Sei sulla pagina 1di 11

How Not to Run a Project: Debacle at Wakka

1 x 67 MW HEP
Sunil Kumar 1, Krishna Moorthy 2, Ananthmula Vittal 2
1
Faculty, 2Dean,
L & T Institute of Project management, Vadodara, India.

Abstract—Power is one of the important areas for life style across the country. It is impossible to dream
development of human kind in modern world but various of living in absence of electricity in modern times. Can
developing countries are facing acute shortage of power find area in our life where electrical power is not touching
for base as well as peak load. India one of the contender us. Be it household or professional level for all type of
for emerging modern economy and on path of self sufficiency,
individual or organization.
is no exception. Till 1990, Indian economy was closed
one and nearly all of the infrastructural area were in Power is an essential requirement for all facets of our
direct control of government or its allied body for life and has been recognized as a basic human need. It
development. But after economic liberalization in 1990, is the critical infrastructure on which the socio-economic
scenario has changed and power sector has become suddenly development of the country depends. The growth of the
lucrative for independent power producer. This has further economy and its global competitiveness hinges on the
opened up avenue for power plant manufacturer and
availability of reliable and quality power at competitive
consultant worldwide and they would like to use vast
talent pool of Indian engineer and cheap labor and local
rates. The demand for power in India is enormous and
material for setting up their Indian operation. But is growing steadily. The vast Indian power market, today
what appears to be easy in a first glance is not true offers one of the highest growth opportunities for private
when it comes to operational level, due to various issue developers. Unlike yester years, power project cycle time
related to project and construction management of has reduced continuously due to tremendous effort by major
large size infrastructural project. It ranges from availability player in the construction field.
of qualified staff at reasonable rate, labor productivity,
India is endowed with a wealth of rich natural resources
business practices and type of ownership, commitment
of customer obligation, resource management, vendor and sources of energy. Resources for power generation
development, logistics problem, area specific issue etc are unevenly dispersed across the country. This can be
which must be taken care of, or else project is destined appropriately and optimally utilized for reliable supply
to be ruined. These entire factors are related to each of electricity to each and every household. Electricity is
other in many ways and leads to failure of the project. considered key driver for the targeted economic growth
The case, written on basis of generalized experience in of India.
hydro sector during last 10-15 years , try to capture
With liberalization starting circa 1991, license era like
ground reality for getting the work done by owner in
field of hydro power project and various issues related investment, industrial and import licensing was done away
to execution of remotely located construction project in with and ended monopoly of some firm came to end,
India has been considered. It may appears that nothing allowing automatic approval of foreign direct investment
in the case has gone in right way but that is how many in many sectors. Power sector which had been funded
of project get done or executed or sometime abandoned mainly through budgetary support and external borrowings
after some preliminary work. Normally we focus on was thrown open to private sector in 1991 giving
successful parameter in any project but even if we are opportunity to various private organizations. Various factors
able to capture what went wrong, it can be eye opener
has been considered as responsible for success of the
for construction project professional operating in India
project, however there is no generalization on the
and will ultimately lead to success of the project by
avoiding all pitfalls. agreement. The aim of this study is to examine factors
that lead to failure of project in hydroelectric sector in
Keywords—Hydroelectric Project, Site Management,
Construction Project, Site Finance, Project Execution. India in the emerging globalized economic scenario.

II. L ITERATURE R EVIEW


I. I NTRODUCTION

A. Power Scenario and Emerging Hydroelectric Construction project mainly cover Planning, Cost
Management, Time Management, Quality Management,
Construction Project
Contract Administration, Safety Management,, it also
The invention of electricity has been one of the wonder includes construction manager practices of defining the
for human kind and more so when we consider the present responsibilities and management structure of the project
management team, organizing and leading by implementing of various area earlier reserved for government firm, advent
project controls, defining roles and responsibilities and of new technology, allowing global competition where
developing communication protocols, and identifying as infrastructure, competitive level of contractor remain
elements of project design and construction likely to give poor or lacking fresh ideas of tackling problem. Purpose
rise to disputes and claims. Due to problem in any of these, of writing this paper is to study and share experience we
project will start deviating from its path and in most of had in hydro electric construction project in the recent
the cases seeds are shown in early stage of the project. time which is also reflecting real work scenario not only
If project has to be completed in true essence of contract, hydro but other infrastructure project as well. It gives
it has to be in control right from beginning. number of input for MNC for better understanding of Indian
K. C. Iyer and K. N. Jha (2006) have identified some situation in project field for better understanding of ground
55 attributes responsible for impacting schedule reality.
performance for Indian construction project. After
preparing initial list of attributes, they were assessed for III. C ASE S TUDY
impact on schedule of project in way of success or failure
or no impact attributes. These factors then analyzed for A. Damyanti Logistics Limited
their property through Statistical package and it was found Damyanti logistics limited (DLL) is a pioneer and leader
that out of 55 attribute, only six factors collectively explain in the door-to-door express distribution and supply chain
80 % of the deviation i.e. Project manager competence, solutions in India. It was the revolutionary approach
supportive owner, proper monitoring and control, favorable adopted by the company that helped launch many path-
work condition, commitment of participant and owner breaking initiatives in the logistics segment and many were
competence. the firsts for the Indian market starting with handful of
Chang, Lung, Ogunlana, Khalid (1991) have given person with dingy single room office in small town of
system dynamics approach to construction project. Kerala. In a span of 40 years, DLL has consistently explored
According to them from inception to completion, ways to bring premium value to the customer, by setting
construction management involve numerous processes, benchmarks in quality of service and customer satisfaction.
parties and variable which interact and affect each other Having started as a cargo management company in
in varying degrees to determine the time, cost, standard 1969, DLL has grown into an organization with more than
of end product and the realization of project objective. 9500 employees and a turnover of Rs 576 crores (approx.
Some of the main ingredient for successful implementation 94 million euro) covering 603 out of 611 districts in India.
of construction project are outlined by Wang (1987) as The fleet consists of over 10000 vehicles on road, fleet
sufficient and timely supply of qualified and experience of refrigerated trucks, container vessels and world class
technical personnel, material required and tools and mechantronic warehousing facilities across India. Be it
equipment. They also inferred that higher schedule pressure flexible point-to-point distribution solutions or complex
on project wosen the system behavior and increase the end-to-end integrated logistics solutions or supply chain
project completion date although it increases the working management, Damyanti Logistics does it effectively and
intensity. It also generates more accidents as well as reduces reliably, and enjoys the trust of its customer base.
quality of work.
Considering liberalization in power sector and
Florence Yean Yng Ling and Thi Thuy Dung Bui(2010) recognizing business potential from the shortfall of 7
have examined the major factors that affect project to 10 % in base load and 10 to 20 % during peak load.
performance in Vietnam , defining with project success The managing director of DLL, Mr. Dagar, after vetting
as completion on time and on budget, and to an acceptable this business potential by various state agencies, called
quality standard. for board meeting. Outlining the company's diversification
One of the finding show that involvement of foreign strategy, Mr. Dagar announced Damyanti Logistics foray
experts is critical to project and has proven to be positive. into power business. One of the long term director differed.
Local construction firms may consider working with expat He had witnessed failure in one of earlier venture ie. foundry
as learning opportunities to transfer technology and business for steel product when steel market was booming.
management skills which is suitable for their country. Due to unfamiliarity to this sector and sudden fall in steel
Whereas foreign firm also need to learn some aspect mainly price in indian market, the venture was abandoned. So
managing cross cultural encounters before entering new he had his reservations for this new venture but then
country in order to use their competitive advantage. Mr. Dagar was a tough man. The director was asked to
There are few studies which has been carried out in quit. DLL was launched to take care of opportunity in
public for post mortem of successful or failed project in hydro power where the government was offering tax
India particularly for newly completed project where project holiday along with other subsidies.
are subjected to new emerging issues such as opening After brain storming session of top executive of DLL
entered into an agreement with North Eastern State Power experience of its team of highly qualified professionals
Development Authority. DLI and NSPDA agreed to work operating around the world.
together on three hydroelectric power projects on Like other consultancy firm setting up offices in India,
Build,Operate,Own and Transfer (BOOT) basis. TCB opened a representative office in Delhi, to provide
1. 67MW at Wakka HEP(Hydroelectric Power a complete range of services to government and private
Project) across rivers Tirap and Bogapani,near clients in the rapidly developing hydropower sector. In
Wakka village, Arunachal Pradesh. 2003 TCB were contracted by a number of private clients
2. 51MW Chasmey HEPP across rivers Anizula, for small, medium and large hydropower projects across
Himachal Pradesh. the country.
TCB Tech AG was taken as consultant by Damyanti
3. 71MW Lilong HEPP across rivers Diaglong
Logistics Infrastructure, however in order to keep their
in Manipur.
cost on lower side only services of civil design were taken
The owner of DLL belonged to conservative family. from TCB leaving elctro mechanical and hydro mechanical
For their miserly attitude and lack of experience they took package with original equipment manufacturer for design,
very small piece of land for power project which would supply, erection and commissioning of the units.
be insufficient during machine installation and
commissioning of the project. Contract for main machine D. Walk Through Project Wakka
along with balance of plant was given to a MNC Malco (i) Kick off meeting between MALCO and Damyanti
who began their Indian operation recently. Logistics Ltd.: Two month after signing of the
contract, kick off meeting was held with customer
B. The Madras Aluminium Company Ltd. (MALCO) in urgency at the behest of customer since banker
MALCO is a global supplier of turnkey to the project were going to review project status
electromechanical equipment and services for power plants before they clear next phase finance and DLL
headquarter at Vienna, Austria, with a leading position were in hurry to get that by showing site mobilization
in the growing market of plant refurbishment. MALCO for electro mechanical work in order to make
has supplied more than 25% of the world's installed power project visible to the inspection team. MALCO
generation capacity. They have set the benchmark for were not prepared enough for the meeting as
innovative, environmentally friendly technologies in the they were still in search for project director and
world of power. Their engineers built the largest power site manager. Though they could manage some
houses worldwide. They provided turnkey integrated power key personnel from headquarter Vienna to attend
plant solutions and associated services for a wide variety the meeting but were caught off the guard when
of energy sources, including hydro, gas and coal. However asked about their requirement from owner and
their earlier Indian operation experience was limited to payment break up finalization. In the meeting customer
setting up few thermal power projects and one hydro power team could make them agree to mobilize site in
by their overseas division taking one consortium partner next 15 days in order to show something to visiting
who typically happened to be Indian company to take team.
care of price advantage in India. In 2002 they opened (ii) Contractual Price break up : while signing
Indian subsidiary with eye on future hydro business and contract, price break up was not finalized but it
on the premise that cheap labor and engineering talent was agreed that it'll be submitted in kick off meeting
is available here. However they were having own problem which could not be done in hastily done meeting.
in terms of quality of manpower for their office being After six month of contract signing, first revision
set up in India and finally ended up in recruiting somehow of the price break up was submitted for approval
the targeted number following pressure from top executive but was turned down due to no relation between
in Vienna. The main equipment required for the hydro activity defined in the contract and milestone
machines were manufactured by MALCO at their works considered for payment. Moreover, project director
in Nasik, which was originally a loss making auto parts wanted to gain as much in the initial phase of the
workshop. As per agreed terms MALCO had to take about contract to improve cash flow and accordingly
100 number of existing worker and supervisor and 200 price break up was made front loaded which was
were added later on after getting some second hand large not acceptable to customer who in turn suggested
machinery from their European factory. new price break up which was back loaded with
C. TCB Tech AG more than 20 % of billable amount against
It is a leading European engineering company with commissioning and performance guarantees.
an extensive service portfolio in energy and environmental Finalization of price break up took six more months
technology. Irrespective of size of the project, customers and till that time, MALCO were paid only ad-hoc
benefitted from the in-depth know-how and broad sum to carry on the operation.
(iii) Planning: Total duration agreed upon for one location spread over 30 kilometer, for the given
unit power house of 67 MW was 42 month from requirement of 10000 sqmtrs. One of the location,
zero date which was six month less compared despite the fact that it was near to power house,
MALCO own standard time for comparable size. was actually filled up soil of the muck and debris
But MALCO took this as challenge in order to dug out of the power house. Other three places
book some job in India and start work. MALCO were not having road connection, heavy equipment
while making master plan , considered very less which started to come in were diverted to this
time for site work and kept more time with engineering, location only to experience truck getting trapped
procurement and manufacturing considering all in muck or component getting sank in the filled
area were new and mainly due to no representation up land, requiring additional resources to handle
in the proposal or planning team from site. In all these emerging issue.
good faith, customer asked MALCO to consider (v) Site Manpower Planning: MALCO being new
duration for civil activity as well in the Master to India had to fill most of the vacancy fast in
Time Schedule(MTS) but all civil activities were order to allocate right professionals in various
given unrealistically low time and were happy to department and project site. As a site head, they
see that MTS has been agreed upon by customer. recruited a person with 35 years of experience in
There was some problem from customer side in telecom department who had retired as regional
deciding the dam level of the project. By the time operation head from government sector and was
dam level was finalized, design of underwater recommended by one of the Indian director for
parts were over by MALCO , so they asked Damyanti having good liaison skills. With due to non availability
Logistics to increase the contract price due to this of large number of qualified personnel opting for
delay, in order to incorporate the changes which construction site works and in order to keep the
was having direct impact on under water part cost to minimum, MALCO hr planned to recruit
steel thickness. Customer took one month to decide person from organization who were serving as
and finally agreed to increase package lump sum sub contractor to MALCO competitors in India.
price by 10 % of the original but got MALCO Hr arranged for their training in Austria and China
agreed to complete the construction as agreed. for various traits but were not very effective. During
Comparison of earlier experience and present MTS the execution though expatriate were not planned
is a given in the annex. for erection and commissioning of Indian project
(iv) Site Material Management: Material management but MALCO had to arrange expat at repeated
at site for electro mechanical work which includes request of customer, since local employee were
turbine, generator, transformer and other balance unable to give quality output. They had to face
of plant was in scope of MALCO. They had to internal problem in getting expatriates from home
build closed and open store on land which was to country while requesting in eleventh hour, since
be provided by customer but no clarity was there many project were under execution in china and
regarding size, development stage and numbers Africa.
of store to be provided. As per dispatch schedule, (vii) Design and Engineering: The basic engineering
material consignment for turbine foundation parts of the power plant equipment was done by MALCO
and other embeddement started to reach site , but team at Vienna but the detail engineering was
the site store was not ready. It was not very clear being carried out by Indian team, where the lead
to site person who joined MALCO recently , what expert from Austria was available. Vienna team
to do with number of lorry carrying various machinery were there for support up to estimated working
getting aligned along the state road, sometime hours but beyond that Indian team had to pay
blocking it. Site was not mobilized fully by that heavy charges for additional support /clarification.
time and even had no crane to unload the material Design team had average age of 27, mostly new
which had started to come. Some of the lorry recruited from campus interview assigned work
driver simple pushed off the package along the after three months training at Vienna, found it
road and fled since no one was listening to them difficult to manage the show. No. of rework use
for unloading .in hurry, some local shed in the to come up after comment from customer and in
nearby area was searched and initial material were some of the cases 9-10th revision of drawing could
placed in old food storage shed which was in be seen, each revision going through arduous cycle
dilapidated condition in village pedong 22 km of approval by customer, some of the revision
from site on semi motorable road. The matter was were very basic in nature. This had effect on all
taken up with customer for storage space who downstream activity i.e. Procurement, Manufacturing
ultimately obliged MALCO with four different and Construction. Most of the designer were new
with few or without practical experience and were up in having large number of supplier spread from
facing problem of actual implementation which all over India, many of them doing these job type
required design tolerances. Day to day fight between for first time.
manufacturing supervisors with designer could
For generator punching, new vendor was developed
be noticed with manufacturing employees, bringing
by providing process know how but they took competitors
the case where tolerance asked for parts were
order due to no order from MALCO for one year after
beyond machine capability. In case of steel plate
they set up their plant and when MALCO required the
were made with reference from European
relevant product, they were asked to wait for further six
manufacturing standard with high tolerance and
month which ultimately delayed assembly of generator
process for manufacturing, whereas the same process
at site.
was not possible with steel plate available from
Indian market. Designers were having many issue One of the vendor who was asked to rework for third
with project managers, who used to impose their time, refused to do so, asking for extra price since every
interpretation of contract clause even on technical time during the fabrication he was getting verbal instruction
area to save on cost without fully capturing the from different person in MALCO for some change and
situation and fall out of their decision which used it lead to total confusion resulting in component getting
to be short sighted. This was evident from the fact rejected finally. The project manager was finding it difficult
that on number of occasion customer. DLL rejected to deal with these supplier who were going their own way.
their design concept and asked MALCO to strictly In case of turbine spiral, a critical turbine component
follow the contract specification by words and where pre assembly check of part component is must,
most natural interpretation of the contract. it was decided to give the work to 6 different vendor spread
(viii) Sub Contracting: Construction phase is normally over india and so pre assembly of the final spiral as required
towards the end phase of execution. When construction in quality plan was not possible resulting in asking waiver
sub contract was getting finalized, project had a of pre assembly from customer , which was granted after
hit of 2% of the contract value in one of the long persuasion and with other condition.
electrical package and so a whip came from project Most of the supplier were not happy with payment
sponsor on contract division to cut cost by at least terms of MALCO which was normally 60 days after
10-20 % on sub contractor rate for construction, dispatch and acceptance of the component. It was
in order to stop margin slippage. The contract manageable for small component but major equipment
manager who had already taken budgetary offer with processing time of 2 to 3 months were having tough
during proposal stage from the entire three good time, which worsen by delay in material or drawing or
vendors for this work, one year ago was finding decision input from MALCO.
it difficult to bring the rate down considering the In case of turbine blade profile machining , it was found
steep hike in prices of cement, steel and other after casting of the blade, that the vendor is still planning
construction consumable. None of the sub contractor to procure the machine required for next operation and
was ready to bring the price down without pruning is not currently having them though he produced some
the scope. On recommendation of one of the director, supplier document at the time of evaluation.
contract manager had to finalize new vendor which
For silt monitoring device, order was placed to USA
was second grade sub contractor involved in small
firm, but on arrival of material found that device would
work under one of these contractor, thereby saving
not work in Indian operating condition, particularly with
15 % for the project team. The said contractor
respect to power supply, environmental condition and work
was having advantage of being customer's contractor
environment. Indian engineering standard had not been
for some other package directly and was already
taken into consideration in the specification of the machine
present at site for that work package.
due to which device could not be terminated at control
(ix) Procurement and Vendor Management: As room, as desired.
MALCO were new to India, it was no established (x) Logistics: Wakka project location itself was
vendor base , and were in process of developing sufficient to through open challenge to logistic manager.
and evaluating vendor and supplier. In the year Situated in the deep forest of Arunachal Pradesh around
2005-06, there was period of economic boom in 40 km off the highway from Bomdilla, the nearest town,
india. So, order book of most of the supplier in connected with semi motorable road with nos. Of rivulet
this line of business were full, no one was ready and land slide zone on the way. Rain was most common
to listen to customers with different requirement season in the area with almost eight month in a year
than the usual one, mainly where new processes witnessing light to heavy rain with cloud burst and flash
were required to be added. It was tough for procurement flood followed by land slide in this mid Himalayan zone.
manger in finalizing various contracts and so ended
The material for project which was to be transported Q Most of the cases, protocol sheets are either
from all over India with oversized cargo, perishable items, being developed or non existing, so difficult
fragile component, and various other types of hard-to- to capture the right dimension and keep them
handle shipments. It had to be planed to transport most in control resulting in problem getting identified
material during non rainy season but going by other aspect at later stage during construction rather than
of project this was becoming difficult to manage resulting inspection .
in major dispatch during financial year closing time which Q Many time there used to be fight between
used to reach site by April - May and during this period
quality supervisor and manufacturing guys
all major consignment moving from Bhalukpong, the
over some tolerance issue and designer getting
foothill town had to be accompanied by one 50 ton mobile
involved in all cases.
crane to position the trailer and to avoid road blockade
on the high way. Q There were instances, where quality supervisor
had objection on product quality from supplier
Route survey and trial run for transportation was done
and no major problem were highlighted in report but one but ultimately these item were dispatched to
of the consignment could not cross bridge due to low height project site without any rectification, making
of the bridge and its critical component had to be the site job miserable.
dismantled from main assembly in order to pass through Q Internal study of the manufacturing revealed
bridge. Transporter were more interested in putting large that in many cases cost of poor quality was
lot on big trailer rather than small trucks which was easier not getting captured properly which could
to maneuver in hilly terrain. throw light on present status of the manufacturing
It was common for transporter to club many but the same could not be managed at site
consignment load and transship it as per their convenience where sub contractor, the other party, were
creating confusion at site in not receiving half of the involved in construction work and in almost
component from same consignment or mixing up material every component, there were issue related
in various boxes. While investigating problem by site with supplier quality.
personnel it came as surprise that all truck moving to this Q New web based ncr system was developed
project in Arunachal had to change truck at Guwahati in which was quite robust and part of their global
Assam the other state, as per local practices which was system but it was hardly been followed in
never considered before. This necessitate to open one store Nasik factory. No root cause analysis was
yard in Guwahati and to arrange additional material getting done in real sense. At the same time
handling equipment. internal 5s and other quality audit reflected
Re handling always created problem since most of the everything in correct order and so top
item were simply stuffed into lorry without considering management were under impression that all
its importance or noting fragile or any other sign on the is well, only to get surprises in the last moment
container. It resulted in cracking of the 400 kv switchgear from end user and customer.
insulator which were imported from Japan. (xii) Site Construction: Right from beginning Wakka
(xi) Quality: the issue of quality in construction has project had many ups and down regarding opening
gained more momentum recently as customer are adding of the project site for electro mechanical work
quality along with pricing and schedule adherence. It is package, which was under MALCO. Customer
very important for contractors also to look quality not were pressing hard to open MALCO site office
only for enhancing their reputation in the market but to even when civil contractor were just mobilizing
control cost as well. MALCO is certified in ISO and site. Ultimately one of the erection sub contractor
OHSAS but these certificate are not more than decorative who was also present for other package of wakak
medal organization are interested to show to other rather project was selected so that he could mobilize site
than for real work oriented quality they should have. Quality in no time and one construction manager was
starts with quality design and when designer themselves posted as site head from MALCO side.
are struggling for sound design practices, its difficult to Sub contractor who had other package also, was
control product quality output. Some of the quality issue smart enough to show mobilization for MALCO
faced by MALCO may be better understood by following but many time it was observed that during actual
illustration. work requirement those very worker were involved
Q Even after arrival of customer inspection, in other package work.
materials were not ready in shop leading to Even the mobilized tools and plants which sub
customer dissatisfaction. Many time consultant contractor was counting was actually serving both
inspector had to return or wait for week before package and so facing problem when required.
actual inspection.
Customer had called MALCO to start the job but On many occasion work by storage sub contractor
they had problem in giving civil front to them, and erection sub contractor was stopped for
which got delayed due to late mobilization of nonpayment of their running bill due to payment
power house excavation contractor. pending from customer. It was difficult for small
The first milestone which was for starting EOT and petty contractor to continue at site even for
crane used for material handling in turbine building one month without payment. Slowly they were
got delayed and MALCO were asked to do equipment loosing whatever good skilled workmen they had
erection by some alternate method. MALCO agreed with them .
to arrange for high capacity ,mobile crane as alternative Some of the extra claim of sub contractor duly
in generosity but while crossing the bridge before signed by site manager were pending for 4-5 months
power house, the heavy mobile crane got overturned. with headquarter due to absence of similar claim
Putting the mobile crane in order became another from customer.
project for MALCO site team for 10 days, diverting (xiv) Issues during execution: When site work
major resources for this urgent work. started, MALCO began to have problem. As per
They could start the foundation parts and could MALCO-Damyanti Logistics contract any drilling
concrete upto 35 % level but “EOT steel column” required for fixing MALCO supplied item was in
required for its movement in unit way were not their scope . For fixing earth mat electrode to be
ready which stopped further electromechanical fixed were steel of 32 mm diameter 4 meter long.
work. As per industry practice, these hole were usually
Many time site construction manager of MALCO part of civil contractor. Sub contractor of MALCO
was in loggerhead with customer site manager on had no means to drill 4 meter hole in hard rock.
issue of client obligation like availability of front, This took month to resolve and finally civil contractor
arrangement of more storage area due to delay in agreed to do at extra cost to MALCO.
erection but material were getting dispatched as All system pipe required for project were to be
per original schedule. dispatched in prefabricated condition, to the extent
Finally, machine and its auxiliaries were ready possible in order to save time and space at site.
for wet commissioning 13 months after initial As per standard practice of MALCO, their project
agreed schedule but then there was surprise from director dispatched raw pipe and fittings to site
customer that the one of the two tunnel of head which got rejected by customer quoting contractual
race was having acute geological problem and clause and initial 3 consignment were returned
have been advised by government agencies to put back. This was taken up with top management fo
it under observation for eight month. customer who finally agreed after two month on
condition of getting the pre fabrication done at
(xiii) Site Finance: MALCO was primarily separate workshop in nearby location.
manufacturing company and in their indian operation
also, none of the finance managers they appointed, (xv) Monitoring and control: At each monthly
had any experienceof project and site work progress meeting which was attended by project
environment , which unlike typical manufacturing team and functional head, the latest issue and
set up, require lot of flexibility in terms of their solution were discussed . It soon became
understanding various site requirement, payment clear that the rate of progress demanded by the
to suppliers and contractors, bond and related contract was not achievable. MALCO , however
issue. Site finance also require on the spot decision attributed the delay to uncertainty perceived at
many a time. his end about the project due to owner's not finalizing
the dam height and due to delay in providing
The cost controller of Wakka, a new recruit from various fronts as planned but customer kept raising
neighboring chemical factory in nasik was least issue of poor mobilization of site team, incompetent
interested in the progress of the project but more site head, non sequential material supply along
to procedure and process he had prepared to be with poor quality of the material received at site
followed by fellow team members at site. Many which was taking major portion of the time of site
of these procedure were marred with practical team.
difficulties for site operation and were mainly
good as very tight finance control measure. If site (xvi) Present Status: what started in the beginning
team had to procure any item above rs 2000, they of the project in big way and work pressure from
had to collect at least three quotation where as in client for making the power house on fast track,
poorly developed nearby market, it was difficult crashing various activity and contract time incurring
to get even one party for quotation. huge financial losses , is not having any conclusive
end. MALCO could build power house upto [5] K. C. Iyer, and K. N. Jha, “Factor affecting cost
mechanical completion bt then were asked to put performance: Evidence from Indian construction
it under preservation till clarification from government projects,” Int. J project manage., vol. 23,
body. MALCO project manager is working out to pp. 283-295, 2005.
put extra claim, customer putting them on hold [6] K. C. Iyer and K. N. Jha, “Critical Factors Affecting
and meanwhile one of the government body set Schedule Performance: Evidence from Indian
up to analyze effect of building dam on local Construction Projects,” J. Construction Eng. Manage.
environment have advised project authority to put vol. 132, no. 8, 2006.
hold on all project lying in particular stretch of [7] K. N. Jha & K. Iyer, “Critical Factors Affecting
the Himalayan zone where this project Wakka is Quality Performance in Construction Projects,”
situated. J. Total Quality Manage.& Business Excellence,
vol. 14, no. 9, pp. 1155-1170, 2006.
R EFERENCES [8] K.N. Jha and K.C. Iyer, “Critical determinants
of project coordination,” Int. J. Project Manage.,
[1] Arunabha, Sen & Parekh, “Challenges in award
vol. 24, no. 4, pp. 314-322, May 2008.
and execution of EPCI Projects in India - Contractor's
Perspective,” Conf. World meet of The Process [9] Krishan K. Chitkara, Construction Project
Industry in India, Org. Chemtech Foundation, Management: Planning, Scheduling and Control,
Mumbai, Feb. 23-26, 2011. 2009, 18 th reprint, Tata McGraw-Hill Publishing
Company Ltd. New Delhi, India.
[2] Brian Cooke , Peter Williams, Construction Planning,
Programming and Control, 2009, 3 rd ed., John [10] Lauri, Koskela, Application of the New Production
Wiley & Sons. Philosophy to Construction, CIFE Technical Paper
Report 72, 1992, Stanford University.
[3] Florence Yean Yng Ling & Thi Thuy Dung Bui,
“Factors Affecting Construction Project Outcomes: [11] R. V. Shahi, “Hydroelectric projects development:
Case Study of Vietnam,” J. Prof. Issues Eng. challenges and response,” ICOLD Conference
Educ. Pract., vol. 136, no. 3, 2010. Montreal, Canada, June 20, 2003. Available:
www.powermin.nic.in/whats_new/pdf/icold.doc
[4] Frederick E. Gould & Nancy E. Joyce, Construction
Project Management, 2008, 3rd ed., Prentice [12] W. D. McGeorge, Angela Palmer & Kerry London,
Hall. Construction Management: New Directions, 2002,
John Wiley & Sons.
TABLE II
50-70 MW FRANSCIS T URBINE MALCO S TANDARD S CHEDULE: I MPORTANT A CTIVITY DETAIL
Fig. 1. Project Details
Fig. 2. Schedule for Damyanti Logistics Wakka 1 x 67 MW

Potrebbero piacerti anche