Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
6.2 602 Cement Concrete Pavement
Construction of un‐reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub
base with 43 grade cement @ 400 kg per cum,
coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding
25 mm, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid
with a fixed form or slip form paver, spread,
compacted and finished in a continuous operation
including provision of contraction, expansion,
construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound,
finishing to lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 539.00 1078.00 L‐12
Mazdoor skilled day 15.000 539.00 8085.00 L‐15
Mazdoor day 35.000 493.00 17255.00 L‐13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 250.00 700.00 P&M‐031
Front end loader 1 cum bucket capacity hour 18.000 800.00 14400.00 P&M‐017
Cement concrete batch mix plant @ 175 cum hour 6.000 7500.00 45000.00 P&M‐067
per hour (effective output)
Electric generator 250 KVA hour 6.000 2000.00 12000.00 P&M‐081
Slip form paver with electronic sensor hour 6.000 2594.00 15564.00 P&M‐006
Water tanker6 KL capacity hour 36.000 600.00 21600.00 P&M‐060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 10.00 241500.00 Lead =10 km
& P&M‐058
d) Overhead charges @ 0.08 on (a+b+c) 497371.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 671451.91
Cost for 1050cum = a+b+c+d+e 7385970.98
Rate per cum = (a+b+c+d+e)/1050 7034.26
say 7034.00