Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
RISK
MANAGEMENT PLAN
RUNNING HEAD: RISK MANAGEMENT PLAN
Name of Student
Name of Instructor
Name of Institution
(Date)
Author Note
2
RISK
MANAGEMENT PLAN
A risk is anything that can happen when involved in any venture. If the risk
probability of less than 100 percent. If the risk has many chances of happening then
it is rated to have a probability of 100 percent. This in other words states that it will
happen. A risk can only be a risk when it has a probability above 0 percent. It also
needs s to show that there is a chance for it to happen or not. If these are not
impact on the project. The impact is what the risk manager tries reduce in order to
avoid have great loses. The negative impacts can cause insurmountable results to
the project and may even ruin the progress of the project. Sometimes there is no
need to avoid a risk but try to neutralize the risks. This is because it may be so
expensive to avoid a risk than having a plan to handle its impact (Project Perfect,
2010).
A risk management plan has four stages. The first stage is identifying the risks
by using a combination of brainstorming and review of standard risk lists. The next
stage is risk quantification. There is a need to assess the impact of the risk and the
probability of the risk occurring also needs to be assessed. The next stage is risk
response. The strategies of risk response are to either avoid the risk, transfer the risk
to someone else ,mitigate the risk or try to reduce the impact to the project or reduce
3
RISK
MANAGEMENT PLAN
the chances of the risk occurring. The final step is risk control. It is important to
continuously monitor risks and identify any change in the status. It is also important
to carryout regular risk reviews so that they can identify risk probabilities and
impacts. This also helps to remove risks that have passed, and identify new risks
the project was analysed there were several risks identified. Preamble planning for
the projects helps to prevent future problems in the middle of the project. The
planning helps monitoring and eliminates chances of small problems from becoming
nightmares as the project progresses deeper. The risks are monitored and dealt with
immediately once they are evident. The ideas expressed in this plan are meant to be
a shield to the potential risks before they take toll on the project development.
The risk plan was developed from a session of brainstorming conducted by all
the stakeholders of the project. In this case they were officials from the Department
of Defence who are the client, consultant engineers and other interest groups.
Putting in mind the nature of the security of the product or project there was a lot of
discrepancy into the matter but we eventually came up with several risks. The list of
potential risks was very long but at least the organisation of the risks into the
particular types made some of them to be combined as they fell under the same
category. The merging of the risks together was able to bring to a total of fifteen risks
Some risks stood out than others such as the possibility of a change in
specifications of the AMDS. This was seen as there were discussions on how some
settings and programming into the systems was suppose to be. This out rightly
meant that the software’s and hardware’s would face changes too. This was a risk
4
RISK
MANAGEMENT PLAN
and it was well prepared for by the team. This is because every model that is to be
There was also a risk of security breach and the AMD’s turn into a hazard.
The sophistication of the product was a clear indication that if anything went wrong
then it would lead to a great disaster. The contingency plan was to ensure that the
system was able to notice faults in the system sand communicate to the fault. This
will ensure that close monitoring of the system and security checks to be carried out
regularly to ensure that the AMD was in form (Mind Tools, 2010).
Another apparent risk was the resources allocated and the time of completion
of the project. The project is expensive in terms of time and development hence it
would be likely to have a plan to look out for activities that could run concurrently so
that the project does not flow out of schedule. This can be seen for example when
the product goes for testing there is a likelihood that it may not be to the complete
requirement in the initial tests thus calling for several tests. However in the project
there is allowance of time for the lag, a high chance is that the opportunities
allocated may be used out and then start to over ride on time of other activities
(Cynthia, 2009).
The unrealistic cost and time estimates in the planning stages of the project
are a considerable possibility due to the very complex nature of approximations that
must be made when compiling the project Work Breakdown Structure. These
estimates are associated with nearly every other risk as well, since any unforeseen
changes in the work plan will lead to changes in cost and time scale. Early noticing
5
RISK
MANAGEMENT PLAN
of this inconsistencies and risks helps to ensure the project is guarded against the
Efforts to obtain more relevant information and searching for similar projects
for comparison was the way to go in order to get a chance to generally build a
broader knowledge base was not so fruitful. This was aimed towards the borrowing
of techniques and of a structure and a more accurate forecast of the resources (time
and cost) needed to satisfactorily complete our project x. There was little that could
be obtained but at least the few comparisons contributed to the coming up with a
structure that will be used. Continuous, routine and timely updates of resource
projections should also be embraced throughout the lifespan of the project in order to
project planning will again be beneficial for all parties in the long run. Along with
general between organizations and the various stakeholders will bring out the
Department of Defence a good system that can effectively monitor the security and
in the right schedule. The AMD is a unique project hence there are unique
challenges and if not well noted they are likely to bring down the whole project
(Cynthia, 2009).
6
RISK
MANAGEMENT PLAN
In summary, project risks are inevitable and are part of life, however there are
many techniques that can be used to mitigate their potential impacts and keep the
project on track. For Project X, we have compiled a list of fourteen significant risks.
They are categorized using the Risk Probability / Impact Matrix. From this activity,
two risks stood out as the most important to plan for and monitor. Budget and time
overruns are a real likelihood given the nature of this project complexity and
uniqueness of the project, but impacts can be mitigated with extensive pre-planning
comparison and research from similar projects. Project scope requirements changes
are nearly a given, though their negative impacts can be diminished with research,
knowledge, and most important, communication between the contractor and the
stakeholder and the client who is the Department of Defence (Mind Tools, 2010).
The risks
x
Quality Risks
1. The Demonstration may not match up to the quality required by
the DoD
2. the technology may be too sophisticated for
the DoD,
EXTERNAL
RISKS
3. the enemy may get to learn the technology and use a more sophisticated
4. there may be natural disasters that may incapacitate the technology for example
earth quakes
7
RISK
MANAGEMENT PLAN
5. change of specifications by the DoD to fit particular needs after
demonstration
INTERNAL
RISKS
6. the failure in hardware and software leading to a fatal
disaster
7. the military personnel carrying out the maintenance may fail to operate the
BUDGET
RISKS
8. the funds allocated to complete project may not be enough it
budget
SCHEDULE
RISKS
10. Project may overrun the time period
of five years
11. the time period may be too short for completion of the
whole project
RESOURCE
RISKS
12. the technology may be too complex for the
staff collected
13. there may be a conflict of ideas with the selected scientists and project team
Impact
Mind Tools. (2010). Risk Impact/Probability Chart. Retrieved June 06, 2010, from