Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Application issues
Operational Issues.
1. The proposed procedure mentioned that RE applicant may offer their surplus electricity
export for sale to the SEC network. Our SCADA system shall be able to remotely access
facilities throughout the Kingdom, and where we could access alarms and event
conditions, data collection and reporting capabilities. For example in case where there is
too much wind production in a day where the demand is at low point, we could do some
curtailments and RE Applicant shall be aware of such capability of our Control System.
2. In case of wind integration to power grids, our SCADA system shall be a turbine supplier neutral.
In the future where many RE Applicant will install wind turbine of different type and of various
PLCs, our SCADA system shall not be dedicated to any one PLC vendor so that we could be free
to provide data reporting format and analysis report irrespective of turbine type.
3. Is it possible for the Grid Impact Studies (GIS) to cover Operating Issues in integrating a
percentage of RE generation in the power system? Operating Issues such as ramping
requirements, load following capacity, regulation capacity, over-generation issues and potential
solutions shall be considered to be studied in relation to the target percentage of renewables in
the power system. Some integration studies concluded that 20% of renewables in the power
systems is expected to increase regulation ramping requirements by plus/minus 15 to 25
MW/min, morning ramp and regulation capacity requirements also increased, and among
others.
4. If the GIS cold not include the above studies on Operating Issues, Does the Network Planning of
the NGSA could do studies on transmission and operational impacts of interconnecting
a percentage of renewables in the power grid. Such study will be helpful to ISO.
Reference Draft Procedure Comments Explanation
page
Page 5 Step 1. Submission 1. The process of The guarantee or deposit
of Application by application of an RE will serve as a bond to these
self RE Power applicant may RE applicant that they will
Producer consider to include and are committed to
guarantee or deposits undertake such projects.
for projects/sites that This will avoid many RE
an RE applicant applicant just submitting
applying. application for purpose of
securing a site then later on
they will not pursue the
project due to problems
with financial closure.