DAY NIGHT ACTIVITY& PERFORMANCE REPORT

FULA CPF, MOGA, FNE, JAKE, KEYI, HADIDA& Sufyan EPF


Date: Jul,15,2020
Report Number: 15072020
Report Prepared By: Hassan Abdo Khalil
Report Approved by: Almaki Hammed

1.0 CPF
1. 1Site personnel:-

Name Company Position


Dayshift Personnel
Luai Gamar Eldeen PE CPF Operation Supervisor
Elnoor Mohamed PE Operation coordinator
Almaki Hammed PE CPF Foreman
Bashir Abdalla PE CPF S Operator
Hassan Abdo Khalil PE CPF CR Operator
Hassan M.Almojtaba PE CPF CR Operator
Siddig Abdelrhman PE CPF Operator
Nightshift Personnel
Amir Hammad PE CPF Foreman
Yassir Ahmed PE CPF S Operator
Osman Adil PE CPF CR Operator
Mohamed Elshami PE CPF CR Operator
Anwar Mohamed PE CPF Operator

Ongoing Operations and Evaluation:


CPF: Daily Activities:
1. Patrol check for all production facilities has been done, monitor & record the parameters.
2. Provide 600 Liter diesel to pipe line section for HC PL sleeve repair.
3. Cooperated with pest control to get rid of bee cell at new sedimentation tanks area.
4. Cooperated with VELOSI staff to check & evaluate pipes inside CPF at TK-1202A, TK-1203A &
water injection area (ongoing).
5. Water drained from TK-1202/3, TK-1501/2/3/4/5/6 and TK-1507.
6. Average flow rate to CPF: 151 Sm3/hr., PS#1: 186 Sm3/hr., BV2: 106 Sm3/hr.

Shipping Tanks level:


TK-1507 (mm) TK-1506(mm) TK-1505 (mm) TK-1504(mm) TK-1503 (mm) TK-1502 (mm) TK-1501 (mm)
3765 3139 3232 2245 1781 2721 2475

Chemical and Heater Operation Activities:-


1. Routine check for all chemical pumps and heaters has been done.
2. Chemical feed:
Evaporation pond:
1. Reclaiming oil from retention ponds by reclaim oil pump.
2. Reclaiming oil from evaporation pond#1 by vacuum trucks.

SHOPC Ongoing Operations:-


Temperature
Time Pressure (K Pa) Flow rate(m3/h)
(C°)
06:00 86 35.5 11.4
12:00 110 35.5 11.2

CPF AGR:
Site Personnel:

Dayshift Personnel
Name Company Position
Ahmed Ali P.E AGR Operator
Ahmed Hassan P.E AGR Operator
Nightshift Personnel
Mohamed Hassan Jummah P.E AGR Operator
Activities of AGR
1. Patrol check for engines, vessels and compressors have been done, monitor & record its parameter.
2. Units A&B running normally, unit C not standby.

CPF AGR daily running and performance report:

AGR Units Running (Hrs.) Outlet Pressure (Mpa) Flow Rate (m³/hr.)
1409-A 15
Fula 4.83 4516
field: 1409-B 15 4.83 4674
1409-C 0 0 0
Natural Gas treatment Package Outlet Pressure (Mpa) Total Flow Rate
1420-A Not lined up - -
1420-B Stopped
- -
FNE 4.73 -
Production well Landing Pressure( Mpa)
FW-4 0.7
Total Outlet Gas Volume (m³)
137859
Site Personnel:
Name Company Position

Dayshift Personnel

Hamdelneil G.alla P. E Field Foreman

Elsharif Salah P. E Field Operator

Mohamed Hamid P. E Field Operator


Nightshift Personnel

Fakhry Elshiek P. E Field Foreman

Ibrahim Osman P. E Field Operator

Fula Field Activities: -


1. Patrol check has been done normal and carefully.
2. 38 wells shut down due to power tripped from 04:30 to 06:30 except FN-138 restarted after fix
electrical problem at 09:30.
3. FN-121 shut down due to belt broken at 08:00.

2.0 Moga FPF


2.1 Site Personnel:
Name Company Position
Dayshift Personnel
Elhiraika Khatim P.E Moga & FNE Supervisor
Ashraf Mohammed P.E FPF Foreman
Alaa Mustafa P.E FPF Operator
Salih Awad P.E CR Operator
Nightshift Personnel
Mohammed Elkhalifa P.E FPF Foreman
Omer Mohiad P.E FP Operator
Mohamed Yousif P.E CR Operator

1.2 Ongoing Operations and Evaluation


1.3 Day Shift Activities
1.3.1 FPF
1. Patrol check for all production facilities has been done, monitor & record the parameter.
2. Cooperated with Petro-need Co to construct the new LC tank (ongoing).
3. Cooperated with maintenance team to tighten the hose suction of chemicals feeding pump.

Surge tank level: 3.7m.


Average transit line pressure: 0.30Mpa.
Average transit line flow rate: 46m3/h.

1.3.3 Field:
1.3.4 Field personnel:

Name Company Position


Dayshift Personnel
Nasr Elsir P.E Field Operator
Mohammed Arafat P.E Field Operator
Nightshift Personnel
Mohammed Freed P.E Field Operator

1. Routine check for all production wells and OGMs has been done.
2. Tested M7-7.
3. Stopped M33-2 for half hour due to change stuffing box seal.
4. Shutdown M1-14 for one hour due to fault alarm, and stopped again at 15:00 due to
motor belts cut.

AGR Activities:
Name Company Position
Dayshift Personnel
Omer Mohiad P.E AGR operator
Night shift

1. Patrol check for engines, vessels and compressors has been done.
2. Unit (PK-2409A) Tripped on Dec.19.2018 due to 3 rd stage damage in crosshead and
crosshead shaft.
3. Unit (PK-2409B) Stopped on Jun.20.2020 to be as standby.

AGR daily running and performance report:

Engine No. Running (hrs.) Outlet Pressure (Mpa) Average Flow Rate(m3/h)

A
B
Total Gas Volume(m3)

3.0 FNE FPF


3.1 FPF Personnel:

Name Company Position

Dayshift Personnel
Rashid Mahadi P.E FPF Foreman
Nazar Mohammed P.E FPF Operator
Fadlalla Ahmed P.E FPF Operator

Nightshift Personnel

Neyazy Abdelmuniem P.E FPF Act/Foreman


Mohammed Abbas P.E FPF Operator
1. FPF:
1.2 Activities:
1. Patrol check for production facilities has been done, monitor & record its
parameters.
2. Drained bottom water of Storage tank TK-8501.
3. Changed over Export pump from P-8501C to P-8501B at 01:00.
4. Cooperated with electrician & DCS staff to fix Export pump P-8501C problem.(On
going).

Tanks Level at 15:20


TK-8201-A TK-8201-B TK-8601-A TK-8601-B TK-8501

15.620m 12.032m 8.559m 8.737m 4.511m


Export pump flow rate 22m3/h
2.0 Field:
2.1 Field personnel:

Abuobaida Bashir P.E Field Operator


Name Company Position
Abdallah Alnoor P.E Field Operator
Dayshift Personnel

Nimir Abd Elsalam Nightshift


P.EPersonnel Field Operator

2.2 Field Activities:-


1. Routine check for all production wells and OGMs has been done.
2. FNE-14 shutdown for two hours due to power fault.
3. FNE-05 shutdown at 08:00 due to VSD power fault.
4. Tightened stuffing box for many wells.
5. Empty sample barrels for some wells.
3.0 Sand Cleaning:
3.1 Sand Cleaning Personnel:

Name Company Position


Dayshift Personnel
Ahmed Kalashob P.E S.C Operator

3.2 Sand Cleaning Activities:


1. OGM-04 Trunk line has been flushed by pumping 3.0 loads of hot water
tanker.

2. Sand Trap at OGM-04 cleaned on line & Drain pit reclaimed.

4.0 Jake FPF


4.1 Site Personnel:-

Name Company Position


Dayshift Personnel
Hisham Awad P.E Operation Supv.
Yousif Abdelkhalig P.E FPF Foreman
Mutaz Ezzeldin P.E C.R Operator
Emad Eltigani P.E FPF Operator
Nightshift Personnel
Rahama Mohamed P.E FPF Foreman
Subhi Amin P.E FPF Operator
1.2 Ongoing Operations and Evaluation
FPF Activities:-

1. Patrol check for production facilities has been done.


2. Fed 1000 Kg of DRD.
3. Continue skimming oil from PWTs.

³
Av.Oil Flow Rate(M /H) To FPF To CPF

37.18 36.27

Storage Tank Parameter:-

Tank Number Level (M) Temp (˚C)


TK-7501 7.7 62

2. Field: -
2.1 Site Personnel:-

Name Company Position


Dayshift Personnel

Abubaker Mahjoub P.E Field Operator

Nightshift Personnel
Ahmed Imam Alaalim
P.E Field Operator

Field Activities:-
1. Routine check for all production wells has been done.

JAKE AGR:-
3.1 Site Personnel:

Name Company Position


Dayshift Personnel
Mohammed Dalil P.E AGR Operator
Awad Mohamed P.E AGR Operator
Eltayeb Ibrahim P.E AGR Operator
Nightshift Personnel
Mohamed Fawzi P.E AGR Operator
Hatim Mohamed P.E AGR Operator
a. Jake M.P AGR
b. Performance Report:-

Activities:-
1. Patrol check for engines, vessels and compressors has been done, monitor & record its parameter.
2. Started unit-B at 8:30.
3. Stopped unit-C at 9:30.
4. Cooperated with maintenance team to repair Hydraulic oil leakage in unit C (Finished).
5. AGR units (A, B) are running normally.

Engine No. Running Status Outlet Pressure (Mpa) Average Flow Rate(m3/h)
PK-7402-A Running 10.35 6000
PK-7402-B Running 10.38 4800
PK-7402-C Standby - -
PK-7402-D Stopped - -
Total Flow Rate 10800

3.3 Jake H.P AGR:-


Activities:-
1. HP units (A & B) (Standby).

Engine No. Running Status Outlet Pressure (Mpa) Suction (Mpa) Average Rate(m3/hr)
PK7403-A Standby - - -
PK7403-B Standby - - -
Total Flow Rate

4. Reclaim System and retention pond progress:-


1. Retention Pond contains approximately 3.0% oil.
2. Level of evaporation pond#1 approximately 50%.

5.0 KEYI FPF


5.1 Site Personnel:

Name Company Position


Day Shift Personnel
Mohamed Osman P.E FPF Foreman
Omer Mohammed P.E FPF Operator
Samih Abdalla Talha P.E FPF Operator
Mohamed Sidahmed P.E FPF Operator
Night Shift Personnel
Yousif Ahmed P.E FPF Operator
Abdelaziz Elgoni P.E FPF Operator
1.1 Ongoing Operations and Evaluation:
1.2 Day Activities:
1. Patrol check for all FPF equipment’s has been done.
2. Continue draining water from storage tanks TK-6501A&B.
3. Housekeeping around some FPF equipment’s.

1.3 Tanks Levels:

Tank Number Tank Level (m) Tank Temperature (˚C)


TK-6501-A 10.9 60
TK-6501-B 7.0 53
Total Flow rate to CPF (m3/hr.) 24 m3/hr.

2. Field:
2.1 Site Personnel:
Name Company Position
Day Shift Personnel
Muntasir Mohammed P.E Field Operator
Waheeb Hassan P.E Field Operator
Night Shift Personnel
Ahmed Galal P.E Field Operator

2.2 Field Activity:


1. Routine check for all wells & OGMs has been done.
2. Cooperated with DCS staff to repair micro-motion & control valve of OGM-4.
2.3 Tested well:
Well name (Liquid Bbl./D)
K-25 1060
K-04 980
6.0 Hadida FPF
6.1 Site Personnel:

Name Company Position


Dayshift Personnel
Faroug Abuagla P.E Operation Supervisor
Muaz Awad P.E FPF Foreman
Ibrahim Algaily P.E CR Operator
Abdelrahman Hamad P.E FPF Operator
Nightshift Personnel
Ammar Mohamed P.E FPF Foreman
Ibrahim Gaber P.E CR Operator
Omer Osman P.E FPF Operator
1.2 Ongoing Operations and Evaluation:
1.3 Day shift Activities FPF:
1. Patrol check for all production facilities has been done, monitor & record the parameters.
2. Water injection pump standby.
3. Exports pump: P-4501-D running for 24 hrs.
4. Co-operated with DCS staff to check and repair water level transmeter LIC-103A of
production separator (onging).
5. Monthly check of fire extinguishers has been done by civil defense team.

Storage tank level A: 3.45m B: 3.44m

Transit line pressure 2333Kpa


Average flow rate 70m3/h

2. FSF:-
2.1 Site Personnel:-

Dayshift Personnel
Abdallah Omer P.E Field Operator
Nightshift Personnel
Bilal Ali Altahir P.E Field Operator

2.3 Field:
1. Patrol check for all production wells has been done.
2. Tested well H-7.

3. Mud Pump Activity:


1. Patrol check has been done.
2. Mud pumps:- A & B
standby.
Name Company Position

7.0 Sufyan Dayshift Personnel FPF


7.1 Site Mohammed Nasur P.E Operation Supervisor Personnel:
Abdelmohsen P.E Operation Foreman
Abdalla
Hosam Aldin Ahmed P.E FPF Operator
Khalid Abdalbagi P.E FPF Operator
Hassan Ibrahim P.E C.R Operator
Nightshift Personnel
Elhadi Noureldin P.E A/Operation
Foreman
Mohammed Alfatih P.E FPF Operator
Asem Fatihalaleem P.E FPF Operator
1.2 Ongoing Operations and Evaluation:-
1.3 Day Shift Activities:-
FPF:
1. Patrol check for all production facilities have been done, monitor & record the
parameters.
2. Nineteen outdoor lights inside the EPF out of service need to repair, and WR sent.
3. Daily top-up 2.551m³ of diesel to power plant day tank.
4. Fuel gas scrubber’s condensate drained.

1.4 Parameters:

Storage tank level A:4.7m B:4.7m


Transit line pressure 2877Kpa
Transit line temperature 69°C
Average flow rate 5.5m3/h

2.0 Field:
2.1 Field personnel:

Name Company Position


Dayshift Personnel

Omer Himadan P.E Field Operator

2.2 Activities:

1. Routine check for all production wells and OGMs has been done.
2. Co-operated with electrical team to detect the underground cables and pipes of Suf-5 in
order to prepare for rig service.
3. Co-operated with mechanic team to tighten the stuffing box of OGM2,3 transfer pumps.
4. Suf-E2 fluid tested.

2.3 OGM Pumps Parameters:-


Transfer Pump OGM-2 OGM-3 OGM-4 Remark
Suction Pressure (Mpa) 0.81 0.83 1.26
Discharge pressure (Mpa) 2.95 2.47 2.72

Differential Pressure (DP)(Mpa) N/A N/A N/A

Temp.(°C) 37 42 44
Set point (Mpa) M M M

Freq. (Hz) 10 10 21