Sei sulla pagina 1di 6

Dennis Travagini Cremonese et al.

Mining
Mineração
A high-level dynamic analysis
approach for studying global
process plant availability and
production time in the early
http://dx.doi.org/10.1590/0370-44672016700043 stages of mining projects
Dennis Travagini Cremonese Abstract
Doutorando
Universidade de São Paulo - USP In the early stage of front-end studies of a Mining Project, the global availability
Departamento de Minas e Engenharia do Petróleo (i.e. number of hours a plant is available for production) and production (number of
São Paulo – São Paulo – Brasil hours a plant is actually operated with material) time of the process plant are normally
dennis.travagini@dynamine.com.br assumed based on the experience of the study team. Understanding and defining the
availability hours at the early stages of the project are important for the future stages of
Bhaskar Karanth the project, as drastic changes in work hours will impact the economics of the project
Global Tech and Engineering Director at that stage. An innovative high-level dynamic modeling approach has been developed
Hatch - Iron Ore BU to assist in the rapid evaluation of assumptions made by the study team. This model
Montréal – Quebec – Canada incorporates systems or equipment that are commonly used in mining projects from
bhaskar.karanth@hatch.com mine to product stockyard discharge after the processing plant. It includes subsystems
that will simulate all the component handling, and major process plant systems re-
Giorgio de Tomi quired for a mining project. The output data provided by this high-level dynamic simu-
Professor Associado lation approach will enhance the confidence level of engineering carried out during the
Universidade de São Paulo - USP early stage of the project. This study discusses the capabilities of the approach, and a
Departamento de Minas e Engenharia do Petróleo test case compared with standard techniques used in mining project front-end studies.
São Paulo – São Paulo – Brasil
gdetomi@usp.br Keywords: mining, dynamic simulation, high-level simulation model.

1. Introduction

The efficiency of complete mineral son, 2001; Ernst & Young, 2013). Many effective utilization of the plant as a total
processing facilities depends on the uti- projects start with a scoping study (FEL1), system, etc. The values for these items are
lization of various subsystems and their followed by a pre-feasibility study (FEL2) assumed based on experience in most stud-
degree of decoupling (Miller, 1979). The and a feasibility study (FEL3), before be- ies; the estimated values may cause change
intermediate stockpiles and surge bins ing approved for implementation. For all in the costs in the future phases of the
are important components that help to the stakeholders, it is very important to project. These assumptions can impact the
avoid unscheduled shutdowns (Berton et sustain project viability throughout these current study outcome or the later phase.
al., 2013). In the current economic condi- phases, with the exception of the identified Any major changes to these parameters
tions, every investment dollar required to risks that may change the project course can influence the cost of the project. To
be spent on surge storage systems in these in the future. The changes in the project enjoy investor confidence in the long term,
facilities should match the production sys- configuration established in the early it would be prudent to carry out front-end
tem utilization. Any deviation from it will stages are expected to include mitigation studies of the project with a better-defined
result in either losing production or poor of risks identified in the previous phase or set of utilization and storage parameters,
capital investment efficiency. additional data availability that supports since future project changes are directly
All current major mining projects a better definition of the project. Most of related to mining or process changes or
go through some form of front-end (FEL) the stakeholders understand and agree identified risks. This will reduce some of
studies, in line with IPA definitions (Stange to most of these changes when they are the uncertainty caused by assumptions
and Cooper, 2008), before reaching the related to better definition of the process based solely on experience during the early
implementation stage. The investment or mitigation of the risks foreseen in the stages of the project.
community is not willing to take as many previous stage(s). However, some of the In an iron ore project, the surge or
risks in the year ahead and puts more pres- parameters that form these studies, which storage stockpiles and bin installations
sure on mining companies to deliver the are not scrutinized a great deal during the contribute to the major cost as they are
project efficiently (Nikkhah and Ander- early stages, are the sizing of stockpiles, of high capacities and are mostly mecha-
REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017 215
A high-level dynamic analysis approach for studying global process plant availability and production time in the early stages of mining projects

nized. The utilization of the system is individual production rates are less prone or inaccurate model can lead to unex-
adversely impacted if the surge capacity or to surprises during future project phases. pected plant behavior, such as underper-
anticipated decoupling of the plant is not Steady-state simulation is less com- formances in critical areas (Asbjörnsson
sufficient. At the same time, excess surge/ plicated to develop and to operate, but et al., 2012; Le Roux et all., 2013; Vasabi
stockpile capacity may decrease the capital dynamic simulation has a higher potential et all., 2014).
efficiency and may result in poor project to predict the actual behavior, as it consid- An innovative high-level dynamic
economics in the early stages, which may ers the impacts of process and material modeling approach has been developed
make it lose its investment attractiveness. handling disturbances (Bergquisst, 2012; by making a generic model that could be
During initial studies, it is better to size Asbjörnsson et al., 2013). By simulating a easily set to evaluate a mining project in a
the surge capacities that will address both system in its totality, and not as isolated few hours (around 8–16 h). As the model
plant utilization and capital efficiency. This subsystems, the simulation approach yields requires less time to be set than traditional
is essential to improve the sustainability globally optimal solutions that meet over- models (which require weeks), it can be
of future operations (Gomes et al., 2015). all system objectives (Cardoso and Teles, used in the scoping study (FEL1) and pre-
The objective of the ‘High-level 1997; Altiok, 2010), as some investments feasibility study (FEL2).
Dynamic Analysis Approach’ is to drive in a determined area do not increase the The contribution of this work is to
engineering to an improved definition of global performance (Juliá, 2010). show that a dynamic analysis can be used
plant availability, considering the stor- The evaluation model is detailed in the early stages of mining projects (FEL1
age or surge capacity sizing, during the enough to be accurate, as accuracy is and FEL2), helping in the early detection
early stages of mining projects, using the dependent on the simulation success, but of capacity and utilization issues of the
total system concept. This will also help detailed simulation will be expensive to complete system, and allowing corrective
as a project parameter verification tool model and difficult to operate. Utilizing the action to update the configuration and
to ensure that the plant utilization and information obtained by an inappropriate design of equipment and storage.

2. Materials and methods

One of the keys to a successful models to be built quickly and accurately and/ or repeated; the initial idea of the flow
simulation study is to follow a complete for maximum benefit. Due to the iterative simulation study is shown in Figure 1 (Cre-
methodology in an organized and well- nature of the method, which does not monese, 2014). The complete methodology
managed way. A comprehensive and necessarily follow a list of sequences, some in the development of a dynamic simulation
disciplined methodology allows complex activities may be performed simultaneously model is described by Cremonese (2014).

Figure 1
Simulation
Methodology (Cremonese, 2014).
216 REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017
Dennis Travagini Cremonese et al.

To develop the model with a suffi- likely value. This most likely value is the resulting data stored are annual through-
cient level of detail, the following assump- time-between-stops as defined by the user out, maximum, minimum and average
tions were considered: with the interface provided. stock levels, and equipment utilization.
• Only solid flow is considered. This The model could be developed in All the data of stockpiles, bins and the
means that the water and particle size are any commercially available discrete simu- necessary information along the simulated
not considered in the model. Inclusion of lation software (Cremonese and Livoratti, time are stored.
other parameters would increase model 2012); however, for this study, the model The model components are devel-
complexity and could make it difficult was developed in the Arena (by Rockwell oped to allow various combinations or a
to use; however, further works are to Automation) software. The input data configuration of equipment with no cus-
include these modes, which could lead to were grouped into tabs in the Microsoft tomizing effort at the programming level.
studies not intended at the early stage of Excel file (Interface), where each tab When the model is set to run, the Visual
the project; describes a unique project system block. Basic for Applications (VBA) obtains the
• The equipment capacity varies in The model design allows for continuous input data from the MS Excel interface
a triangular statistical distribution, and improvement and expansion, as well as and inserts it into the Arena model, mak-
all the parameters are defined by the user the inclusion of additional process steps ing the links between the system blocks,
with the interface provided; as necessary. such as the Primary Crushing to Stock-
• Unplanned maintenance occurs The model input data template for pile 1 and so on. This interface allows
in a triangular statistical distribution that the equipment includes the flow of the an engineer with minimal experience in
considers the minimum value to be 50% material, equipment capacities, planned simulation software to set the input data
and the maximum value 150% of the most and unplanned maintenance. The typical and run the model.

3. Results and discussion

An iron ore project was used as a test material handling equipment (Belt Convey- FEL 3 stage of the project.
case. There are 230 pieces of equipment at ors, Bins, Piles, Stacker-Reclaimers, etc). The Run of Mine (ROM) ore is 7
the process plant, made up of 100 catego- The FEL2 study data were used million tons per annum (Mtpa), and the
ries. There are 47 pieces of process equip- as input to the model. It is therefore production time and average capacity
ment (Crushers, Screens, Spiral Classifier, possible to analyze whether the model defined by the project team are shown
Thickeners, Mills, Cyclones, etc,) and 53 of output gives useful information to the in Table 1.

Area Production time (hours/year) Plant average capacity (t/h)

Table 1 Primary Crusher System 5400 1400


Production time
Process Plant 6400 1200
and average plant capacity.

The static analysis shows that 7 Mtpa. consider the sizes of stockpiles, bins and
the Primary Crusher System achieves However, the production times of unexpected failures of the system, etc.
540 0 h /yea r x 140 0 t / h = 7. 56 5400 and 6400 hours/year are based on The ‘High-level Dynamic Analy-
Mtpa; and the Process Plant achieves the experience of the project team and do sis Approach’ considers the statistical
6400 h/year x 1200 = 7.68 Mtpa. Both not account for all the system interrela- variation occurring in the process, such
are at least 8% higher than the necessary tions and interdependencies. It does not as equipment through capacity variation,

Figure 2
ROM considering confidence
interval of the mean and sigma intervals.
REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017 217
Dennis Travagini Cremonese et al.

unexpected failures, bin levels, etc. 99.73% of the years will achieve a ca- The intermediate stockpile has a capac-
Considering planned and un- pacity of between 6.82–7.05 Mtpa. ity of 200 kt and is almost full or com-
planned maintenance, equipment data, For a 7 Mtpa capacity, estimated pletely full after half the simulation time.
and storage capacity, the model shows from team experience, using the same This shows that the mine and primary
that the plant availability and produc- configuration, the dynamic simulation crushing area are not the bottleneck.
tion time will not be achieved. The shows that in some years, the capacity Figure 3 shows the utilization of
ROM ore achieved an average of 6.94 can only be 6.82 Mtpa. the main equipment as a percentage of
Mtpa. Figure 2 shows that considering It is therefore evident that capac- time. The dotted red line represents the
a confidence level of 99.9% of the mean, ity will not be achieved. The question separation (battery limit) between the
the mean ROM achieved along the year is: “why this is, and what can be done crushing plant and the process plant.
is between 6.91–6.97 Mtpa, which is to achieve it?” The number inside the “(#XXX)” is the
less than the 7 Mtpa target. The first step is to analyze the bin block number. Each block is one equip-
Furthermore, at the 3-sigma level, and stockpile utilization over a period. ment in the model.

Figure 3
Equipment utilization.

Figure 4 shows the storage level of intermediate stockpile (#180) as a percent- the separation (battery limit) between the
each bin/tank (#189 to #199) and of the age of time. The dotted red line represents crushing plant and the process plant.

Figure 4
Bin and stockpile utilization.

The analysis from Figure 5 shows the equipment and bins. 200–800 t. Both of these bins were
that the capacity of the process plant To test the influence of bin capac- sized at 500 t. The two bins were in
was reduced by the dynamic behavior ity on global availability, the Screen a critical area, as they filled between
of the equipment. One way to increase 2 Bin (#193) and Tertiary Crusher 80–100% of the capacity about 30%
the capacity is to enable decoupling of Bin (#194) were made variable from of the time.
REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017 218
A high-level dynamic analysis approach for studying global process plant availability and production time in the early stages of mining projects

Figure 5
Production (Mtpa) versus bin capacity (t).

The plant’s mean production ca- ity is minor compared to the changes dynamic simulation model at the end
pacity is achieved by increasing the bin that need to be carried out in FEL 3 of FEL 3. Discipline engineering, such
capacities to 650 t, and is expected to and project implementation or worse, as Mechanical and Civil, needed to be
achieve a confidence level of 99%. in plant operation. revised, since the belt conveyor length
This bin capacity change in the In this test case, insufficient bin had to be changed, and the load of the
FEL 2 stage to achieve the plant capac- capacity was discovered in a complete structure was increased.

4. Conclusions

The “High-level Dynamic Analysis ensuring the quality of the engineering issues of the complete system, and allows
Approach” evaluates capacities consider- work can enhance investors’ confidence corrective action to update the specific
ing all the system blocks of the project; in the project as the project evolves into system configuration and design.
the results are closer to global availability. the next level. The results also show that As shown in the test case, the
The work is carried out with standard evaluating the system as a whole rather utilization of the High-level Dynamic
information available to the study team in than in isolation would drive the values Analysis Approach in the FEL 2 would
the early stage of the project, but with less closer to the optimized system. How- lead to defining the bin capacities in the
engineering effort compared to a detailed ever, the High-level Dynamic Analysis early stages. This would avoid the need
dynamic simulation model. Domain ex- Approach is not meant to be used in the of revised discipline engineering, such
pert judgment or the operating staff input later stages of the project, as it is necessary as Mechanical and Civil, once the belt
on systems or the experience of the user to simulate the system with more details conveyor length had to be changed and
is required to obtain reliable results from to optimize the project systems or when the load of the structure increased. This
this tool. However, it does not require more details of the system are available. occurred at the end of FEL 3.
modeling software experience. The approach helps to combine the total Further work to enhance the model
Using this approach and based on project systems and to provide data for is being undertaken to incorporate related
the system dependability and system sizing the storage systems, instead of in- systems, such as water storage require-
dynamics, one can assure that the plant tuitive sizing based on experience, which ments, to make this approach more ef-
availability is sized to achieve the antici- may lead to surprises in future phases of fective by considering all the systems that
pated utilization of the systems included the project. This approach can help in the influence the production or sizing in the
in the project. This innovative way of early detection of capacity and utilization early stages of the project.

Acknowledgments

We would like to acknowledge sup- and FAPESP (grant #2016/00647-2,


port for this project from CAPES, CNPq São Paulo Research Foundation).

References

ALTIOK, T. Large-scale simulation modeling of ports and waterways: approaches and


Challenges. In: WORKSHOP ON GRAND CHALLENGES IN MODELING,
SIMULATION AND ANALYSIS FOR HOMELAND SECURITY. Anais... Wa-
shington: US DHS - Science and & Technology Directorate, 2010.
ASBJÖRNSSON, G., HULTHÉN, E., EVERTSSON, M. Modelling and dynamic
simulation of gradual performance deterioration of a crushing circuit – Including
time dependence and wear. Minerals Engineering, v. 33, p. 17–19, 2012.
ASBJÖRNSSON, G., HULTHÉN, E., EVERTSSON, M. Modelling and simulation
219 REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017
Dennis Travagini Cremonese et al.

of dynamic crushing plant behavior with MATLAB/Simulink. Minerals Enginee-


ring, v. 43–44, p. 112–120, 2013.
BERGQUIST, B. Traceability in iron ore processing and transports. Minerals Engine-
ering, v. 30, p. 44–51, 2012.
BERTON, A. et alii. Ore storage simulation for planning a concentrator expansion.
Minerals Engineering, v. 40, p. 56–66, 2013.
CARDOSO, C.R.O., TELES M.B. Simulação de terminal portuário. In: ENCON-
TRO NACIONAL DE ENGENHARIA DE PRODUÇÃO, 17. Anais... Gramado
(RS): ABEPRO, 1997.
CREMONESE, D.T. Desenvolvimento e aplicação de metodologia para estudos de
simulação dinâmica na cadeia do minério de ferro. São Paulo: Escola Politécnica,
Universidade de São Paulo, 2014. 157 p. (Master’s Dissertation in Mineral Engi-
neering).
CREMONESE, D.T., LIVORATTI, P. Simulation tools: a study of application at
the Nouadhibou Port. In: INTERNATIONAL CONFERENCE ON INTELLI-
GENT PROCESSING AND MANUFACTURING OF MATERIALS, 7. Anais...
Foz do Iguaçu (PR): IPMM, 2012.
ERNST & YOUNG. Canadian mining companies focused on cost control, project
execution in 2013. Ernst & Young. News Release, 7th Feb 2013. Available at:
http://www.newswire.ca/news-releases/canadian-mining-companies-focused-on-
-cost-control-project-execution-in-2013-ernst--young-511933581.html [Last ac-
cessed: 10 March 2016].
GOMES, R. B., DE TOMI, G., ASSIS, P. S. Impact of quality of iron ore lumps on sus-
tainainability of mining operations in the Quadrilatero Ferrifero Area. Minerals
Engineering, v. 70, p. 201–206, 2015.
JULIÁ, A. F. Desenvolvimento de um modelo de simulação para dimensionamento
de um sistema integrado pátio-porto na cadeia do minério de ferro. São Paulo:
Escola Politécnica, Universidade de São Paulo, 2010. 165 p. (Master’s Dissertation
in Logistic Systems Engineering).
LE ROUX, J. D. et al. Analysis and validation of a run-of-mine ore grinding mill cir-
cuit model for process control. Minerals Engineering, v. 43–44, p. 121–134, 2013.
MILLER, M. J. Stockpiling and reclaiming systems in mill design. SME. SME-AIME
Fall Meeting and Exhibit, Tucson, Arizona, v. 79, p. 326. 1979.
NIKKHAH K, ANDERSON C. Role of simulation software in design and operation
of metallurgical plants: a case study. In: SME SME ANNUAL MEETING. Denver
Colorado, v. 1, p. 176, 2001.
STANGE W., COOPER B. Value options and flexibility in plant design, metplant
- metallurgical plant design and operating strategies. Perth (Australia): Australa-
sian Institute of Mining and Metallurgy, 2008.
VASEBI, A., POULIN, E., HODOUIN, D. Selecting proper uncertainty model for
steady-state data reconciliation – Application to mineral and metal processing in-
dustries. Minerals Engineering, v. 65, p. 130–144, 2014.

Received: 21 March 2016 - Accepted: 24 October 2016.

REM, Int. Eng. J., Ouro Preto, 70(2), 215-220, apr. jun. | 2017 220

Potrebbero piacerti anche