Sei sulla pagina 1di 10

Chapter 11

Concrete mix design

Brian Addis and John Goodman

11.1 Introduction Note on terminology


The ingredients of concrete, namely cementitious material, In this chapter, the word cement is used to indicate all the
water, sand, stone, and possibly admixture, must be cementitious material in a concrete mixture. Cement may
proportioned in a mixture that : therefore be a “common cement” (see Chapter 1) or a blend
• in the fresh state, can, without segregating, be of common cement and one or more cement extender.
transported, placed, fully compacted and finished
if necessary;

• in the hardened state, achieves the required strength, 11.2 C&CI method
adequate durability, and satisfactory dimensional This method is derived from ACI Standard 211.1-91[11.2] and
stability; is based on the following:
• The strength, at a given age, of fully compacted concrete,
at the lowest cost. cured under standard conditions, is governed by water:
cement ratio w:c and type of cementitious material
Because of the large number of variables involved in used. Note: w:c means the ratio of total mass of the
designing a mix theoretically, the use of approximations and water in the mix, including water in the aggregates, to
short-cut methods is justified and undue refinements may the total mass of cementitious materials.
be discarded.
• The amount of water required per unit volume of
According to McIntosh:[11.1] concrete for a given consistence and with given materials
"Precise relationships have not been established is substantially constant regardless of cement content,
between the properties of concrete, and even the w:c or proportions of aggregates and cement. The
more specific characteristics of the mix such as water: main factors determining the amount of water are
cement ratio, aggregate:cement ratio and grading aggregate properties, cement properties, maximum
let alone such elusive qualities as aggregate particle size of the stone and the selected workability range.
shape and texture. The data used in selecting mix (This assumption is normally valid in the strength range
proportions should be expected to do no more than of 20 to 30 MPa, but the water requirement of concrete
serve as a guide. Mix design is a matter of trial and of strengths outside this range should be determined.)
error, and any calculations based on design data are • For any particular concrete mix and combination of
really only a means of making an intelligent guess at materials, there is an optimum stone content which
a starting point for the first tests to be made." depends on size, shape and compacted bulk density
of the stone, fineness modulus of the sand and desired
A competent concrete technologist can combine the science consistence of the concrete.
of mix design with experience and intuition and obtain
• The volume of compacted concrete produced by any
proportions which will be so close to the final figures that
combination of materials is equal to the sum of the
only one or, at most, two trial mixes will be required.
absolute volumes of the cement and aggregates plus the
volume of water and that of any entrapped or entrained
Mixes are normally proportioned in the laboratory using
air. The absolute volume of each material is calculated
samples of specific materials to be used for the concrete.
from the mass and the relative density of the material (D).
Proper care during sampling is essential in order to obtain
a representative sample, but clearly it is also important for
the materials being used in the concrete to be as uniform as Mass of material, kg . ..................(1)
Absolute volume, m3 =
possible. D x 1 000

This chapter describes a method of mix design used by the While all concrete mixtures contain some air, normally this
Cement & Concrete Institute and gives guidelines for mixes may be ignored when calculating the concrete yield, except
for some special applications. Worked examples are also when air-entraining admixtures are used.
included.

219
Fulton’s concrete technology • Concrete mix design

For practical purposes any discrepancies in the above • Select materials.


assumptions are normally small enough to be of no
• Characterise materials.
consequence. The purpose of the trial mix is to verify the
validity of the assumptions, and any significant inaccuracy • Proportion materials.
would be revealed at this stage. • Make and assess a trial mix.

• Specify mix proportions.


11.2.1 Applying the method
Practical mix design is a process involving the actions
In the figure, arrows indicate the inputs required for each
shown in Figure 11.1.
action. For the sake of simplicity, the use of admixtures is
not included.
Actions in the mix design process can be categorised as
follows:
The following notes refer to numbered actions in Figure
• Specify concrete properties and characteristics – the
11.1. Responsibilities are for conventional circumstances but
starting points for the process.
could be otherwise in specific cases.

Figure 11.1: Mix design process: actions and inputs

220
Fulton’s concrete technology • Concrete mix design

1 and 2: Specify strength of concrete and stone size Effective particle relative densities of blends of different
By the designer of the structure. Optimum stone size materials should be calculated as follows.
depends on the dimensions of structural elements, depth of
cover and spacing of reinforcement. D= 100
. .........................................(2)
%X %Y
Dx + Dy + ...
3: Specify slump
By the contractor to suit methods of transporting, placing where D is the effective particle relative density of the
and compacting. blend; %X and %Y are percentages by mass of materials X
and Y respectively in the blend; and Dx and Dy are particle
4, 5 and 6: Specify cement type, maximum w:c ratio and relative densities of materials X and Y respectively.
minimum cement content
By the designer/consultant to meet durability requirements. Values for factory-blended cements may be obtained from
Not done in all cases. Sometimes these items alone are cement producers.
insufficient to provide adequate durability and additional
protective measures, eg a protective coating, may have to be FA blends tend to reduce the quantity of water required for a
used. Specification should be in line with the latest relevant given consistence and permit higher stone contents.
code or technical literature.
11: Characterise stone
7: Select cement type and source CBD – Compacted bulk density is a measure of
By the mix designer for maximum economy but choice packing capacity.
could be overridden by action 4 above. (See Table 11.7 for RD – Particle relative density is needed to
guidelines for selecting cements and blends for specific calculate solid volume.
applications.) Consider all requirements for the concrete, Grading – A sieve analysis is done to determine or
eg any requirement for early strength. verify nominal size.

8 and 9: Select stone and sand 12: Characterise sand


By the mix designer for maximum economy of overall mix RD – Particle relative density is needed to
while still meeting any aggregate specification requirements. calculate solid volume.
Use concrete technology knowledge to select appropriate Grading – A sieve analysis is done to determine
aggregates for the application. In South Africa sands are often distribution of particle sizes.
blended to achieve better concrete properties (see Chapter 3). FM – Fineness modulus is calculated from the
sieve analysis.
Note: The cheapest materials do not necessarily produce the Particle shape – Assess by eye, eg rounded, cubical, flaky,
cheapest concrete (see actions 14 and 15). elongated.
Surface texture – Affects water requirement of concrete.
10: Characterise cement
This includes: 13: Select w:c ratio
• Strength performance, needed to select w:c To achieve a target strength to satisfy a specified strength
requirement, based on the performance of the specific
• Particle relative density, needed to calculate solid volume
cement. The selection may possibly be overridden by
• Possible effect on workability of concrete requirements of actions 5 and 6.

The strength performances of South African cements may be Note that the compressive strength of site-made, 150-mm cubes
obtained from cement producers. may be about 2 MPa lower than that of 100-mm laboratory
specimens. This difference is small and may be ignored.
Particle relative densities of some cementitious materials are
shown in Table 11.1. 14: Estimate water requirement, W
Table 11.1: Particle relative densities of cementitious materials Depends on:
• Particle shape and surface texture of sand
Material Particle relative density
• Stone size
CEM I 3,14
GGBS 2,9 • Required slump
FA 2,3
• Type of cementitious material (The inclusion of FA
CSF 2,1
tends to reduce water requirement.)

221
Fulton’s concrete technology • Concrete mix design

An estimate of the water content of the mix, using the 15: Calculate cement content, C
particular aggregate and cement combination selected, may C = W ÷ w:c from actions 13 and 14. May be overridden by
be made in one of three ways: requirement of action 6.
• By using figures obtained from mixes previously made
with the same materials 16: Calculate stone content
The formula for stone content is:
• By estimating, based on experience of similar materials
Ma = CBD (K - 0,1 FM) . . . . . . . . (3)
• By using average figures from Tables 11.2 and 11.3
where
The water contents given in Table 11.2 are for concrete made
Ma = mass of stone in one cubic metre of concrete, kg
with an optimum quantity of 19-mm stone and having a
slump of 75 mm. CBD = dry compacted bulk density of stone, kg/m3,
determined in accordance with SANS 5845 [11.3]
For other sizes of stone, adjust the water content by the K = a factor which depends on the maximum size
amount shown in Table 11.3. of the stone and the workability of the concrete
(Values for K are given in Table 11.4.)
A difference in water content of between 10 and 15 l/m3 will
FM = fineness modulus of sand determined in
normally halve or double the slump.
accordance with SANS 201[11.4]

Note that there are limits to stone content for workable


Table 11.2: Water requirements of concrete mixes (19-mm
stone, 75-mm slump) concrete. At Ma = CBD x 1,0, for example, concrete would
be completely unworkable. Approximate maximum
3
Water content, l/m Ma = CBD x 0,8 for general-purpose concrete.
Sand quality
Natural Crusher

Very poor 240 235 If a FA blend is used, calculated stone content may be
Poor 225 225
increased as shown in Table 11.5.

Average 210 215

Good 195 205


Table 11.5: Increase of stone content when using FA
Excellent 180 195
FA content as %
Percentage
by mass of total
additional stone
Table 11.3: Adjustments to water content to compensate cementitious material

for stone sizes other than 19 mm 15 3

Maximum 25 4
size of 9,5 13,2 19,0 26,5 37,5
stone, mm 30 5

Correction, 40 6
3 +20 +10 0 -10 -20
l/m 50 7

Table 11.4: Values of K for determining stone content

K
Approximate
slump range, Placing
Maximum size of stone, mm
requirement
mm
9,5 13,2 19,0 26,5 37,5

75 - 150 Hand compaction 0,75 0,84 0,94 1,00 1,05

25 - 100 Moderate vibration 0,80 0,90 1,00 1,06 1,10

0 - 25 Heavy vibration 1,00 1,05 1,08 1,10 1,15

60 - 125 Pumped - 0,83 0,86 0,87 -

25 - 50 Concrete roads * - - - - 1,2

* Calculated on CBD of 37,5-mm stone when using a blend of 37,5- and 19-mm stone

222
Fulton’s concrete technology • Concrete mix design

17: Calculate sand content 22: Reject mix


The sand content is calculated, assuming full compaction of Reject the mix if results of actions 19 and 20 are not
the concrete, from the fact that volume of concrete is equal acceptable.
to the sum of absolute volumes of cement, sand, stone and
water. 23: Modify design
Reproportion the mix after doing one or more of the
For 1 m3 concrete (ignoring air content): following.
• If mix is too stony, reduce stone content by 100 kg/m3.
Mc Ms Ma Mw
1 = + + + ....... (4) • If mix is too sandy, increase stone content by 100 kg/m3.
Dc x 1 000 Ds x 1 000 Da x 1 000 1 x 1 000
• If mix lacks cohesion, do one or more of the following:
– Use a finer sand.
where M and D refer respectively to mass, kg and particle
relative density; subscripts c, s, a and w refer respectively to – Use a sand with a higher percentage passing the
cementitious material, sand, stone and water. 300-µm sieve. This may be achieved by sub-
stituting a finer sand for some of the original sand.
Ms = • Use a smaller stone. (If permitted. This will increase
water requirement and hence binder content and
Mc Ma Mw
Ds x 1 000 1 – – – ....... (5) increase material cost.)
Dc x 1 000 Da x 1 000 1 x 1 000
• If mix is too sticky, use a coarser sand or a sand with a
lower percentage passing the 75-µm sieve.
The effective particle relative density of a blend of fine
aggregates of different RDs should be calculated from • If slump is incorrect, adjust water content. A difference
equation (2) above. of 10 to 15 l in 1 m3 of concrete will normally halve or
double the slump.
18: Make trial mix
Done in a laboratory. A mix that yields 15 l is normally A practical short-cut method is to start with water
enough. content higher than estimated, and then, after
measuring slump, effectively reduce water content
19: Measure slump in stages by adding predetermined increments of
sand and stone. Thus the amount of water stays
20: Assess stone content and cohesiveness of concrete constant but the yield of the trial mix increases.
This requires skill and experience. Some techniques are:
• Feel the resistance the concrete offers to the tamping rod In practice, initial amounts and aggregate increments
when doing the slump test. In a workable concrete, if can be easily calculated using a computer spread-
the slump is correct, the stones should move away easily sheet program.
from the tip of the rod. A harsh grating sound indicates
that stone content is too high. Water content for the required slump may be
determined by interpolating between contents
• After the slump has been measured, tap the base plate
straddling the required slump.
with the end of the tamping rod. If the concrete is
cohesive, it will collapse in a solid mass. If it lacks
cohesion, it will break apart as it collapses. No attempt should ever be made to improve workability
simply by increasing the amount of mixing water.
• Smooth the surface of the concrete with a steel trowel.
A closed surface without voids should be achieved if
24: Specify mix proportions for manufacture of concrete
stone content is not too high.
Based on the outcome of the previous actions. If reactive
• Compact some concrete at least 250 mm deep, eg in a aggregates have been used, check that adequate precautions
bucket. Scratch the surface of the concrete. Stones are taken against deleterious ASR (see Chapter 10). To allow
should be a millimetre or so beneath the surface. If they for moisture in the sand, the mass of sand is increased
are deeper, stone content is too low. If stones protrude proportionally and the amount of added water decreased to
above the surface, stone content is too high. keep w:c ratio the same.

21: Approve mix To calculate the yield of a batch, add the total water content
Approve the mix if results of actions 19 and 20 are acceptable. and solid volumes of cement, sand and stone.
Make cubes, preferably for crushing at seven and 28 days, to
check that strength development is normal.

223
Fulton’s concrete technology • Concrete mix design

11.3 Mix design for special applications state, as a starting point for the design of AEC. To calculate
This section gives guidance on the design of mixes for the the proportions for the first trial mix of the AEC:
following:
• Reduce the water content by 7%.
• Concrete mixes for pumping
• Increase the cement content per m3 by 20 kg for lean
• Air-entrained concrete
concrete (20 MPa or less at 28 days) to 40 kg for rich
• High-density concrete concrete (30 MPa or more at 28 days).
• Low-density concrete • Use the same stone content.
• Mixes for compaction by heavy vibration • Include the volume of air expected to be entrained in
• Mixes made with very fine sand the calculation of absolute volumes.

• Shaft linings The design of AEC may require several trial mixes to
• Sliding formwork verify air content and consistence of the fresh concrete, and
strength of the hardened concrete.
11.3.1 Concrete mixes for pumping
The method of design is similar to that used for conventional 11.3.3 High-density concrete
concrete but, because of certain restrictions imposed by the Concrete with a high density may be produced by using
pump and pipeline system, there are some limitations to the high-density aggregates as discussed in Chapter 18.
range of materials and concretes that can be used:
The methods of design of mixes for high-density concrete
Cement content is usually in the range of 250 to 380 kg/m3, are the same as for normal-density concrete.[11.2] High-
however, concretes containing higher cement contents can density concretes are, however, more prone to segregation,
be pumped using suitable admixtures, if necessary. All particularly if there is a large difference in the particle
common cements are suitable for pumped concrete. The relative densities of the coarse and fine aggregates and if
inclusion of FA may improve pumpability. mixes with a high slump are used. Often a number of trial
attempts are required in order to produce a cohesive mix
Water content is normally about 10 to 15 l /m3 higher than with minimal segregation and bleeding.
in conventional concrete when slump is 125 mm.
11.3.4 Low-density concrete
Sand of good particle shape should be selected. At least Because of the difficulty of estimating water contents
20%, but preferably 30%, of the sand should pass the of mixes containing low-density aggregates, conventional
300-micron sieve. Sand content, by mass of total aggregate, methods of mix design as described in this chapter are
is generally about 3 to 8% higher than that for conventional usually unsatisfactory. Low-density mixes are often designed
mixes, and the fraction of sand by mass of total aggregate is on the basis of cement content rather than on w:c.
usually in a range of 38 to 55%.
Useful data on methods of designing mixes for low-
Stone of good particle shape is recommended. The size density concretes are given in the ACI Guide for structural
of stone for 100-mm delivery pipes should be limited to lightweight aggregate concrete[11.5] and in the FIP Manual
26,5 mm but 19,0 mm is preferable. The stone content may of lightweight aggregate concrete.[11.6]
be estimated using the K factor given in Table 11.4.
11.3.5 Mixes for compaction by heavy vibration
Admixtures are beneficial in some instances but they should Mixes of very low workability that are suitable for intense
be tested under site conditions. vibration are designed in the usual manner. Note that:
• Water content for very low workability will be about
A slump range of between 60 and 90 mm is regarded as 20 l/m3 less than for medium workability.
optimal for piston pumps, and 100 to 125 mm for pneumatic • Stone content may be determined from equation (3)
pumps. and Table 11.4.

• The Vebe test may be used to assess consistence.


11.3.2 Air-entrained concrete (AEC)
It is preferable to use the proportions of a normal concrete • The mix should be tested under site conditions.
mix, made with the same materials and having the same
consistence in the fresh state and strength in the hardened A method of designing concrete mixes for intense vibration
was developed by Stewart and is described in reference 11.7.

224
Fulton’s concrete technology • Concrete mix design

11.3.6 Mixes made with very fine sand desired mix having characteristics not necessarily covered
In cases where the only available sand is very fine by conventional methods. It should preferably be done in a
(FM < 1,7), a satisfactory mix may be designed by using one laboratory pan mixer having a watertight pan.
of the following two approaches.
The method is especially suited to the design of mixes for:
The first approach is to blend 6,7-mm stone with the sand. • Exposed aggregate concrete
The ratio of 6,7-mm stone to sand should be such that the
• High stone content and heavy vibration
FM of the blend is about 2,5. Use equation (3) to determine
stone content. • Special placing conditions such as pumping and placing
by tremie
The second approach is to use a blend of two sizes of stone • High-strength concrete
instead of a single size. The smaller stone should be about
half of the size of the larger stone. As a starting point, use Method
a ratio of one part of smaller stone to two parts of larger 1 . Select w:c.
stone.
2. Weigh the water (usually 1,5 or 2,0 kg) and the cement
and place them in the mixer.
Insert the CBD for the larger stone together with its K value
from Table 11.4 in equation (3) to determine total stone 3. Have ready sufficient sand and stone weighed in
content. containers in easily handled quantities (5 or 10 kg).

4. Add about 5 kg of sand to the pan and start the mixer


11.3.7 Mine-shaft linings and add further sand until experience indicates that the
The use of 13,2-mm stone will in many cases be as economical mortar part of the mix is still slightly too wet.
as 19,0-mm stone in these very wet mixes in a slump range of
150 to 200 mm. Flaky or elongated stone should be avoided. 5. With the mixer still running, add stone and finally
Stone contents are similar to those used for pumped correct the consistence with sand.
mixes. The sand should have a low water requirement, 6. Record the quantities of sand and stone used.
and sufficient material passing the 600-µm sieve to ensure
7. Determine the slump or Vebe consistence, air content
adequate cohesion.
and wet density and make the appropriate test
specimens.
For these mixes, accelerators and superplasticisers or high-
range water reducers are commonly used to reduce the 8. Calculate the mix proportions per cubic metre using the
water and cement contents to acceptable levels. recorded quantities of materials used for the mix and
the measured air content and wet density.
Usually, the strength requirement is an average of 5,0 MPa
at eight hours. Suggested starting points for trial mixes are
w:c = 0,55 and 0,65 when cements of strength classes 42,5N 11.5 Examples of calculations
and higher, respectively, are used with calcium chloride as
an accelerating admixture (at 2% by mass of the cement
Example 1: Determine the stone content of a mix
content). The calcium chloride flake should be dissolved as
a 30% solution in water before being added to the mix. A concrete for hand compaction is to be made using a
19,0-mm stone with a compacted bulk density of 1 720 kg/m3.
The flow table test may be used to assess consistence. The sand has a fineness modulus of 2,8.

11.3.8 Sliding formwork From Table 11.4: K = 0,94


The mix is designed using the normal procedure and the
stone content is determined in the same way as that for and substituting the values in equation (3):
conventional concrete.
Ma = 1 720 x (0,94 - 0,1 x 2,8) = 1 135 kg
The grading of the sand, however, has a significant influence
on the success of the slide, and it is recommended that not Example 2: Calculate the particle relative density of a
less than 30% of the sand should pass the 300-µm sieve. blend of two aggregates with different densities

The blend consists of 60% of aggregate A with a particle


relative density of 2,65, and 40% of aggregate B with a
11.4 Designing a mix by eye particle relative density of 4,55.
This method of mix design is an effective laboratory
method requiring an experienced operator to produce a

225
Fulton’s concrete technology • Concrete mix design

From equation (1): Step 5: Sand content


From equation (5):
100
D = = 3,18 315 1 185 210
60 40 Ms = 2,65 x 1 000 1– – –
+ 3 140 2 700 1 000
2,65 4,55

= 665 kg
(The result is very different from the intuitive
[0,6 x 2,65] + [0,4 x 4,55] = 3,41.)
The quantities per cubic metre of concrete are therefore:
Cement 315 kg
Example 3: Design a trial mix
Sand 665 kg
Type CEM I 42,5N Stone 1 185 kg
Cement
Dc 3,14 Water 210 l
Ds 2,65
Sand FM 2,30
Example 4: Design a trial mix
Quality Average Type CEM I 42,5N
Given
Cement
Da 2,70 Dc 3,14
Stone Size 19,0 mm
Ds 2,65
CBD 1 540 kg/m3
Sand FM 1,90
Degree of control “Average” Quality Excellent
Given
Characteristic Da 2,74
25 MPa
strength at 28 days Stone Size 26,5 mm
Required
75 mm CBD 1 460 kg/m3
slump for Degree of control
Consistence
moderate " Good"
vibration
Characteristic
35 MPa
strength at 28 days
Step 1: W:C 25 mm
Required
Consistence
For “average” degree of control, strength margin is slump
10 MPa (see Table 16.1). For characteristic strength of
Maximum w:c for durability 0,43
25 MPa, target strength is therefore 25 + 10 = 35 MPa. From
cement producer,w:c = say, 0,67.
Step 1: W:C
Step 2: Water content For “good” degree of control, strength margin is 8,5 MPa
The sand is of average quality. (see Table 16.1).

Either from Table 11.2 or by visual examination of the sand, For characteristic strength of 35 MPa, target strength is
estimate the water content of the mix, say 210 l/m3. No therefore 35 + 8,5 = 43,5 MPa.
adjustment is necessary for size of stone (Table 11.3) because
the stone is 19,0 mm, or consistence because the required From cement producer: w:c for strength = 0,60.
consistence is 75-mm slump.
But maximum w:c is specified as 0,43; this value must be
Therefore water content = 210 l/m3 used.

Step 3: Cement content Step 2: Water content


Mc = Water content The sand appears to be of excellent quality, therefore say
w:c 180 l/m3 (for 75-mm slump). See Table 11.2.
= 210/0,67
= 313 kg/m3, say 315 kg/m3 Adjustment for size of stone from Table 11.3 is minus 10 l.

Step 4: Stone content Adjustment for slump is minus 10 l (roughly, slump halves
From equation (3) and Table 11.4: for each 10 l reduction).
Ma = CBD (K - 0,1 FM)
= 1 540 (1,0 - 0,1 x 2,30) Water content = 180 - 10 - 10 = 160 l/m3
= 1 186 kg/m3, say 1 185 kg/m3

226
Fulton’s concrete technology • Concrete mix design

Step 3: Cement content The amount of moisture in the stone is usually very small
Mc = Water content and it is customary to ignore it.
w:c
= 160/0,43 Assume that the sand in Example 4 contains an estimated
= say 370 kg/m3 4% of moisture by mass. Adjustments are made as follows:

Step 4: Stone content Mass of dry sand = 93 kg


From equation (3) and Table 11.4: 4% moisture = 93 x 4/100 = 3,7 kg,
Ma = CBD (K - 0,1 FM) say 4 kg
= 1 460 (1,06 - 0,1 x 1,9)
Mass of damp sand to be used = 93 + 4 = 97 kg
= 1 270 kg
Say gross volume of water = 22 l
Step 5: Sand content Water in sand = 4 kg = 4 l
From equation (5):
Net water required = 22 - 4 = 18 l
370 1 270 160
Ms = 2,65 x 1 000 1– – – Example 6: Calculate volume proportions and quantities
3 140 2 740 1 000
If the loose bulk densities of the aggregates are known, in
= 685 kg either the dry or damp state, the masses of the materials
may be converted to volumes.
The quantities per cubic metre are:
Cement 370 kg In Example 4 above, assume that the loose bulk densities are:
Sand 685 kg Stone: 1 410 kg/m3
Stone 1 270 kg Sand: Dry 1 640 kg/m3
Water 160 l Sand: Damp 1 360 kg/m3 (this lower density is due to
the bulking of sand caused by dampness)
The above mix contains 370 kg cement = 370/50 bags
= 7,4 bags The quantities of aggregates per cubic metre are therefore:
Stone: 1 270/1 410 kg/m3 = 0,90 m3
Sand: Dry 685/1 640 kg/m 3 = 0,42 m3
The proportions by mass for a one-bag mix are therefore:
Cement 370/7,4 = 50 kg Sand: Damp 1,04 x 685/1 360 = 0,52 m3
Sand 685/7,4 = 93 kg
Stone 1 270/7,4 = 172 kg These figures are used for calculating quantities or for
ordering materials.
Water 160/7,4 = 22 l
and yield (per one-bag batch) = 1/7,4 = 0,135 m3 = 135 l If the damp bulk density of the sand is not known, the dry
density may be used and the volume so obtained increased
Example 5: Correct mix proportions for moisture content by between 20 and 30% to allow for bulking:
of aggregates
The steps described in section 11.2.1 are based on the use of Volume of damp bulked sand = (93/1 640) x 1,20 = 0,068 m3
dry aggregates. If the aggregates contain moisture this must
be taken into account in the proportions for the mix.

Table 11.6: Batching quantities for Example 6

By volume, aggregates rounded to nearest 5 l


Material By mass
Dry sand Damp sand

Cement 50 kg 1 bag 1 bag


Sand 93 kg 93/1 640 = 0,055 m3 97/1 360 = 0,070 m3
Stone 172 kg 172/1 410 = 0,120 m3 172/1 410 = 0,120 m3
Water 22 kg 22 l 22 - (93 x 0,04) = 18 l

227
Fulton’s concrete technology • Concrete mix design

Table 11.7: Guidelines for selecting cements for concrete


Note: The guidelines given below assume appropriate proportioning of mixes and that good practice is followed.

Application Comments

The cement is normally selected for economy.


Conventional structural SANS 50197-1 common cements should be suitable.
concrete in a non- Site blends of CEM I cement with 50% GGBS or 30% FA have been extensively and successfully used in South Africa.
aggressive environment A site blend of CEM I cement and about 8% CSF is technically feasible but there is relatively little local experience of its use.
Blends with more than one extender have been used successfully.
Large placements where
temperature rise, due to Best results are likely to be achieved with cements with extender contents in excess of 50% GGBS or 30% FA.
heat of reaction, is to be See section 15.3.2.
kept as low as possible
Choice of cement will depend mainly on strength requirements at early ages.
High early strengths, without steam curing, may be achieved most economically with cements of strength grade 42,5R and
Structural precast
higher and with low extender content.
Cements with high extender content are better suited to steam curing.
Precast bricks, blocks
The cement should meet durability requirements, if any, and ensure sufficient strength to allow handling at an early age,
and pavers
typically the day after casting.
(See Chapter 22)
Strength class should be 42,5N or higher.
The inclusion of about 8% CSF is common practice in this application.
High-performance
Other cement extenders may also be used for technical or economic benefits.
concrete (See Chapter 17)
Superplasticiser is an essential ingredient in high-performance concrete.
The compatibility of the specific cement and superplasticiser is important.
Concrete for these applications must develop strength rapidly enough to permit joint sawing before the concrete cracks due
Floors, roads and
to restrained drying shrinkage. The mature concrete must have good abrasion resistance.
pavements with sawn
These properties are likely to be achieved most economically with cements of strength grade 42,5N or higher, with extender
joints
content not greater than 30%.
Reinforced concrete in Based on research done with South African materials,cements containing 30% FA, 50% GGBS or 10% CSF are
marine environment recommended. See Chaper 9.
Concrete made with The total alkali content in pore solution of the concrete should be maitained below limits (See Table 10.1) or the cement
alkali-reactive aggregate should contain not less than 40% GGBS, or 20% FA, or 15% CSF. However the use of 15% CSF usually results in a sticky
(See section 10.6) concrete requiring the use of a superplasticiser.
Caution should be exercised with concrete in sulphate environments and it is recommended that C&CI, specialist literature,
Concrete exposed to
relevant codes or a cement manufacturer should be consulted for guidance. Concrete made with 70/30 CEM II/FA blends
sulphate attack
normally gives better sulphate resistance than an equivalent CEM I concrete.
Extenders should meet the requirements of SANS 1491 parts 1-3[11.8] as relevant

References
11.1 Mclntosh, J.D. Basic principles of concrete mix 11.5 ACI 213R-03, Guide for structural lightweight-
design, Proceedings of a Cement and Concrete aggregate concrete, Farmington Hills, Michigan:
Association symposium on mix design and American Concrete Institute, 2003.
quality control of concrete, London, May 1954,
11.6 Federation Internationale de la Precontraint
pp.3-27.
(FIP), FIP manual of lightweight aggregate
11.2 ACI 211.1-91, Standard practice for selecting concrete, 2nd ed. Glasgow: Surrey University
proportions for normal, heavyweight, and mass Press, 1983.
concrete, Farmington Hills, Michigan: American 11.7 Stewart, D. A. The design and placing of high
Concrete Institute, 1999. quality concrete, London: Spon, 1951.

11.3 SANS 5845:2006, Bulk densities and voids 11.8 SANS 1491:1, 2 and 3:2005-2006, Standard
content of aggregates, Pretoria, South African specification for portland cement extenders.
Bureau of Standards, 2006. Part 1: Ground granulated blastfurnace slag.
Part 2: Fly ash. Part 3: Condensed silica fume,
11.4 SANS 201:2008, Sieve analysis, fines content Pretoria: South African Bureau of Standards,
and dust content of aggregates, Pretoria: South 2005-2006.
African Bureau of Standards, 2002.

228

Potrebbero piacerti anche