Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
METHODOFSTATEMENIT
COBRA Approved by
1. PURPOSE
2. SCOPE
3. RESPONSffiiLITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISKRATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
METHODOFSTATEMENIT
COBRA Approved by
PREPARED BY REVIEWED ADCO
D.
Name : K.G Premnath
(b . 0 (. 'UJ !':1-
Name: SuhasAher
16/tN/ 1)-
Name :
VJ.-TLS.t ~
Date
Sign /@/)
f1
Date
Sign
(h_., .......
.
Date
24-I dl:2 C
'2 P/J-
-
I"
7
~f'
I
Sign
-f/"1/
--
1. PURPOSE
2. SCOPE
3. RESPONSffiiLITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISKRATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
3. RESPONSffiiLITIES
3.1 Site Engineer (cobra): Responsible for monitor execution of all the Site activities,
ensure the works are carried out as per the relevant Standards & comply ADCO HSE
requirements, availability of all required Resources and progress of Work as per the
schedule ·
3.2 Site Supervisor/Job Performer (cobra): Responsible to carry out the maintenance
activities with own team following QC and HSE procedures, allotment and supervision of
works individual groups, guide and monitor the work force and progress, Report to the
Site Engineer on regular basis
4. REFERENCES
The following documents are reference for this Method Statement:
5. DEFINITIONS
• Contractor cobra
• MOS Method Of Statement
• PTW Permit To Work
• HSE Health, Safety and Environment
• PPE Personal Protective Equipment
• AA Area Authority
• IA Issuing Authority
• JO Job Originator
• JP Job Performer
• TBT Tool Box Talks
• OHL Over Head Line
• lAP Insulated Aerial Platform/Bucket
• TRA Task Risk Assessment
6.1 Mobilization .The crew consisting of Manpower, equipment's and tools as per the contract
and as described in section 7 below is mobilized to each field on agreed plan and approval
from contract focal point, (Mr. Mazen Tahboub-TL(Power)-Bab )
6.2 PTW. Permit to work is obtained from corresponding ADCO Area Authority in charge for
the electrical network where the maintenance activity is to be carried out. A detail task risk
assessment is carried out and approval taken from all parties concerned prior to raising the
permit.
6.3 HVEC. For all live line works,HVEC to be obtained on COBRA authorized personnel,
enrolled with ADCO eptw system. The same to be cancelled on suspension/completion oflive
line works. For all works on isolated/de-energized lines, HVEC to be issued to ADCO
personnel and attached to the eptw.
6.4 Live Line Check list. Cobra's mandatory checklist is carried out by the JP/Live Line
Supervisor prior to start of the work followed by TBT on a day to day basis.
( 1) After ensuring the condition and stability of the structure to be worked upon the lAP
mounted truck to be positioned in such a manner to get access to the required point of
work with minimum maneuver.
(2) Connect the truck to the earth system.
(3) Cleaning of the lAP boom with rags and acetone.
(4) Connecting the leakage current measuring instrument and raising the lAP boom from the
platform of the truck to enable the lAP platform in contact with any of the phase line
conductor.
* To commence the work it is mandatory to have the reading done above to be less than 33
microamperes for 33Kv.
7.1 Manpower:
• Site engineer 1
• HSEO 1
• Site Supervisor/Job performer 1
• Live Line Technicians 4
• Cold Technicians/Cable jointer : 2
• Worker/Helper 1
• HD/LD Driver : As required
7.2 Equipment/Tools:
8. RISKRATING
As all the activities carried out above ground, with thorough & strict Supervision, competent
Workforce and TRA attached to be strictly complied.
9. HSE REQUIREMENTS
9.1 ADCO Standard PPE will be worn by all the personnel at site at all times. Special PPE
(Fluorescent Jacket) identifying Rigger & Banks man will be used.
9.2 Full Body Harness shall be used by Over Head Fitters while Climbing the Tower and
Working at Height
9.3 Ensure anchoring Lanyard of Full Body Harness always & above Head Level while
Climbing & Working at Height
9.4 Only Experienced & Trained/Competent Lineman should be assigned for the Work
9.5 Assign Safety Watch while Work 1s m progress simultaneously at High &
Bottom/Ground Levels
9.6 Use appropriate Carrier for Tools while Climbing & Working at Height
MOS 33kV OHL OPENING/CLOSING OF JUMPERS
Page 5 of 6
9.7 No Tool/Material should be hoisted unless it is properly tied & secured
9.9 Lifting Gears to be used shall be properly Certified &Colour Coded as per ADCO
current code
9.11 Fire extinguishers for all equipment (Crane) will be inspected by competent person and
kept in good operational condition
9.12 Conduct TBT to all the work force including drivers and operators involved in Work
emphasizing the criticality of Site Conditions
9.13 Make all the individuals aware of ADCO Emergency Response Procedures prior to
Work
10.1 Live Line Checklist shall be maintained for each day task.
10.2 Daily Accomplishment Reports
10.3 Look Ahead Plan
10.4 Manpower/Equipment Schedule
11. ATTACHMENTS
M£THODOFSTATEMENIT
COBRA Approved by
1. PURPOSE
2. SCOPE
3. RESPONSffiiLITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISKRATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
3. RESPONSffill-ITIES
3.1 Site Engineer (cobra): Responsible for monitor execution of all the Site activities,
ensure the works are carried out as per the relevant Standards & comply ADCO HSE
requirements, availability of all required Resources and progress of Work as per the
schedule
3.2 Site Supervisor/Job Performer (cobra): Responsible to carry out the maintenance
activities with own team following QC and HSE procedures, allotment and supervision of
works individual groups, guide and monitor the work force and progress, Report to the
Site Engineer on regular basis
4. REFERENCES
The following documents are reference for this Method Statement:
5. DEFINITIONS
• Contractor cobra
• MOS Method Of Statement
• PTW Permit To Work
• HSE Health, Safety and Environment
• PPE Personal Protective Equipment
• AA Area Authority
• IA Issuing Authority
• JO Job Originator
• JP Job Performer
• TBT Tool Box Talks
• OHL Over Head Line
• lAP Insulated Aerial Platform/Bucket
• TRA Task Risk Assessment
6.1 Mobilization .The crew consisting of Manpower , equipments and tools as per the contract
and as described in section 7 below is mobilized to each field on agreed plan and approval
from contract focal point, (Mr. Mazen Tahboub-TL(Power)-Bab)
6.2 PTW. Permit to work is obtained from corresponding ADCO Area Authority in charge for
the electrical network where the maintenance activity is to be carried out. A detail task risk
assessment is carried out and approval taken from all parties concerned prior to raising the
permit.
6.3 Live Line Check list. Cobra' s mandatory checklist is carried out by the JP/Live Line
Supervisor prior to start of the work followed by TBT on a day-to-day basis.
(1) After ensuring the condition and stability of the structure to be worked upon the lAP
mounted truck to be positioned in such a manner to get access to the required point of
work with minimum maneuver.
(2) Connect the truck to the earth system.
(3) Cleaning of the lAP boom with rags and acetone.
(4) Connecting the leakage current measuring instrument and raising the lAP boom from the
platform of the truck to enable the lAP platform in contact with any of the phase line
conductor.
* To commence the work it is mandatory to have the reading done above to be less than 33
microamperes for 33kV
7.1 Manpower:
• Site engineer 1
• HSEO 1
• Site Supervisor/Job performer 1
• Live Line Technicians 4
• Cold Technicians/Cable jointer 2
• Worker/Helper
• HD/LD Driver As required
7.2 Equipment/Tools:
7. RISK RATING
As all the activities carried out above ground, with thorough & strict Supervision, competent
Workforce and TRA attached to be strictly complied.
8. HSE REQUIREMENTS
9.1 ADCO Standard PPE will be worn by all the personnel at site at all times. Special PPE
(Fluorescent Jacket) identifying Rigger & Banks man will be used.
9.2 Full Body Harness shall be used by Over Head Fitters while Climbing the Tower and
Working at Height
9.3 Ensure anchoring Lanyard of Full Body Harness always & above Head Level while
Climbing & Working at Height
9.4 Only Experienced & Trained/Competent Lineman should be assigned for the Work
9.5 Assign Safety Watch while Work 1s m progress simultaneously at High &
Bottom/Ground Levels
1. PURPOSE
2. SCOPE
3. RESPONSffiU,ITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISKRATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
2. SCOPE
This MOS covers all the Steps & Description of Work for carrying out Replacing of Damaged
Components, for 33 kV OHL' s Network at ADCO fields and terminals.
3. RESPONSffiiLITIES
3.1 Site Engineer (cobra): Responsible for monitor execution of all the Site activities,
ensure the works are carried out as per the relevant Standards & comply ADCO HSE
requirements, availability of all required Resources and progress of Work as per the
schedule
3.2 Site Supervisor/Job Performer (cobra): Responsible to carry out the maintenance
activities with own team following QC and HSE procedures, allotment and supervision of
works individual groups, guide and monitor the work force and progress, Report to the
Site Engineer on regular basis
4. REFERENCES
The following documents are reference for this Method Statement:
5. DEFINITIONS
• Contractor cobra
• MOS Method Of Statement
• PTW Permit To Work
• HSE Health, Safety and Environment
• PPE Personal Protective Equipment
• AA Area Authority
• IA Issuing Authority
• JO Job Originator
• JP Job Performer
• TBT Tool Box Talks
• OHL Over Head Line
• lAP Insulated Aerial Platform/Bucket
• TRA Task Risk Assessment
6.1 Mobilization. The crew consisting of Manpower , equipment' s and tools as per the contract
and as described in section 7 below is mobilized to each field on agreed plan and approval
from contract focal point, (Mr. Mazen Tahboub - TL(Power)-Bab)
6.2 PTW. Permit to work is obtained from corresponding ADCO Area Authority in charge for
the electrical network where the maintenance activity is to be carried out. A detail task risk
assessment is carried out and approval taken from all parties concerned prior to raising the
permit.
6.3 HVEC. For all live line works,HVEC to be obtained on COBRA authorized personnel,
enrolled with ADCO eptw system. The same to be cancelled on suspension/completion of live
line works. For all works on isolated/de-energized lines, HVEC to be issued to ADCO
personnel and attached to the eptw.
6.4 Live Line Check list. Cobra's mandatory checklist is carried out by the JP/Live Line
Supervisor prior to start of the work followed by TBT on a day-to-day basis.
7.1 Manpower:
• Site engineer
• HSEO
• Site Supervisor/Job performer 1
• Live Line Technicians 4
• Cold Technicians/Cable jointer 2
• Worker/Helper 1
• HD/LD Driver As required
7.2 Equipment/Tools:
7. RISK RATING
As all the activities carried out above ground, with thorough & strict Supervision, competent
Workforce and TRA attached to be strictly complied.
8. HSE REQUIREMENTS
9.1 ADCO Standard PPE will be worn by all the personnel at site at all times. Special PPE
(Fluorescent Jacket) identifying Rigger & Banks man will be used.
9.2 Full Body Harness shall be used by Over Head Fitters while Climbing the Tower and
Working at Height
9.3 Ensure anchoring Lanyard of Full Body Harness always & above Head Level while
Climbing & Working at Height
9.4 Only Experienced & Trained/Competent Lineman should be assigned for the Work
9.5 Assign Safety Watch while Work is m progress simultaneously at High &
Bottom/Ground Levels
9.6 Use appropriate Carrier for Tools while Climbing & Working at Height
MOS REPLACING OF DAMAGED LINE COMPONENTS
Page 5 of 6
9.7 No Tool/Material should be hoisted unless it is properly tied & secured
9.9 Lifting Gears to be used shall be properly Certified & Colour Coded as per ADCO
current code
9.11 Fire extinguishers for all equipment (Crane) will be inspected by competent person and
kept in good operational condition
9.12 Conduct TBT to all the work force including drivers and operators involved in Work
emphasizing the criticality of Site Conditions
9.13 Make all the individuals aware of ADCO Emergency Response Procedures prior to
Work
9. QA/QC REQUIRMENTS:
10.1 Live Line Checklist shall be maintained for each day task.
10.2 Daily Accomplishment Reports
10.3 Look Ahead Plan
10.4 Manpower/Equipment Schedule
10. ATTACHMENTS
METHODOFSTATEMENIT
COBRA Approved by
J!lJlA-.~
QJ_ ..... "
Sign '?J} Sign :
./'_
~tn_...
I
Sign
I
1. PURPOSE
2. SCOPE
3. RESPONSffiiLITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISK RATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
3. RESPONSIDILITIES
3.1 Site Engineer (cobra): Responsible for monitor execution of all the Site activities,
ensure the works are carried out as per the relevant Standards & comply ADCO HSE
requirements, availability of all required Resources and progress of Work as per the
schedule
3.2 Site Supervisor/Job Performer (cobra): Responsible to carry out the maintenance
activities with own team following QC and HSE procedures, allotment and supervision of
works individual groups, guide and monitor the work force and progress, Report to the
Site Engineer on regular basis
4. REFERENCES
The following documents are reference for this Method Statement:
5. DEFINITIONS
• Contractor cobra
• MOS Method of Statement
• PTW Permit To Work
• HSE Health, Safety and Environment
• PPE Personal Protective Equipment
• AA Area Authority
• IA Issuing Authority
• JO Job Originator
• JP Job Performer
• TBT Tool Box Talks
• OHL Over Head Line
• lAP Insulated Aerial Platform/Bucket
• TRA Task Risk Assessment
6.1 Mobilization .The crew consisting of Manpower, equipment's and tools as per the contract
and as described in section 7 below is mobilized to each field on agreed plan and approval
from contract focal point, (Mr. Mazen Tahboub-TL(Power)-Bab )
6.2 PTW. Permit to work is obtained from corresponding ADCO Area Authority in charge for
the electrical network where the maintenance activity is to be carried out. A detail task risk
assessment is carried out and approval taken from all parties concerned prior to raising the
permit.
6.3 HVEC. For all live line works,HVEC to be obtained on COBRA authorized personnel,
enrolled with ADCO eptw system. The same to be cancelled on suspension/completion of live
line works. For all works on isolated/de-energized lines, HVEC to be issued to ADCO
personnel and attached to the eptw.
6.4 Live Line Check list. Cobra' s mandatory checklist is carried out by the JP/Live Line
Supervisor prior to start of the work followed by TBT on a day-to-day basis.
(1) Shifting adjacent poles conductors on to pulley by installing pulleys to insulators free
movement for the section in which a pole is to be replaced.
(2) Detach Earth wire/ OPGW from the pole which is to be preplaced
(3) Detaching conductors from Insulators and holding it apart using Insulated ropes for the pole
which is to be replaced
(4) Removing cross arms from the pole which is to be replaced
(5) Putting Protective covers on the pole and holding it with non-conductive webbing sling
hooked to a mobile crane boom
(6) Removing the earth used to bury the pole foundation using mechanical device
(7) Lifting the Pole vertically up above the ground controlling movement using tag line
RESOURCES
7.1 Manpower:
• Site engineer
• HSEO 1
• Site Supervisor/Job performer 1
• Live Line Technicians 4
• Cold Technicians/Cable jointer 2
• Worker/Helper 1
• HD/LD Driver As required
7.2 Equipment/Tools:
7. RISK RATING
MOS REPLACING OF WOODEN POLE STRUCTURE
Page 5 of 7
As all the activities carried out above ground, with thorough & strict Supervision, competent
Workforce and TRA attached to be strictly complied.
8. HSE REQUIREMENTS
9.1 ADCO Standard PPE will be worn by all the personnel at site at all times. Special PPE
(Fluorescent Jacket) identifying Rigger & Banks man will be used.
9.2 Full Body Harness shall be used by Over Head Fitters while Climbing the Tower and
Working at Height
9.3 Ensure anchoring Lanyard of Full Body Harness always & above Head Level while
Climbing & Working at Height
9.4 Only Experienced & Trained/Competent Lineman should be assigned for the Work
9.5 Assign Safety Watch while Work 1s in progress simultaneously at High &
Bottom/Ground Levels
9.6 Use appropriate Carrier for Tools while Climbing & Working at Height
9.9 Lifting Gears to be used shall be properly Certified &Color Coded as per ADCO current
code
9.11 Fire extinguishers for all equipment (Crane) will be inspected by competent person and
kept in good operational condition
9.12 Conduct TBT to all the work force including drivers and operators involved in Work
emphasizing the criticality of Site Conditions
9.13 Make all the individuals aware of ADCO Emergency Response Procedures prior to
Work
9. QA/QC REQUIRMENTS:
10.1 Live Line Checklist shall be maintained for each day task.
10.2 Daily Accomplishment Reports
10.3 Look Ahead Plan
10.4 Manpower/Equipment Schedule
10. ATTACHMENTS
M£THODOFSTATKMENIT
COBRA Approved by
1. PURPOSE
2. SCOPE
3. RESPONSffiiLITIES
4. REFERENCES
5. DEFINITIONS
6. SEQUENCE OF ACTIVITIES
7. RESOURCES
8. RISKRATING
9. HSE REQUIREMENTS
11. ATTACHMENTS
3. RESPONSffiiLITIES
3.1 Site Engineer (cobra): Responsible for monitor execution of all the Site activities,
ensure the works are carried out as per the relevant Standards & comply ADCO HSE
requirements, availability of all required Resources and progress of Work as per the
schedule
3.2 Cable Jointer/Job Performer (cobra): Responsible to carry out the maintenance
activities with own team following QC and HSE procedures, allotment and supervision of
works individual groups, guide and monitor the work force and progress, Report to the
Site Engineer on regular basis
4. REFERENCES
The following documents are reference for this Method Statement:
5. DEFINITIONS
• Contractor cobra
• MOS Method Of Statement
• PTW Permit To Work
• HSE Health, Safety and Environment
• PPE Personal Protective Equipment
• AA Area Authority
• IA Issuing Authority
• JO Job Originator
• JP Job Performer
• TBT Tool Box Talks
• OHL Over Head Line
• lAP Insulated Aerial Platform/Bucket
• TRA Task Risk Assessment
6.1 Mobilization .The crew consisting of Manpower , equipments and tools as per the contract
and as described in section 7 below is mobilized to each field on agreed plan and approval
from contract focal point, (Mr. Mazen Tahboub - TL(Power)~Bab)
6.2 PTW. Permit to work is obtained from corresponding ADCO Area Authority in charge for
the electrical network where the maintenance activity is to be carried out. A detail task risk
assessment is carried out and approval taken from all parties concerned prior to raising the
permit.
6.3 HVEC. For all works on isolated/de-energized lines, HVEC to be issued to ADCO
personnel and attached to the eptw.
6.4 Live Line Check list. Cobra's mandatory checklist is carried out by the JP/Live Line
Supervisor prior to start of the work followed by TBT on a day-to-day basis.
(1) Ensure that the cable to be terminated I spliced are isolated by using the Hot Tester
(2) Discharge the cable to be terminated I spliced using portable Earth stick & apply earth on
either side of the point of work on the OHL.
(3) Mark the cores to terminal to match later, before disconnecting the cable from the OHL
(4) Measure the Insulation Resistance of the cable and record
(5) Prepare the bale for termination /splicing
(6) Carry out the termination/ Splicing as per the instructions given by the manufacture and
standards in practice
(7) Measure the Insulation Resistance of the cable and record
(8) HIPOT to be done as per clients requirement
(9) Connect both end of the cable to the OHL, the cores to match as marked earlier (step-3)
(1 0) Remove the local earth applied on both side of the cable
(11) House Keeping
7. RESOURCES
7.1 Manpower:
8. RISKRATING
As all the activities carried out above ground, with thorough & strict Supervision, competent
Workforce and TRA attached to be strictly complied.
9. HSE REQUIREMENTS
9.1 ADCO Standard PPE will be worn by all the personnel at site at all times. Special PPE
(Fluorescent Jacket) identifying Rigger & Banks man will be used.
9.2 Full Body Harness shall be used by Over Head Fitters while Climbing the Tower and
Working at Height
9.3 Ensure anchoring Lanyard of Full Body Harness always & above Head Level while
Climbing & Working at Height
9.4 Only Experienced & Trained/Competent Lineman should be assigned for the Work
9.5 Assign Safety Watch while Work is m progress simultaneously at High &
Bottom/Ground Levels
9.6 Use appropriate Carrier for Tools while Climbing & Working at Height
9.9 Lifting Gears to be used shall be properly Certified &Colour Coded as per ADCO
current code
9.12 Conduct TBT to all the work force including drivers and operators involved in Work
emphasizing the criticality of Site Conditions
9.13 Make all the individuals aware of ADCO Emergency Response Procedures prior to
Work
10.1 Live Line Checklist shall be maintained for each day task.
11. ATTACHMENTS