Engineering Material Date: 26.06.

2020
S.No Description Used For Vendor PO Status Lead Time EDA
1 Spares for Sovereign KBF system - Sovereign Tech Engineering PO Sent Reached Factory
2 Ring Blower - Raico Engineers PO Sent Reached Factory
3 Festo Cylinder DNC 200PPV New Nickel Coating Machine Festo India PO Sent Reached Factory
4 Carbon Brush 48X40X32mm Electrical Maintenance Premier Carbon Industries PO Sent Reached Factory
5 SPA Groove Pulley New Nickel Coating Machine Dynamic Trading Waiting for PO approval 1 Week 03.07.2020
6 3 Ton Motorised Hoist Electrical Maintenance CAC India PO Sent 6 Weeks 20.07.2020
7 Ceramic Pulleys, Casptan Block etc., Spares for Tandem Line Machino Techniks PO Sent 4-6 Weeks 20.07.2020
8 PLC Material - K&N Automation PO Sent 12 Weeks 24.08.2020
9 Galvalume Sheet and Gutter Roof for Stores and Scrap Area Metco Roof PO Sent 1 Week 04.07.2020
Waiting for PO approval
10 SMC Valve - Hindustan Hydraulics 3 to 4 Weeks 24.07.2020
with PP sir
11 Humidity Controller QC Asian engineering PO Sent 2 Weeks 02.07.2020
12 Hioki IR Probe QC Elmack Engineering Services PO Sent 4 Weeks 12.07.2020
13 Hand Pallet Truck QC CTR Manufacturing PO Sent 3 Weeks 16.07.2020
14 Thermocouple K type Sensor QC Padmavathi Electricals Waiting for Quote 04.07.2020
15 Oven Spares. Heater & fuse QC SATA PO Sent 2 Weeks 10.07.2020