Sei sulla pagina 1di 12

SPE 30364

HPHT Drilling and Completion Design for the Erskine Field


EEiE
Seebty
OfPotrebum
w

Endnws

G.S.Elliott SPE, R.A.Brockrnan, Texaco North Sea UK Co, R.M.ShiveIS III, SPE, Texaco Ltited.

Cwyright 1995, Society of Petroleum PSIPineers, Inc. well in the spring of 19% (Fig.2). Two wells will be
tin paper was prapar.d for premntition at Offmhore -opa 95 held
in Aberdeen 5-a September 1995. xti through the jacket structure and suspended prior to
l’his papr was selected for pre8aatation by an SPE Proprm C_ttee
the platform topsides chxk being lifted into place in 1997.
following review of tha infomtion contained in an abstract NhOitted
The appraisal well will be tied back and wells will then be
by the author(s) . Contents of the paper, as presented, have not hen
reviewed by the Society of Petroleum Eupimers
correct ion by the author [s ) . The material,
&@ are mbjectad
as prasentad, does not
to
completed ready for commerc ial gas export in late 1997.
necessarily
Snginears,
refhct
its officers,
any position
or mmbers.
of
Paprs
the society
present.d
of POtrolaum
at SPE metixs
Further wells will then be drilled and completed as required.
are subject to *licatiOn rwiaw by Mitorial Camitt-a of the
society of Petroloum zineers. permission to copy is r*9trictad to
an abstract of not more than 300 W*. Illustration may not be * ~~~ @ un~~ K~gdOM
COM&LGnrdShelf @erations Ntike ~ MY
COPi~. me abtract should contain cmspicuous aclmmledg-t of
wfmre and by wham the -r was presmtsd. Write Librarian, SPE, P.O. well where the undisturbedbottom hole temperosureis 3(X7For greeter and
BOX 833836, RiCtiOn, TX 75083-3836, U.S.A., fax 01-214-952-9435.
either the POWpnmsum exceeds 0.8 psVji or pressure control equipment
greater then IO,(W) psi roted working pressure is required

Abstract
Platform Concept Outline
This paper summarises the factors influencing the well
By North Sea standards Erskine is a marginal field (335
design for a high pressure high temperature (HPHT)* field
MMSCF gas, 66.5 MMBBL oil). The resultant development
&velopment using a Not Normally Manned Installation
has mwolved around this in order to make development
(NNMI) in the UK sector of the Central North Sea (CNS). economic. The following lists the main fetures of the
development.
introduction
The Erskine gas condensate field is a 50% Texaco / 50% BP
1) Simple W 12 slot wellhead platform providing
venture and will be the iirst HPHT field developed in the
unprocessed multiphase fluids expxl to host platform
North Sea with first gas sciwduied for 1997 (Fig. 1). Tbb -- ...”
with a projeeted tielcl hre of i5-20 years.
field development concept is to install a not normally
manned installation (NNMI) with multiphase export of
2) Platform design and slot layout which enables access to
produced fluids to the Lomond platform from six platform
all slots for cantdevered jack-up drilling in the 300 ft
wells. Drilling and completion operations will be carried out
water depth.
using a harsh environment jack-up rig in cantilever mode.
~e~ ~~~ Cc.-...- -
nAlcm3&n_*
Primary functional requirements for the wells include high
reliability, high productivity and the ability to perfoH13
Primary considerations for the well design are:
through tubing plug-backs. Reserves in the COE area are
found in three separate but generally overlying Jurassic 1) Reservoir fluids containing H# and COP Reservoir
sandstone producing horizons, the Kimmeridge, Erskine, and pressure +/-14.,000 psi, temperate 3500’F,initird surface
Pentland sands.
shut-in pressure 10,600 psi (Table 1).

A multi-discipline project team consisting of reservoir,


2) Design flow rates required horn each well will be up to
production, drilling and facilities engineers was set up to 60 mmscfklay of gas.
progress the development concept. Specific well design
principles wem adopted and an iterative approach was used
3) The wells that are initially completed as Pentkmd sand
to produce a robust and reliable drilling and completion
producers will water out and require to be plugged back
design that is compatible with the overall development
and m-completed as Erakine sand producers. Due to
concept and provides reliability on a NNMI in HPHT service
availability and cost of large jack-up rigs, this requires to
conditions.
be a rig-less operation.

Jackup drilling will commence over the platform jacket 4) Possible future production enhancement with fracturing /
which will be instaIled over an existing sub-sea appraisal
103
2 HPHT DRILLING AND COMFLETION DESIGN FOR THE ERSKINEFIEUl SFE 30364

laterals. 130 ksi tubing below the safety valve with 5“ x 0.400” WT,
130 ksi tubing alxwe to accommodate wireline insert safety
5) Wells must be reliable because ofl valve installation.
. .. ~k @&@ ~w *U ~:p~ f~~~~.rs~]Qac b&don initial
a) lnnited rig avaiidiiity and ‘high rig cost.
shutin weilhead pressures of 10,600 psi and flowing
b) NNMI concept allowing very limited personnel access wellhead temperatures of 325 deg F. The collapse load has
without support vessels. been baaed on minimum bottom hole pressure with a 18.0
ppg packer fluid. Triaxird analysis has been performed to
c) platform maintenance, inspection and well intervention confirm the tubing design together with tubing movement
only being planned for once yearly. calculations for various operational load cases.

6) Well and drillhg progranune features to minimke well Metallurgy. The combiion of high temperatures, COZand
CQsts. H# partial pressures, formation water salinity, and
multiphase flow requires the use of CM materials for the
Well Desii Primary Features tubing and production liner to ename reliable corrosion
control (’hble.1). A 28%Cr-31 %Ni CRA has been selected
Primary well design features to meet these requirements SIW as the base case material with a yield strength of 130 ksi
which has been &rated for use at elevated temperatures
1 \
1]
mz.-
NIUU~WIG
L-— ---1
cUU#UUU
L,... c .
LO1 lG-IW
-l:. Al= 4-..
uuuup
*I.I h.h;”e
W.IU6
nlmm
y..~ m --/
\“. .d f~
m —- --- IW32M imkotropy [0.9)1 (Fig 4).
backs.
.—A.
Environmental testing of 13%Cr, “Super” 13%Cr and duplex
2) Polihed Bom Receptacles (PBR) instead of packers. stainless steels has been conducted in an effort to qualify
lower cost materials for the tubing string. Preliminary results
~) Comsioa Resis’m’. .Allnv=
-.”>. \w..’ ., fhr
~f’nA) .-. ~ flow we@ indicate that 13%Cr and “Super” 13%Cr materials are not

surfaces. suitable, whereas 25%Cr can be used, but with limitations on


the ab~lty to acidize wells.
5) Standard, field proven materials and technology whenever
possible. PBR vs Packer. Isolation of the reservoir km the
production casing annulus is achieved by use of a PBR
6) Use of API bit sizes which are common in the North Sea system. The PBR is installed as an integral part of the
if necessary at the expense of non-standard casing sizes. production liner, directly below the liner hanger with the
seal mandd and stack run with the completion string. A
Completion Design PBR style completion was selected over a packer style
The requimrnemt for through tubing plug backs, high completion because it provides:
production rates, and wellbme reliability drove the proposed
completion design. The completion design (Fig.3) is based 1) Simpler workovem (no deep milling oprations required
on a PBR. It consists of a seal mandrel mn on 4.1/2” CRA that could lead to loss of a platform well).
tubing with a full bore tubing retrievable surface controlled
subsurface safety valve (TRSCSSSV). Landing nipple III’s 2) Lower tubing stresses.
have been selected to allow through tubing plug backs using
cast iron bridge plugs (CIBP). The production string will be 3) Simpler completion design.
nm in a non kill weight packer fluid prior to perforation of
the wells on wireIine. 4) SuccessfiIl experience in US HPHT wells and recently on
the Strathspey field in the North Sea.
‘Ihbing Design. A 4. lR” tubing string satisfies both the
production requirements and provides a workable overall To maximise completion reliability and reduce the chances
well design. Nodal analysis indicated that 3.1/2” tubing of a workover, the seal stack will be maintained in a static
would not achieve the required production rates of 60 position during all production operations. Sufficient weight
mmscfld 5.1/2” tubing would provide a modest increase in will be set down together with annulus pressure to prevent
flOW Ciiptity, but would fJlldy illCIK%W the Cost and seal movement during hot producing and cold shutin periods.
complexity of the casing programme. It would cause the The stack is positioned in the PBR to accommodate upward
Pentland wells to water out pmnaturely due to the effect of movement during well kill operations or stimulation
high liquid loadings in the tubing. Even with high flow rates treatment Seal stack testing at shmdated bottom hole
the number of wells could not be reduced due to reservoir conditions is ongoing to determine the best available
recovery considerations. configuration.

TIE production string will consist of 4.1/2” x 0.320 WT, TRSCSSSV. The running of tandem tubing retrievable
104
SPE 30364 G.S.ELUG’IT, R.A.BRGCKMAN,R.M.SHIVERS III 3

surface controlled subsurface safety valve’s was considered. ~~L- =-w


However the increase in the overall completion reliability This has been analyzed on a global systems basis with
and Workwer cow benefit W* not significant when various well ales@. In all cases, pressure build-up in a
compared to the added complexity and increased cost of the sealed annulus due to thermal expansion from production
completion ales@. Hence a single safety valve with a conditions results in unacceptable loads on casings. This
communication nipple was =i=ti asthebasecase. ‘Mean will be preven’d by tbe fo!!mving measures.
timetofailure of the safety valve have been dmated as 20
years based on available North Sea data. 1) pressure will be bled off from all annuli at the surface
wellhead on initial production start-up.
A single piston non-equalizing flapper type valve with all
metal to metal seals will be used. To maintain the through 2) For dcilling casings below 20 conductor, cement tops
tubing workover abtity a 4.1/2” full bore safety valve will may be left below the previous casing shoe, thus
be run. The vrdve is rated to 15,000 psi at ao opemting providing a natural relief valve to the formation.
tempemtum of 350 deg F. It will be manufktured from
Inconel 718 material with a 7.875” OD and a 3.813” bcue. 3) For the tubing to production tieback anmdus, pmssme
Skimming the valve OD to 7.750 at the expense of a Will illitiy be bled Off. h addition, _Ote ~SStUe
reduction in wmkkg preemtt $0 14,000 pd is being monitoring will be provided on the host platform for this
considered. Fluid velocities across the valve am well below anmdus. In addition application of a pressmised nitrogen
100 ft/sec which should ensure no erosion for sand &e cushion is Ixing eonsidemd for this annulus.
Productionz.
Workover/Mervention Philosophy
A separate communication nipple will be run above the valve Workovers and well interventions will be minimki by high
to allow wimliie retrievable subsurface safety valves well reliability and only carrying out data gathering required
(WRSSV) to be run should the primary va.he fail. Separate to maximise hydrocarbon recovery. Major workover and
control lines wiU be run for the primary valve and the well interventions will be carried out where possible during
communication nipple. In the event of control line failme to the summer months. Typical through tubing operations are
the primary valve a full tubing workover would not be expected to lxx
required as a WRSSV will be run to maintain production.
1) Plug back and re-perforation of 2 Pentland wells as
I%cker Fii Seiin. Packer fiuici seketton has ‘been rOdUr~~S+
Er#dnn. p... .
driven by
2) Production logging on all wells on a yearly basis.
1) Improving tubing workover abfity.
3) Installation of wireline retrievable safbty valves.
2) Minimizing tubing movement.
Full tubing workovers are likely to be caused by PBR seal,
3) Passive to production tubing and tieback materials. tubing hanger, tubing or TRSCSSSV failure. It is estimated
that at least 2 full tubing workovers will be required over the
4) Cost effectiveness. fife ~f fi~d bac~
— .m thmfiwemll
“U . . -. .- rdiah~ty
..-— Of &t? COI@etiOIJ.

On unperforated wells the completion string will be run in Shutin wellhead pressures decline sharply (Fig.5) to allow
11.3 ppg calcium chloride brine giving an initial pressure through tubing plug backs to be carried out using
differential across the seal stack of 5300 psi. Seawater has conventional wireline and coiled tubing techniques with
been disregarded as a suitable fluid due to the high through tubing CIBP’S. The platform has been designed to
differential pressure and excessive tubing movement allow wireline, coiled tubing, and snubbing / hydraulic
occurring during production operations for a smalI reduction wodcover unit operations. However, logistical support must
in cost. low volubility of oxygen in a satumted calcium be provided by a bridge linked Mobile Support Vessel. Full
chloride brine will ensure that only low geaerai corrosion tubimg ‘wCitkOV~rS can be CO”dC*d at any *ti- !))’ a hbsh
occurs. environment jackup or a medium size (CEFM 2005-C)
jackup in summer. Modular WOI’kOV= I@ Cm dSO be
Work is ongoing to try to establish safe, efficient reliable utilised by the addition of capping beams to the piatform
means of completing perforated wells with underbalanced thus enabling full tubing workovem to be accomplished
clean packer fluids. If necessary perforated wells will be without using a jackup rig.
compleled using kill weight fluids with weights up to 18.0
ppg. Pseudo oil based muds will b used for the heavier Enhanced Recovery
weight fluids as opposed to zinc bromide and formate The deliverability of the welk completed in the Erskine sand
brines. deciine with the sharp drop iti m—wii presmre which is a
b‘-h--’”=~”~”
aww.1.uw “. -. .-..
“f ‘hi’ I“w ~~———.—.,
ilitv maxvoir. A number
105
4 HPEIT DRILLINGAND COMPLEXIONDESIGN FOR THE ERSIUNE FIELD SPE 30344

of enhanced recovery techniques have been considered and L]thology / pressure Regime. Erskine lies in the Central
their impact on well ddgn identified. Graben area of the CNS. ‘Ile Iithology / pore pressure /
mud weight diagram is shown in Figure 6. Tertiary
The technical feasibdity and design of fracturing the Edcine formations extend to approximately 11500 ftss. These
Sand to improve recovery has been investigated. Both formations are primarily normally pressured, but reactive
technology and equipment exist to enable Ihcture stimulation unstable / overpressured shaks of the Eocene age have
to be carried out. However, erosion of production equipment required oilbased mud of 12.5 ppg to maintain good hole
caused by proppant flowback over time is a major problem conditions.
especially when associated with high flow rates and wellhead
pressmes. This stimulation tectilque will not be used Upper Cretaceous chalk and calcareous limestone then
initially due to the increased risk of equipment failure which continue to around 14,500 ftas. In most of the CNS, Lower
will impact on the platform ndiability and safety. Cretaceous shales and marls then continue to the Late
Jurassic Kimmeridge formation which is often overpressured
High angle wells have also been considered as a means of due to compaction. The pressure transition zone is usually
improving well &liverability. There am however a number over this Lower Cretacaus interval. Most CNS wells
of technical problems that have yet to be solved targeted for the Jurassic formation set intermediate casing in
the Lower Cretaceous pressure transition zone. In the core
1) Limitations of current down hole tools (especially area of the Erskine field however, the Lower Cretaceous is
slim-hole Measurement While Drilling tools at high virtually absent. This results in a rapid pressure transition
temperatures). towards the base of the Upper Cretaceous calcareous
limestone. Intcmnediate casing has to be set in the base of
2) Boxe hole stability in depleted reservoirs limits the the Upper Cretaceous formation. Although there am useful
maximum hole angle that can be successfully drilled. formation markem such as the ‘Black Limestone Marker’,
picking this casing point has always been a problematic part
3) At initial memoir conditions, tiacture gradient decreases of the Erskine appraisal wells. Conect placement of the
with increasing hole angle, thus narrowing further the intermediate casing shoe is essential to ensure sufficient
margin between tkacture gradient and pore pressme. fracture strength to weight up the mud and drill the
overpressured reservoir’.
Studies are ongoing and it is possible that the production
liner design on the two later Erskine sand producers maybe The Jurassic. reservoir sequence consists of Late Jurassic
modified to allow a future short radius horizontal sidetrack Kimmeridge formation containing Iiited Kimmeridgian
to be performed within the Erskine sand. hydrocarbon bearing sandstones, then Mid Jurassic sequences
that contain the Ed&e and underlying Pentland sand
- *4W sequence. Pentland sands are anticipated to exhibit a strong
water drive, whereas the Erskine and Kimmeridgian sands
Platform / Rig Interfaces. The field development plan are depletion drive. Jurassic pore pressure at Erskine ranges
provides for cantilever Jack-up drilling over the NNMI from ca. 17.8 ppg EMW in the Kimmeridge sands to 17.2
platform. Advantagea of this are simplified platform des@n ppg EMW in the Pentland sands. Fracture pressure is in the
and elimirlatictl of skidoff eq@xnent reqttiremerlts. The range !8:5 to 20 ppg EMW. Thus there is a very liited
disadvantage is relative motion of the platform and jacket window in which to operate allowing for mud ECD’S etc.
structwes and possible limits on operability in severe In addition, overbalance of mudweight over pore pressure
weather. Field data suggests that actual movements will not increases through the sequence, and mud losses particularly
be as large as the theoretical movements predicted by to the more permeable Pentland sands have caused a drilling
structuml analyses. It is estimated that down time due to liner to be required to reach TD on several appraisal wells.
excessive relative motion will be limited to 1 year storm Significant time has been spent controlling influxes and
conditions or similar. Following selection of the Santa Fe losses to these formations during appraisai driiiing, and the
‘Monitor’ for the development drilling campaign, an differentiation of influxes from kicks and formation
operabii~ty study is underway to identify means of ballooning has been difficult.
minimizing downtime. For example a flex-connect system
is planned to be installed in the riser between the rig and Casing Setting Depths The generic development well
BOP. design is shown in figure 7.

Other platform rig interfaces inclu& provision and tie-in of 30” Structurof Ciasing provides sufficient formation
ESD, alarms, fire and gas, firewater, kill manifold, integrity to support loads and drill 26” hole for the 20”
navigation lights, power, telecomms / PA, air, water, and conductor.
access bridges. Early selection of the jack-up rig has
allowed the platform des@n to suit the jack-up to reduce rig 20” COn&CtOr is set at 2,500 ftss in order to case off
modification cost wherever possible. hitial build section and obtain a formation strength in the
106
SPE30364 G.SEUKYtT, R.A.BRGCKMAN,R.M.SHIVERS III 5

15-16 ppg EMW range. 6) Provision of one contingency drilling liner for the
reservoir interval and acceptance of reaching TD in a
S@rce CWng is set in the top of the Upper Cretaceous 6.1/4 equivalent hole size.
chalk to case off the unstable shaIes of the Eocene age and
the permeable Pakocene sands. 7) Isolation of the liner lap to remove the risk of liner top
leakage from completion with an underbalanced packer
htermedkte C3rsingis set in the pressure transition zone fluid.
towads the base of the Upper Cretaceous formation as
described above. The design considerations specific to each casing string are
discussed in mom detail below. This has been laid out in
Drilling Liner is contingent to be set during the drilling the order of ascending casing size as well design is primady
of the reservoir sequence if required. c-hiven by completion design and TD hole size. Table 2
shows a summary drilling and production string lotxl criteria
PmAction Liner is set at TD and cases off the reservoir used in the well design.
sands and dtilling liner if run.
MetaUargy. Due to the casing clearance requirements, it was
Pmductbn Tieback Sbing is cemented in place in the desirable to use high strength sour service casing for
tieback PBR on top of the production liner, and ties back to intermediate and production string applications. A
surfkce as the production string. qualification testing prograrnnm Commenced in 1991 and
NACE TM0177 method A coupons and full scale casing
Directional Drill@. Wells will be ‘S’ shaped. This is joint testing have both taken place. Notable differences were
possible with quite low tangent anglca due to the relatively seen in results horn coupons and full scale casing. Full
small areal extent of the field. The furthest stepout well scale casing qualiikation testing is preferred because 1) a
requires a tangent angle in the region of 35°. ‘S’ shaped full scale test sample has an area equal to approximately
weiis etde the weii to be verticai fiwrn intt casing 200,000 cou~.s thus incree=inu - -—-
statistical confidence, 2) the
~intm~tiuse~gti~for~tikkti internal surface of the full scale sample is that which must
highest temperature part of the well. The drillstring will also prevent initiation of SSC and contains imperfections
be kept simple in the reservoir sectiom simplifying well mnaining from the manufactming process. These
control and minimizing circulating pressure losses. presumably account for the differences seen in coupon and
full scale results.
Build rates will be limited to a plarmed rate of 1.5°/100ft in
the 26 hole and Arnco 200XT or Armacor M drillpipe NAC13 TM 0175 method A high-end C1OO COUpOnS WC= .

hamlbanding will beusedin order tominimiae casing wear. found to have 90% thm%old of SMYS in s%ndarr NKE
solution, but full scale joints failed this environmmt at 80%.
Well DesigII Pldlosophy. The following lists the general Low end C90 was used as a control and passed full scale
ptiiples used in the development of the Erskine well testing at 90% of SMYS inthiscalvironment
design in addition to the considerations for completion
design previously discussed. Further W scale joint testing took place using a 1.5 psi H.#
partial pressure modified NACE environment (conservative
1) Use of AiiI bit sires common iu the North Sea hole sizes, Erskine environmentt). ‘fhiS qudifkd high end yield Stf4?Z@h
if wceamry at the expense of non-standard casing sizes. C1OO at 90% SMYS, a dramatic rise from the testing at
NACE environment conditions. Confirmatory CiOO ‘@sting
2) Tapered casing strings to accommodate the TRSCSSSV. is underway, and Cl 10 sample testing is planned.

3) Allowances made for casing wear, casing yield strength Selection of surface and drilling casing grades foIlow NACE
reduction with tempemtum (Fig.4) and td-axial stress MR 0175 tempczature and service exposure criterion, using
analysis. the production casing test fuii scaic quai@aticm as “b initiai
reference at surface c4mditions (Table.3).
4) Specification of ‘extreme’ and ‘expected load cases
where appropriate, with differing safety thctors for the Thus, for production applications on Erskine C1OOhas been
two cases. Lame’s casing burst strength equation was qualifid and CIIO is planned to be used for intermediate
used for uniaxial design calculations rather than API casing in pseudo oil based mud drilling environnumts.
Bariow equation. ~~rkW~ t~@ ~~ ~m q~~ify C 1iO for production
applications on Erskine4.
5) Opdmisation of running cleamnces on completion, casing
in casing, and casing in open hole. Consideration of Pmhwtkm Liner. A 4.1/2”, 2896Cr-31%Ni production liner
fishing capabilitica of well cleanout strings and tubing. will be used. The corrosive nature of the fluids requites the
use of CRA’S and the selection of this materkd for the
107
6 HPHTDRILLINGAND COMPLETIONDESIGN FOR THE ERSKINEFIELD SPE 30364

production liner is based on the absolute requirement for top. Running clearances for the tieback string inside the
!Gfigey~~yfi~~ ~~ !~~~~. ~J~ ~i~ p~Qvi&.s monQbore intermediate string are a minimum of 0.5” on couplings and
features to the well for ease of plugback with cast iron are around 1” on pipe.
bridge plugs and simplified workover operations. 3.1/8”
wireline perforating guns can be run for sufficient The tieback string will be tacked in place with cement in
perforating performance and 2.7/8” cleanout strings can be order to prevent tieback seal movement. Following
used. cementation, it is necessary to pull tension in the production
tieback string to prevent high axial compressive loads from
The driving load considered is collapse load of full temperature deep in the sting which could exceed triaxial
undepleted formation pressure externally with depleted stress safety factors in the event of a tubing leak during
.-.. — at ‘&e ~-
production peSSLIK a-~ U1
,..C LIGIUILLQUw,uau,
G-1A IX- :“*a-mIl., . nmrhlrtinn
y.-”. . . .

Reservoir compaction was calculated, and connections will


be Selected to mmimise resistance to compression. DriUing Liner. This will serve the function of a drilling
liner only, as the production liner top will straddle and
.. . . . . . AL:-1:-- m.. -
Isolate w liner. I IIUSMUS WU1 w dm*Wi to ~V=- ●v ●-
l_..A” . ...11 h 1: .
ZOnai isolation is critical when piugging back the Fentiand I .“’s- *- b

producers to Erskine producers after watering out. Thus formation for collapse and pressure testing and gas
cementation quality including anti migration properties wiIl evacuation for extreme burst loads. The liner selected for
be important. this application in 8.1/’2” hole is 7“, 23 ppf which provides
good clearance for cementing and allows drilling to TD in
With the tubing PBR below the liner hanger, hanger and 6.1/4 hole for the production liner.
tieback equipment can be of 140 ksi carbon steel at these
temperatures (+30@Fj. The hydraulically actuated hanger It is anticipated that this liner will be required on between 2
will be above the tieback receptacle and hence isolated from and 4 of the 5 new wells.
the production wellbore fluids and pressure. therefore it is
designed only for hanging loads. The liner lap will be behind Intermediate Casing. The setting depth for the intermediate
the tieback casing, and thus overbalanced by kill weight casing in 12.1/4” hole is in the pressure transition zone as
mud. aheady described. This hole section will continue the use of
the pseudo oilbased mud system to be used for the 17.1/2”
Production Tieback String. The production tieback string hole. It is planned that Gamma Ray-Resistivity LWD and
is run to provide protection against possible production VSP’S will be used to assist in picking the intermediate
loads. Prima@ a surface tubing leak at initial shut-in casing point, as them are some identifiable features for
pressure on top of the brine packer fluid with degraded mud reference in this interval. Following mnning and cementing
backup was taken as the expected load case. In the extreme of the intermediate casing, the reservoir is drilled in 8.1/2”
case a tubing leak on top of kill weight mud packer fluid has / 6.1/4 hole to TD of the well through this casing string.
also been considered. The intermediate casing provides a
degree of redundancy in the event of a breach of the Design criteria for this casing string are an ‘extreme’ burst
production tieback sting. This is considered of benefit for load defined as gas evacuation to surface from the reservoir.
the first HPHT field in the North Sea environment. Other ‘Expected’ load is that of partial gas evacuation. In any
benefits provided by the production tieback include isolation event sour service casing is required. Collapse loads
of the liner top behind the production casing and elimination considered are that of mud level dropping to minimum
of casing wear concerns on the production string. formation pmssum. In addition, the lowermost section of the
intermediate casing is designed for production loads as a
The tieback’s internal size is driven by the completion contingency against failure to land or seal the production
components. The 15M 4.1/2” TRCSSSV’S available have tieback in the liner tieback PBR.
ODs in the region of 7.7/8”, although it is expected that
Ed&e valves will be skimmed to 7.3/4” at the expense of In order to accommodate the 9.5/8” casing at the top of the
—.-.. —___
a slight drop in pressure rating. Thus 9.5/8” C1OO sour tieback string, and .be compatiiiie with a i 3.5/%”wc’W5ari /
service casing provides the requhed strength capabilities with BOP, a 12.1/8”, 90 ppf, Cl 10, casing with Marubeni ULT
a 7.95” drift. This provides a minimum running clearance in connections was selected for the top of the intermediate
the completion brine of 0.2. Increasing this clearance may casin~. The nmainder of the intermediate casing is 10.3/4”,
be possible if Cl 10 casing is qualified for Emkine production 73ppf, Cl 10 down to 2(WF inside the surface casing, and
conditions. 10, 72ppf, Q125 in 12.1/4” open hole. The 10 casing has
~~ g. ~,~ &d@.. 17rw4m~Ce-~
..— f~~ nmnin
..—.g d CemdDg this

In order to be able to meet the requirement to washover and string inside the surface casing are a minimum of around 1”
fish 4.1/2” tubing with 5“ T&C couplings, a 6.3/8” minimum diameter on the 10.3/4” couplings. This provides acceptable
drift diameter is required below the TRCSSSV. The tieback running surge pressures and cementing ECD’S.
casing selected is therefore 8 CIOO from the TRCSSSV to
200”F and 7.5/8” Q125 below this to tk production liner Surface Casing. The surface casing string is required to 1)
108
SPE 30364 G.mLim’iT, R.A.BRGC”*” x, “A.1v l.oru
“--e v-. Ill
m 7

case off the Tertiary and Palaencene sequence, 2) modified buttress thread. Intermediate and smaller casings
accommodate the 12.1/8” casing at the top of the will all utilise premium comections.
intermediate casing, 3) provide a 12.1/4 drift for drilling to
intermediate casing point. Design criteria is baaed on a Due to the small annular clearance between some casing
limited kick due to knowledge of the area from 8 previous strings, there are requirements for slimline couplings on
exploration and appraisal wells. Sour service is not required relevant casing sizes. For example the 12.1/8” casing at the
for this string. Losses considered are mudweight dropping to top of the intermediate string has a coupling OD restriction
balance pom pressure. It is planned that 17.1/2” or 16 open due to 13.5/8” wellhead design constraints, however this is
hole will be drilled with a pseudo oil based mud system to also an am of high tensile loads. The Marubeni ULT
inhibit the reactive and unstable Tertiary formation. Surface comection was selected due to it’s high tensile efficiency,
casing will be set in 12.5 ppg mud. The mudweight may full drift and restricted comection OD features. Connection
●I..
‘=a ‘~ ~~~ f~i ● AAS -ma+:fi”
*e ~~.~/# Uuav .“.
tfi ~till thm
w Salu u. ~~;m .al~fi
—.*.. l~mda
...” .. itw.lf
..— .-. . tn —- mmlication.
-- thi~ --J--. —.—----, hf@
--- _ CUStOmkXI
Upper CmtaceOus chalk in order to increase penetration rate for specific pipe sizes. Qualification testing is also planned.
and assist in detection of the pressure transition zone. The remainder of the intermediate string utilises
Mannesmann ~ COtMl(@iOt3S.
A 16” x 13.3/8 taped casing string has been selected as
the surface casing. 16 will be run inside the 20 conductor Tieback and production lier connections have not yet been
and 13.3/8” mn below the TRSCSSSV depth and across the selecte4 but similar criteria exist.
open hole. A modified buttress thread has been selected for
this application on both casing sizes. WellheadaJXmas Trees
n.
L-
t....
II= VT
A..*,JCSWk+-
:..lr *R. W.StW.W
UUby
“nm.;rl.mri fnr 17?.clrirma-
s“. u“--- -“
Umlr=mllv
~“--..a..-=
Conductor. The conductor will be set at 2,500 ftss to equipped with 21.1/4” / 13.5/8” BOP systems. Use of a
provide a 15+ppg EMW formation stnmgth, and to case off single 18.3/4 15M BOP was considered to reduce BOP
the build section of the well. 26 hole will be chilled with handling and possibly simplify casing hanger configuration
seawater and viscous sweeps, with returns to the platform for the Erskine casing programrne However, the savings do
deck elevation. 20”, 133 ppf, X56 casing will then be run not justify the considerable expense of supply and fitting of
and cemented. Design criteria are based on kick loads such a BOP and handling system for a 6 well development.
limited to the 20 shoe formation strength. Due to siting of
the platform over an existing weIl and site survey results, The wellhead system is designed for the 21.1/45M x 13.5/8”
shallow gas is considered to be extremely unlikely. 15M BOP ccdguration and consists of stacked casing
spools. DriUing casings will normally be suspended by
Structural (hai~ Structural casing is 30 diameter. Pre- mandrel hangers with contingency hanger systems will be
installing the jacket allowed omission of a mudline provided for all casing strings. Metal to metal seals will be
—.. .
suspension system. Full hanging weight of til casings WKI‘be provided for intermediate and tieback casing strings.
supported by the 30/20 casings. Structural analysis Because it is necessary to pull tension in the production
showed 30 x 1” wall, X52 material is suitable for weUs tieback string to prevent high compressive loads deep in the
ddled through the platform jacket, A proviso on this is that string during production a slip and seal is required.
in severe storms it will be necessary to release the jackup
!lom the ccmductor/BOP if dative motion of the two As jackup drilling will take place through the platform jacket
structures approaches 3 ft. Operations analysis is underway casings can be hung at surface and a mudline suspension
to determine maximum Aative movements that will be system is not required.
allowed for continuing operations. The 30 casing from
seabed to wellhead will be coated with flame sprayed To facilitate safe and efficient BOP / wellhead handling,
aluminium for corrosion protection. ‘quick connect’ type connections will be utilised on all
wellhead and riser connections that are routinely made up
Analysis early in the project planning showed that if wells and broken.
were to be drilled horn a jackup without the jacket in place,
30 structural casing would have required significant The tubing hanger will be 11“ nominal to facilitate the
redesign tlom the above sizes. possible use of 11“ BOP’s during future woxkover or well
intervention that requires only manipulation of the tubing.
36 hole will be drilled vertically with seawater and viscous
sweeps and the 30 casing will be run and cemented. The x-mas tree will be nominal 4.1/16API 15M to be
Driving the 30 was discounted due to fm shallow compatible with the tubing bore, and will be a stacked valve
ffi-mt:n.e
.Wa—””. .“#’l*b
— - — d ●m.1im;mata Anmlamc
. “.u— .“~.~. .9“A
. —m!lw;mica Prmfi
--..~ mmnti
. . . fin
. . @ facfl&@ *A* Qf Compomnt Valve

directional control. replacement. The tree is of split design consisting of a tubing


bonnet and upper valve assembly. The upper valve assembly
Casing Connections. 30 and 20 use established thraded consists of a solid block cross containing an actuated master
connectors. The surface casing uses the Dalrnine ATS valve and manual swab valve. An actuated flow wing valve
109
8 . HPHT DRILLINGAND COMPLETIONDESIGN FOR THE ERSKINEFIELD SPE 30364

and a manual service wing am bolted to thier respective 90° 7. S.A.Cruaer, Texaco E&P Technology. “HPHT Production
outlets. A connection for methanol injection is provided Experience in the United States” unpublishedproprietaryreport.
between the service wing and upper master valve. This
confimration has been adopted to facilhte ease of change 8. RM.Shivers, J.P.Brubaker,Texaco Ltd. “Development Planning
~—- . .- —-— —..
for the HPHT ErsIune ~kid’ ~FE 30376 P-nAA a
out of component parts of the tree assembly. Trees will be
Offshore Europe Conference in Aberdeen, Scotland, 5-8
fire resistant to maximise well security in the event of fire
September 1995.
on the platform. Production bore valves am not required to
cut wireline, as this feature will be provided by the block
valve assembly that will IE utilised during the wireline
operations. This will minimise the chance of removing a
tree valve that may have been used to cut wire.

Concluaiona

1. HPHT development wells can be designed to be safe, cost


effective and reliable using current fieid proven
technology.

2. Well design requirements and considerations should be


thoroghly evaluated. The design process should start with
the completion string and work outwards. An iterative
approach allows optimisation of well design.

3. AU intemated team ammach enables tiling ~d well


design ;asuea to be- ;onsidered in the overall field
development concept.

Acknowledgements
The authors wish to thank Texaco and BP for their support
and permission to publish this paper, and all parties who
contributed to the well design and project progression.

References

1. J.B.Greer,Greer Engineering Co. ” Yield Strength Reduction at


Elevated Temperatmes and Anisotropy of Yield Strength in
PerformanceDesign for OC’IKi”unpublished proprietaryqort.

2. S.J.Svedeman, K.E.Arnold. “ Criteria for Siziig Mukiphaae


Flowlines for Erosivt#Corrosive Service” SPE Production &
Facilities jouti Febmary 1994.

3. S.D.Csssidy, Texaco E&P Technology. “Solutions to Problems


Drilling a High Pmssure, High TemperatureWell” SPE 24603
pnxented at 67th Annual Technical Conference and Exhibition
of the SPE in Washington, DC, 4-7 October 1992.

4. J.B.Gmer, Gmer Engineering Co. “ Test Progmmmc for 110 til


Sour Service Casing” unpublished propriety report-

5. E.F.Klementich, S.C.Morey, M.L.Payne, W.T.AabiU,


E.O.Banker,J.KBouche. “Development and Acceptance Testing
of a Flush Joint Casiig Connection with Improved Performance
Properties”SPE 26320 presented at the 68th Annual Technical
Conference and Exhibition of the SPE in Houston 3-6th
October 1993.

6. The Institute of Petroleum. “WeU Control During the DriUing


and Testing of High Pressure QIMore Wells”.

110
SPE 30364 G.S.BLLWIT, R.A.BRGCKMAN, R.M.SHIVBRS III 9

Table 1- Reservoir Cbaracteristica

Reservoir Pressure (psia) 14,000


Reservoir Temperature (“F) 345
Reservoir De@ (tvd@) 15,000
CITHP (@t) 10,600
mm 325
WeIl Fluid Gas/condensate
H2S (pplllV) 18-33
C02 (mol %) 3.5 -5.5
Formation Water Cl (ppm) up to 160,000

Table 2- DrW@l%d uction String Load Criteria

LOAD CRITERIA BURST COLLAPSE TENSION

Drilling 1.20” @rig. Gas evacuatkmnot to exceed fracture Limited 10SSCS


while drilli~- Pmsslu’etest on bumping
Casings gradientat shoe. P@.
Fluid bd drops to baiancc a

2. Surftwccasing. Limited kick. formationpmssurc. Mud weight String weight plus


(16” /13 3/S”) behind casing string. 100,OOO lbs over pull.

3. Intwndi* casing. Full gas evacuationfrom pm pmssurc Dynamic siig%ndmg.


(12 1/s”/103/4”/10”) at 111 of next hok section.

Mud weight behind casing string as


backup (All strings)

Producdon 1. Tw&k S@@. Tubing kakatsurfacc acting on 11.3 BcIow PBR- pore pressureoutside Pressuretest on bmnping
Casings (9 Slrlrn 5/s”) ppg packerfluid. with mrnlmumbottom hole plug.
~. or
Dcgrdcd mud outside casing string as String weight plus
-. Above PBR- Mud weight outside. 100,OOO lbs over pull.
seawater inside drops to cqudkc
r IXWSWof depktcd mscrvoir. DylUmic sl&Mding.

Production 1. Tubing string. Maximum shotin tubing pmssum plus Kill weight fluid outside with Seals seh m PBR
Tubing (5”/4 In”) exass pmasurcrcquked to start minimum pressureinside stringdue preventingmovement of
bunhcad kill. to depleted leservoir. the string during well kill
opwations.
seawater 55 backup. a
String weight plus
Ioo,ooo lb? Ovcspldl.

Table 3- OCTG Grade Selection va Temperature and H# Exposure

Vertical Depth Minimum Drilling casing Production


(h) Temperature (deg F)
Caaing Liner Tubing

0-9.000 50 Cllo Cloo CRA

27,500 175 Q125 Q125 CRA

213,500 300 140 140 CRA CM

111
: manmter_

I‘-4
F’mnldirlg

Fig.1 -Ed&e Field Location Map. Fig2-JdKu@-ti=m Interface During Operations

F~S-Erskine Completion 95/6’/6’/7w


Flolh@&TiatlU_
String Schematic.

<— 41/2 Pmduuimlhar

2
, RMS-~ 11
SPE 30364 G.SELLI~. R.~BR~

s.

..

..

13 Cr/Sqrer13Cr(Q6m ““*. -%-&.:.....


9 -.
..
LowAlloyBte912 * .;
--- ●

28 Cr(Ni-Cr-Mo) ..
.. . . . . -..
*..
22/25 CrColdVWted
---- -..
●. .
=.O
“.s..
-..
- ..~.
.-.
..

8 10 u
0 2 4
C2xmAM8

Fig.5-WeUhead l%ewure Over Life of Field

113
SPE 30364
12 . HPHTDRILLINGAND COMPHON DESIGN FOR THE ERSIUNE _

9sm’’ls’’l75lr
-’PniddM— —
Thbadlstlm

ltr/132/rsurmco* ,
8t+/-ll,5aattvd

121 PJ’I102WIW
hltoMdMcsga+Flm*ti

YorlllhgLlnu-contm-Y*
Eddlmsaldwda.~
W~!3andw@18.
Fig.6-Generalised Lithology/Pore PressureMud
Weight Plot 41/2” Llnuto +/- 15,=itti

Fig.7-Generic Erskine Well Design

114

Potrebbero piacerti anche