1. In the shortest route problem, the objective is to find the shortest route from an
origin to a destination through a network.
A. True
B. False
2. Shortest path algorithm given in the text will work even if the costs (distances) of
the arcs are negative.
A. True
B. False
3. In the linear programming formulation of the shortest path problem, the constraint
corresponding to the origin will have 1 on its RHS.
A. True
B. False
5. In flows in network, the optimal solution to the maximal flow problem cannot
have flows simultaneously in both directions of an arc.
A. True
B. False
6. In the spanning tree algorithm, we try to find the shortest arc from the connected
nodes to any nodes of the rest of the graph.
A. True
B. False
7. In the spanning tree problem, one is trying to find the longest tree from the origin
to the destination.
A. True
B. False
8. In the shortest route problem, the algorithm will find all shortest paths from any
node to any node.
A. True
B. False
9.
In Figure 1, using the shortest route algorithm presented in the text, the node that
would be labeled with a permanent label next will be
A. 1.
B. 2.
C. 3.
D. 5.
10.
In Figure 2, using the shortest route algorithm presented in the text book, the
label and the node that would get the permanent label will be
A. 3 and [5,2].
B. 4 and [8,2].
C. 5 and [7,1]
D. 2 and [3,1]
11.
In Figure 3, bold arc and all nodes attached to it is the connected node. Using the
algorithm in the text for finding the minimal spanning tree which will be the next
node that will be added to the set of connected nodes?
A. 3.
B. 6.
C. 4.
D. 5.
12.
What is the maximum flow possible from source to sink in the network given in
Figure 4?
A. 9
B. 8
C. 7
D. 10
Retake Test
Chapter 10 : AHP
3. In goal programming, hard constraints are satisfied and soft constraints are brought
to acceptable levels (satisficing).
A. True
B. False
11. Which of the following phrases best describes deviation variables in goal
programming?
A. The acceptable level of goal achievement
B. The gap between actual achievement and target performance.
C. The variability of resource availability.
D. The difference between maximum and minimum achievement levels of
goal achievement.
1. Given the following key factors and their importance weights, determine a
total weighted evaluation for A1.
0.59
Your Answer:
Correct Answer: 0.76
2. Given three alternatives and their total weighted evaluation, which action
should be selected?
Alternative A or Alternative C
Your Answer:
Correct Answer: Alternative C
Incorrect. See section M1.2.
Component B B1 B2 B3
B1 0.69 0.720 0.563
B2 0.23 0.240 0.375
B3 0.07 0.040 0.063
B1 B2 B3
Your Answer:
0.706 0.200 0.092
Correct Answer:
B1 B2 B3
0.658 0.281 0.060
CORRECT.
Compute .
4.0
3.0
2.5
approximately 3
Your Answer:
CORRECT.
1.2
Your Answer:
CORRECT.
0.125
Your Answer:
CORRECT.
CORRECT.
CORRECT.
The form below can be used to email these results to up to four different email addresses.
E-mail Your Results
Text
E-mail my results toInstructor
Text
E-mail my results toTA
Text
E-mail my results toOther
Help
2. Which of the following, if any, may not be one of the questions answered
by PERT or PERT/Cost?
3. PERT
CORRECT.
6. Given the following activity’s optimistic, most likely, and pessimistic time
estimates of 6, 10, 14 days, respectively, compute the PERT time for this
activity.
5
Your Answer:
Correct Answer: 10
7. What is the critical path for the project described in the following table?
A, B
Your Answer:
Correct Answer: B, D
0.98
Your Answer:
CORRECT.
CORRECT.
The form below can be used to email these results to up to four different email addresses.
E-mail Your Results
Text
E-mail my results toMe
Text
E-mail my results toInstructor
Text
E-mail my results toTA
Text
E-mail my results toOther
Help
1. In PERT, an activity that has slack can be delayed without affecting the
start of any other activity.
True
Your Answer:
Correct Answer: False
2. In PERT, if the early finish and late finish times are the same, an activity
has no slack.
True
Your Answer:
CORRECT.
3. The latest finish time (LF) is the earliest time an activity can end without
delaying the entire project.
True
Your Answer:
Correct Answer: False
Incorrect. See section 13.2.
True
Your Answer:
Correct Answer: False
True
Your Answer:
Correct Answer: False
6. PERT is more appropriate than CPM for managing projects that are
unfamiliar and for which we can only estimate activity durations.
True
Your Answer:
CORRECT.
False
Your Answer:
Correct Answer: True
False
Your Answer:
Correct Answer: True
True
Your Answer:
Correct Answer: False
CORRECT.
The form below can be used to email these results to up to four different email addresses.
E-mail Your Results
Text
E-mail my results toMe
Text
E-mail my results toInstructor
Text
E-mail my results toTA
Text
E-mail my results toOther
Help
event
Your Answer:
CORRECT.
crashing
Your Answer:
CORRECT.
4. PERT often assumes that the time estimates follow the _______
probability distribution.
Poisson
Your Answer:
Correct Answer: beta
chore
Your Answer:
Correct Answer: activity
Incorrect. See section 13.2.
arcs
Your Answer:
Correct Answer: nodes
CPM, PERT
Your Answer:
Correct Answer: PERT, CPM
8. The earliest start (ES) of an activity is the _________ earliest finish (EF)
of the immediate __________.
largest, successors
Your Answer:
Correct Answer: largest, predecessors
nonlinear fashion
Your Answer:
Correct Answer: linear fashion
The form below can be used to email these results to up to four different email addresses.
E-mail Your Results
Text
E-mail my results toMe
Text
E-mail my results toInstructor
Text
E-mail my results toTA
Text
E-mail my results toOther
Help
3. In pruning (evaluating) a decision tree, you write the expected payoff at a random
outcome node inside the circle or square representing that node.
A. True
B. False
5. If a decision theory problem has 3 decision alternatives and 4 states of nature, the
number of payoffs in that problem will be
A. 3
B. 4
C. 12
D. 64
A. d1
B. d2
C. d3
D. d4
A. d1
B. d2
C. d3
D. d4
A. d1
B. d2
C. d3
D. d4
11 Prior probabilities for economic boom, moderate growth and recession in the
. Land_of_the_bipeds is given below. There is a Land_of_Mortals where there are
only two states Boost or Roast. Conditional probability of Boost or Roast given
various states of economic conditions in the Land_of_the_bipeds is also known
and presented below.
The P(Boost) is
A. 0.16
B. 0.15
C. 0.46
D. 0.54
12 Prior probabilities for economic boom, moderate growth and recession in the
. Land_of_the_bipeds is given below. There is a Land_of_Mortals where there are
only two states Boost or Roast. Conditional probability of Boost or Roast given
various states of economic conditions in the Land_of_the_bipeds is also known
and presented below.
The P(Roast) is
A. 0.16
B. 0.54
C. 0.46
D. 0.04
Retake Test