Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
We are thankful to our teacher Er. Dinesh Ghimire, Department of Electrical Engineering,
Institute of Engineering, Pulchowk Campus for helping in our visit about necessary
requirements and process for micro hydro design. Also we are very grateful to him for
giving us the opportunity to accomplish the task which has helped us to explore the
practical side, apart from the theoretical knowledge only. Thus, it broadens our mind and
we are able to deal with upcoming future design activities.
Our special thanks go to Mr. Anjan for assisting and guiding us during the visit. He has
assisted us in guiding us towards each and every step in computation of the distribution line
parameter. We would also like to thank all the operation committee members, operators and
local villagers who helped us by providing us the necessary information and replied to our
questions related to technical and socio-economic factors of the project.
We would also like to express our deep gratitude to our families and friends in creating an
environment to accomplish this report.
Group Members
Prakash Pandey 070BEL330
Rochak Silwal 070BEL334
Sagar Bhatta 070BEL335
Samar Bariya 070BEL336
Bimal Gyawali 070BEL349
OBJECTIVES
Following were the objectives of our visit:
To study and view the present civil, mechanical and electrical works of the visited
micro hydro project
To measure the head and discharge of the visited project and do required calculation
for micro hydro design based on our study
To study the socio-economic condition of the beneficiary group from the micro
hydro
To design a complete micro hydro scheme for the visited site after technical and
socio-economic study
METHODOLOGY
Technical Information
Civil
11 month exceedance flow : 67 l/s
Design discharge : 212 l/s
Gross head : 25 m
Power output : 26kw
Head race : stone soling with cement pointing (1.2km), pipe canal (114 m)
Mechanical
Turbine:
Type : Pelton
Gross head =27m
Discharge =22 l/s
Shaft power =26.73 kw
Coupling system: Direct coupling
Electrical
Generator:
Type=Synchronous
Voltage = 400v, 3 phase
Capacity=40 kva
Speed=1500 rpm
Governing mechanism: ELC with ballast load
Ballast capacity=22kw
3 phase
Special feature with over/under voltage trip circuit, current and frequency protections.
Water sealed ballast heater tank holding ballast heater
Transmission/distribution system: overhead
Aim of project:
Village electrification for lightning and development of small- scale industries
PRESENT STATUS OF PROJECT
Socio-Economic Condition
Ethnic groups:
There are 150 households, which are benefited from this MHP scheme. The total population
benefited by this project is about 900. Communities like Tamang, Chhetri and Damai/Kami
are residing in the project area. Tamang holds the majority of almost more than 95% but
other communities also are in same respect.
Economic condition
Economic condition of the village is not very sound. Illiteracy percentage is high. The main
source of income of the people is agriculture. Almost 90% household depends upon
agriculture. In average 4 persons per household are involved in agriculture. About 10%
household depend on labor works; in an average one man per household is involved.
Average land holdings per household in the project area are 14 ropanies. The major crops
grown are rice, maize, wheat, millet, oilseeds etc. besides potatoes, garlic, beans and orange
are major horticultural crops grown in the vicinity.
The main crops grown in the vicinity are rice, maize, wheat and vegetables. Implication of
irrigation has increased the land yield. The water output for irrigation purpose is designed to
be 12 l/s. with this large land has been irrigated under different cropping pattern.
Farmers growing cereal crops generally get their cereal products milled at an agro-processing
unit (Ghatta). Farmers engaged in vegetable growing sell their products to local main bazaar
Nau khande, Palung, Hetauda, Tistung and products go to Kathmandu also for which
middlemen plays significant role in determine price of the commoditized.
Villagers have already formed the users committee. Their organizational structure for this
project is shown as below:
Originally, the discharge measured was 150 l/s with salt dilution method. The minimum flow
has been determined and the 11 months exceedance flow is 67 l/s. the design discharge is 22
l/s and extra 12 l/s is designed for irrigation purpose.
The system has been designed with an overall efficiency of 50%, which is fairly in safe side
for the project with Pelton turbine.
The intake location is at Ghatte khola ward no. 3 has been fixed after supervision and
consultation with the villagers. As the 50% of the canal length passes through ward 3 the
locals has purposed to use the canal for irrigation in non-lighting hours. The semi-permanent
gabion wall with 1 m high is constructed for the maintenance of design flow with minimal
head loss during the low flow period. The site intake with rectangular orifice of 0.1m* 0.5 m
has been made. A coarse trash rack has also been proposed from flood risk for which, 15m
long and 4 m high gabion is made.
The gravel trap and other structures like desanding basin and spillway has been made. The
size of the gravel trap is 2m long and 0.5 m wide and 2.96 m of collection depth, which is
located close to intake. The spillway in the canal just after the gravel trap is with 3m wide.
Canal
Type = trapezoidal stone soling with cement pointing
Top width = 0.7m
Bottom width = 0.3m
Side slope = 1:1
Free board = 0.3m
Depth = 0.2m
Penstock pipe
Penstock pipe connects the forebay tank with the turbine. The penstock length of the project
is 221m.
HDPE pipe of OD 250 mm, 4-kg/cm3 [79 m]
MS pipe of ID 200 mm, 3.0-mm thick (33m)
MS pipe of ID 200 mm, 3.5-mm thick (109m)
Expansion joint
Expansion joints 5 nos. is used after every anchor blocks.
Anchor blocks
There is one horizontal bend and two vertical bends. For the support of MS penstock pipe
portion, 5 anchor blocks are used.
Support piers
36 numbers of support piers are used to support the MS pipe portion. Pipe clamp are used to
restraint the movement of penstock pipe in the later direction and tarpapers are used to reduce
the friction while it moves along its longitudinal axis in the temperature variation.
Turbine:
Type: pelton
Gross head =88m
Discharge =42 l/s
Shaft power =26.73 kw
Generator:
Type=synchronous
Voltage = 400v, 3 phase
Capacity=40 kva
Speed=1500 rpm
Coupling system: direct coupling
Governing mechanism:
ELC with ballast load
Ballast capacity=22kw
3 phase
Special feature with over/under voltage trip circuit, current and frequency protections. Water
sealed ballast heater tank holding ballast heater
This is a community based project. People do have deep concern to the project and are ready
to work for it. They have already formed 11 member users committee in the chairmanship of
Mr. Ram Bahadur Syangtang for the project. The anticipated level of community
participation in the MHP project is very high. The entrepreneurial sprit level was found fair.
The managerial, business skills of the community were found fair. The local people are no t
educated up to higher level but they have selected person for the operation of the plant. They
have send him for the training to acquire knowledge and operational skill for operation of the
plant. One plant manager and one operator has been selected for the operation of the plant.
Environmental Impact
In this project, there is no risk of flood exposure. The headrace alignments were in use since a
long time for irrigation purpose. So the negative environmental impact seems unlikely.
The nearest grid point is Nau khande, which is at a distance of 5 km from the project site.
There seems no possibility of extension of NEA grid line within next 5 years.
fund collection
S.N. Source RS
1 VDC 40000
2 District development committee 400000
3 drinking water/women committee 38450
4 local collection 1342500
5 Alternative energy promotion center(AEPC) 1344644
6 Labour cost 1268237
S.N. Expenditure RS
1 survey and technical expenditure 33000
2 administrative expenditure 125325
3 electrical equipment purchase 258713.5
4 organisation register 500
5 Transportation 9727
2725087.
6 machinery equipment 1
7 Miscellaneous 4733
1268237.
8 labour cost 7
9 bank मौज्दात (बैंक मौज्दात ) 5000
10 cash मौज्दात (नगद मौज्दात ) 8508
4438831.
Total 3
The technical details of the spare parts may vary depending upon the suppliers. It is
recommended to the suppliers to provide the spare part as required for their equipment. The
general list however has been provided here:
Turbine bearing
Turbine seals
Gaskets for pipe
Nuts and bolts
Grease (1 kg)
Bearing for the generator
Control fuses (HRC fuse)
Ballast load heater
OBSERVATIONS AND FINDINGS
DISCHARGE MEASSUREMENT
Area Velocity method
This Method is based on the principle that for a fluid of constant density flowing through a
cross-section, the product of cross-sectional area and mean velocity will be constant that is
the discharge.
Float Method:
Sn Dist travelled
(L)m Time sec Surface Velocity m/sec Mean Velocity m/sec
1 24 44.23 0.5426 0.35269
2 24 46.83 0.512 0.3328
3 24 44.7 0.537 0.349
4 24 42 0.571 0.371
5 24 46 0.522 0.339
6 24 42 0.571 0.371
7 24 42 0.571 0.371
8 24 39 0.615 0.399
9 24 38.7 0.62 0.403
10 24 41.63 0.576 0.374
V= 0.366 m/s
The velocity is to be measured using the float method. The surface velocity of a smooth
section of stream is to be determined along with its average area. Different Floats are allowed
to pass through the section of measured length of the stream and the time taken is measured.
Then the surface velocity is calculated. TO obtain the true velocity, the surface velocity is to
be multiplied by correlation factor depending on the nature of the stream.
= 0.366*0.0525
= 0.0192 m3/s
= 19.2l/s
The ‘Salt gulp’ or the salt dilution method of flow measurement has been proved easy to
accomplish, accurate (< 17%) and reliable in a wide range of stream types. Using this method
stream flow can be measured in less than 10 minutes and very little equipment is needed. The
main device is conductivity meter. The calculations following take a little longer if done
manually. Disadvantage of this method is the cost of the meter. The probe is immersed, close
to the bed of the stream (not near the surface) or ideally at mid-depth. A bucket of heavily
salted water should be thrown into the stream. The 'cloud' of salty water in the stream starts to
spread itself out while travelling downstream. At a certain point downstream it will have
filled the width of the stream. The cloud will have a leading part which is weak in salt, a
middle part which is strong in salt, and a lagging part which is weak. Salt conducts
electricity, so the saltiness of the water can be measured with an electrical conductivity meter.
If the stream is flowing slowly, and has a small volume of water passing the meter each
second, it will take a long time for the cloud to pass. Since not much water is present, it will
not dilute the salt very much, so the electrical conductivity (which is greater the saltier the
water) will be high. lt is apparent, then, that low flows are indicated by high conductivity
measured in the cloud, and long cloud passing times.
Observation Table
S.N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Tim 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
e
2 2 2 2 2 2 6 11 9 7 5 4 3 3 3 2 2 2
2 2 2 2 2 2 3 11 12 7 5 4 4 3 3 3 2 2
2 2 2 2 2 2 6 13 10 7 5 4 3 3 3 2 2 2
2 2 2 2 2 4 6 6 6 5 5 4 4 3 3 2 2 2
14
12
10
Conductivity
0
0 20 40 60 80 100 120
Time
Area Under the Curve.
So, Q= (m k-1)/A
Where
Q= Discharge in l/sec
Then Q= 18 l/sec
HEAD MEASUREMENT
Water-filled tube
This method of head measurement is useful for low head sites, since it is cheap and
reasonably accurate. A Height marker is required. A person can act as a reference height if
necessary or the graded rods can be used for better results. Two or three separate attempts
must be made, so that you can make sure that your final results are correct and reliable. ln
addition the results should be cross-checked against measurements made by another method.
Nylon hose, either transparent or with transparent ends can be used. A hose diameter of
between 4 and 10 mm is convenient.
Sighting Meters
Hand-held sighting meters (also known as Clinometers or Abney levels) can measure the
angle of inclination of a slope. They can be very accurate if used by an experienced person.
They are small and compact, and sometimes include range-finders which save the trouble of
measuring linear distance. Since the method demands that the linear distance along the slope
is recorded, it can have the advantage of measure of the length of penstock pipe as well.
Sample Calculation:
SELECTION OF TURBINE
Taking ,
The discharge =22l/s considering percentage exceedance Q92%.
Gross Head =180; So Net head = 162m considering 10% head loss.
Taking Turbine efficiency = 75%, other mechanical efficiency = 85%, generator
efficiency= 90%.
The nomogram is used in order to select the turbine best suited for our purpose.
Choosing a turbine shaft speed of 1500 rpm for direct drive between turbine and 5OHz 4-pole
generator.
Constrained in the boundary marked by shaft power of 26.73KW, net head 162m, and a
turbine speed of 1500 rpm and taking percentage exceedance of 92% , the best suited
turbine from the nomogram chart is single jetpelton turbine.
As Turbine Speed =1500 rpm, Generator speed = 1500 Rpm so, we do not require any
speed changing mechanism, So to avoid the losses imposed in other transmission
systems like belt drive, we choose the Direct Coupling mechanism with rubber glands
coupling.
Features of Direct coupling
Compact and simple
Efficiency approaches 100%.
No additional loads on bearings.
Both turbine and generator can be bolted to concrete foundation metal adjustable
packing with slides is required.
Alignment of shafts must be correct to in order to prevent failure of coupling or
bearings.
Flexible in-line coupling is needed because shaft alignment is never perfect.
No speed change option is available.
Selecting Electronic Load Controller (ELC) as it is best for micro hydros considering
synchronous generator used. We select Thyristor fired type ELC.
Then
SELECTION OF GENERATOR
Two types of ac generator are suitable for use in a micro-hydro powers. These are
synchronous generators (or alternators) and induction generators.
Induction generators uses induction motor as a generator but are used in small micro-hydro
schemes(<10KW) ranges. They are they are easily and cheaply available as motors, simply
constructed and repaired, reliable, require little maintenance and also can withstand 100%
overspeed.
Induction generators are easily used as generators when connected to an existing supply
system (grid) and when used in a stand-alone application such as an isolated micro-hydro
scheme they require fitting with excitation capacitors. They require a voltage plus speed
governing system known as Induction Generator Controller.
Unlike Induction Generators, the synchronous generators are used in larger systems. They
have separate excitation system. The excitation generator is supplied by the excitation system
(Generally an AVR) and the output of the generator is given to the main generator field using
the rotating diode to convert it to DC. Though higher efficiency, better voltage and frequency
regulation ability as well as synchronization capabilities, it has more maintenance
requirements.
Generator sizing:
Considering the better lifetime and performance characteristics and allowance for tansmission
losses, as well as considering reactive power consumption use with ELC it should be
overrated 60%
Excitation System
In a synchronous generator, the main field winding should be provided with current in order
to generate the required magnetic field. The output voltage of the generator can regulated by
varying the field current. For this purpose we require a proper excitation system. The
Brushless excitation system is selected for our purpose. In this type of excitation system, we
have a small synchronous generator attached to the main generator. The excitation generator
has its field winding as its stator. The field is supplied by regulated DC power supply by an
AVR which senses the Generator terminal output voltage. The Main field is supplied through
rotating diodes which is mount to generator shaft supplied by the rotor winding of the excitor
generator. This avoids the requirement of any carbon brushes commutator/ sliprings .
We take Brushless excitation with an AVR. The mounting of the AVR is done in a separate
panel to avoid the possible moisture and vibrations.
COST ESTIMATION
Estimated Cost Categorisation:
Sn Particulars Amount
1 Expexted Subsidy from Govt. 1440000
2 Loan Form Bank 1500000
3 Labour Contribution by locals 900000
4 Investment from Locals 693785
Total Investment 45,33,78
5
TARRIF DESIGN
Load Distributions:
Considering the following loads will probably incurr to the plant throughout the year:
=443.52 KWHr
270
EnergyConsumed ∗11
Plant Factor = = 443 = 0.553
EnergyGenerated
12
1500000
This amount must be considered to be returned in payback period of 6 yrs with Rate of return
of 10%
i∗(1+i)n 1500000∗0.1∗(1+0.1)6
So Annual Cost should be A =P¿ =
(1+i)n −1 (1+0.1)6−1
=Rs 3,44,411/-
Now