Sei sulla pagina 1di 3

Pt C, Ch 2, Sec 6

SECTION 6 SEMICONDUCTOR CONVERTORS

1 Constructional and operational 1.2.2 Overcurrent or overvoltage protection is to be


requirements installed to protect the convertor. When the semiconductor
convertor is designed to work as an inverter supplying the
network in transient periods, precautions necessary to limit
1.1 Construction the current are to be taken.

1.1.1 Semiconductor convertors are generally to comply


with the requirements for switchgear assemblies (see Ch 2, 1.2.3 Semiconductor convertors are not to cause distortion
Sec 8). in the voltage wave form of the power supply at levels
exceeding the voltage wave form tolerances at the other
1.1.2 The monitoring and control circuits are generally to user input terminals (see Ch 2, Sec 2, [2.4]).
comply with the requirements of Part C, Chapter 3.
1.2.4 An alarm is to be provided for tripping of protective
1.1.3 For liquid-cooled convertors the following provisions devices against overvoltages and overcurrents in electric
are to be satisfied:
propulsion convertors and for convertors for the emergency
• liquid is to be non-toxic and of low flammability source of power.
• drip trays or other suitable means are to be provided to
contain any liquid leakages 1.3 Parallel operation with other power
• the resistivity of the cooling fluid in direct contact with sources
semiconductor or other current carrying parts is to be
monitored and an alarm initiated if the resistivity is out- 1.3.1 For convertors arranged to operate in parallel with
side the specified limits.
other power sources, load sharing is to be such that under
normal operating conditions overloading of any unit does
1.1.4 Where forced cooling is used, the temperature of the
heated cooling medium is to be monitored. not occur and the combination of paralleled equipment is
stable.
If the temperature exceeds a preset value an alarm is to be
given and the shutdown of the convertor is to be activated.
1.4 Temperature rise
1.1.5 Where forced (air or liquid) cooling is provided, it is
to be so arranged that the convertor cannot be or remain 1.4.1 The permissible limit of temperature rise of the enclo-
loaded unless effective cooling is maintained. sure of the semiconductors is to be assessed on the basis of
Alternatively, other effective means of protection against an ambient air temperature of 45°C or sea water tempera-
overtemperature may be provided. ture of 32°C for water-cooled elements, taking into account
its specified maximum permissible temperature value.
1.1.6 Stacks of semiconductor elements, and other equip-
ment such as fuses, or control and firing circuit boards etc.,
1.4.2 The value of the maximum permissible temperature
are to be so arranged that they can be removed from equip-
of the elements at the point where this can be measured
ment without dismantling the complete unit.
(point of reference) is to be stated by the manufacturer.
1.1.7 Semiconductor convertors are to be rated for the
required duty having regard to the peak loads, system tran- 1.4.3 The value of the mean rated current of the semicon-
sient and overvoltage and to be dimensioned so as to with- ductor element is to be stated by the manufacturer.
stand the maximum short-circuit currents foreseen at the
point of installation for the time necessary to trip the protec-
tion of the circuits they supply. 1.5 Insulation test

1.5.1 The test procedure is that specified in IEC Publication


1.2 Protection
60146.
1.2.1 Semiconductor elements are to be protected against
short-circuit by means of devices suitable for the point of 1.5.2 The effective value of the test voltage for the insula-
installation in the network. tion test is to be as shown in Tab 1.

60 Bureau Veritas April 2009


Pt C, Ch 2, Sec 6

Table 1 : Test voltages for high voltage test 2.2.5 The UPS unit is to be monitored and audible and
on static convertors visual alarm is to be given in a normally attended location
for:
Um • power supply failure (voltage and frequency) to the con-
-= U
------- Test voltage
2 nected load
V
in V (1) • earth fault
U 60 600 • operation of battery protective device
60 < U  90 900 • when the battery is being discharged
2 U + 1000 • when the bypass is in operation for on-line UPS units.
90 < U
(at least 2000)
(1) Um: highest crest value to be expected between any 2.3 Location
pair of terminals.
2.3.1 The UPS unit is to be suitably located for use in an
2 Requirements for uninterruptible emergency.
power system (UPS) units as
2.3.2 UPS units utilising valve regulated sealed batteries
alternative and/or transitional power may be located in compartments with normal electrical
equipment, provided the ventilation arrangements are in
2.1 Definitions accordance with the requirements of IEC 62040 or an
acceptable and relevant national or international standard.
2.1.1 Uninterruptible power system (UPS)
Combination of converters, switches and energy storage 2.4 Performance
means, for example batteries, constituting a power system
for maintaining continuity of load power in case of input 2.4.1 The output power is to be maintained for the duration
power failure (see IEC Publication 62040). required for the connected equipment as stated in Ch 2, Sec
3, [3.6.3] and Pt D, Ch 11, Sec 5, [2.2.3].
2.1.2 Off line UPS unit
2.4.2 No additional circuits are to be connected to the UPS
A UPS unit where under normal operation the output load unit without verification that the UPS unit has adequate
is powered from the bypass line (raw mains) and only trans- capacity.
ferred to the inverter if the bypass supply fails or goes out-
side preset limits. This transition will invariably result in a 2.4.3 The UPS battery capacity is, at all times, to be capa-
brief (typically 2 to 10 ms) break in the load supply. ble of supplying the designated loads for the time specified
in the regulations.
2.1.3 Line interactive UPS unit
An off-line UPS unit where the bypass line switch to stored 2.4.4 On restoration of the input power, the rating of the
energy power when the input power goes outside the preset charge unit shall be sufficient to recharge the batteries while
voltage and frequency limits. maintaining the output supply to the load equipment.

2.1.4 On line UPS unit


3 Testing
A UPS unit where under normal operation the output load
is powered from the inverter, and will therefore continue to
operate without break in the event of the supply input fail- 3.1 General
ing or going outside preset limits.
3.1.1 Convertors intended for essential services are to be
subjected to the tests stated in [3.2].
2.2 Design and construction
3.1.2 The manufacturer is to issue a test report giving infor-
2.2.1 UPS units are to be constructed in accordance with mation on the construction, type, serial number and all
IEC 62040, or an acceptable and relevant national or inter- technical data relevant to the convertor, as well as the
national standard. results of the tests required.

2.2.2 The operation of the UPS is not to depend upon 3.1.3 In the case of convertors which are completely identi-
external services. cal in rating and in all other constructional details, it will be
acceptable for the rated current test and temperature rise
2.2.3 The type of UPS unit employed, whether off-line, line measurement stipulated in [3.2] not to be repeated.
interactive or on-line, is to be appropriate to the power sup-
ply requirements of the connected load equipment. 3.1.4 The tests and, if appropriate, manufacture of conver-
tors of 50 kVA and over intended for essential services are
2.2.4 An external bypass is to be provided. to be attended by a Surveyor of the Society.

April 2009 Bureau Veritas 61


Pt C, Ch 2, Sec 6

3.2 Tests on convertors 3.3 Additional testing and survey for unin-
terruptible power system (UPS) units as
3.2.1 Convertors are to be subjected to tests in accordance alternative and/or transitional power
with Tab 2.
3.3.1 UPS units of 50 kVA and over are to be surveyed by
Type tests are the tests to be carried out on a prototype con- the Society during manufacturing and testing.
vertor or the first of a batch of convertors, and routine tests
are the tests to be carried out on subsequent convertors of a 3.3.2 Appropriate testing is to be carried out to demon-
particular type. strate that the UPS unit is suitable for its intended environ-
ment. This is expected to include as a minimum the
3.2.2 The electronic components of the convertors are to following tests:
be constructed to withstand the tests required in Ch 3, Sec • functionality, including operation of alarms
6. • ventilation rate
• battery capacity.
3.2.3 Final approval of convertors is to include complete
function tests after installation on board, performed with all 3.3.3 Where the supply is to be maintained without a break
ship’s systems in operation and in all characteristic load following a power input failure, this is to be verified after
conditions. installation by practical test.

Table 2 : Tests to be carried out on static convertors

N° Tests Type test (1) Routine test (2)


1 Examination of the technical documentation, as appropriate, and visual inspection (3)
X X
including check of earth continuity
2 Light load function test to verify all basic and auxiliary functions X X
3 Rated current test X
4 Temperature rise measurement X
5 Insulation test (dielectric strength test and insulation resistance measurement) X X
6 Protection of the convertors in case of failure of forced cooling system X X
(1) Type test on prototype convertor or test on at least the first batch of convertors.
(2) The certificates of convertors routine tested are to contain the manufacturer’s serial number of the convertor which has been
type tested and the test result.
(3) A visual examination is to be made of the convertor to ensure, as far as practicable, that it complies with technical
documentation.

62 Bureau Veritas April 2009

Potrebbero piacerti anche