternative and/or transitional power may be located in compartments with normal electrical
equipment, provided the ventilation arrangements are in
2.1 Definitions accordance with the requirements of IEC 62040 or an
acceptable and relevant national or international standard.
2.1.1 Uninterruptible power system (UPS)
Combination of converters, switches and energy storage 2.4 Performance
means, for example batteries, constituting a power system
for maintaining continuity of load power in case of input 2.4.1 The output power is to be maintained for the duration
power failure (see IEC Publication 62040). required for the connected equipment as stated in Ch 2, Sec
3, [3.6.3] and Pt D, Ch 11, Sec 5, [2.2.3].
2.1.2 Off line UPS unit
2.4.2 No additional circuits are to be connected to the UPS
A UPS unit where under normal operation the output load unit without verification that the UPS unit has adequate
is powered from the bypass line (raw mains) and only trans- capacity.
ferred to the inverter if the bypass supply fails or goes out-
side preset limits. This transition will invariably result in a 2.4.3 The UPS battery capacity is, at all times, to be capa-
brief (typically 2 to 10 ms) break in the load supply. ble of supplying the designated loads for the time specified
in the regulations.
2.1.3 Line interactive UPS unit
An off-line UPS unit where the bypass line switch to stored 2.4.4 On restoration of the input power, the rating of the
energy power when the input power goes outside the preset charge unit shall be sufficient to recharge the batteries while
voltage and frequency limits. maintaining the output supply to the load equipment.
2.2.2 The operation of the UPS is not to depend upon 3.1.3 In the case of convertors which are completely identi-
external services. cal in rating and in all other constructional details, it will be
acceptable for the rated current test and temperature rise
2.2.3 The type of UPS unit employed, whether off-line, line measurement stipulated in [3.2] not to be repeated.
interactive or on-line, is to be appropriate to the power sup-
ply requirements of the connected load equipment. 3.1.4 The tests and, if appropriate, manufacture of conver-
tors of 50 kVA and over intended for essential services are
2.2.4 An external bypass is to be provided. to be attended by a Surveyor of the Society.
3.2 Tests on convertors 3.3 Additional testing and survey for unin-
terruptible power system (UPS) units as
3.2.1 Convertors are to be subjected to tests in accordance alternative and/or transitional power
with Tab 2.
3.3.1 UPS units of 50 kVA and over are to be surveyed by
Type tests are the tests to be carried out on a prototype con- the Society during manufacturing and testing.
vertor or the first of a batch of convertors, and routine tests
are the tests to be carried out on subsequent convertors of a 3.3.2 Appropriate testing is to be carried out to demon-
particular type. strate that the UPS unit is suitable for its intended environ-
ment. This is expected to include as a minimum the
3.2.2 The electronic components of the convertors are to following tests:
be constructed to withstand the tests required in Ch 3, Sec • functionality, including operation of alarms
6. • ventilation rate
• battery capacity.
3.2.3 Final approval of convertors is to include complete
function tests after installation on board, performed with all 3.3.3 Where the supply is to be maintained without a break
ship’s systems in operation and in all characteristic load following a power input failure, this is to be verified after
conditions. installation by practical test.