Sei sulla pagina 1di 86

Article No : b04_477

Chemical Plant Design and Construction


ERICH MOSBERGER, Lurgi AG, Frankfurt, Federal Republic of Germany

1. Introduction. . . . . . . . . . . . . . . . . . . . . . 250 4.1.4. Know-How Contracts via Engineering


2. Feasibility Study . . . . . . . . . . . . . . . . . . 250 Contractors . . . . . . . . . . . . . . . . . . . . . . . 287
2.1. Initial Work. . . . . . . . . . . . . . . . . . . . . . 251 4.2. Design and Supply Contracts with
2.2. Cost Estimation . . . . . . . . . . . . . . . . . . . 252 Engineering Contractors . . . . . . . . . . . . 288
2.2.1. Investment Costs . . . . . . . . . . . . . . . . . . . 252 4.2.1. Selection of Engineering Contractors . . . . 288
2.2.1.2. Global Methods of Investment Cost 4.2.1.1. Importance of Risk in the Plant Business . . 288
Estimation. . . . . . . . . . . . . . . . . . . . . . . . 253 4.2.1.2. Selection and Award Criteria . . . . . . . . . . 288
2.2.1.3. Detailed Methods of Investment Cost 4.2.2. Form and Content of Contracts . . . . . . . . 289
Estimation. . . . . . . . . . . . . . . . . . . . . . . . 254
4.2.2.1. Basic Concerns in Contract Writing . . . . . 289
2.2.1.4. Item-by-Item Calculation . . . . . . . . . . . . . 255
4.2.2.2. Contract Types and Provisions . . . . . . . . . 290
2.2.1.5. Cost Indexes . . . . . . . . . . . . . . . . . . . . . . 256
4.2.2.3. Essential Elements of a Contract . . . . . . . 291
2.2.2. Operating Costs. . . . . . . . . . . . . . . . . . . . 256
5. Execution of the Project . . . . . . . . . . . . 293
2.2.3. EDP Support . . . . . . . . . . . . . . . . . . . . . . 257
5.1. Scope of Work . . . . . . . . . . . . . . . . . . . . 293
2.3. Profitability Analysis . . . . . . . . . . . . . . . 257
5.2. Project Organization and Management . . 294
2.3.1. Profitability Analysis as an Engineering Task 257
5.2.1. Matrix Project Management . . . . . . . . . . 294
2.3.2. Methods of Profitability Analysis . . . . . . . 258
5.2.2. The Project Manager . . . . . . . . . . . . . . . . 295
2.4. Site Selection . . . . . . . . . . . . . . . . . . . . . 259
5.2.3. The Project Team . . . . . . . . . . . . . . . . . . 296
2.5. Decision between Alternative Investments 259
5.2.4. The Start Phase of a Project . . . . . . . . . . . 296
3. Preliminary Design . . . . . . . . . . . . . . . . 260
5.3. Project Control (Schedules, Progress,
3.1. Preliminary Design Costs. . . . . . . . . . . . 260
Costs). . . . . . . . . . . . . . . . . . . . . . . . . . . 297
3.2. Final Selection of Site Locations . . . . . . 261
5.3.1. Time Scheduling . . . . . . . . . . . . . . . . . . . 297
3.3. Process Design . . . . . . . . . . . . . . . . . . . 263
5.3.2. Progress Planning and Control . . . . . . . . . 299
3.3.2. Optimization . . . . . . . . . . . . . . . . . . . . . . 267
5.3.3. Cost Planning and Control . . . . . . . . . . . . 300
3.3.3. Safety Aspects and Environmental Control 269
5.3.4. Project Report . . . . . . . . . . . . . . . . . . . . . 302
3.3.3.1. Protection Against Emissions . . . . . . . . . . 270
5.4. Detail Engineering . . . . . . . . . . . . . . . . . 303
3.3.3.2. Noise Control . . . . . . . . . . . . . . . . . . . . . 270
5.4.1. Process Engineering. . . . . . . . . . . . . . . . . 303
3.3.3.3. Occupational Safety and Health . . . . . . . . 272
5.4.2. Plant Layout . . . . . . . . . . . . . . . . . . . . . . 303
3.3.3.4. Plant Availability . . . . . . . . . . . . . . . . . . 272
5.4.3. Apparatus and Machinery . . . . . . . . . . . . 305
3.3.3.5. Authority Engineering . . . . . . . . . . . . . . . 273
5.4.4. Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . 308
3.4. Basic Engineering . . . . . . . . . . . . . . . . . 275
5.4.5. Control Systems . . . . . . . . . . . . . . . . . . . 312
3.4.1. Equipment Specification from the Process
5.4.6. Electrical Design . . . . . . . . . . . . . . . . . . . 315
Engineering Standpoint . . . . . . . . . . . . . . 275
5.5. Procurement . . . . . . . . . . . . . . . . . . . . . 316
3.4.2. Materials of Construction. . . . . . . . . . . . . 275
5.5.1. Purchase of Equipment and Services . . . . 316
3.4.3. Plant Layout . . . . . . . . . . . . . . . . . . . . . . 279
5.5.2. Expediting. . . . . . . . . . . . . . . . . . . . . . . . 317
3.4.4. Preliminary Piping and Instrumentation
5.5.3. Shipping . . . . . . . . . . . . . . . . . . . . . . . . . 317
Diagram . . . . . . . . . . . . . . . . . . . . . . . . . 281
5.6. Planning and Execution of Civil Work and
3.5. Calculation of Plant Costs . . . . . . . . . . . 281
Erection . . . . . . . . . . . . . . . . . . . . . . . . . . 317
3.5.2. Equipment. . . . . . . . . . . . . . . . . . . . . . . . 282
5.6.1. Planning of Civil Work and Erection . . . . 318
3.5.3. Bulk Materials. . . . . . . . . . . . . . . . . . . . . 283 5.6.1.1. Planning of Civil Work (Including Structural
3.5.4. Other Costs . . . . . . . . . . . . . . . . . . . . . . . 284 Steel Work). . . . . . . . . . . . . . . . . . . . . . . . 318
3.6. Conclusion of Preliminary Design Phase 285 5.6.1.2. Erection Planning . . . . . . . . . . . . . . . . . . 319
4. Contract Writing and Forms of Contracts 286 5.6.2. Execution of Construction . . . . . . . . . . . . 319
4.1. Licensing Agreements . . . . . . . . . . . . . . 286 5.6.2.1. Construction-Site Organization and
4.1.1. Patent Licenses . . . . . . . . . . . . . . . . . . . . 286 Management . . . . . . . . . . . . . . . . . . . . . . 319
4.1.2. Process Licenses . . . . . . . . . . . . . . . . . . . 286 5.6.2.2. Time Scheduling and Progress Control . . . 320
4.1.3. Process Licenses via Engineering Contractors 287 5.6.2.3. Construction Work . . . . . . . . . . . . . . . . . 321

 2012 Wiley-VCH Verlag GmbH & Co. KGaA, Weinheim


DOI: 10.1002/14356007.b04_477
250 Chemical Plant Design and Construction Vol. 8

5.7. Commissioning. . . . . . . . . . . . . . . . . . . . 322 6.2. EDP Infrastructure and Systems . . .... 327
5.7.1. Plant Design and Commissioning . . . . . . . 322 6.3. Coordination and Interfaces . . . . . .... 328
5.7.2. Operating Manual . . . . . . . . . . . . . . . . . . 323 7. Quality Assurance . . . . . . . . . . . . . .... 328
5.7.3. Responsibility and Organization . . . . . . . . 325 8. Training of Plant Personnel. . . . . . .... 329
5.7.4. Preparation for Commissioning . . . . . . . . 325 References . . . . . . . . . . . . . . . . . . . .... 330
5.7.5. Plant Startup . . . . . . . . . . . . . . . . . . . . . . 325
6. Computer Support. . . . . . . . . . . . . . . . . 326
6.1. Role of Computers in Project Execution 326

1. Introduction The implementation phase consists of the


engineering of the chemical plant, procurement
Since the 1930s, the design and construction of of plant equipment and material, construction,
chemical plants have become increasingly spe- and commissioning. The engineering contractor
cialized. Chemists and engineers collaborate to either performs all of these tasks or brings in
develop process and engineering concepts, subcontractors or personnel employed by the
which engineers and designers then transform owner to carry out a portion of the work.
into detailed plans and specifications for all the Plant equipment is fabricated by specialized
components of a chemical plant. Purchasing manufacturers. Only in rare cases does the engi-
agents procure equipment from specialist man- neering contractor or the plant owner have pro-
ufacturers. Construction and installation firms duction facilities.
are put under contract to build the plant. After a successful test run, the plant is handed
Plant design and construction starts as an idea over to the owner. (Fig. 1 shows a schematic
of the potential owner. Increasingly complex diagram of the development of a chemical plant
markets and the interrelations of the world eco- project.)
nomic and political systems require critical ex- This article does not discuss the design and
amination of every project for feasibility, eco- construction of small, simple plants that special-
nomic relevance, and environmental impact. As a ized firms can supply ‘‘off the rack.’’ It deals with
rule, this is done with the aid of a feasibility study larger, more complicated projects in the field of
that includes preliminary design work. Market chemical plant construction. The term chemical
analyses are carried out to determine potential plant design and construction is used in a very
sales, future demand dynamics, availability of broad sense. It also relates to allied technologies,
raw materials, and the competitive situation. The such as metallurgy, environmental protection,
plant capacity and location are specified. Partic- fiber and food production, and petroleum and
ular attention must be paid to environmental natural gas processing. Some of these basic
protection. Studies are supplemented by suffi- project development and execution principles
ciently accurate estimates of capital require- can also be applied to general industrial plant
ments and profitability. construction.
Once the decision has been made to go ahead
with the construction project, whereby the owner
may have opted not to carry it out himself, the 2. Feasibility Study
owner will prepare an accurate, comprehensive
definition of the plant which is used as the basis At the start of a project, the bases used for
for inviting bids from competent engineering planning are still very inexact. No major costs
contractors. This approach is increasingly em- should be incurred until it is known whether the
ployed, especially for large projects. (If the own- project is feasible or not. Nevertheless, all alter-
er has an adequate pool of experienced design natives must be considered. A great deal of
engineers, construction specialists, and procure- experience is needed if uneconomic variants are
ment staff, he may plan and construct the plant to be discarded without generating high design
himself.) The conceptual phase of the project costs. The first steps toward accurate definition of
ends when an appropriate engineering firm is the project are carried out by the company that
chosen and the contract signed. wishes to erect the plant. A small working group
Vol. 8 Chemical Plant Design and Construction 251

Figure 1. Development of a project

is formed, consisting of process engineers, sales experienced market analysts, even if the product
engineers, and other engineering personnel. It is has a comprehensive international sales history.
useful to appoint a project leader to coordinate These specialists evaluate literature on the de-
the team. Normally, the same person will later velopment of similar products, determine the
become responsible for implementing the project capacity of existing production facilities, carry
if the decision is taken to proceed. out representative surveys, obtain suitable con-
Preliminary studies aimed at defining the ditions from downstream processors in the case
objective partly depend on initial economic es- of intermediate products, and forecast the future
timates and generally include: market for the product. They must also provide a
realistic evaluation of the competition and the
1. Market analysis and trend analysis world economic situation. Forecasts of costs for
2. Fixing of production capacity raw materials and working capital play an im-
3. Examination of competing processes and of portant role in the economic analysis.
the patent and license situation A new chemical product usually experiences
4. Legal aspects slow early growth with a relatively high price and
5. Estimation of investment costs low output. The market then expands; production
6. Estimation of production costs climbs faster and prices drop. Finally, prices
7. Estimation of profitability stabilize at a low level, and older, smaller plants
8. Selection of an appropriate plant location are shut down (see Fig. 2). If market analysis
shows that world output of the product is still
increasing rapidly, expansion of capacity
2.1. Initial Work through erection of a new plant may have a good
outlook if other conditions are favorable. The
Market Analysis and Production Capa- future price decline must, however, be allowed
city. Before the economically optimum plant for in the calculations.
capacity is set, a careful market analysis must be In the upper part of the trend curve, invest-
carried out. This analysis must be performed by ment only makes sense if a clear demand is
252 Chemical Plant Design and Construction Vol. 8

ating costs. Operating costs are favorably influ-


enced by long component and equipment life-
times, improvements in maintenance and con-
sumption, and other factors. Cost prediction as
the basis for profitability analysis should there-
fore include the determination of investment
costs as well as subsequent production and oper-
ating costs.
The following sections discuss methods of
determining investment and operating costs.

Figure 2. Development of a new product


2.2.1. Investment Costs

A proven technique in investment cost estima-


perceptible in the market. The production curve tion is to subdivide the project into onsite and
for the old process may fall off if a new, more offsite items.
economical production process appears. (Exam-
ple: low-pressure process for methanol produc- Onsite Items. The term onsites denotes all
tion forces shutdown of older high-pressure pro- facilities required to make the desired product.
cess.) The new process may open up new markets
and lend new impetus to development [1–4]. Offsite Items. Offsites are all facilities that
are normally not located within the process plant.
Competing Processes, Patent and License They include facilities for the delivery of steam,
Situation. The patent and license situation electric power, gas, solid or fluid fuels, water,
must be investigated at the beginning of the compressed air, and instrument air. Furthermore,
study. Foreign patents may block the construc- this group includes stockpiles and warehouses
tion project if the owner of the patent is not for raw materials and semifinished and finished
prepared to grant a license (see also Chap. 4). products; service facilities (administrative build-
ings, canteens, workshops, stores, laboratories,
Legal Aspects. Extensive, far-reaching en- parking, fire protection, roads, tracks, and harbor
vironmental regulations mean that it is essential facilities); and, finally, power plants; loading
to make an early approach to authorities that will docks; facilities for treating raw materials, off-
later have to approve the operation of the plant gas, wastewater; and waste disposal facilities.
(see Section 3.3.3.5). In the United States, offsites are usually di-
vided into storage and handling (stocks of raw
materials and finished products), utilities (gener-
2.2. Cost Estimation ation or delivery of energy as steam, electricity,
and water), and service facilities (e.g., offices,
If initial planning work has shown that invest- recreation rooms, laboratories, workshops,
ment is desirable and the market analysis has led warehouses).
to a tentative capacity figure, a first estimate of On grounds of cost, an attempt must be made
investment costs and subsequent operating costs to carry out an ‘‘order-of-magnitude’’ estimate at
is performed. minimal cost. This estimate is of course inexact,
Simply calculating and analyzing the invest- but later it makes it easier to decide whether to
ment costs is not sufficient because, over the bear the costs for an accurate analysis. The
service life of a plant, operating costs make up approximate determination of investment costs
a much greater proportion of life- cycle costs than is subdivided into simple ‘‘global’’ methods and
investment costs do. The goal of cost estimation ‘‘detailed’’ methods. Methods for estimating in-
in the conceptual phase is to optimize the life- vestment costs are now well-established; those
cycle costs of a chemical plant. This often means now in use are described in publications mainly
increasing investment costs so as to lower oper- dating from 1960 – 1984.
Vol. 8 Chemical Plant Design and Construction 253

2.2.1.2. Global Methods of Investment Cost technique is based on costs for plants already on-
Estimation stream. The exponents are used to estimate in-
vestment costs for the planned facility as a func-
Global methods permit investment costs to be tion of plant capacity.
estimated relatively easily and with an accuracy Investment costs for proces plants are pub-
between  30 % and  50 %. Several methods lished from time to time and can be used for
are outlined below [5]. initial cost estimation. The costs of identical or
similar plants within the same company can be
Single Complexity Factor. In the single- used in a similar way. In 1967, J. E. HASSELBARTH
complexity-factor method [6] processes are clas- [8] published the costs of process plants for 60
sified as having a low, medium, or high com- chemical products, including investment costs
plexity factor. per tonne of annual capacity. His figures referred
Low Complexity Factor. This class includes to costs within battery limits (i.e., within the plant
all batch processing plants and all processes boundary), exclusive of land and offsite facili-
involving simple syntheses (e.g., production of ties. In 1970, K. M. GUTHRIE [9] compiled the
sulfuric acid). investment and operating costs for 54 chemical
Medium Complexity Factor. This class and refinery processes covering a wider capacity
comprises processes with gas and fluid phases range. The degression exponents cited in both
that run at ordinary pressures and temperatures. publications allow the calculation to be applied to
High Complexity Factor. This class covers other capacities. (Example: Given a degression
processes with high pressures and/or tempera- coefficient of 0.7, doubling the capacity leads to
tures, as well as polymerization processes. an increase in investment costs by a factor of
Investment costs depend on the complexity 20.7 ¼ 1.65.)
factor and the required plant capacity, and are When specific degression exponents are used
determined from empirical data obtained in other it should be noted that the error range grows with
processing plants. Auxiliary and utility units are the capacity scaling factor. This type of calcula-
taken into account by adding 45 %. tion generally gives acceptable results only for
This method has the advantage that it permits scaling factors of up to 1: 3. Furthermore, the use
estimation of investment costs in the orientation of the method depends on the state of the art
phase when little information about the process is because changes in processes, apparatus, and
available. mechanical technique can change the exponents.

Turnover Ratios. The turnover-ratio meth- Comparative Methods. When adequate


od allows costs to be estimated without process data are available from an existing plant similar
information by using market information such as to that being planned, the investment costs of the
product sale price and sales volume [7]. old plant can obviously be used to calculate the
On the basis of plants already on-stream, a costs of the new one.
capital turnover ratio is obtained by dividing the The following information is needed [5]:
annual return on sales by the investment costs. A
statistically determined turnover ratio and an 1. Production capacity
expected annual return on sales are then used to 2. Construction time
estimate the investment costs of new plants. 3. Investment costs (inside and outside battery
Turnover ratios in the chemical industry lie limits)
between 1.2 and 1.5. 4. Location
Statistical turnover ratios can be found for the
analysis of individual plants, companies (based Costs inside and outside battery limits are both
on balance sheets and profit-and-loss statements determined with degression exponents. Cost es-
of typical firms), or a whole industrial sector. timation outside battery limits must, however, be
preceded by a critical analysis of the auxiliary
Degression Exponents. The use of degres- and utility units needed. The figures are adapted
sion exponents (cost-versus- capacity exponents) to the location by the use of indexes to adjust for
per-mits relatively accurate cost estimation. The the following [5]:
254 Chemical Plant Design and Construction Vol. 8

1. Construction location Other authors have extended and refined the


2. Economic situation of the industry Lang method. For example, BURGERT in 1979
3. Taxes published an analysis of investment- cost struc-
4. Labor market tures for more than 100 projects [15].
5. Qualifications of available labor In 1965, MILLER [16] devised another system
based on modified Lang factors. MILLER assumed
2.2.1.3. Detailed Methods of Investment Cost that the factors are influenced by three other
Estimation parameters besides those used by LANG (solid,
solid – fluid, fluid):
If the preliminary planning as embodied in
technical documents has reached an advanced 1. Size of main equipment items
stage, it can form the basis for investment 2. Material from which the plant is constructed
cost estimation that takes into account specific 3. Pressure for which the plant is built
details of the project. Methods used for this
are mainly based on analogies with plants that Increasing size, more refined materials, and
are already on-stream. Detailed methods of higher operating pressure increase the relative
plant matching [10] and multiplication-factor costs of the main equipment items in relation to
techniques of cost determination are emp- storage, utilities, and service facilities, thus di-
loyed. minishing the factors. According to MILLER, all
factors can be referred to the mean per-piece
Lang Factor Method. If the process is well costs of plant parts and depend on these.
characterized, the required capacities of fur-
naces, apparatus, and machinery can be specified Guthrie’s Modular Technique. The mod-
in preliminary flow sheets [11]. These specifica- ular technique published by GUTHRIE [17] in 1968
tions cover main plant items such as furnaces, is also based on LANG’s method and is the best of
columns, filters, reactors, heat exchangers, ves- the multiplication-factor approaches. The project
sels, and machinery. The estimator can determine is first broken down into six modules [10]:
the costs ‘‘free-on-site’’ for such items or obtain
the costs from suppliers. Five direct modules
LANG used cost analyses of existing plants to Chemical processes
derive multiplication factors that allow determi- Solids handling
nation of the investment costs for process units Site development
within battery limits if the costs of the main Industrial structures (civil work)
equipment items are known [12]. The factors Auxiliary and service facilities outside battery
depend on the type of plant. LANG distinguishes limits (offsites)
three types according to the state of aggregation
of the raw material and product: ‘‘solid’’ (e.g., ore One indirect module
sintering), ‘‘solid – fluid’’ (e.g., oil – shale re- Indirect project costs
torting with shale – tar recovery), and ‘‘fluid’’
(e.g., petroleum refineries, petrochemical plants). The key costs of the direct modules are deter-
If the costs for the main plant items are taken mined first. For the ‘‘chemical process’’ module,
as 100, total processing-plant costs are found by these might be costs for machinery and equip-
multiplying by 3.10 (solid-processing plant), ment. As shown in Figure 4, the key costs of the
3.63 (solid – fluid-processing plant), or 4.74 direct modules are multiplied by the gross mod-
(fluid-processing plant). ule factors. The sum of the individual ‘‘gross
CHILTON [13] and HAND [14] have improved module costs’’ gives the investment costs for on-
these approximate Lang factors by introducing and off-battery facilities.
supplements to the costs of main equipment GUTHRIE proposes a variety of methods for
items. Estimates of the total costs of a ‘‘grass- calculating the equipment costs of a module. The
roots’’ plant can then be made. Figure 3 outlines multiplication factors required for this include
the procedure for preliminary calculations by the not only size of the component (magnitude fac-
Lang – Chilton method. tor) and the alloy factor, but also indirect effects.
Vol. 8 Chemical Plant Design and Construction 255

Figure 3. Preliminary cost estimate using factors (Lang – Chilton method)

This relatively accurate modular technique has alternative is to calculate investment costs item
not found wide acceptance, however, because it by item. The plant equipment and the engineer-
is relatively difficult to perform the calculation ing work must be specified. The procedure and
and maintain the statistical data base. amount of work required for such a cost estima-
tion are the same as those described for calculat-
2.2.1.4. Item-by-Item Calculation ing plant costs (see Section 3.5). Close coopera-
tion between the subsequent operator of the plant
When detailed methods of investment- cost esti- and an engineering firm has proved advantageous
mation do not give sufficient accuracy, the only for this approach.
256 Chemical Plant Design and Construction Vol. 8

Figure 4. Simplified modular concept for estimating investment costs


F ¼ net module factor; F2 ¼ gross module factor

2.2.1.5. Cost Indexes 2.2.2. Operating Costs

The methods of investment-cost estimation dis- Along with the investment costs, the operat-
cussed above are generally based on historical ing costs incurred in the production of a given
statistics derived from existing plants. The cost product also play an important part in deciding
figures obtained by these methods are therefore
referred to given periods, such as 1985. If invest-
ment costs are to be estimated for the year 1990,
the estimates must be adjusted to current prices.
Every industrial country publishes one or more
indexes for this purpose. Some widely used
indexes for the United States and Germany
follow:

1. Bureau of Labor Statistics cost index for


equipment, machinery, and materials in the
U.S. market
2. Chemical Engineering Plant cost index
[18–20]
3. K€olbel – Schulze index for chemical plants
(K€olbel – Schulze Index f€ ur Chemieanlagen)
[21]
4. Producer price index for commercial products
(Index der Erzeugerpreise gewerblicher Pro-
dukte) compiled by the German Federal Sta-
tistical Service (Statistische Bundesamt)

These indexes are based both on chemical- Figure 5. Development of cost indexes
plant cost structures and on national primary a) CE Plant cost index, 1959 ¼ 100, successively published
in [18] (1982 revision of productivity factor from 2.50 to
price indexes. Figure 5 compares important cost 1.75); b) K€olbel – Schulze index, 1976 ¼ 100, successively
indexes over time. published in [19]
Vol. 8 Chemical Plant Design and Construction 257

whether to erect a plant. The technical and eco- Scaleup Methods. When operating costs for
nomic literature, however, contains little infor- similar plants are known,specific data can be
mation on the preliminary calculation of operat- used to derive scaling coefficients for propor-
ing costs. Possible reasons are the complexity of tional, personnel-dependent, and investment-
the problem and the company’s possible loss of dependent costs. The operating costs can then
maneuvering room if internal operating data be estimated.
were published [22].
The methods of estimating operating costs
discussed below are based on data from compa- 2.2.3. EDP Support
rable plants or empirical data from plants belong-
ing to the same company [22]. A number of manufacturers and operators have
They are related, but differ as regards starting established electronic data processing (EDP)
information: published data, empirical data, programs for estimating investment and operat-
business information, physical data, correlations, ing costs. Examples are Factest (ICI) [26] and the
and information from comparable plants. In or- ASPEN package [27]. The ASPEN PLUS soft-
der to check the reliability of the results, operat- ware, a flow sheet simulation program, is sup-
ing costs should be estimated by several methods plemented with a costing module.
so that the calculations can be verified and error The program sizes the most important
ranges given. equipment and machinery from the process
simulation. Investment costs are estimated by
Graphical Method. The graphical method the use of multiplication factors and cost
is based on statistical evaluation of operating indexes to adjust to current price levels.
costs in existing plants. Operating costs per unit ASPEN PLUS allows the calculation not only
of product are plotted versus plant capacity. It is of fixed costs for an investment, but also
important to be aware of the scope of the plotted operating costs.
costs. The graph usually includes only the To determine operating costs, the program
manufacturing costs of a product: raw materials, calculates fixed and variable components sepa-
power, catalysts, chemicals, wages, depreciation, rately. Variable costs include raw materials,
and maintenance. Plant overheads, fixed costs, fuels, catalysts, disposal, and ‘‘running royal-
and indirect production costs should also be ties’’. Fixed costs comprise personnel costs for
taken care of by multiplication factors. maintenance and operation, overheads, insur-
ance, and taxes. The program generates summa-
Business Analysis. The analysis of bal- ries and details of annual operating costs. Finally,
ance sheets and profit-and-loss statements the software can evaluate a variety of profitability
from companies that manufacture the product measures (Section 2.3).
in question as their main commodity may also
be helpful.
2.3. Profitability Analysis
Energy-Based Methods. Chemical produc-
tion processes involve large amounts of energy. 2.3.1. Profitability Analysis as an
The chemical reactions themselves often contrib- Engineering Task
ute very little to energy requirements but up-
stream and downstream operations do. This fact In profitability calculations, it is necessary to
provides the basis for several methods used to keep in mind that a plant erected without reserves
estimate operating costs [13], [23–25]. (standby units) for unavoidable shutdowns and
repairs will produce for only 330 days (or
Key Cost Categories. If it is assumed that 8000 h) a year; that is, it will attain only ca.
chemical plants show relatively constant operat- 90 % of rated capacity on a long-term basis.
ing- cost structures for a given product, operating Manufacturers generally rate their equipment for
costs can be calculated with multiplication fac- operation at 10 % over capacity. However, this
tors if a single cost category is known accurately figure only applies to intermittent overloads and
[22]. is not guaranteed.
258 Chemical Plant Design and Construction Vol. 8

If full-load operation is required all year, the


plant must not be designed as a single-train
(single processing line) facility, unless it is set
up for 110 % capacity and adequate storage is
provided for the finished product. Large storage
areas are needed if sales are seasonal (e.g.,
fertilizers).
Because the feasibility study includes com-
parisons between alternative processes, two pro-
cesses with equal profitability need not be ranked
equally. For example, both may have equal
production costs but different fixed costs.
Fixed costs usually comprise interest pay-
ments and operator wages. Nearly all other costs Figure 6. Schematic showing the course of capital
depend on output and are therefore variable (e.g., investment
a) Accumulated profits; b) Return on investment; c) Total
costs of raw materials, power, and fuel). If production costs (fixed and variable); d) Fixed costs; e) Ac-
market conditions make it necessary to reduce cumulated cash flow
the output to, say, 80 % of rated capacity, the
plant with high fixed costs will become unprofit-
able more quickly. Thus, in the case of two [34], [35], so that alternative proposals can be
equally profitable plants, the plant with the lower obtained with a justifiable amount of effort.
fixed-cost contribution will be preferred. High
fixed costs often have to be accepted, if the need Payout (Payback) Period. If alternatives
for reliable operation dictates that critical parts of are only to be compared, it may be adequate to
the plant must be designed with 100 % standby divide invested capital by gross excess revenues
capacity or the plant must be subdivided into (proceeds from sales minus operating costs).
parallel trains. This method gives a quick indication as to
The profitability calculations must take into whether the investment is attractive. If, for
account that 2 – 2.5 years usually elapse be- example, a value of 3 (payout period 3 years)
tween the start of planning and the commission- or less is obtained, the investment should be
ing of the plant. Interest therefore has to be paid profitable. This does not mean, however, that the
on design and construction costs. Working capi- plant will be completely written off after three
tal is also needed for storage of raw materials and years on stream.
product. Finally, for technical or market-related A more realistic figure can be obtained by
reasons, a period of 6 – 12 months generally including taxes and interest under expenses and
elapses after commissioning before the utiliza- listing revenues by year after commissioning
tion of the plant is sufficient to cover the costs (higher operating costs in the first year when full
(break-even point). Only then does the return capacity has not been reached, future decline in
flow of capital begin. earnings).
The history of an investment is illustrated
schematically in Figure 6. Return on Investment (ROI). In large
chemical companies, investments depend not so
much on the payout period but on whether the
2.3.2. Methods of Profitability Analysis investment will increase total profits, i.e., divi-
dends to the stockholders. Thus a large company
Methods for assessing the profitability of a proj- will only invest if a certain return on invested
ect [1, pp. 285 – 401], [28–33] differ in the way capital is ensured. The ROI method is employed
investment, revenue, and risk are associated. The in such cases. The annual profit before taxes and
three most important techniques are described interest, but after depreciation, is divided by the
briefly below. invested capital. In contrast to the preceding
These profitability calculations are combined method, startup losses are neglected and data
and linked with operations research techniques for design- capacity operation are used in the
Vol. 8 Chemical Plant Design and Construction 259

calculation. The result is a pretax rate of return on ranking, which allows unsuitable sites to be elim-
invested capital. inated quickly. The short list of remaining sites
should then be examined as described below.
Dynamic Calculations are based on the Site Quality, Topography, Soil Conditions,
discounted cash flow (DCF) method. The DCF Climate, Flood Risk. The short list should in-
method is an advance over ROI. It allows for the clude only locations that appear suitable for the
fact that investment costs precede revenues. plant and possible subsequent expansions from
Since only funds existing at the same time can the standpoint of size, price, transportation facil-
be compared, all revenues and expenses that are ities, and buildability.
directly or indirectly related to the project from If the terrain is not flat, it should be established
the start of planning onwards are discounted to a whether grading or filling is necessary and
fixed time, usually the start of production. A rate whether piles must be driven for foundations. If
of return is then sought that makes the sum of the transportation facilities (roads, railroad tracks,
discounted annual excess revenues equal to the water routes) are lacking, the expense of devel-
cash value of the total investment at the start of oping them must be ascertained. Only costs for
production. Since excess revenues are spread developed sites can be compared.
throughout the entire year, they are all recalcu- Raw-Material Availability Including
lated to the middle of the year and discounted Power, Fuels, and Water. Raw materials of good
from then on. The calculation runs over the quality must be available at a favorable price
economic life of the project, but usually only throughout the service life of the plant. Other
10 years, since the longer-term market position prerequisites are availability of sufficient fresh
can scarcely be foreseen. Furthermore, the equiv- water, electric power, and fuels. Obtaining power
alent value of revenues after more than 10 years is and steam on a grass-roots site can be expensive.
so small that it has little effect on the result Environmental Conditions, Environmental
(internal rate of return). Legislation, and Infrastructure of the Con-
struction Site. Improved roads, rail connections,
and location on harbors or year-round navigable
2.4. Site Selection rivers are important criteria.
Long-Term Availability of Qualified
The selection of an optimal site is a high-priority Labor. In developing countries, leading person-
item in the feasibility study. Every economic nel – from foremen to management – must meet
region has its advantages and disadvantages. The very stringent requirements. Only after years of
present and future importance of correct site schooling will local personnel have the required
selection can scarcely be overstated. Wrong site standard of education.
choices cannot be corrected later and have led to Raw-material costs, wages, and maintenance
the downfall of many companies. costs are also crucial in site selection. Finally, it
The development of world trade and the de- must be taken into account that the phase of
cline of tariffs have changed the environment of startup losses will be longer if an industrial site
many existing plants for the worse. Formerly, for has to be developed from scratch.
example, the steel mill was located near the coke
plant and iron ore transported to it. Today, the
most important Japanese steel mills are located 2.5. Decision between Alternative
on the coast and import coal and ore from over- Investments
seas. Petroleum refineries used to be sited at
petroleum sources. Now that giant tankers and Preparation for Decisionmaking. Large
pipelines have come into wide use, refineries are investment projects involve exploration of wide-
often located in consumption centers. ly varying options. In addition to straight profit-
Many large chemical companies are now in- ability analysis, qualitative factors should also be
vesting in coastal and foreign property. Good considered (e.g., special site problems, political
surveys of publications important in site selection environment, market development). These
can be found in [1, p. 439], [36–38]. STOBOUGH qualitative factors involve risks, which must
has devised a selection system, based on a point also be assessed. The preparation phase for
260 Chemical Plant Design and Construction Vol. 8

decisionmaking therefore includes not only cal- access to such good raw-material sources that
culation of investment and operating costs, but the company considering the project cannot com-
also risk and sensitivity analysis [39]. pete. It may be that environmental regulations
have a prohibitive effect on costs. The planning
Risk Analysis. In risk analysis, all constraints work should then be stopped until new informa-
that can have an adverse effect on life- cycle costs tion or analyses suggest a different conclusion.
and earnings must be identified, documented, and The avoidance of huge losses on a badly planned
assessed. These include: facility far outweighs the costs incurred up to this
point. If, however, the feasibility study reveals a
1. Estimation of sales market positive situation, the next step is to incorporate
2. Energy cost development the capital requirement into the company’s in-
3. Availability of raw materials vestment program and give the go-ahead to start
4. Plant construction risks preliminary design.
5. Management-related risks (e.g., site-depen-
dent problems, reliability of vendors and
subcontractors) 3. Preliminary Design
6. Organizational risks
The following results from the feasibility study
The financial effects of the identified risks are provide the basis for deciding to proceed to the
quantified by experts in risk-assessment proce- preliminary design phase:
dures and the results then evaluated in a Monte
Carlo simulation [39]. 1. Plant capacity has been set on the basis of
market research
Sensitivity Analysis. Sensitivity analysis 2. The choice between expansion of an existing
should be carried out to find out how the profit- facility and construction of a new one has
ability and risk situation changes when certain been made
assumptions and constraints are varied. For ex- 3. The list of potential sites has been shortened to
ample, it might be asked how much the invest- two or three alternatives
ment costs would have to be reduced to allow the 4. The projected capital outlay has been
desired profit and an acceptable amortization. determined
A calculation of annual revenues based on the 5. The projected production costs for the product
quantity of product that can be sold in the market have been determined
and its price allows a variational calculation of this 6. The payout time and profitability have been
type to be made. The expected profit is deducted estimated
from the sum over the project life. The remainder
represents the maximum available investment and The main task in preliminary design is to
operating costs that have to be optimized in several obtain a more exact calculation that takes into
steps. This approach is called ‘‘design to cost.’’ consideration all costs up until commissioning.
Investment costs are often minimized in this ap- The first step toward this objective is to work out
proach by designing low- cost plants (usually the engineering details.
open-air plants with simple equipment and no A qualified project leader directs the prelimi-
storage capacity for intermediate products). nary design. Specialist engineering teams (e.g.,
Several iterations are usually required to reach for process calculations, equipment design, plant
an optimum between investment costs and oper- layout, and estimations) provide advisory sup-
ating costs. port [40].

Decisionmaking. Profitability, sensitivity,


and risk analyses may lead to the conclusion that 3.1. Preliminary Design Costs
execution of the project is not desirable. Recent
publications may have already shown that similar The funds and time spent on preliminary design
projects undertaken by third parties will oversat- can be considerable, depending on how pre-cise
urate the market. Other companies may have planning and budget are to be. Although highly
Vol. 8 Chemical Plant Design and Construction 261

accurate results are always sought, technical Contract forms have been developed for the
documentation and calculations should be re- collaboration between the customer and the en-
fined only to the degree necessary for subse- gineering firm in the basic-design and/or detai-
quently deciding whether to implement the proj- lengineering phases, as well as for procurement,
ect. Events during the preliminary design period supply, construction, construction supervision,
may force the abandonment of the project. and commissioning (Section 4.2.2).
If the feasibility study predicts very favor- Another option for cutting design costs is for
able profitability, less accurate calculations (say the chemical firm to obtain a process license, with
 20 %) may be acceptable; if the project is the licenser providing the complete ‘‘basic
expected to be marginally profitable, better design.’’
accuracy (e.g.,  10 %) is needed. Figure 7
[41] shows the basic information required for
given accuracy levels. Even if the upper and 3.2. Final Selection of Site Locations
lower limits of the percentage ranges in Figure 7
are made equal, the probability of exceeding the After the feasibility study two or three suitable
projected costs is greater than that of falling sites are often available for the new plant. A
short of them. This is primarily due to subse- final decision can be made only after detailed
quent additions that are not known at the time study.
when the calculation is performed. A ‘‘contin- If the potential sites are close to the client’s
gencies’’ item is therefore commonly included parent plant, similar fringe conditions can be
in the calculation. assumed to apply for the purpose of site compar-
Design costs for preliminary calculations at ison. If, however, a branch plant is to be erected in
various accuracy levels, according to the Ameri- a foreign country, conditions are usually differ-
can Association of Cost Engineers [42], are pre- ent which means that each of the alternatives has
sented in Table 1. Specific empirical figures are to be carefully analyzed.
given in [43]. Important constraints besides those already
Preliminary design requires a special project listed in Section 2.4 include:
team consisting of persons with the necessary
expertise. A chemical company whose engineer- 1. Medium- and long-term capacity of the local
ing staff is oriented mainly toward maintenance (national) market to absorb the product
and the occasional addition of new pieces of 2. Export to nearby countries
equipment should not attempt to perform the 3. Availability, quality, and price of raw
preliminary design of a large plant or a branch materials
plant in-house. Such a department lacks appro- 4. Political situation and risks (e.g., risk of
priate experience and is also short of capacity. nationalization)
The need to hold down design costs and maintain 5. Tax laws, tariffs, possibility of repatriating
the performance level of in-house engineering profits
staff on their specific tasks, forces even large
chemical firms to collaborate closely with exter- If, for example, one country has cheap raw
nal engineering contractors who will later be in materials but a limited capacity to absorb the
charge of executing the project. External engi- product, partial upgrading of the raw material and
neering firms usually offer cost advantages be- fabrication of intermediate products should be
cause they have so much experience in their considered. Manufacture of the end product
routine fields that they can quickly estimate would then take place where there is adequate
reliable cost figures for projects based on well- long-term demand and a suitable distribution
known processes. network.
The client’s role is limited – at least as far as A team of the client’s experts should perform
established processes are concerned – to making a thorough on-site examination of each alterna-
process knowhow available, purchasing li- tive before the final decision is made; close
censes, and cooperating with the engineering contact with national and local government agen-
contractor in customizing the plant to relevant cies is important. The recommendations of this
requirements. team should weigh heavily in the choice of site.
262 Chemical Plant Design and Construction Vol. 8

Figure 7. Accuracy of cost assessment based on available information [41]


Vol. 8 Chemical Plant Design and Construction 263

Table 1. Design costs for cost estimates [43]

Type of estimate Synonymous terms Accuracy, % Costs as percentage


of project value

Order of magnitude estimate ratio estimate  30 –  50 0 – 0.1


seat of the pants estimate
ballpark estimate
guesstimate
Study estimate evaluation estimate  20 –  30 0.1 – 0.2
predesign estimate
factored estimate
Preliminary estimate sanction estimate  10 –  25 0.4 – 0.8
funding estimate
authorization estimate
budget estimate
Definitive estimate project control estimate  5 –  15 1–3
Detailed estimate tender estimate 2–5 5 – 10
contractor’s final
cost estimate

Partnership with qualified domestic enter- feedstocks and auxiliaries (type and quantity),
prises is becoming increasingly popular (e.g., and local conditions (environmental situation,
joint ventures). elevation, climate, energy situation). This objec-
tive, together with the overall state of the art and
the experience of the operater, licenser, or plant
3.3. Process Design See also ! Process design and construction contractor, provide the
Development, 1. Fundamentals and basis for process selection.
Standard Course Process selection can be done most simply in
the form of a block flow diagram (Fig. 8), in
The feasibility study defines the process objec- which each block represents a unit operation or,
tive, i.e., it specifies products (type and quantity), in complex plants, a plant section containing

Figure 8. Block flow diagram (olefin plant)


264 Chemical Plant Design and Construction Vol. 8

several unit operations. The blocks are joined by On the basis of the process flow diagram, the
lines representing the principal material and preliminary process parameters, and the above-
energy streams. mentioned specifications are used to prepare
The first step in process design is to establish material and energy balances for the process
the operating parameters for the major stages in steps and finally for the entire process. This
the process: objective is not generally achieved in a single
set of computations. The experienced process
1. In the case of chemical reactions, the pres- engineer must use an iterative procedure to mod-
sures, temperatures, concentrations, reactor ify the process flow diagram and/or the process
type, and reactor size are defined or estimated parameters so that a closed material and energy
on the basis of the reaction kinetics and balance is attained as simply as possible. The
experience gathered in existing plants following must always be ensured:
2. In the case of mixing (stirring, gas disper-
sion, suspension) or separation (distillation,
drying, precipitation, filtration) of sub- 1. Compliance with emission limits.
stances, the pressures, temperatures, con- 2. Plant safety (i.e., adequate margins of safety
centrations, and type and size of apparatus relative to critical operating conditions).
are defined or estimated on the basis of 3. Maintenance of product quality.
established rules. 4. Control of startup operations and of planned
and unplanned shutdowns. This includes
If information needed for setting the operat- specification of components and media re-
ing parameters or designing reactors/apparatus quired (e.g., heatup burners, cooling and
is not known, it must be obtained in bench or purge gases, and pressure-reducing valves).
pilot-plant tests or calculated approximately on
the basis of similar reactions or unit operations. These calculations must also take account of
The unit operations used in process engineer- long-term effects, such as increasing contamina-
ing are described in [44–49]. tion (resulting in a higher pressure drop and less
efficient heat transfer) or aging of catalysts
Process Flow Diagram. The next step is to (lower conversion, changes in temperature and
prepare a process flow diagram from the block concentration profiles).
flow diagram. Standard symbols (e.g., defined in The calculations give mass and energy values
DIN 28 004) are used to represent reactors and for all important points of the plant, preferably
other apparatus, including equipment for con- downstream of each unit operation. The mass and
veyance and control of important streams. energy flow rates and the final process parameters
In complex plants, it may be necessary first to are tabulated at the foot of each process flow
prepare a synoptic flow diagram (Fig. 9) and then diagram and keyed to points in the plant
to draw up individual flow diagrams, giving the (Fig. 10).
needed detail for plant sections and auxiliary The preliminary sizes of the reactors and
operations. apparatus are now checked and, if necessary,
modified in the light of the final process
Determination of Final Process Data. parameters.
When the desired effective operating time per If a plant is to be operated at reduced capacity
year has been set (e.g., 8000 h, corresponding to for short or long intervals, appropriate calcula-
91 % availability), the design capacity of the tions must be performed. If unacceptable operat-
plant (i.e., the mass throughput per unit time) is ing conditions or bottlenecks are found in certain
defined. The next step is to compile the specifica- plant sections, additional measures must be taken
tions for all feedstocks, auxiliaries, catalysts, (e.g., supplementary heating, gas recycle, or the
utilities, and end products, and to estimate what partial shutdown of some unit operations). A
intermediate products are to be expected. These similar treatment applies when occasional over-
specifications include relevant physical and loading of the plant is expected.
chemical properties as well as the battery-limit Other factors are then determined, namely the
states of all substances received and shipped. quantities of substances that have to be available
Vol. 8
Chemical Plant Design and Construction

Figure 9. Overall process flow diagram (olefin plant)


265
266 Chemical Plant Design and Construction Vol. 8

Figure 10. Individual process flow diagram for a plant section


a) Heat exchanger; b) Purification tower; c) Control valve; d) Block valve; e) Steam trap; f) Blind; g) Control loop (temperature,
pressure, flow)

for the initial charges and the storage capacities Inc. and SRI International. A survey of produc-
(including those outside the battery limits) need- tion processes for initial and intermediate organic
ed for feedstocks, auxiliaries, intermediates, and products is given in [50].
end products.
Finally, a detailed process description is writ- Process Simulation. Process design calcu-
ten. Assessments of known processes are avail- lations for multistage, interconnected processes
able on a subscription basis from Chem Systems with material and energy recycle soon become
Vol. 8 Chemical Plant Design and Construction 267

very complex. Computer tools enable designers The operating result is primarily determined
to develop key concepts in a reasonable time and by product earnings, expected profit, and costs.
thus to optimize the process according to certain Obviously, costs decrease with longer plant ser-
criteria (investment cost, yield, energy economy, vice life and higher availability. The feasibility
production costs). ‘‘Flow sheeting’’ programs are study should provide data about both of these
complicated computer programs that model unit factors.
operations mathematically and allow them to be Most chemical production facilities are oper-
interconnected. A plant can thus be represented ated around the clock. Since fixed costs represent
as a network of unit operations with material and a significant proportion of the operating costs
energy streams and thus simulated [51], [52]. The (interest payments, personnel, energy supply,
material and energy balances can be calculated as overheads), high availability is essential for an
functions of the process parameters. An iterative optimal result and is often more important than
procedure can be carried out to bring the balances maximal process optimization.
to equilibrium for individual and interconnected Single-train plants with many unit operations
unit operations. in series are more susceptible to breakdowns than
Simulation programs are available for steady- plants in which the critical sections are multi-
state operation and dynamic conditions (e.g., trained or have standby equipment. The draw-
ASPEN PLUS, DESIGN II, PROCESS, HYSIM, back of a larger capital investment must be
and SPEED UP). weighed against the advantage of a higher ex-
Design calculations for reactors and other pected availability.
equipment (e.g., heat exchangers) can be per- In established methods of risk analysis, the
formed with special-purpose design programs and plant concept is systematically analyzed on the
process simulation packages. The program for a basis of process flow diagrams, process descrip-
fired tubular furnace (e.g., steam reformer) allows tion, equipment lists, and operating experience
calculation of process conditions as a function of (e.g., reliability and maintainability, RAM). An
the configuration and geometry of the tubes, bur- initially higher expenditure on equipment not
ners, and combustion chamber. An important func- only results in better availability but also lowers
tion of such programs is to simulate the equipment repair and maintenance costs.
when connected into systems and to identify and Optimization of process engineering must
remedy bottlenecks (de-bottlenecking). then be investigated. The process design ob-
Process simulators have integrated substance jective of a unit operation or a plant can be
data bases that meet the needs of most applica- achieved with various combinations of capital
tions. Further data can be obtained from data costs and variable production costs (feed-
bases [53] and compilations of physical and stocks, auxiliaries, utilities, energy consump-
chemical data [54–56]. Proprietary data and em- tion, disposal) as the following simplified
pirical factors (interactions, long-term effects) examples show:
can also be input.
1. In plants with high gas throughputs, the cross-
sectional areas of piping, fittings, and reac-
3.3.2. Optimization tors/apparatus determine the pressure drop in
the plant and thus the energy that must be
The object of plant optimization is to obtain an expended to transport the gaseous media.
optimal economic result. This is a continual Large cross sections, with correspondingly
problem during the operation of a plant, espe- higher capital costs, lead to lower energy costs
cially if its capacity is diminished by aging or and vice versa.
increased by expansion, or if product earnings, 2. In heat exchangers, such as those used for
costs, or expected profits change during its life- waste-heat recovery, the quantity of trans-
time. The parameters necessary for subsequent ferred heat increases with increasing ex-
optimization must, if possible, be established in change area (¼ higher capital costs) and in-
the design stage. They relate to process design, creasing flow velocities (¼ higher pressure
the plant concept, the selection of equipment, drop ¼ higher energy consumption) and vice
and the process control system. versa.
268 Chemical Plant Design and Construction Vol. 8

In each case, there is an optimum for given If individual cost items in subsequent operat-
economic parameters. The second example is ing periods are expected to deviate significantly
more complicated, because not only must the from the values chosen initially, new calculations
cost optimum for a given quantity of heat be can be made for the few key points, taking
determined but also the optimal quantity of heat maximum and minimum values (sensitivity
to be exchanged. It must further be taken into analysis).
consideration that the cost of waste-heat transfer A practical application of this method is the
to the environment decreases when more heat is comparison of designs ‘‘on an evaluated basis.’’
recovered. The costs for the necessary capital (often with
Similar examples could be cited for the opti- allowance for the expected return on investment
mization of conversions, the optimization of the and tax considerations) and for capital goods are
product mix when products are coupled, and the represented in a formula. The actual require-
simultaneous minimization of byproducts and ments for capital and capital goods are substitut-
residues and of their reprocessing or disposal. ed into the formula. The lowest resultant value
The examples lead to the following conclu- identifies the best concept for the selected pre-
sions: identical plants do not have a unique mises. Details of cost structure and financing
optimum; instead, they have a variety of optima need not be known.
that depend on the crucial technical and econo-
mic constraints of a given site location. Optimal Optimization of Individual Tasks. For the
design of the plant is based on economic para- calculation of various reactor types, see !
meters employed in the design phase. Subsequent Mathematical Modeling and ! Model Reactors
deviations may partly offset one another or may and Their Design Equations.
accumulate in the result. Enthalpy – temperature (H/T ) diagrams and
The objective is thus to assign cost factors to exergy analysis (formerly also availability anal-
the functional dependences of the process design ysis) are being increasingly used in conjunction
or, in mathematical terms, to express the depen- with simulation programs to optimize the energy
dence of the costs on the engineering variables in economy of the plant [57]. This is especially
the form of a cost function. Limiting parameters worthwhile for processes with high heat turnover
always have to be introduced, e.g., emissions, or high compression ratios. Apparatus costs must
plant reliability, product quality, and safety fac- be determined separately.
tors for equipment and material (to ensure maxi- The design of heat-exchanger networks is
mum lifetime and on-line time). Optimization based on analysis of the heat fluxes in the network
can be solved by a suitable method (linear and as a whole. One representative of such methods is
nonlinear optimization, mixed-integer program- the Linnhoff ‘‘pinch’’ method, see ! Pinch
ming, gradient and search procedures). Technology. This technique uses the H/T dia-
The large number of variables in a plant gram with cumulative curves for the quantities of
design and the high degree of interaction in plants heat dissipated and absorbed in various sections
with many process loops mean that a facility of the plant at defined temperatures. The method
cannot be completely optimized during the de- can be applied to utility systems and to the
sign phase. The dimensions of such a program integration of thermal engines [58]. Software is
exceed any reasonable and justifiable computer available for the design of heat-exchanger net-
effort. works by this method (e.g., HEXTRAN and
It is useful to begin by performing an eco- ADVENT). An alternative method for heat-ex-
nomic – technical analysis of the process based changer/utility networks is based on the
on the ‘‘standard design’’ (not yet optimized). mixed-integer method [59].
This analysis reveals the process stages in which Synthesis-gas processes offer an example of
significant fractions of the costs are incurred, integrated loops. These reactions are mostly
consumed, or transformed, and expresses them exothermic, and an attempt is made to transfer
as a proportion of the total costs. As a rule, a few the excess heat of reaction to steam instead of
key points dominate the economics of the entire cooling water. Use of waste heat from gas
plant. Optimization work can thus be facilitated production to supply the heat required for gas
right from the start. purification and converting processes has led to
Vol. 8 Chemical Plant Design and Construction 269

a variety of integrated loops with significant Process data processing systems print data in
reductions in operating costs, for example in the form of diagrams, graphs, and tables. They
ammonia and methanol synthesis and in the are an indispensable aid in the commissioning
production of nitric, sulfuric, phthalic, and and optimal operation of plants. Process-based
maleic acids. simulation programs allow on-line and off-line
Another optimization possibility is the use of balancing and prompt detection of abnormal
heat pumps. The mechanical compression of occurrences.
vapors and their condensation at higher pressure
offers interesting solutions with relatively low
investment costs, for example in the distillative 3.3.3. Safety Aspects and Environmental
separation of components with similar boiling Control
points (e.g., such as ethylene – ethane and pro-
pene – propane). In the following section the essential elements of
The operability and economics of integrated safety and environmental control are treated –
loops must be checked during process design. relevant to the design and construction of a
This can be done by using LINNHOFF’s method of chemical plant, using Germany as an example.
heat integration analysis [60], [61]. The laws and decrees cited are only valid in
Germany, however, there are similar laws in
Process Synthesis. The development of op- other countries, e.g., those issued by the EPA
timal combinations of unit operations is an itera- and OSHA in the United States and the ‘‘Stoom-
tive process that is now carried out with the aid of wezen’’ in The Netherlands.
simulation programs. An advanced program per- The materials present in a chemical plant,
forms computer-aided process synthesis by au- their processing, and processing equipment con-
tomatically generating design variants and se- stitute a source of risk to persons and property in
lecting the best ones under consideration of the plant area and its surroundings. The level of
uncertain data, i.e., when material properties, risk depends on the nature, extent, and probabili-
thermodynamic data, and kinetics of partial pro- ty of occurrence of injury or damage [66]. Safety
cesses are incomplete. Results can be applied to engineering institutes measures that reduce (lim-
some practical problems [62–64] especially to it) the risk to a degree acceptable to the public
heat-exchanger networks (HENs) and utility require that:
systems.
The design of separation processes is much
more difficult because of the great number of 1. Potential hazards must be identified
species present. Process synthesis has therefore 2. Effective safety standards against these ha-
not reached a comparable level. A survey of the zards must be established
design of column cascades appears in [65]. 3. The standards must be transformed to engi-
Optimization has to be customized for every neering and/or management safety practices
application, key points can be identified only by 4. It must be proved that the safety level meets
economic and technical analysis of a process. requirements
The boundaries between ‘‘routine’’ optimization 5. The effectiveness of the adopted measures
during process design and a special, supplemen- must be evaluated and improved [67]
tal optimization study are not clearcut. The
practical operability of a plant should never be Safety-related functions are the responsibility
ignored. Overly complicated circuits, highly of governmental supervisors, the plant operator,
complex control systems, dewpoints and corro- and the engineering contractor. In approving the
sion limits that are too close together, and in- plant, the regulatory authorities not only ratify
creased maintenance costs can all wipe out cal- the safety objectives but also evaluate the scope
culated cost savings. and quality of the safety measures. The operator
Continuous optimization is needed through- is responsible for correct execution of these
out the service life of a plant. Digital process measures. The design and construction firms
monitoring and control systems allow appropri- must assist the operator in complying with the
ate data acquisition, storage, and archiving. standards [68–70].
270 Chemical Plant Design and Construction Vol. 8

3.3.3.1. Protection Against Emissions into a system approved by the local authority
[82], [83].
The following important environmental protec- Wastewater produced in case of fire (fire fight-
tion goals are necessary for the approval of a new ing water) must be collected in a retention basin
plant and are therefore the concern of authority whose capacity is usually sufficient to hold the
engineering: water used in 1 h against the design fire- case [84].

Landscape and Surroundings. The erec- Soil. Soil protection is afforded by sealing
tion of a plant on a site not expressly intended all plant areas that might be contaminated by
for industrial use can run into difficulties [71]. It hazardous liquids or solids under normal operat-
is also necessary to clarify in advance what ing conditions or in an accident [85].
effects the plant will have on nearby residential
areas and what levels of emissions and noise are Waste. ‘‘Waste’’ denotes all those sub-
acceptable in industrial areas [72–75]. stances and parts that cannot be recycled to the
The appearance of the plant must be appro- production process or otherwise reused.
priate for the surroundings. This factor is gov- As early as the process selection step, special
erned by restrictions on building height, design, attention must be paid to waste prevention be-
materials, color, the construction of visual bar- cause waste is difficult to dispose of. In large
riers, and landscape plantings. chemical complexes, wastes from one process
can often be used as feedstocks in other proces-
Air Pollution. Pollution control begins with ses. This alternative should be investigated close-
the classification of hazardous substances and ly in feasibility studies performed at a very early
prevention or minimization of emissions to the stage of the project [86–88].
atmosphere. Release under normal operating
conditions is prevented by using appropriate 3.3.3.2. Noise Control
design and process conditions (e.g., gas collec-
tion and recovery systems, use of low-polluting The primary objectives of noise- control design
burners, catalytic gas purification, use of high- are in compliance with contractual and legal
quality flange connections and seals) [76–78]. provisions while ensuring that the plant is easy
Safe operation of a chemical plant must be to maintain and runs economically. Noise can be
ensured to prevent or minimize the hazard to the controlled at the source by selecting low-noise
surroundings. Possible sources of danger (acci- products and processes. Low-noise equipment
dents) include release of large amounts of haz- often has the welcome side effect that it offers
ardous substances (gases, liquids, solids), fire in low energy consumption and longer service life.
the plants, and explosions [72]. Basic concepts and research in acoustics are
Safety aspects must be taken into consider- discussed as examples in [89–92].
ation in process design, plant layout, and equip-
ment selection; in the construction, operation, Regulations. Noise- control regulations are
and maintenance of the plant; and in the training intended to protect the surroundings and the plant
of plant personnel [69]. personnel.
The ‘‘hazard and operability study’’ (HAZOP)
is often used and can reveal weak points in plant Protection of the Surroundings. The basis
equipment and operation while the facility is still for immission noise limits in Germany is the
under design. This method of risk analysis has Bundes-Immissionsschutzgesetz (Federal Im-
been proven in years of use [79–81]. mission Control Act) and the TA L€arm (Engi-
neering Directive on Noise Control) contained in
Wastewater. The wastewater generated in a it [93]. The directive lays down permissible
plant is collected and treated in systems classified immission noise levels as a function of land use
according to water quality (e.g., severely con- (Table 2). The site of measurement varies; as a
taminated, moderately contaminated, uncontam- rule, it is 0.5 m in front of an open window of the
inated, rain water). If the systems are properly residence. Regulatory practice has been to treat
designed, the treated wastewater can be released the permissible levels cumulatively: if several
Vol. 8 Chemical Plant Design and Construction 271

Table 2. Permissible noise immission levels Design. The engineering firm must guaran-
Type of builtup area Standard value, dB(A)
tee compliance with noise regulations at the
workplace and in residential areas. The contract
Day Night should also stipulate the type of noise measure-
Exclusively industrial utilization 70 70 ment and the operating conditions at the time of
Mainly industrial utilization 65 50 measurement.
Equal housing and industrial 60 45 Planning for noise control begins in the pre-
utilization liminary design phase and continues through
Mainly housing areas 55 40
Exclusively housing, health 50 35 basic and detail engineering. The engineer must
resorts, and hospitals carry out the following activities:

1. Calculate the permissible sound level for the


plants emit to one receiver, the maximum level entire plant on the basis of the maximum
must be distributed among all the emitters. Fur- level allowed in the residential area and
thermore, if a plant is expanded, its permissible available studies on the workplace noise-
noise-level contribution must not be exceeded. level limits.
This approach ensures that the permissible total 2. List noise-producing components and estab-
noise level in the residential area is not exceeded. lish their permissible sound levels. Noise-
On the other hand, new plant sections are only protection practices are dictated by practical
approved if they meet strict noise standards. and economic considerations.
3. Prepare noise specifications (including per-
Protection of Plant Personnel. The basis for missible sound levels) as part of the bid
noise regulations at the workplace in Germany specifications for all noise-emitting
comprises the Arbeitsst€atten Verordnung (Work- equipment.
place Regulation) [94] and the relevant sections 4. Check the bids (e.g., for machinery, control
of the Unfallverh€utungsgesetz L€arm (Accident valves) to ensure that noise requirements are
Prevention Code) [95] which contain references satisfied.
to DIN standards and VDI guidelines. These 5. Compile specifications for silencers, hoods,
regulations set a maximum personal noise level and insulation; check bids and orders for
of 85 dB(A) for an 8-h shift and recommend the these items.
use of personal hearing protection above 85 dB 6. Compile noise specifications for the
(A). Personal hearing protection must be worn at building.
levels over 90 dB(A). 7. After the design is complete, write a design
The most important regulations for plant de- report on residential and workplace noise
sign follow: levels.
8. Inspect installation of equipment at the con-
struction site.
Measurement of noise at DIN 45 635 part 1,
machines and following parts
9. Measure noise levels of noise-generating
Average level and assessed level temporal DIN 45 641 equipment at the workshop where it is man-
fluctuating sound processes ufactured, and also later when it is installed
Sound propagation in the open VDI 2714 in the plant and the plant is on stream.
Assessment of working noise in the VDI 2058 sheet 1
neighborhood
10. Prepare a final report.
at workplace regarding danger to hearing VDI 2058 sheet 2
with regard to various occupations VDI 2058 sheet 3 Manufacturers of noise-generating equipment
Sound projection from industrial construction VDI 2571 have many ways of reducing noise. Examples
Noise from piping VDI 3733
Noise abatement for ventilation and air VDI 2081
follow:
conditioning plants
Personal soundproofing VDI 2560 Electric motors: Reduction of cooling air re-
Soundproofing by mufflers VDI 2567 quirement, use of low-noise cooling fans, use
Soundproofing by shielding VDI 2720
sheets 1 þ 2
of improved insulation.
Soundproofing by metal cladding VDI 2711 Control valves: Division of large-expansion
cross sections into smaller areas (perforated
272 Chemical Plant Design and Construction Vol. 8

cage), division of pressure release into multi- cal burdens on the employees caused by working
ple stages, optimized flow control. and other conditions must be limited to a gener-
Air coolers and small cooling towers: Reduction ally accepted level. Measures must also be taken
of rotor peripheral velocity, modification of to prevent or control risks in case of an accident
blade profile, increase in number of blades, [70].
use of low-noise gears. The occupational safety and health authorities
Pumps: Optimization of impeller design, avoid- have defined general conditions for ventilation,
ance of cavitating conditions, reduction of lighting, and ambient temperatures at work-
impeller peripheral velocity (below 45 m/s). places, protection against weather and noise, and
Steam generators and process furnaces: Low- the safe use of traffic routes inside the plant.
noise, forced-air burners; use of ceramic-fiber Accident insurance regulations are especially
linings on interior walls. important for plant layout and process design of
Compressors: Frequency- controlled drives, chemical plants. These rules concern: harzardous
low-noise oil systems, direct drives (no gears), operations, work involving hazardous substances
low-noise surge-limit control. [77], [78], use of special auxiliary equipment,
and ergonomic design of the workplace [96].
Important secondary practices of noise abate- Suitably equipped ‘‘social’’ facilities such as rest
ment include: and changing rooms, washrooms, toilets, and
medical stations must also be included in the
1. Soundproof enclosures design [94].
2. Soundproof hoods and barriers Warning of unavoidable dangers must be
3. Soundproofing insulation on piping, ducts, given, and appropriate protective measures
and machine housings must be instituted (e.g., signs marking fire or
4. Silencers in the form of absorbers, resonators, explosion hazard zones and appropriate safe-
or combinations of both types guards against ignition). Escape routes and
protected areas with emergency lighting, fixed
In most chemical plants, on-battery sound personal protection facilities (emergency
pressure levels can be held to 85 dB(A) by means showers), and alarm systems must be provided
of careful design. Large compressor sections are [94], [97].
an exception; levels up to 100 dB(A) can be Appropriate layout of buildings and apparatus
expected and such areas must be designated as or enclosures around particularly dangerous
high-noise areas. equipment help to minimize injuries and damage
Investment costs for noise control normally [96].
range from 0.5 to 3 % of total plant material and Effective fire fighting measures include short
installation costs. These percentages are ex- access routes as well as fixed or mobile fire-
ceeded if residential restrictions make it neces- extinguishing equipment with an assured supply
sary to enclose the entire plant. of extinguishing media and an adequate action
Plant safety and reliability must not be im- radius.
paired by noise- control measures. Low-noise Occupational safety and health measures also
machines must therefore be preferred over loud apply during construction of the plant. They
machines with soundproof enclosures. If hoods relate to the structural design and size of the
or enclosures cannot be avoided, accessible areas plant and the construction methods. As much as
inside noise enclosures on gas-handling devices possible of the equipment used in subsequent
must be provided with adequate ventilation, gas normal operation of the plant must be available
alarms, and possibly fire fighting systems. Noise- during commissioning for protection of the
control barriers and shielding must not block workers [96].
escape routes.
3.3.3.4. Plant Availability
3.3.3.3. Occupational Safety and Health
Capacity and profitability calculations for a
The principal requirement in occupational safety chemical plant are normally based on 8000 h/a
and health is that physiological and psychologi- on-stream (corresponding to roughly 330 d/a).
Vol. 8 Chemical Plant Design and Construction 273

Shutdowns are generally planned at intervals Allowance must also be made for operator
of one or two years to allow cleaning of heat error so that consequential damage (e.g., over-
exchangers, apparatus, and piping; charging of heating or pressure buildup in uncontrolled
new catalysts and chemicals; replacement of exothermic reactions) can be avoided. Auto-
worn mechanical parts; and prescribed inspec- matic emergency-shutdown devices are pro-
tions by regulatory authorities. vided for such cases. They are often redun-
Unplanned shutdowns are usually caused by dantly included in both the measurement and
mechanical defects or automatic emergency shutdown systems. They must be regularly
shutdowns when operating parameters are out- inspected by the plant operator or the regula-
side the limits for normal plant operation. tory authorities.
Important items of equipment are duplicated
(standby equipment) to ensure continuous oper- 3.3.3.5. Authority Engineering
ation between scheduled shutdowns. This is
standard practice for continuously operated The construction and operation of chemical
pumps and reciprocating compressors. Standby plants are affected by many legislative provi-
turbine compressors are not necessary because of sions and regulations that are concerned with
their longer maintenance intervals. In auxiliary environmental protection and plant safety [68].
systems (e.g., the lubrication system), however, These requirements have major consequences
the necessary reliability is provided by installing for plant design and construction. It is no
standby pumps and filters. longer sufficient to comply with all laws,
If operating conditions make regeneration or standards, and specifications applicable to a
cleaning necessary during production, standby given plant at a given site. Instead, a formal
equipment is again used (e.g., fixed-bed reactors, approval process, usually with public partici-
molecular-sieve adsorbers, dryers, and filters). pation, must be gone through in the design
Piping (as used to convey suspended solids or phase. Only then can construction of the plant
powders) may be susceptible to plugging. Instal- begin [98], [99].
lation of standby piping or flushing connections The length of the approval process depends on
may be desirable. the type of plant, the environmental sensitivity of
Measures to ensure reliable plant operation the plant site, and the nature of the approval
during power outages must be considered at an procedure. Another important point is whether
early stage (emergency planning). the project involves expansion of an existing
The drives of important process equipment facility or an entirely new ‘‘grass-roots’’ plant
(e.g., cooling-water pumps, instrument-air com- on a previously nonindustrial site.
pressors, boiler feedwater pumps) are usually The time taken for an application for a con-
dual (electric motor plus steam turbine). struction permit to be approved is usually six
Emergency power-generating units are need- months to a year, but sometimes longer. This is
ed to maintain safety-relevant drive and control preceded by a lead time of about a year, during
functions (including emergency lighting, com- which the conditions for the plant are discussed
munication facilities, and computer-aided pro- and preliminary talks are held with the regulatory
cess control systems) during power outages. In authorities. The total span from the investment
the case of particularly critical equipment, a decision to groundbreaking is therefore about 1.5
separate power source (e.g., battery, instru- years. This is a substantial fraction of a total
ment-air reservoir, nitrogen reservoir) must be project duration of 2 – 3 years.
provided to bridge the startup time of the emer- The granting of construction and operational
gency generator. permits requires close collaboration between the
Control functions and process control systems plant owner, the engineering firm, and the au-
play a vital role in reliability and safety. Relevant thorities (Fig. 11). All activities aimed at devis-
process parameters and the points where they are ing an approved plant concept are grouped under
to be measured must be defined during process the heading ‘‘authority engineering’’ and are
design so that indicators and alarms will warn the usually the responsibility of the engineering firm.
operating personnel promptly whenever operat- Typical activities carried out during the design
ing conditions become abnormal. phase are listed below.
274 Chemical Plant Design and Construction Vol. 8

Figure 11. Principle flow scheme of German authority approvals procedure

Feasibility Study/Preliminary Design. 3. Which regulations, especially local ones,


The feasibility study and preliminary design must be complied with?
include technical and economic optimization of 4. What is the public opinion at the intended
the process with minimization of environmental- location?
ly harmful factors. The following parameters are 5. Has any nearby project gone through appro-
established val proceedings recently? If so, with what
result? How much time did the proceedings
1. Nature and quantities of substances present take?
2. Waste and residues 6. Will special restrictions over and above nor-
3. Wastewater mal legislation and regulations apply to the
4. Emission of air pollutants site? [75], [100], [101].
5. Type and design of plant equipment
6. Nature (open or closed) of processing In order to clarify these points, informal contact
systems with the regulatory authorities should be initiated
7. Safety and reliability standards [77], [78] as soon as the initial concept of the plant is set.

As soon as site selection is complete, the Process Design/Basic Engineering. Re-


following questions must be answered: sults obtained during the preliminary phase are
used for process design/basic engineering (e.g.,
1. Which authorities are responsible for approv- for planning off-gas collection and combustion
ing the construction and operation of the systems and wastewater systems). A preliminary
plant? safety analysis may be useful to identify potential
2. Which laws must be observed? risks (e.g., threat to the environment due to
Vol. 8 Chemical Plant Design and Construction 275

release of substances, or risk to the plant due to 3.4. Basic Engineering


hazards in the vicinity). This kind of analysis is
called an environmental impact study [73]. The The focus has so far been on process design
results of such an analysis may influence the plant (process flow diagrams and parameters such as
layout [72], [75]. operating temperatures and pressures and flow
rates). Now the geometric dimensions of indi-
Detail Engineering, Construction, and vidual equipment items, the design temperatures
Commissioning. Many authority engineering and pressures, the materials of construction, and
activities take place in the detail engineering the layout of the entire plant must be established.
phase. They include: (The main elements of basic engineering docu-
mentation are described in Section 5.1).
1. Preparation of project documentation
2. Preparation of a detailed safety analysis
3. Engineering escort duty during approval 3.4.1. Equipment Specification from the
proceedings Process Engineering Standpoint
4. Implementation of design changes required
during approval proceedings Equipment dimensions and capacities are dictated
5. Management of partial approval procedures by the process. Data from the process flow sheet
that take place in parallel with the main can be used for the sizing of process equipment,
approval procedure machinery, piping, etc. Examples of data that can
6. Selection of experts and technical cooperation be derived in this way are the diameter, number of
with them to clarify detail questions raised trays, and tray spacing for distillation towers.
during approval proceedings These design data are entered in process engi-
neering data sheets (Fig. 12) that contain all
The activities of engineering and authority relevant specifications for the specialist engineer.
engineering must be well coordinated if the For example, the data sheet for process equipment
progress of work at the construction site is not includes a schematic drawing with overall dimen-
to be held back. sions, operating and design pressures and tem-
An important point for the success of a peratures, number and nominal diameters of noz-
project is that the engineering activities con- zles and manholes, material of construction, cor-
cerned with early civil work activities should be rosion allowance, insulation thickness, etc.: in
taken care of early. This is especially important short, the information that the equipment design
for the plot plan and buildings; escape, emer- engineer needs in order to perform strength cal-
gency and access routes; and fire fighting culations and prepare a more detailed drawing.
concept. For pumps, the data sheet must show normal,
The authorities grant partial approvals (e.g., maximum, and minimum flow rates, inlet and
for civil work, erection, and commissioning of outlet pressures, operating temperature, material
plant sections) so that progress is not unneces- of construction, type of medium, and physical
sarily delayed. They also check that relevant properties of the medium. On the basis of this
regulations and provisions are observed during information the mechanical engineer can select
construction and installation. When construction the optimal pump with the best efficiency.
is complete the entire plant is examined by the Specifications are prepared similarly for con-
authorities. Deficiencies must usually be reme- trol systems, safety valves, and all other items of
died immediately. The authorities only grant plant equipment. The nominal diameters of pip-
permission for commissioning when the accep- ing are calculated for the specified flow rates,
tance report has been made. physical properties of the streams, and economi-
During commissioning proof of compliance cally acceptable pressure drops.
with approved levels of emissions, wastewater
values, etc. must be submitted. Measurements 3.4.2. Materials of Construction
are difficult to perform and time consuming. If
improvements to the plant are required at this See also ! Construction Materials in Chemical
stage, they may be very expensive. Industry.
276 Chemical Plant Design and Construction Vol. 8

Figure 12. Data sheet with process information for a deethanizer


Vol. 8 Chemical Plant Design and Construction 277

Materials of construction in chemical plants Steels for hydrogen service at elevated tem-
must be able to withstand mechanical, chemical, perature and pressure
and thermal stresses and must not be attacked by
Chemical attack together with thermal and me-
the medium with which they come in contact.
chanical stresses:
Two criteria must be met:
Ferritic chromium alloy steels
Austenitic chromium – nickel steels
1. Materials must be approved for use in pres-
Ferritic/austenitic steels (duplex steels)
sure-bearing parts under the pertinent regula-
tions, i.e., their guaranteed values, processing,
The selection of steels for predominantly
and permissible service conditions are defined
mechanical stress depends on strength, tough-
and can be reproduced at any time.
ness, and weldability. States of mechanical stress
2. Materials must be suitable from the corrosion
in individual parts are often incompletely known.
standpoint. Their behavior and properties
Design is therefore based on approximate rules
should show little or no change under the
derived from simple loading modes (tension,
action of the media with which they come in
crushing, bending). The time dependence of load
contact.
(e.g., static or cyclic) must also be considered.
The operating pressure, operating tempera-
Material selection should be solved by close
ture, and number of load cycles are crucial for
collaboration between the materials specialist,
strength calculations of apparatus and piping.
the designer, and the process engineer or chemist
The temperatures determine the strength (yield
[102–109]. The materials most commonly em-
point). The use of fine-grained structural steels,
ployed in process engineering are unalloyed,
with higher yield points than normal carbon
low-alloy, and high-alloy steels. Both solid steel
steels allows design of equipment with thinner
and cladded steel fabricated by rolling, weld
walls and thus results in significant savings in
overlaying, or explosion bonding are used in
weight and welding work.
vessels, towers, heat exchangers, storage tanks,
Equipment must be sized so that it does not
piping, and other equipment.
fail by ductile fracture, brittle fracture, fatigue, or
creep (Table 3).
Stresses. Materials of construction must
The choice of steels for chemical service, or
withstand temperatures from ca.  180 to
where chemical attack occurs together with ther-
1100  C and pressures from vacuum to several
hundred bar. mal and mechanical loads, is difficult because
The selection of a material is dictated by three several types of corrosion are possible, each
criteria: mechanical stress, thermal stress, and resulting in a different type of failure. The prob-
chemical attack. Seldom do these three types of lem of material selection in this case is often very
stresses occur singly; the usual case, in which two complicated because corrosion is due to multi-
or all three are present at once, governs material component systems.
selection.
The most important ferrous materials used in Alloys. Corrosion-resistant alloy systems
have been developed which form a passive layer
plant construction, are the following steels:
that affords protection against corrosion. Such
Predominantly mechanical stress: alloys must remain stable during subsequent
Structural steels treatment (e.g., welding) so that phase precipita-
Fine-grained structural steels tion does not affect the passivity of the material.
Quenched and tempered steels The most commonly used alloy systems for
Steels for low-temperature service chemical plant construction are those based on
iron, nickel, and copper. Figure 13 shows these
Coexisting mechanical and thermal stresses: three groups schematically, with the maximum
Steels for high-temperature service concentrations of the alloying elements singly or
High-strength alloy steels for high-tempera- in combination. A great number of alloys with the
ture service desired properties can be produced with these
Heat-resisting steels systems.
278 Chemical Plant Design and Construction Vol. 8

Table 3. Nature of failure of materials

Nature of fault Cause Measure

Ductile fracture unacceptably high loads calculation with elasticity limit or safety correction values
Brittle fracture stress also below the permissible elasticity calculation of the brittle fracture safety with fracture
limit by influences from mechanical values on the basis of
1) multiaxial state of stresses the combined effect of material faults and
2) thermal stress stresses
3) state of material highly dependent on
4) state of defect 1) material production
5) geometry of component 2) quality of manufacture
3) fault finding and
4) fault description with nondestructive testing
Fatigue introduction of crack and crack propagation calculation with conventional strength values for
by alternating stress alternating stress (e.g., fatigue limit) taking into account
all stresses as with the danger of brittle fracture
fatigue crack propagation at existing fault sites consideration of mechanical fracture principles and
their mathematical utilization
Creep, time interval time-dependent deformations and fractures at high 1) calculation with creep strength
temperature and stresses below the 2) calculation of time yield limit
elasticity limit 3) crack propagation by existing defects

Other metals and alloys used in plant con- Corrosion. For a detailed description of
struction are aluminum, titanium, zirconium, and corrosion, see ! Corrosion, 1. Electrochemical,
tantalum. See also ! Construction Materials in ! Corrosion, 2. High-Temperature. Corrosion
Chemical Industry. phenomena (e.g., selective corrosion, diffusion,
crevice corrosion, and pitting) must be given
special attention but are not amenable to design
calculations.
The most frequent form, general corrosion,
can be dealt with by appropriate corrosion al-
lowances of ca. 1 – 5 mm. The corroded mate-
rial must not, however, interfere with the process
or affect the product (discoloration or flavor
changes in the pharmaceutical, beverage, and
food industries).
Charts, tables, empirical values, and proces-
sing guidelines are available for material selec-
tion according to corrosion criteria. Carbon
steel, for example, is attacked only slightly by
water, but severely by water in the presence of
air. Pitting occurs if air-containing water is
heated, or if oxygen is present in steam and
condensate piping; this often rules out the use of
carbon steel. Although stainless steels resist
many media, they also suffer pitting or stress
corrosion cracking in the presence of halogen
compounds.
Material selection has to take into account
both the chemical nature and the flow of the
medium. Rapid motion of a liquid along a pipe
wall can accelerate corrosion, whereas a protec-
Figure 13. Alloy systems most commonly used in chemical tive film often forms on the surface when the
plant construction velocity is low.
Vol. 8 Chemical Plant Design and Construction 279

Intergranular stress corrosion cracking may For large plants, the planner begins with
be caused, for example, by alkaline solutions 1: 500 layout sketches that merely show the
above 100  C under pressure in welded vessels space required for individual units. Such prelim-
of unalloyed steels. inary layouts are used to determine the most
Transgranular stress corrosion cracking can expedient arrangement with possible transfer
occur in equipment made of austenitic Cr – Ni points at battery limits for material and energy
steels, while crevice corrosion results from im- streams. Conventional layout techniques employ
proper fastening of tubes in tube sheets; these adhesive films and overlaying of transparent
types of corrosion are both accelerated by vibra- sketches; PC and CAD programs are also finding
tions (corrosion fatigue). use.
Electrolytic corrosion can take place when The layout should include approximate data
metals widely separated in the electrochemical on the positions and sizes of storage areas for raw
series (e.g., copper, iron, and aluminum) are not materials, intermediates, and end products, as
insulated from one another in the same piece of well as pipe bridges, roads, underground piping,
equipment apparatus and come in contact with and sewerage. Control room and electrical sub-
conductive liquids. stations, compressor buildings and service facil-
Other corrosion-related problems are hydro- ities, and road and rail connections are shown
gen embrittlement, embrittlement at low temper- with their overall dimensions. The accessibility
ature, and high-temperature corrosion. of plant equipment for repair and maintenance,
The same degree of corrosion protection can construction aspects, safety, and inspection must
often be obtained with several materials. In such be considered from the very start. The conse-
cases, price, service life, and profitability must be quences of later expansion must also be taken
balanced [110]. into account.
Costs can be saved by applying more noble If the existing information is adequate, the
materials as a coating or cladding. Electro- layout should be drawn to scale. The layout and
plated coatings cannot be employed in chemi- the process flow diagram then permit assessment
cal plant apparatus because they do not offer of the production sequence, mass transport, and
long-term protection. Claddings of nonferrous storage (Fig. 14).
metals, their alloys, or austenitic steels can be On the basis of the layout and specifications,
used if the contact between the corrosive buildings should be inserted next as needed
stream and the load-bearing steel shell of an (ground plan, number of floors, height between
apparatus can be prevented by appropriate floors).
design. Layout Model. The layout can also be made
In simpler cases, plastic coatings can be em- into a block model (Fig. 15). Layout models have
ployed in place of cladding. Stoving finishes proved especially useful for complicated instal-
(duroplastic) have proved suitable for contami- lations such as refineries and petrochemical
nated cooling water and weak acids in heat plants. They convey a general impression of the
exchangers (service up to 240  C). Polytetra- final appearance of the plant, even at an early
fluoroethylene coatings are highly resistant to stage. Approximate 1 : 100 or 1 : 50 models of
acidic and alkaline substances (up to 300  C). equipment items are made of foamed polystyrene
Rubber and hard rubber, respectively, are effec- or a similar material and can then be moved
tive against weak acids and salt solutions up to ca. around to establish suitable positions and
þ 100  C. It should be kept in mind that plastic spacings.
coatings tend to swell and unbond in the presence The layout model includes steel structures
of organic substances, especially at elevated but does not cover the details of pipe runs. It
temperature. mainly serves as a basis for discussion, permit-
ting a number of fundamental questions to be
clarified.
3.4.3. Plant Layout At this stage of basic design (at the latest),
the design engineer is thus able to decide which
The layout becomes a high-priority item during parts of the plant will be outdoor or enclosed
basic engineering [111]. facilities, and whether it will be on one or more
280 Chemical Plant Design and Construction Vol. 8

Figure 14. Plant layout plan


a) Steam generation; b) Process steam generation and fuel oil system; c) Oil wash with dispersed oil separator; d) Propene –
propane separation; e) Debutanizer; f ) Depropanizer; g) Deethanizer; h) Condensate and slop system; i) Hydrogen
methanization; j) Hydrogenation; k) Propene refrigeration; l) Ethylene refrigeration; m) Charge gas compressor; n) Caustic
wash; o) Water wash with gasoline stripper; p) Cracking furnaces; q) Substation, transformer station; r) Control room;
s) Social facilities; t) Ethylene – ethane separation; u) Charge gas dryer; v) Acetylene conversion; w) Demethanizer;
x) Cold box; y) Compressor house; z) Pumps, compressors

levels. A process plant should be outdoors ings. Pumps, in contrast, are usually placed out-
unless there are pressing reasons to enclose it. doors; they are installed in pump houses only if
This allows substantial savings in construction this is necessary on environmental grounds (e.g.,
costs; machinery and equipment remain more for noise protection).
accessible; and the danger of fire and explosion Production facilities that are sensitive to am-
is reduced for processes involving flammable bient conditions (e.g., film and fiber production,
materials. The outdoor setting, however, entails paper mills, pharmaceutical plants, catalyst
more expense for shelter against weather, heat, plants, packaging facilities) must be set up inside
and cold. buildings. Raw materials and products that are
For some types of plant equipment, the layout sensitive to moisture and sunlight must be stored
criteria are nearly always the same. For example, in covered areas or enclosed buildings.
turbocompressors, reciprocating compressors In contrast to the solidly constructed buildings
and their drives; coolers and oil circulation lines required in Europe, buildings in tropical regions
should be located in sheds or compressor build- can be lightly constructed. Sheds open on two
Vol. 8 Chemical Plant Design and Construction 281

Figure 15. Layout model (hydrocracker complex), courtesy of Lurgi AG

sides, affording protection against wind and rain 5. Significant dimensions of equipment and
only, may be adequate if the process does not call machinery
for climate control. 6. Essential data on materials of construction

3.5. Calculation of Plant Costs


3.4.4. Preliminary Piping and
Instrumentation Diagram Once the engineering documents for the calcula-
tions at the requisite accuracy are available, plant
A piping and instrumentation diagram, based on costs can be determined. It is useful to employ a
the process flow diagram, is needed for more scheme as shown in Table 4 for this. A ‘‘stan-
accurate calculations at the preliminary design dard’’ scheme has been proposed by ARIES and
stage. For the basic engineering package it should NEWTON [112] and other authors. The calculation
contain the following information: is subdivided into three groups of items: equip-
ment, bulk materials, and indirect costs; each has
1. All equipment and machinery, drives, piping to be calculated differently.
or transport routes, and fittings (including The equipment group includes all itemized
installed spares) plant equipment such as towers, reactors, and
2. Nominal diameter, pressure, material of con- heat exchangers, vessels and machinery that are
struction, and design information of piping calculated ex factory without packaging. These
3. Field instruments, control devices, and con- items are normally specified individually in en-
nections between them gineering design allowing a rapid, detailed, pre-
4. Special fittings required for process control liminary calculation to be made.
and safety, e.g., check valves, safety valves, The bulk materials group covers items such as
level gauges, condensate drain lines pipes, control systems, electrical equipment and
282 Chemical Plant Design and Construction Vol. 8

Table 4. Example of a calculation scheme for plant costs as a whole and cannot be determined until the
Designation % of 1 % of 1 % of 1 % of 1
equipment and bulk materials costs are known.
þ2 to 3 to 4

Equipment
Columns 12.5 7.4 4.7 3.4
3.5.2. Equipment
Reactors 6 3.5 2.2 1.6
Heat exchangers 22.5 13.3 8.4 6.1 Because most pieces of equipment are ‘‘tailor-
Tanks 18 10.6 6.7 4.8 made,’’ manufacturers’ price lists are not often
Furnaces 10 5.9 3.7 2.7
Machines 26 15.3 9.6 7
available for cost calculations. The best way to
Other equipment 5 3 1.9 1.4 get accurate prices is to submit enquiries to the
Total 1 100 59 37.2 27 manufacturers. This can be done on the basis of
Bulk material the design specifications, but applicable stan-
Steel structures 8.3 4.3 3.1 2.2
Piping 25 14.7 9.3 6.7
dards (e.g., DIN or ASA), design specifications,
Control systems 15 8.8 5.5 4 and acceptance conditions (e.g., AD-Merkblatt
Electricals 9.5 5.6 3.5 2.5 documents, ASME Code, TÜV, Lloyd’s) must
Noise abatement 0.7 0.4 0.3 0.2 be indicated. Such inquiries are, however, time-
Catalysts 2.5 1.5 0.9 0.6
First charges 1.2 0.7 0.4 0.3
consuming and make a great deal of work for the
Spare parts 7.5 4.4 2.8 2 vendors; they are accordingly unwelcome.
Total 2 69.7 41 25.8 18.5 Therefore inquiries are only made with compli-
Total 1 þ 2 100 cated equipment and machinery. Simpler items
Package units
Erection (including 43 27 19.5 are estimated on the basis of in-house documents.
material for An engineering firm normally has a data base
insulation containing important data (including weights
and painting) and prices) on all equipment and machinery
Civil work 16 10 7.2
Total 3 59 37 26.7 covered by orders and inquiries in recent years.
Total 1 þ 2 þ 3 100 The data base must be kept up to date, this
Other costs requires close cooperation with the purchasing
Packing 3 2.2 department. Armed with such a system, the firm
Transport 2 1.4
Insurances 1.5 1.1 can make fairly accurate estimates, for example,
Planning costs 14 10.1 of the cost of heat exchangers per square meter or
Supervision of 5 3.6 per kilogram, given the size, type, pressure, and
construction material of construction. The same holds for
Commissioning 4 2.9
Allowance for 4 2.9 towers, reactors, and vessels; here also the size,
inflation pressure, temperature, and material must be
Unforeseen 5 3.6 known. The costs of simple machinery can be
Total 4 38.5 27.8 determined similarly. The use of computer pro-
Total 1 to 4 ¼ 100
project costs grams makes it an easy matter to calculate the
weights of equipment items.
Before such prices are incorporated into the
estimate, correction factors must be determined
materials, insulation, and paint. Exact determi- so that current prices can be obtained. There are
nation of these costs is expensive and time con- two reasons for such a correction:
suming and can be done only on the basis of
detailed material takeoffs (MTOs). This group 1. The figures stored in the data base cannot be
also takes in civil work, structural steel and completely up to date, and there may be a lag
erection work. of half a year or more before the order is issued
2. Purchase prices depend not only on market
Other Costs include engineering, procure- trends but also on the economic situation of
ment, construction supervision, commissioning, the manufacturer
travel costs; price inflation during the construc-
tion period; insurance, duties, and contingencies. The use of such a data base system necessi-
These items can be only calculated for the project tates the availability of appropriate cost-index
Vol. 8 Chemical Plant Design and Construction 283

figures for price adjustment. More information necessary to perform a preliminary static calcu-
on cost-index figures is given in Section 2.2.1.5. lation so that the foundation size and/or the
number of piles needed can be determined more
accurately. The other civil-work items are often
3.5.3. Bulk Materials handled by means of multiplication factors.
The same holds for structural steel, although
Provided the engineering documentation (layout, here the costs are found in terms of the weight and
piping and instrumentation diagrams etc.) is the price per tonne for heavy, medium, and light
exact enough (see Fig. 7, Section 3.1), bulk ma- steel construction.
terial costs can be calculated fairly accurately by
applying unit prices (per piece, m, m2, m3, kg, Control Systems. The trend toward plant
etc.) to material takeoffs. Installation costs are automation and increasingly strict safety stan-
also derived from takeoffs classified according to dards have increased the contribution of control
functional disciplines (unit prices for construc- systems to plant costs. The degree of sophistica-
tion activities plus costs of site preparation, tion of the control system of a chemical plant
erection equipment, materials, etc.). If unit prices depends strongly on the future operator. Accord-
from an in-house data base system are used for ingly, it is often impossible to work with general
bulk materials, they must be adjusted in the same multiplication factors. Costs are therefore calcu-
way as equipment prices (see Section 3.5.2). lated from the number of control circuits, re-
Another option is to obtain detailed current quired computer capacity, number of displays
unit prices from the manufacturers or construc- and control panels, etc. Multiplication factors are
tion contractors. This method yields accurate used only for installation materials.
results, but is time consuming and involves high
costs. It should therefore be employed only when Electricals. Since the number and sizes of
a highly accurate estimate is needed. electric motors are normally known from the
The engineering documents available in the detailed equipment estimate, it is relatively
design stage are usually incomplete. The trend in simple to determine cost-intensive electrical
bulk materials estimation is therefore toward items such as motors, transformers, switchgear,
applying multiplication factors to the estimated and cables. Costs for other items, such as
total equipment costs. The latter can be obtained grounding, lightning protection, lighting, and
only, however, by analyzing projects already installation materials are handled with multipli-
realized. In order to achieve satisfactory accu- cation factors.
racy, separate multiplication factors must be
derived for each plant type and each process. Erection. The determination of equipment
The larger the number of facilities evaluated, the installation costs on the basis of unit-weight
more accurate are the multiplication factors. The formulas gives adequate accuracy; it is also
percentages given in Table 4 represent multipli- simple because the cost of major equipment
cation factors for the individual cost items of a (other than machinery) is usually based on
typical chemical plant; normally, material and weight. A similar method can be used for ma-
construction costs for a bulk item are determined chinery, but the calculation process is often
separately. Other multiplication factors are pub- divided into equipment setting (unit-weight for-
lished in [7]. mulas) and equipment alignment (hourly basis).
If the required accuracy is 4  10 %, how- Installation costs for bulk material items (e.g.,
ever, these two estimation approaches are control systems, electrical, insulation, and paint)
combined. and for catalysts and first charges are usually
determined by applying multiplication factors to
Civil Work and Structural Steel. For the material costs.
structures such as compressor houses, control The civil work discussed above normally in-
rooms, laboratories, and workshops the enclosed cludes installation costs. Erection costs for struc-
volume is usually determined and the costs esti- tural steel are established on the basis of unit-
mated by using unit costs. In the case of adverse weight installation formulas and subdivided into
soil conditions or heavy structures, it may be heavy, medium, and light steelwork.
284 Chemical Plant Design and Construction Vol. 8

Serious difficulties arise in the accurate esti- prepared for each functional discipline. The latter
mation of piping installation because the exact is more accurate.
material takeoff and the exact routes of pipe runs Itemized Equipment Approach. The num-
are seldom known. The labor cost of installation ber of hours per equipment item can be referred to
depends on the number of welds and flange the work done on each item; all equipment items
connections, pipe diameters, wall thicknesses, are then added together with multiplication fac-
materials of construction, and installation tors for other functional disciplines. Alternative-
heights. Estimation is therefore done with unit- ly, a total number of hours per equipment item
weight prices tabulated for each nominal diame- can be determined for all functional disciplines.
ter or nominal-diameter group. A separate calcu- This total number of hours varies widely, de-
lation is needed for each material of construction. pending on the processes employed, the scope of
Installation costs can also be estimated from authority engineering, and existing design docu-
the number of welds per meter of straight pipe ments. It generally lies between 600 and 1200 h
and the nominal diameter but this requires de- per equipment item. This method can be used
tailed knowledge of the piping design. only if experience has been gathered with exist-
Vendors normally offer package units, such as ing plants of the same type.
cooling towers and refrigeration units, including Calculation Based on Documents to be
installation; the entire scope of supply and in- Prepared. The estimation of man-hours based
stallation costs given in the bid specifications can on the number and size of drawings and docu-
therefore be incorporated in the calculation as a ments presupposes a great deal of experience in
lump sum. project execution and the availability of docu-
The calculation of the construction of a plant ment breakdowns from earlier projects (includ-
must also cover the costs of site preparation, ing empirical figures for the hours spent on all
utilities, construction equipment, transportation other activities, such as procurement and expe-
equipment, scaffolds, site roads, fencing, secu- diting, dealing with vendors, and inspection of
rity, first aid, and other items. equipment). This procedure also calls for an
exact definition of the individual services (ser-
vice catalog) so that the various functional dis-
3.5.4. Other Costs ciplines can be clearly isolated from one another.
In practice, a blend of the two methods of calcu-
Bulk material costs are commonly determined lation is often used.
for each section of the plant, whereas ‘‘other’’ After the man-hour requirements for engi-
costs are calculated for the project as a whole. neering and procurement of a project have been
Multiplication factors are employed for items determined, they are subdivided into categories
such as packaging, shipping, insurance, price and multiplied by appropriate hourly rates to
escalation, and contingencies. determine the costs. Travel, communications,
Before the contingency factor is established, it reproduction, computer costs, and the cost of the
is necessary to make certain that the calculations model must be added.
for the various functional disciplines do not
contain any multipliers of this type, since other- Construction Supervision Costs are often
wise contingency amounts grow out of control. obtained by applying multiplication factors to the
Engineering, procurement, construction supervi- equipment and bulk materials groups or to the
sion, and commissioning costs are, however, engineering hours. A better, slightly more com-
usually determined individually. plex method is to determine the costs on the basis
of construction and manpower schedules.
Engineering and Procurement Costs. In The manpower schedules include supervisory
addition to the approximate method of obtaining personnel for the functional disciplines used by
engineering and procurement costs by applying the operator and the engineering contractor; also
multiplication factors to plant costs, two more the installation specialists provided by the man-
accurate methods are available: calculation of ufacturers of complex apparatus, machinery, and
engineering hours and procurement hours on the package units; and supervisory personnel, if any,
basis of equipment items or the documents to be assigned by the licenser.
Vol. 8 Chemical Plant Design and Construction 285

In contrast to engineering costs, estimates are 3. Travel expenses for personnel not belonging
based not on hours but on person-days and daily to the company
rates. These rates normally include accomoda-
tion and food costs for personnel. The calcula- Indirect Costs. Other indirect costs can ac-
tion must also cover overtime, travel expenses, count for a large portion of investment costs.
and costs for the construction office and its They are:
operation.
1. Licensing fees
Commissioning Costs. The costs of 2. Land costs
commissioning relate to the time from the end 3. Land development costs
of erection to the start of production. They are 4. Fees for government inspections and
also classified as investment and must therefore approvals
be incorporated into the estimate. Commission- 5. Financing costs
ing usually lasts one to three months, but up to six 6. Administrative costs and costs for possible
months for very large multistage plants. This cost expansion of sales organization to market the
group includes the following items: product
Personnel Costs. Personnel costs are gener- 7. Public relations work to inform the public
ally determined in the same way as installation about the new plant
supervision costs. 8. Working capital, such as raw materials stocks
and finished product storage
1. Operating personnel on a rotating shift
basis
2. Laboratory personnel on a rotating shift basis
3. An on-call installation crew who remedy 3.6. Conclusion of Preliminary Design
mechanical problems and/or reinforce the Phase
shift crew in the workshop
4. Specialists assigned by vendors for commis- The last step in preliminary design is the prepa-
sioning special equipment and machinery ration of a report containing the following
5. Consulting or supervision by licenser’s information:
personnel
6. Possible increased deployment of process and 1. The updated feasibility study.
specialist engineers from the operator’s engi- 2. Profitability calculation with graphs of accu-
neering department mulated revenues and expenses, the break-
7. Consultation or supervision by personnel be- even point, and profits (similar to Fig. 6,
longing to the engineering contractor Section 2.3.1). If a clear decision in favor
of one of the alternative investments is pos-
Other Commissioning Costs. These costs sible, the profitability calculation is limited
have to be estimated case by case. For routine to a single proposal. If, however, entrepre-
processes where most products are directly mar- neurial questions figure in the analysis, the
ketable, raw material, auxiliary, and fuel costs report should include the two best alterna-
can be virtually neglected. In larger, more inno- tives.Inaccuracies in the primary documents
vative plants running difficult processes, these and the amounts added to allow for these
costs may be very high. Further difficulties may should be established and specified in all
arise if the market for a new product has to be calculations.
created. Other commissioning costs are divided 3. Schedule for financing requirements.
into 4. Schedule for personnel requirements.
5. Time schedule for the phases of execution up
1. Training of company personnel (possibly in to the start of production.
the licenser’s facility) 6. The project manual containing all the studies
2. Raw materials and auxiliaries as well as utili- and results from preliminary design (basic
ties needed to replace defective charges or engineering documentation), including the
product not up to specification estimate.
286 Chemical Plant Design and Construction Vol. 8

4. Contract Writing and Forms of because inevitable setbacks and lost time on
Contracts going from the pilot plant to a first production-
scale facility (‘‘scaleup risk’’) usually cost more
4.1. Licensing Agreements than a process license.
In acquiring a process license, company A
Process development has become so expensive will commonly be confronted with one or more
that development costs can seldom be covered by of the following possiblities:
royalties. Aside from government-funded re- Case 1. To date, company B has only built its
search, new processes are developed chiefly by own full-scale plant. It has not yet granted any
production-oriented chemical companies or pet- licenses to third parties and therefore has no
rochemical concerns, which regard license fees as design documentation on plants with different
incidental income. In cases where engineering feedstocks and utilities, as needed by A for its
firms hold licensing rights, they either arise from plant. B is not prepared to guarantee third-party
license agreements with production companies or plants, but only to offer a patent and know-how
represent improvements to established processes. contract. Once such a contract has been signed, it
Licensing agreements may relate to patent permits A to examine the operating records and
licenses (rights to use granted patents, Sec- assemble the documentation needed for the pro-
tion 4.1.1), process licenses (which include pat- jected plant.
ent rights and all know-how, Sections 4.1.2 and Case 2. Company B is interested in world-
4.1.3), and straight transfers of know-how for wide licensing of the process, maintains a large
processes not protected by patent (Section 4.1.4). in-house engineering department, and has
worked out the complete process design. In
addition to the license and know-how contract,
4.1.1. Patent Licenses B will offer guarantees, and may even be ready to
undertake engineering, procurement, construc-
Suppose chemical company A has developed a tion supervision, and commissioning with sepa-
process that is under patent protection but is rate billing for these services.
wholly or partly covered by the earlier protection A variant of this case is when B has developed
of chemical company B. Company A will seek to the process in collaboration with an engineering
join B by exchanging patent rights, a mutual contractor and granted exclusive use or construc-
grant of rights to use the patents, or the purchase tion rights to that company. Here again, licensee
of a patent license from B. Usually, company B A cannot seek competing bids because the pro-
asks for compensation in an amount that depends cess is a ‘‘monopoly.’’
on the age, the importance of its rights, and the Case 3. As in case 2, B owns the process
degree of overlap. This fee only covers the design and is prepared to give guarantees in the
particular use in question. The licenser does not context of a license and know-how contract. B
disclose experience above and beyond the pub- leaves it to licensee A, however, to select an
lished contents of the patents. If the fee asked is engineering contractor to construct the plant.
too high for A or there are doubts about the Company A requests competitive bids from sev-
validity of B’s patents, then in the absence of an eral engineering firms, each of which must enter
agreement A can either seek to have the courts into a confidentiality agreement regarding the
declare B’s patents invalid or can disregard them working documents delivered to it. Licenser B
and risk legal action by B. will opt for this procedure when its patents have
given it the lead on the market for a long enough
time and disclosure to several engineering con-
4.1.2. Process Licenses tractors will lead to the wider use of the process
and generate royalties.
As a further example, B has plant-scale experi- Case 4. Since patent protection for processes
ence while A only has experience with a pilot declines in value with age, it is in B’s interest to
plant for the same or a similar process. Even if the secure its know-how to the maximum extent.
new process is clearly an improvement, it is Accordingly, B will hand over the acquisition
expedient for A to purchase B’s experience and licensing rights to one or two trusted
Vol. 8 Chemical Plant Design and Construction 287

engineering firms in the form of a license agree- ing firms are able to undertake all design, supply,
ment (which may be exclusive or nonexclusive, and plant construction tasks, including commis-
for stated countries or for the world). Licensee A sioning. Competitors offering the same process
can then acquire process rights, engineering, and will design different plants because of their
plants only by contracting with one of these different design and construction experience. In
engineering companies. comparing bids, the customer must therefore
Process licensers usually give limited guar- consider not only the price, but also the refer-
antees on the functioning of the process and ences, guarantees, and quality of the bidders.
product quality, but their liability commonly Production companies granting licenses only
extends only to half of the license fee. Commis- tend to guarantee the typical basic features of the
sioning assistance is generally given – in special process (yield and product quality). They never
cases, after training of the operating personnel in take responsibility for plants erected by third
B’s own plant or another licensee’s plant. In parties. Engineering firms thus see an opportuni-
developing countries, licenses are only granted ty to guarantee the whole plant. This is, of course,
with long-term management contracts, which only possible when the company has built many
many banks require as a condition of financing. plants and has wide experience and knowledge.
For profitable processes, royalties amount to The licenser generally remunerates the engineer-
1 – 4 % of the product value for the life of the ing firm for this aid by paying it part of the royalty
patent, but for at least 10 years. A running royalty in return for the additional responsibility.
is a license fee levied on a specific measurable If the engineering firm has no special experi-
quantity of production from a specified technol- ence, it will supplement the licenser’s process
ogy. A paid-up royalty generally represents the guarantee with a guarantee of correct engineering
current value of 10 years’ royalties and is thus design; in the case of supply contracts, it will
equal to 5 – 6 times an annual royalty. If supply relieve the customer of some risk by giving a
contracts are in effect, the royalty may also be material and price guarantee. Depending on ex-
calculated in terms of the plant value (e.g., 5 % of perience, the firm may also guarantee the capaci-
the value of the entire facility or 10 % of the value ty of the plant and the utilities consumption
of the process facility proper) or as a fixed within stated tolerances. When processes are
amount per unit product, often with price escala- licensed from the licenser either directly or via
tor clauses. an engineering firm, it is important for the licens-
er to ensure that ‘‘secret know-how’’ remains
secret and that the exchange of experience, in-
4.1.3. Process Licenses via Engineering cluding supplementary discoveries of the licens-
Contractors ee (feedback), remains confidential. Naturally,
the licenser will compensate the licensee for
Cooperation with engineering contractors often economically valuable improvements.
increases the licenser’s chances of obtaining
additional revenue by licensing its entire operat-
ing know-how. The licenser simultaneously re- 4.1.4. Know-How Contracts via
duces the load on in-house engineering capacity Engineering Contractors
because the external engineering firm bears the
main load of establishing engineering documen- The know-how contract is a modification of the
tation, interpretation, and training. Licensing is process license agreement. When patent protec-
therefore being increasingly handled by engi- tion ceases, the process licenser attaches great
neering firms who check and extend the process importance to keeping its undisclosed know-how
documentation and may also optimize some secret. This know-how is given to a few engineer-
equipment items or process steps. Improvements ing firms under strict confidentiality agreements,
are possible when new operational know-how which are binding on the firms’ employees. Com-
has not yet been implemented as redesigns in the panies interested in the construction of plants may
licenser’s first full-scale plant; this is difficult be told solely what has already been published.
with good processes because of market require- They can only obtain more precise information
ments (supply contracts for products). Engineer- after having signed a secrecy agreement.
288 Chemical Plant Design and Construction Vol. 8

The texts of know-how contracts are compa- A unique feature of the plant design and
rable to those of license agreements, but the fee is construction business is that these risks are gen-
lower. The activity of engineering firms and any erally cumulative, so that both the investor and
guarantees they might give are similar to those the engineering contractor must practice risk
discussed under license agreements. management, i.e., measures aimed at identifying,
Some engineering companies have often man- assessing, and limiting risks.
aged to improve current processes that are no Since the investor and the engineering con-
longer protected so that new applications result. tractor deal with potential risks in different ways,
In most cases, however, the activity of such firms the formulation of a plant construction contract
is limited to simpler processes (e.g., gasification between these parties is extremely important:
and gas purification), unit operations, or improve- both parties must be satisfied that their interests
ments in thermal economy, automation, environ- are protected.
mental protection, and disposal technology. Generally, there is no benefit to the investor in
looking too hard for every competitive advan-
tage. This is especially so when the engineering
4.2. Design and Supply Contracts with contractor may fall into the danger of trading off
Engineering Contractors plant quality for savings as a result of accepting
below- cost prices and unsatisfactory conditions;
Should an investor bring in an engineering firm such shortcuts often become apparent only after
to construct its plants? This question arises the plant is on-stream. As a rule, sharp competi-
whenever the investor does not have adequate tion forces engineering firms to seek an optimal
in-house engineering capacity. In the following outcome at minimum cost. These considerations
sections it is assumed that the investor needs an have promoted cooperation between investor and
outside engineering contractor for a construc- engineering contractor and have become crucial
tion project. points in contract drafting.

4.2.1.2. Selection and Award Criteria


4.2.1. Selection of Engineering
Contractors The investor develops his own criteria for se-
lecting an engineering firm to carry out a con-
4.2.1.1. Importance of Risk in the Plant struction project. Bid invitations and bid com-
Business parisons are used to award a contract that is
acceptable to both parties. The most important
The intention to build a chemical plant presents criteria follow:
the investor and the candidate engineering firm
not only opportunities for success but also risks.
The erection of a large plant entails above-aver- 1. Does the engineering firm have experience or
age, qualitative and quantitative risks. The fol- references relevant to the tasks it may have to
lowing features of the large-plant business are perform?
crucial in risk assessment: 2. Does the firm have experience in the country
and locality where the plant is to be built
(logistics) ?
1. Complexity and duration of the project 3. Is there a danger of communications problems
2. Responsibility for long-term operation of the during execution of the project (language
plant barrier) ?
3. Transfer of investor’s entrepreneurial risks to 4. What kind of staff situation exists within the
the engineering firm and vice versa engineering firm? Will it be able to organize
4. Priority of the project in investor’s and engi- good project management?
neering firm’s business results 5. What standards and specifications will govern
5. High financing budget the work? Can the engineering firm ensure
6. Heavy dependence on market development of compliance with standards that may be new
the product and unfamiliar to it?
Vol. 8 Chemical Plant Design and Construction 289

6. What references does the firm offer with 12. Deadline for bid submission.
regard to the quality of supply and services 13. Period for which bid must remain binding.
and compliance with time schedules? 14. General conditions.
7. Is the firm’s credit rating adequate for the
requirements of a large contract? A qualified engineering firm may still decide,
not to submit a bid – possibly because it sees too
In the bid invitation, the investor states what is little chance of realization of the project or a
wanted and required with regard to the technical chance of success in the face of stiff competition.
concept (process technology, scope of delivery The simplest approach to bid comparison is to
and services, quality requirements, etc.) and the prepare schedules of prices, delivery times, terms
commercial concept (type and contents of con- of payment, terms of delivery, exclusions, and
tract, financing, marketing, etc.). miscellaneous conditions. Large investor com-
A thorough, detailed bid represents a signifi- panies send preformulated tables to bidders,
cant cost to the bidder. A company will only especially for standard processes; the bidder
make this investment if it has a good chance of merely has to enter the services, exclusions, and
winning the competition. The bid invitation must miscellaneous conditions.
therefore be written in a clear, understandable The differences found in the bid comparison
manner so that the potential bidder can precisely should be analyzed and then discussed with the
identify the task to be performed. bidder. Discussions are often time consuming
In order to make bids comparable, all bidders and should be carefully planned. An efficient
must be given the same documents and informa- negotiating program should cover the following
tion. The bid invitation should always include the topics, in order:
following:
1. Fundamentals, infrastructure, overall con-
1. General description of project with site lay- cept, process engineering, economics
out plan. 2. Equipment, material, and services to be pro-
2. Services and deliveries desired (e.g., basic vided; exclusions
engineering and know-how, complete engi- 3. Special and general conditions; guarantees
neering, complete engineering plus procure- 4. Price
ment assistance, delivery with or without 5. Time schedule, including intermediate targets
construction and commissioning).
3. Precise data on the process or process stages
to be covered by the bid. If the bidder does 4.2.2. Form and Content of Contracts
not have rights to the process, the invitation
must state whether the process license is also 4.2.2.1. Basic Concerns in Contract Writing
to be covered or whether this will be handled
by the investor directly with the process In writing the contract, both the party inviting
licenser. bids and the bidder can propose, negotiate, and
4. Production capacity and product quality. conclude agreements. The elements of the con-
5. Available feedstocks, auxiliaries, and utili- tract must therefore cover all those aspects that
ties (composition and quantity available). the potential contracting parties deem not satis-
6. Availability of electric power and water for factorily governed by other provisions (usually
construction purposes. by relevant legislation).
7. Available infrastructure (e.g., workshops, Efforts to reach contractual agreement aside
laboratories, warehouses, and social from relevant legislation are primarily devoted to
facilities). making the potential risks manageable. Details
8. Overall time schedule. on contract drafting can be found in [37], [38],
9. Guarantees desired for production, quality, [113–115].
consumption rates, materials, date of Since the profit margins of the engineering
completion. contracting business are small, it is important to
10. Pricing terms of payment desired. identify, assess, and allot all risks. For a multi-
11. Standard codes and guidelines to be applied. million-dollar project differences of a few tenths
290 Chemical Plant Design and Construction Vol. 8

of a percent can decide whether a bid is accepted 3. The liability provisions set forth in the con-
or rejected. tract should bar recourse to liability laws
Often the only other possibility for absorbing because these do not make appropriate allow-
risks is the contractor’s profit, which averages ca. ance for the special features of the plant
2 – 4 % of contract value in the plant design and construction business.
construction business. Such a small margin can 4. No liability for indirect or consequential da-
only cover limited cost overruns on a single mages, such as lost profits, loss of use, and loss
project. of production. From the engineering contrac-
Methods of dealing with potential risks at the tor’s standpoint, this is a nonnegotiable
contract drafting stage can be classified into two clause. If such liability were accepted, the
groups. First, each of the parties must consider existence of even financially sound contract-
the well-established policies of its company. The ing companies might be endangered.
extent of potential risk for the company resulting
from deviation from such a policy governs which 4.2.2.2. Contract Types and Provisions
person in the company hierarchy has the power of
decision. The person in charge of the negotiations Although there are many types of contracts, the
must therefore know when the limits of his following are particularly important:
jurisdiction have been reached. The decision
whether to accept or reject conditions proposed Engineering Contract. An engineering
by the other party must then be passed on to an contract normally governs compensation for en-
appropriately higher level in the company gineering and procurement services, and the
hierarchy. supervision of construction, and commissioning.
Second, there are modifiable (dispositive) It usually provides for reimbursement of inciden-
goals for the negotiating parties. The limits of tal costs such as travel, communications, com-
negotiability (breaking points) are reached when puter support, and accomodation.
one or the other party’s willingness to make The contract can be for complete engineering,
compromises has been exhausted or when accep- including procurement and supervision at the
tance of the other party’s proposals would result construction site up to the successful completion
in incalculable risks. of the guarantee run.
As a rule, the engineering contractor has to The contract may, however, be limited to
decline to accept liability for indirect and partial services, such as basic engineering, de-
consequential damages. Furthermore, the con- tailed engineering, procurement services,
tractor cannot be held responsible if postpone- supervision of construction, supervision of
ments of deliveries and services occur as a commissioning, and supervision of third-party
result of circumstances beyond his control engineering services.
(e.g., war, revolution, strikes). Other possible An engineering contract does not include
breaking points include excessive guarantee delivery of plant equipment or the performance
requirements. of plant construction. The procurement services
The engineering contractor will reject a pro- that may be included are generally carried out ‘‘in
posal for unlimited liability. Limitations on lia- the name and on behalf of ’’ the investor.
bility include: The contractor’s liability in an engineering
contract extends to correcting design errors at
1. Limitation of total liability for delays and/or no cost to the investor, and often includes a
nonattainment of process guarantees and/or percentage of costs incurred as a result of
for costs incurred for the correction of design correcting problems in equipment or during
errors in equipment or during construction construction.
and installation.
2. Time limits on the guarantee for materials, Reimbursable Contract. In the reimbursable
typically x months after commissioning of the contract, every hour of work performed by the
plant; if commissioning is delayed and this is engineers and procurement staff is paid for, plus
not the fault of the engineering contractor, a all incidental costs. Proof of working hours is
‘‘not later than’’ date must be agreed on. required.
Vol. 8 Chemical Plant Design and Construction 291

A reimbursable contract offers an advantage truck used to transport the equipment to the
when the scope of work is not well-defined (so construction site. The engineering contractor’s
that it is impossible to determine a fixed price) or responsibility can, however, extend to the receipt
when abandonment of the project is anticipated. of equipment on site.
The hourly or daily rates specified in the A turnkey contract includes the provisions of
contract are often classified by category. The the supply contract, plus construction services. If
contract must state what is included in the hourly the engineering contractor does not have the
rates (e.g., salary, other payroll costs, workplace personnel resources for construction work, it
costs, profit). generally subcontracts this work to specialist
An important drawback of this type of con- firms but assigns its own management and su-
tract is that the investor can strongly influence the pervisory personnel to maintain single-line re-
contractor’s execution of the project. Because the sponsibility to the investor.
scope of engineering services is generally not In supply and turnkey contracts, all goods and
adequately defined, control of the service budget services are procured in the name and on behalf
is difficult. of the engineering contractor. The contractor
thus assumes liability to the investor for the
Reimbursable Contract with Target Price. mechanical functioning of equipment as provid-
In this type of contract, the engineering contrac- ed by the contract. In turn, the liability risks
tor accepts a share of the risk for staying within associated with this material guarantee are
the calculated service costs. A target price is set shifted to the relevant suppliers and subcontrac-
on the basis of the calculated costs; the engineer- tors. Similarly, the engineering contractor will
ing contractor generally takes a certain percent impose penalties on the suppliers and subcon-
participation in any overrun, but receives a bonus tractors for late delivery or installation to reduce
if the work comes under the target price. its own time risk.
The target-price provision can also extend to Supply and turnkey contracts are based on a
equipment and construction costs. A sufficiently lump-sum price, sometimes with a provision for
exact definition of the services is required so that price escalation. In order to keep the price risk
a fairly reliable calculation is possible. The in- quantifiable, the bid must be based on a detailed,
vestor gains the advantage of better budget accurate definition of the scope of deliveries and
control. services for the plant to be erected.

Lump-Sum Engineering Contract. If the 4.2.2.3. Essential Elements of a Contract


bid invitation for a chemical plant defines the
scope of work well enough, a lump-sum bid can The structure and delimitation of scopes of de-
be prepared. This type of contract has the advan- livery and work are very important, especially
tage for the investor that the budget is set in because these factors affect liability questions,
advance (provided no additional work is needed contractual provisions, and the negotiation pro-
in the course of the project). The engineering cess. They are expressed in the form of
contractor has much better control over the proj-
ect with regard to costs (man hours) and sche- 1. Specifications of services
dules. In contrast to the reimbursable contract, 2. Description of the scope of delivery with
the investor has a limited say in decisions taken delivery boundaries
during the project. 3. Guarantees and liabilities
4. Criteria for handing the plant over to the
Supply Contract, Turnkey Contract. As a investor
rule, a supply contract commits the engineering
contractor to provide engineering, and supply of Specification of Services. Although the
all plant equipment and materials needed for the specification of technical and commercial ser-
construction of a complete chemical plant. The vices is not usually problematic from the stand-
contract must define the limit of responsibility of point of contract law, it is often highly relevant as
the engineering contractor for plant equipment; a basic fact and for later reference. Since this
the boundary may be the ship, railroad car, or specification normally comprises a very large set
292 Chemical Plant Design and Construction Vol. 8

of documents, it should be formulated as one or parts subject to wear. A period (e.g., 12 or 18


more appendices to the contract. Much unneces- months) is defined in which repair or replacement
sary discussion between the contracting parties is undertaken by the contracting party or suppli-
can be avoided if the specification of services is ers at no cost to the investor.
carefully prepared in detail and states clearly
what services must be performed by whom. Process Guarantees generally relate to the
It is useful to prepare a list of services for the capacity of the plant, product quality, and the
project, which can be based on the specification consumption figures for utilities such as steam,
services contained in the bid invitation, as well as cooling water, and electric power.
in the bid. Any modifications made in the course The contract should state the conditions used
of contract negotiations must be incorporated. to verify the process guarantee (e.g., analysis of
The specification of services must also contain feedstock, quality of utilities). Furthermore, it
the detailed conditions and constraints needed to should define the measurement and analysis
carry out the assignment, a procedural description, methods used in the guarantee run and its
and a list of relevant regulations and standards. duration.
The list of services should give a detailed The forms of guarantees are different for
description of technical and commercial services utilities (steam, electric power, fuel gas), where
to be performed, indicating what design docu- a certain amount of over- and underconsumption
mentation is to be prepared (e.g., drawings, data can offset each other, and for plant capacity and
sheets, specifications, flow sheets and sche- product quality, where shortfalls result in
matics, lists, approval documents). penalties.
Moreover, it must be stated which of the If the plant does not meet the agreed figures in
services will be performed by the engineering the guarantee run, the engineering contractor is
contractor, the investor and third parties. given an opportunity to make improvements. If
these are not successful either, the relevant con-
Scope of Delivery/Delivery Boundaries. A tractual consequences take effect.
supply contract must describe the equipment and
materials to be supplied; a turnkey contract must Handing Over the Plant. The criteria for
also define the construction services. In addition, handing the plant over to the investor are usually
the scopes of delivery and work must be delim- stated in the contract. The plant is often handed
ited with respect to third parties. over section by section and/or in phases. Several
The description of the scopes of delivery and forms of handover are employed:
work should contain the most complete list pos-
sible of apparatus and machinery; a description
of electrical equipment and materials and control 1. Transfer to the operational custody of the
systems; approximate quantity requirements for investor : This, as a rule, takes place at the
piping, concrete, cables, and structural steel; and beginning of test operation. The investor’s
a description of construction services. It is not, personnel run the plant under the direction
however, expedient to set down exact numbers of the engineering contractor.
because final data on equipment size, pipe rout- 2. Provisional handover: Provisional handover
ing, etc. cannot be made until the design work is takes place after a report on the successful
under way. Establishing the details too early guarantee run has been signed, or after a ‘‘not
could hinder subsequent optimization of the de- later than’’ date has passed (if the guarantee
sign, this would not be in the investor’s interest. run has not been done for reasons that the
investor has to justify).
Guarantees. Forms of guarantee for chem- 3. Final handover: Final handover comes
ical plants have been devised that are technically after all defects listed in the report made
meaningful and can be verified at a reasonable after the provisional handover have been
cost. corrected.

Mechanical (Material) Guarantees relate Final inspection of the plant, performed by


solely to individual pieces of equipment, but not both parties, completes the handover procedure.
Vol. 8 Chemical Plant Design and Construction 293

5. Execution of the Project project (basic engineering and/or procurement,


and/or construction). The remaining activities (or
Design and construction of chemical plants are the whole project) are executed by an engineer-
complex operations comprising many interrelat- ing firm under contract.
ed activities (Fig. 16). Plant design and the pro-
curement of equipment occupy workers from Basic Engineering is based on process de-
nearly a dozen special engineering and procure- sign (Section 3.3) which is performed during the
ment disciplines. preliminary design phase by the investor, by the
Medium-sized to large projects [contract licenser, or by an engineering firm in close
value (50 – 250)106 DM; (30 – 170)106 $] cooperation with the investor. Process design is
have a design period of approximately 15 – 18 a component of basic engineering.
months and a total project duration (up to Basic engineering documentation includes the
commissioning) of ca. 18 – 24 months. Some process flow diagrams, piping and instrumenta-
100 – 150 engineers and procurement staff are tion diagrams, plant layout, equipment list (bro-
involved at the peak of such a project in the ken down according to plant sections), utilities
design offices alone. distribution scheme, process engineering data
sheets, noise protection concept, electrical equip-
ment list, summary of electrical consumers (one-
5.1. Scope of Work line diagram), data sheets for control equipment
and instrumentation, functional process control
Work on total chemical plant project comprises and instrumentation plan, description of the pro-
basic engineering, detail engineering, procure- cess control system, and soil report.
ment, civil work and erection, and commission- The content and level of detail in basic engi-
ing. (The ‘‘authority engineering’’ activity, in neering documentation is such that detail engi-
which documents are prepared for submission neering can be done (possibly by another engi-
to the authorities having jurisdiction, is generally neering firm) without significant difficulties.
carried out during both basic and detail
engineering.) Detail Engineering. In detail engineering
Depending on its engineering capabilities and the engineering and procurement teams pre-
resources the investor may execute part of the pare detailed plans, drawings, specifications,

Figure 16. Main tasks of project execution


294 Chemical Plant Design and Construction Vol. 8

calculations, and descriptions so that the follow- contract have been passed, the plant is handed
ing steps can be carried out: over to the owner. Minor activities remain that
are carried out by the engineering and/or con-
1. Preparation of bid invitations for all plant struction contractor. This work is specified in a
equipment, material, and services such as punch list and must be completed within a stated
civil work and erection of plant equipment time.
2. Selection of manufacturers, vendors, subcon-
tractors; placing of orders
3. Execution of quality assurance operations at 5.2. Project Organization and
manufacturers’ and vendors’ workshops Management
4. Shipping of plant equipment to the plant site
5. Execution of civil work and erection of plant The design and construction of a chemical plant
equipment within a predefined time and budget calls for
6. Commissioning careful organization of the people working on the
project, a clear definition of their responsibilities
Procurement Services include all activities and competences, and an appropriate manage-
in connection with preparation of bid invitations, ment concept.
evaluation of bids and bid comparisons, and A chemical-plant engineering firm usually
placing of orders. They also involve ensuring executes many such projects, differing in size,
on-time performance of manufacturers and ven- duration, and complexity, at any one time. The
dors (expediting), as well as the planning and contracting firm is geared to this kind of assign-
supervision of the shipping of plant equipment to ment; it often develops its own set of ‘‘tools’’ and
the plant site. is organized exclusively for these activities.
The following description of the relatively
Civil Work and Erection of a facility are complex steps in the execution of a chemical
generally subcontracted to specialist firms by the plant project is given from the viewpoint of an
engineering contractor or by the investor. The engineering contractor. It should not, however,
work is often supervised by the same organiza- be forgotten that investors and/or operators of
tion that does the detail engineering. It must not chemical plants also follow a similar procedure
be overlooked that the construction documenta- to design and construct plants in their own areas
tion prepared by the engineering contractor will of expertise.
not be free of errors, so that corrections have to be
made on-site. Such corrections should be carried
out by the engineering contractor’s specialists. 5.2.1. Matrix Project Management [116],
The contract should state which partner is [117]
responsible for construction execution time and
costs: the investor, the engineering contractor, or The first powerful management concepts for the
(as at large, complex plants) a general contractor execution of complex, single projects were de-
accepting overall responsibility. vised in the United States during the last years of
World War II. It was recognized that existing
Commissioning of a plant comprises all the forms of organization were not suited to the
work done after ‘‘mechanical completion’’ up to solution of complicated armaments assignments
certification of the guarantees embodied in the on a crash basis. This management philosophy
contract. The term ‘‘mechanical completion’’ was subsequently employed in the space pro-
should be defined unambiguously and in detail. gram, and later found use in the industries of
Once ‘‘mechanical completion’’ has been certi- Western Europe. It can be defined as follows:
fied, the plant passes into the custody of the ‘‘Project management is a management concept
builder. Preparatory work for commissioning for the solution of a well-defined problem within
and commissioning itself are usually performed a predefined time subject to a cost framework
by employees of the future operator under the specified for the project’’ [117].
direction of the engineering contractor or licens- Personnel from a wide range of disciplines
er. When the guarantee tests defined in the within a company work on a defined project in an
Vol. 8 Chemical Plant Design and Construction 295

interdisciplinary setting and must be coordinated the technical responsibility for the performance
and directed. This means: of these team members. The project manager
determines the ‘‘what’’ and ‘‘when’’ of a task in
1. Assignment of appropriate personnel to the the project, while the department managers de-
project from functional organizations in the termine the ‘‘who’’ and ‘‘how.’’
company For smaller, simpler projects and projects of a
2. Organization of the personnel into a project repetitive character, which do not keep a project
team for a defined period of time manager busy full-time with management tasks,
3. Designation of a project manager the matrix system can easily be modified so that
4. Establishment of responsibilities and compe- project management is taken over by a qualified
tences for the duration of the project person from a functional department, who also
carries out the required specialist work.
The organization of the project team and,
above all, the responsibility and competences of
the project manager and his colleagues, have 5.2.2. The Project Manager
three basic forms: functional, matrix, and auton-
omous project management. The execution of a project in the matrix organi-
The matrix form of project management, ei- zation concept places heavy demands on the
ther in pure or modified form, is the most suitable project manager [117], [118]. He assumes ‘‘proj-
concept for engineering contractors because they ect responsibility’’ to company management for
perform ‘‘multiproject’’ management. Such an the assigned project: compliance with budgeted
organization represents the best solution for in- project costs, agreed time schedules, and all
tegration of temporary project teams into the contractual conditions, particularly the attain-
company organization. It also ensures that the ment of the agreed quality level.
projects are optimally executed. For the customer, the project manager is the
Matrix project management is characterized first representative of the engineering firm for the
by division of competences (Fig. 17). The proj- project, and also his first partner in discussions.
ect manager is responsible to company manage- The management tasks of the project manager are
ment for the realization of project targets. The to set targets, establish guidelines, promote in-
managers of the functional departments (engi- formation flow, supervise, analyze and correct,
neering and procurement) involved in the project motivate, and report. He must accord the same
are responsible for delegating appropriate per- weight to the interests of the customer as he does
sons to the project team. The managers also carry to his own company.

Figure 17. Matrix project management


296 Chemical Plant Design and Construction Vol. 8

The technical capabilities of the project man- Tasks, responsibilities, and competences are
ager should include not only specialized knowl- unambiguously defined. The project manager
edge of the project and the technology, but also bears responsibility for meeting targets until the
knowledge of how design and construction work project is handed over to the owner, he is
is executed and ability in engineering, procure- therefore placed above the construction site
ment, contract drafting, and project control. manager, who in turn heads the construction
These capabilities should be complemented by site organization.
familiarity with the client’s language, country, Efficient coordination, with short lines of
and the client, as well as skill in giving presenta- communication within the project team, is cru-
tions and in moderating discussions. Other qual- cial. An effort is therefore made to separate the
ities include analytical ability, leadership and project team members physically from their
negotiation skills, ability to work under physical functional departments within the company and
and psychological stress, ability to make deci- locate them close together.
sions, and at the same time ability to integrate and The team members remain subordinate to the
to make compromises. project manager in regard to project requirements
In larger projects, project engineers are put and for the duration of their participation in
under an experienced project manager; they take project execution. They continue to make their
responsibility for the execution of portions of the technical and functional ‘‘residence’’ in their
project. home departments.

5.2.3. The Project Team 5.2.4. The Start Phase of a Project

A project team comprises employees from tech- The most important phase in the execution of a
nical and procurement departments. If they are project is the start phase [119], [120]. The first
not fully occupied by a project (e.g., as it winds 1 – 3 months are crucial to the success of the
down), they may also belong to a team working project. In this period all basic decisions must be
on another project at the same time. The orga- made; all project-specific documents needed by
nization of a project team (Fig. 18) must be the team members and the project manager must
adapted to the specific needs of the project. be generated.

Figure 18. Organization of a project team


Vol. 8 Chemical Plant Design and Construction 297

The essential decisions and documentation to be implemented so that the target status can be
include: regained.

1. Selection of project manager and key 5.3.1. Time Scheduling


personnel
2. Creation of project team and its organization Time scheduling and control involve the use of
3. Working out project structure, including bar charts or network diagrams. The choice is
definition of subprojects and work packages made at the start of execution and depends on the
4. Planning of project execution and prepara- size, complexity, and criticality of the project,
tion of project execution guidelines and the customer’s requirements. Schedules are
5. Identification of codes and standards govern- usually prepared and updated by computer
ing the project (usually included in the (mainframe and/or PC).
contract)
6. Preparation of detailed time schedules (bar Bar Charts. Bar charts are used for plan-
charts and network diagrams) as a basis for ning and control of small, simple projects em-
time scheduling and control ploying established processes and involving little
7. Drawing up a detailed budget as a basis for time risk. These charts show the planned elapsed
cost control time for each discipline and their important
8. Preparation of a detailed man-hour budget activities. In general, the following areas are
for each of the technical and procurement included: process engineering, plant layout, civil
disciplines work and structural steel, mechanical equipment
9. Determination of nominal progress curves (furnaces, process equipment, machinery), pip-
for all disciplines involved, as a basis for ing, electrical, and control systems.
monitoring compliance work progress The schedules cover the full span of the
10. Manpower planning (office and construction contract period and are broken down into the
site) following activities: engineering (specifications,
drawings); procurement (bid invitations, bid
comparisons, orders, delivery time, shipping);
5.3. Project Control (Schedules, construction and commissioning.
Progress, Costs) Figure 19 shows an example. A ‘‘dual-bar’’
system is employed to check the status of indi-
(Project control during the construction phase is vidual activities with respect to the due dates at
described in Section 5.6.2.2). The control of any time during execution. The upper bar shows
project execution is one of the most important the planned duration of the activity. The lower
tasks of the project manager. As early as possi- bar indicates, as of the cutoff date, the actual or
ble, the project control team (schedule and cost expected start and end of the activity. The prog-
control engineers) provides information about ress of the activity is indicated by filling in the
the time situation, the progress of work, and the lower bar.
consumption of man-hours in relation to due If needed, bar charts for individual disciplines
dates and determines the cost situation for de- can be expanded to show more detail. This is
liveries and services [121]. Regular analysis of done, for example, when an early activity plan is
outstanding activities, expected time consump- prepared for the first three months of project
tion, and cost and man-hours up to the end of the execution, or when a detailed chart is drawn up
project is used to update these values. A com- if the status of work in one area is critical.
parison of the actual/expected/target values
shows the reliable status of the project, enabling Network Diagrams. The network tech-
the project manager to identify problems at an nique is widely used in industrial operations
early stage. After appropriate analysis, he and research [116], [121–124]. According to DIN 69
his coworkers devise solution options, which 900, the term ‘‘network diagram technique’’
then lead to decisions about further steps. This includes all methods used to analyze, describe,
procedure generally allows corrective measures plan, oversee, and control processes on the basis
298 Chemical Plant Design and Construction Vol. 8

Figure 19. Bar chart


Vol. 8 Chemical Plant Design and Construction 299

of graph theory; considered parameters include of the 1970s, these techniques had been opti-
time, costs, and materials. The main application mized for mainframe systems. Since the begin-
of network diagrams is in project planning and ning of the 1980s, a variety of personal computer
supervision. The project is broken down into programs have been written, and network dia-
steps (activities), which are placed in a network gram techniques have come into wide use. Main-
diagram according to their logical dependences frame and PC software are capable of outputting
(precedences). the results of network calculations in the form of
Formal representation employs arrows and due date lists, bar charts, and network plots.
nodes (a node may be represented by a rectangle To control progress effectively, the actual
or a circle). Network diagram techniques differ in status of project execution must be determined
how the logical conditions ‘‘event’’ and ‘‘acti- at regular intervals, the results compared with the
vity’’ are assigned to these fundamental elements. target data from the network chart, and the con-
Event-on-node plan: The network is formu- sequences ascertained by recalculating the net-
lated mainly in terms of events, which are re- work to the end of the project.
presented by nodes. An event is the start or finish Event-oriented network systems play a sec-
of an activity and has no duration. ondary role in project planning and control.
Activity-on-node plan: The network is for- Activity-on-node and activity-on-arrow charts
mulated mainly in terms of activities, which are are about equally important in the planning and
represented by nodes. control of all kinds of projects, including research
Activity-on-arrow plan: The network is for- and development.
mulated mainly in terms of activities, which are Some engineering firms have their own soft-
represented by arrows. ware for calculating network plans. Lurgi, for
The following network methods based on the example, uses the PDM method to prepare
above approaches were devised independently of network charts (unless the customer requires
one another. otherwise). The calculation is done with the
The Program Evaluation and Review Tech- Lurgi Netzplan System, which was developed
nique (PERT) is an event-on-node method and in-house and is specially adapted to the condi-
was devised in 1958 by the U.S. Navy in collab- tions of chemical plant construction. Network
oration with the Boots & Hamilton consulting diagrams are used for large, complex projects,
firm and Lockheed. The impetus for its develop- chiefly when there is a great time risk. The
ment was the program to design and construct project is broken down into individual activities
nuclear submarines. PERT uses three time esti- of the various divisions involved, similar to the
mates for each activity: optimistic, probable, and procedure for bar charts (see above). The level
pessimistic. The analysis is run with each esti- of detail is predefined by the project manager
mate and the results are averaged. and scheduling engineer. The stored data can be
The Critical Path Method (CPM) was also quickly updated on screen (interactive opera-
developed in the United States in 1957. It is an tion) and the network diagram immediately
activity-on-arrow network method that was de- recalculated.
vised by Du Pont and Remington Rand. It was When the network calculations are complete,
first used for planning maintenance and conver- the results can be output as lists of due dates
sion work in the chemical industry. sorted under all kinds of criteria, or bar charts
The Metra Potential Method (MPM) was first with or without interdependence. Figure 20
used in the design of nuclear power plants and shows the steps involved in project control with
was developed in 1958 by the French consulting network planning.
firm SEMA. It is an activity-on-node technique.
Several other network methods have since
been worked out. The Precedence Diagram 5.3.2. Progress Planning and Control
Method (PDM) was developed from MPM and
allows greater flexibility in the way precedences Progress planning and control is performed for
are represented. each discipline involved. For management
The advantages of network diagram planning needs, these individual plans are assembled into
can best be exploited with computers. By the end an overall plan.
300 Chemical Plant Design and Construction Vol. 8

Figure 20. Project control with network system

The progress plan is generally plotted graphi- 5.3.3. Cost Planning and Control
cally. A ‘‘target’’ curve for the planned progress
of work, for example of engineering, is drawn up Costs. The objective of cost control is to
in the following way. The work of each engi- provide correct information, as early as possible,
neering discipline is broken down into individual on the cost status for equipment, materials, ser-
activities. The duration and the expected monthly vices, and indirect costs, and to identify reliable
consumption of work units (e.g., man-hours) trends in cost development.
available from experience is specified for each The project manager instructs the cost control
activity. The sums of the monthly work units engineers to analyze planned orders for equip-
planned for individual activities are expressed as ment and services so that cost budgets are met.
a fraction of the total number of work units This ‘‘cost engineering’’ already involves the
required to give a target progress curve. These cost engineer at the stage of bid invitation, price
planning curves are prepared at the start of the comparison, and assignment of order stages.
project. During execution, they form the basis for Cost control is used throughout the entire
control of actual work progress and actual con- project for engineering and procurement, as well
sumption of work units (e.g., man-hours). as for construction. All costs connected with the
Actual work progress(physical progress)is de- project are considered, such as costs of equip-
termined by scheduling engineers who query the ment and bulk materials (mechanical, electrical,
discipline engineers and evaluate the work per- control systems, structural steel); spare parts;
formed. An example of such a work progress civil work and erection; third-party services;
chart is shown in Figure 21. The positions of the indirect costs (e.g., travel, computer services,
curves of physical progress and work units con- communications); and costs for engineering, pro-
sumed, relative to the target curve, give the curement, and construction supervision.
project manager a clear indication of the time Figure 22 illustrates the operation of a com-
compliance situation and the efficiency of the puter-supported project cost control system.
personnel involved. If there are significant devia- Cost control is based on the calculation used to
tions from the target curve, the causes should be obtain the contract price. A detailed budget is
analyzed and appropriate corrective measures prepared at the start of project execution. In the
taken. course of project execution, this budget will be
Vol. 8 Chemical Plant Design and Construction 301

Figure 21. Engineering work progress

modified if change orders are received from the influence on the project. The effects of these risks
client. The project team members responsible for on costs and their probability of occurrence
each of the disciplines involved, in collaboration cannot generally be clearly defined. One ap-
with the cost engineer, keep a continual watch on proach to risk quantification is the Lurgi ‘‘project
the technical and cost developments of the proj- risk analyis’’ concept [125], [126]. The concept is
ect in their respective areas of responsibility. based on the risk profile developed during expert
A data link between purchasing and cost conferences.
control allows updating of actual costs. Cost
control, however, is based on comparison of Cashflow Schedule. Knowledge of how to
calculated and expected values, i.e., the calculat- procure funds for equipment and services at the
ed values are always compared with the costs appropriate time is important for the investor,
forecasted up to the end of the project. This but also for the engineering firm working on
forecast is repeatedly updated for each discipline supply or turnkey contract. A project cashflow
by the specialist engineer and the cost engineer. schedule is a combination of cost planning,
Forecasts are based on the order values at the time scheduling, and progress planning. The
cutoff date, the calculated values of equipment following procedure is used to prepare such a
not yet ordered, and expected cost increases or schedule:
decreases. The cost control cycle closes when
data for the forecast and costs for approved
changes are input to the cost control system. 1. Planning of deliveries and services, including
payment modalities agreed on with the sup-
Risk Analysis. The analysis of orders still to pliers of equipment and subcontractors
be carried out and services still to be performed is 2. Determination of relevant actual figures
fed into the latest forecast. This analysis often 3. Deviation analysis (e.g., postponements)
reveals potential risks that may have a decisive 4. Revision of the plan
302 Chemical Plant Design and Construction Vol. 8

Figure 22. Principles of cost controlling

Figure 23 is a graphical representation of a b. Detailed information


cashflow schedule. Payments can be read off in . Progress of individual disciplines (pro-
detail from the associated lists. cess engineering; civil engineering,
structural steel; apparatus; piping, ma-
chinery, electrical, control systems, pro-
5.3.4. Project Report curement civil work, and construction)
. Problems in execution and recom-
The preparation of regular reports for the man- mended remedies
agement of the engineering firm and the inves- . Forecast for the following month and
tor is the task of the project manager. These key points
project status reports should provide compre-
2. Graphs and lists
hensive information; information on cost and
. Time schedules
man-hours should not, however, be included in
. Progress curves (for individual disciplines
the report to the investor in the case of a lump-
and the project as a whole)
sum contract.
. Network diagrams and lists
The report should contain the following items:
. Procurement lists

1. Text 3. Cost report


a. Summary (highlights): project status, . Analysis and assessment
trends, problems . Status of costs and man-hours
Vol. 8 Chemical Plant Design and Construction 303

Figure 23. Cashflow schedule

. Cost report (computer printout), summary which includes specifications for products, by-
. Cost report (computer printout), detailed products, residues, and wastes; emissions; safety
analyses; and HAZOP studies.
5.4. Detail Engineering

5.4.1. Process Engineering 5.4.2. Plant Layout

Most of the process engineering of a project is Plant layout is an interdisciplinary activity. Its
performed at the basic engineering stage (Sec- most important components are the layout (plot
tions 3.3 and 3.4). In addition, the process en- plan) and the piping and instrumentation dia-
gineers devise the plant control concepts in col- gram. Both documents are created, in prelimi-
laboration with the control system engineers. The nary form, during basic engineering (see
contribution of process engineers to the comple- Sections 3.4.3 and 3.4.4). They are continually
tion of piping and instrumentation diagrams ex- updated in the course of detail engineering.
tends far into the detail engineering phase. The
process engineers also prepare the process des- Plot Plan [38], [111]. The layout of, for
cription, which states how the process operates example, a petrochemical plant is usually drawn
and identifies important control functions and to 1: 100 scale. It shows the outlines of equip-
special features. ment items, pipe bridges, and buildings, all di-
In cooperation with the appropriate specialty mensioned. In the case of buildings and platforms
engineers, the process engineers write detailed on tanks and towers, horizontal projections in
startup instructions which are needed for commis- appropriate planes and vertical sections are also
sioning. The process engineers responsible for included (see Fig. 24).
process design should also be involved in commis- An experienced erection engineer should be
sioning because they are familiar with the process involved in the layout planning so that allowance
and control details of the plant. They can also gain can be made for erection operations, in particular
considerable expertise in operation of a plant, the space required for the installation of heavy
know-how that they can use in future design. apparatus. Other factors that must be considered
If the engineering firm is responsible for include maximal exploitation of available space,
‘‘authority engineering,’’ the process engineer placement of heavy apparatus on the ground
also makes a significant contribution to the ap- floor, operability of important block valves, easy
proval documentation (see also Section 3.3.3.5), maintenance of machinery, and short runs of
304 Chemical Plant Design and Construction Vol. 8

Figure 24. General arrangement drawing

pipes with large diameters and/or made from mation provided by equipment vendors during
expensive materials. There must be adequate detail engineering necessitate continual changes
safety distances between pieces of equipment, in the layout. In order to avoid delays in the start
escape routes for operating personnel, and access of construction, an attempt must be made to
for fire fighting vehicles. ‘‘freeze’’ the building dimensions and the posi-
It is also advisable to discuss the basic plot tions of heavy apparatus as early as possible.
plan with the client’s personnel (plant operators, The final layout is the result of design work
maintenance personnel) at an early stage. The performed by all the disciplines involved in the
progress of construction and new detailed infor- execution of the project.
Vol. 8 Chemical Plant Design and Construction 305

Piping and Instrumentation Diagram. the document reflects the ‘‘as built’’ state of the
The piping and instrumentation (P & I) diagram plant.
or mechanical flow diagram is based on the
preliminary P & I diagram from basic engineer-
ing. The latter is developed and elaborated in 5.4.3. Apparatus and Machinery
detail engineering, as new information is ac-
quired from the engineering disciplines and All important process engineering data for appa-
equipment vendors. ratus (e.g., heat exchangers, reactors, towers,
The final P & I diagram describes the whole vessels, tanks) and machinery (e.g., pumps,
plant in detail (by use of coding). The contents of blowers, compressors, turbines) are specified
the P & I diagram from the basic engineering during basic engineering. Data sheets prepared
stage (Section 3.4.4.) are supplemented during in this stage contain essential information on
detailed engineering by: overall dimensions, pressures, temperatures,
quantities, materials of construction, etc., of each
piece of apparatus and machinery. In detail en-
1. Operating data and dimensions of equipment gineering the apparatus and machinery engineers
2. Design data for machinery complete this information. The result of this work
3. Data on insulation and heating of equipment, is a set of specifications in the form of drawings
machinery, and piping and descriptions, which enable qualified manu-
4. Elevation of machinery and equipment facturers to submit bids for apparatus and
5. Information on noise abatement machinery.
6. Delivery boundaries The equipment engineers prepare so- called
7. Codes for equipment nozzles guide drawings, which are scaled drawings indi-
8. Codes for fittings cating all dimensions dictated by process engi-
9. Detailed information on electricals and con- neering (e.g., number and diameter of trays in a
trol systems tower, spacing of trays, and tower height). All
dimensions of importance for shipping are also
The utility systems (e.g., steam, instrument shown. Relevant legal provisions must be taken
air, and condensate systems) are diagrammed into account. Nozzle tabulation and other impor-
separately from the process systems. In larger, tant design data are attached to the guide drawing
more complicated chemical plants, P & I dia- (see Fig. 26). The wall thickness is estimated so
grams may comprise > 100 DIN A2 sheets. that the weight of the apparatus can be calculated
The P & I diagram contains all essential The number and dimensions of the nozzles, and
information developed by the individual disci- frequently their elevations, are stated. The hori-
plines: process engineering; equipment, machi- zontal orientation of the nozzles is determined
nery, piping engineering; engineering for elec- later when the exact position can be ascertained
tricals and control systems. It must also include from the piping design.
data provided by the manufacturers of equipment The guide drawings and supplementary infor-
and machinery (e.g., the control system of a mation form the technical portion of the bid
compressor). This information becomes avail- invitation, which is sent to selected manufac-
able over a prolonged span of time. turers. The information in the bid invitation must
The P & I diagram is therefore revised sev- be presented in such a way that the bidders can
eral times in the engineering stage (Fig. 25 is a submit comparable bids (see also Section 5.5.1).
portion of a P & I diagram). An attempt should The design office of the manufacturer pre-
be made to review the P & I diagram with all pares detailed workshop drawings and calculates
responsible persons (and, if possible, represen- the final wall thicknesses. The workshop draw-
tatives of the client). After this review, the P & I ings are checked by the engineering firm who
diagram is ‘‘frozen’’ and only essential changes also fixes the position of the nozzles and informs
should be subsequently allowed (e.g., changes the manufacturer of any changes.
concerned with plant safety). Minor changes are Once the drawings have been approved, pro-
often made during commissioning; these should duction can begin. The manufacturer is respon-
be incorporated into the P & I diagram so that sible for compliance with legal provisions.
306 Chemical Plant Design and Construction Vol. 8

Figure 25. Section of a piping and instrumentation (P & I) diagram


(e.g., LIC ¼ level control; TE ¼ local temperature indicator; TI ¼ temperature indicator in the control room; TIC ¼
temperature control)
Vol. 8 Chemical Plant Design and Construction 307

Figure 26. Guide drawing for a vessel


308 Chemical Plant Design and Construction Vol. 8

Specialist engineers periodically inspect com- The engineering of piping systems is closely linked
plicated equipment, even during its production. with the engineering of all other disciplines. In the
Such inspections are independent of those per- initial phase of engineering, information is incom-
formed by a third party (e.g., one of the German plete and often preliminary. The data become more
TÜV organizations or Lloyds) when mandated complete and exact as work progresses. Because
by law (e.g., for pressure vessels). The equipment the need for on-time availability of piping data
is cleared for shipping only after final acceptance requires early information from the other engineer-
by the same specialist engineers. ing disciplines, a step-by-step procedure is em-
The specification and procurement of machin- ployed. Often the first steps are based on assump-
ery are similar to that for apparatus. In contrast to tions, so that frequent corrections are required later.
apparatus, which is usually custom-built and thus Piping accounts for a relatively high propor-
individually designed and drawn, an attempt is tion of chemical plant costs and piping engineer-
made to use off-the-shelf machinery. There are ing may represent as much as 20 – 40 % of total
two reasons for doing so: to minimize engineer- engineering. Refineries and petrochemical plants
ing costs and to hold down the purchase price. lie at the upper end of this range.
The machinery engineers prepare specifica- Piping engineering can begin once the follow-
tions for every machine to be procured. The ing information (at least in preliminary form) is
specifications are based on the data sheets com- available:
piled by the process engineers, which contain all
information relevant to the process (operating 1. Standards and codes (of the investor or the
conditions, materials of construction). As an engineering firm)
example, Figure 27 shows a data sheet for cen- 2. P & I diagram
trifugal pumps taken from the bid specification. 3. Layout model
The machinery manufacturer supplements the 4. Plot plan
data sheet with further information on the model 5. Guide drawings for apparatus
he has selected for the bid. 6. System drawings for machinery
An important element of order handling is the 7. Preliminary civil and structural steel drawings
time schedule according to which the machinery 8. Data on electricals and control systems
manufacturer is to submit information about the
machine (e.g., dimensions, weight, vibratory be- Piping Specification. For the sake of effi-
havior). It is important for the engineering firm to ciency in engineering, procurement, and piping
obtain this information as early as possible to installation, and in view of the wide variety of
avoid delays in the design of footings and foun- piping components and design, a piping specifi-
dations, buildings, and piping. Such information cation is first prepared. This document is based
should also be finalized as soon as possible to on the standards and codes applicable to the plant
avoid duplication of work. and relevant engineering regulations. The piping
For noise-abatement design see Section specification also contains special piping design
3.3.3.2. guidelines for the project.
Spare parts required for plant startup and the An important element in the piping specifica-
first two years of on-stream operation are com- tion is the piping classification which minimizes
monly ordered at the same time as the machinery. the different types of piping components re-
The manufacturer recommends the type and quired. All piping components (pipe, fittings,
quantity of spares. The subsequent operator of flanges, bolts, seals, etc.) are classified on the
the plant makes the final decision once the spe- basis of flowing media, pressures, and tempera-
cialist engineer has checked the bid. tures that occur in the plant.
A piping class comprises the expected dimen-
sions of components and their materials of con-
5.4.4. Piping struction for a given set of media, pressures, and
temperatures. The classification is based on pres-
The objective of piping design is to prepare all sure – temperature diagrams from DIN 2401 or
drawings and specifications needed for procure- ANSI B 16.5 (see Fig. 28). Each of the areas
ment and installation of the piping components. represents one piping class. All components
Vol. 8 Chemical Plant Design and Construction 309

Figure 27. Data sheet for a centrifugal pump


310 Chemical Plant Design and Construction Vol. 8

The isometric drawings are supplemented by


plans for pipe bridges and underground pipe
runs.
The model shop uses the plot plan to make a
basic model at 1 : 33 1/3 or 1: 25 scale that
includes all apparatus, buildings, frameworks for
equipment, stairs, ladders, platforms, and pipe
bridges (Fig. 30). The piping model forms the
center for coordination of all detail designs [127].
Installation work carried out on the model in
parallel with piping includes air conditioning and
cable ducts, control panels, hoists, and cranes.
A piping model has the following advantages:
Figure 28. Piping classes (pressure – temperature diagram)
1. Piping routes are easy to check for collisions
with other equipment
within one such area are uniformly sized. Fittings 2. The plant operator can check ease of operation
and flanges are standardized according to pres- and maintenance
sure level. Wall thicknesses are calculated from 3. The model can serve as a training facility for
the pressure and temperature. Once the piping operating personnel and as a form of instruc-
classes have been worked out, the figures are tion during installation
stored in a data base and can be retrieved as
needed. The use of such a data base greatly The completed model should be thoroughly
reduces the amount of work to be done in speci- assessed by all discipline engineers, the later
fying the piping system for a plant. maintenance engineer, and the operator. Any
necessary changes made at this stage are much
Piping List. All pipe runs are identified by a less costly than if they are made later on the
code number and a piping class, and are compiled construction site.
in a piping list. The associated data are stored in a
data file. The piping list is prepared at the same Piping Calculations. Piping calculations
time as the P & I diagram. cover strength calculations for individual ele-
ments (wall thicknesses, flanged joints) and
Isometric Piping Drawings and Piping stress analysis of the piping system.
Model. Drawings that show both the geometry Wall thicknesses are calculated from the pres-
of the run and its location in the plant are needed sure and temperature ratings of the piping class.
for the prefabrication and installation of piping. It The safe functioning of a piping system de-
used to be common to plot every pipe run and pends on correct sizing and proper layout. Spe-
every fitting in a piping diagram with plan, cial attention should be given to the elasticity of
elevation, and section views. This method has the piping and the use of supports and anchors.
been largely replaced by a diagram of a single Temperature changes give rise to stresses in
pipe run and its components, along with mea- piping systems, which in turn generate forces
surement and control devices and piping and moments at connection and support points.
supports. Computer-aided elasticity calculations are per-
The initial piping studies and the final formed to make certain that the strains resulting
isometric drawing of a pipe run are done in from stresses in a given piping layout are within
parallel with the construction of a piping the elastic range. If the stresses are too high, a
model. A bill of materials containing all pip- different configuration must be selected or com-
ing components is drawn up for every pipe pensators must be inserted. For small-diameter
run. Figure 29 gives an example of such an pipes and moderate temperatures, these expen-
isometric drawing. Computer-aided design sive calculations are often superfluous, since
(CAD) techniques are used increasingly in experienced piping engineers lay out such piping
preparing isometrics. with adequate elasticity.
Vol. 8 Chemical Plant Design and Construction 311

Figure 29. Isometric piping drawing


Symbols and designations mark piping components (e. g., valves, flanges, reducers), dimensions, position of the pipe run

Material Takeoff and Procurement. A worked out after all isometrics and piping
first rough material takeoff can be performed plans are complete.
when the P & I diagram has reached a certain The preparation of the material takeoffs is
level of completeness and the plot plan has been computer-aided. Sorting and condensing pro-
drawn up so that fittings can be counted and the grams calculate the quantities that have to be
lengths of the main pipe runs can be estimated. ordered [128]. An integrated materials manage-
The objective of this preliminary takeoff step is ment system allows the print out of lists and
to invite bids and place orders for piping com- calculations for every step (e.g., bid invitation,
ponents with long delivery times. Sufficient ma- ordering, expediting, and material handling on
terial can thus be made available on site when site). The efficient use of such a system requires a
piping installation begins. consistent high-order data structure as well as the
As piping design advances, isometrics and unambiguous definition of piping components in
piping plans with bills of material are gener- terms of piping classes.
ated. Another (not yet final) material takeoff is
then prepared and has a higher degree of Insulation and Coatings. The thickness of
accuracy than the preliminary takeoff. Further insulation needed on equipment and piping must
orders are then placed. At this stage, bid be established at a fairly early stage since this
invitations can be sent for the installation value may influence other parameters such as the
work, and the piping installation contractor length of nozzles and the width of pipe bridges.
can be selected. The final material takeoff is Insulation thicknesses are entered on the P & I
312 Chemical Plant Design and Construction Vol. 8

Figure 30. Piping model (fluid catalytic cracker complex, courtesy of Lurgi AG)

diagram and in the piping list. Thermal insulation stringent requirements of modern process opera-
for pipes carrying hot media generally consists of tion. The objectives are to improve the availabil-
mineral wool enclosed in galvanized or alumi- ity of operating process plants, enhance their
num jackets. Polyurethane foam enclosed in reliability, and optimize their operation.
sheet metal is widely used for pipes carrying The distributed functions facilitate the engi-
cold media to prevent icing and cold bridges. neering, operation, and maintenance when bro-
Uninsulated surfaces of tanks, piping, and ken down into levels (Fig. 31).
steel structures must be painted to protect them Centralization of process control systems
against corrosion. As a rule, machinery is deliv- means that plants are chiefly fitted with electronic
ered with the specified prime and topcoats. Rust devices, since this kind of equipment with its
must be removed from the surface before appli- reliable signals is suitable, even for explosion
cation of the prime coat. In many cases, a second hazard areas. Pneumatic instrumentation is lim-
prime coat is needed before the first and second ited to pneumatically actuated controllers and
topcoats are applied. low-order local control loops.
Underground pipe is either coated with as- With the help of process monitoring and
phalt or jacketed in plastic. control systems, advanced control strategies can
be built up in modular form. The modules per-
form both computing and dynamic functions, so
5.4.5. Control Systems [129–133] that a variety of signal processing algorithms can
be selected for optimal control strategy.
Automation of chemical plants is increasing. The control of material streams, plant optimi-
Rapid progress in microprocessor technology has zation, and balancing is implemented by process
led to the development of distributed control control computers at a level above the process
systems (DCS) that can meet the increasingly control systems. These computers may have an
Vol. 8 Chemical Plant Design and Construction 313

on-line function or a data management function. 1. Size of process plant


Software vendors offer appropriate modular soft- 2. Continuous or batch process
ware. Such programs are linked together to per- 3. Behavior of process over time
mit control of products by centralized programs. . Steady and stable
Optimization programs did not gain wide use . Product output or quality strongly affected
until stable on-line analytical instruments with by load variations and/or perturbations
short response times were developed. The addi-
4. Complexity of process
tional investment is amortized after as little as . Simple control strategies
one to two years. Complicated analytical sys- . Complex interdependences
tems, however, have higher costs for mainte- . Frequently changing recipes
nance, which is performed by specially trained
personnel. 5. Local or central process control
Analytical instruments are built in prefabri- 6. Startup and shutdown strategies
cated enclosures and tested at the vendor’s work- 7. Upgradability
shop. Installation simply involves connecting the 8. Amenability to changes
process loop lines, utilities, and data cables. 9. Capability of linking with automation sys-
tems at other plants, other monitoring/con-
Plant Safety and Availability. Regulations trol levels, or information systems
on plant safety and environmental protection 10. Type of reporting
have rapidly become more stringent, influencing 11. Safety, availability
the choice of automation hardware and system 12. Standardization
structure. Safety control requires the use of re- 13. Environmental restrictions
dundant systems approved by the regulatory 14. Maker and service capabilities
authorities. Interfaces connect these systems to 15. Personnel considerations (crew size,
the process control system, special attention qualifications)
should be paid to transmission time between the 16. Economic and management aspects
different systems.
Only close collaboration between process en-
Process Monitoring and Control System. gineering and process control specialists belong-
In petroleum refineries and petrochemical plants, ing to the staff of the engineering contractor and
it is often necessary to operate 3000 – 4000 loops the owner can ensure proper decisions.
and give the plant operator access to these in a In the central control room, the operating and
meaningful order. monitoring devices collect all needed process
Sensor signals relating to the process and information. All signals from the plant (flow,
control functions, along with signals to motor pressure, temperature, etc.) are dynamically dis-
control centers (MCC) and valve actuators, are played on a screen. Two to three screens per
handled in the processing stations, which per- workstation, with the necessary operating fea-
form configured tasks such as signal condition- tures (touch screen, light pen, keyboard), have
ing, control, and signal processing. The proces- proved optimal with regard to cost and volume of
sing stations are assembled from modules and information. The process control system in-
tailored to individual functions. Process informa- cludes reporting features that maintain a contin-
tion is transmitted to the operating and monitor- uously updated record of alarm and condition
ing system via serial busses. reports, series of measurements, balances, and
The chemical plant is controlled with exten- operator actions. Trend displays of the process
ded software functions for graphical display, variables are replacing conventional chart recor-
along with process graphics overlays. The hier- ders. The latter are needed only as required by the
archical information structure of data represen- regulatory authorities (e.g., emission measure-
tation leads the operator to the proper level in the ments) or to record guaranteed values (e.g.,
information structure. The alarm functions notify temperatures in a catalyst bed).
the operator directly of the inititating measuring The workstations and peripherals should be
point in the process. The automation structure is arranged so that the operator sees the whole
governed by the following important criteria: working field as a closed area and operators can
314 Chemical Plant Design and Construction Vol. 8

Figure 32. Control room, courtesy of Lurgi AG

exchange information in order to coordinate their grams for process and device control sys-
actions in case of abnormal occurrences tems, instrument list, quantity structure list,
(Fig. 32). requirements for process measurement and
control system
Engineering of Control Systems. It is use- 2. Preparation of instrument specifications such
ful to break the engineering of modern measure- as data sheets for all instruments to be in-
ment and control equipment into field devices stalled, with information on designation of
and central control rooms (process control sys- measurement location, process data, man-
tems). Different levels of detailed knowledge are ufacturer’s data, materials of construction
needed for these two areas. The high rate of 3. Engineering of process measurement and
innovation in process monitoring and control control system: configuration documentation,
systems demands continuous retraining of the process graphics, loop sheets, description of
design engineers. process measurement and control system
The main activities involved in engineering 4. Planning of central facilities such as power
follow and make use of computer-aided engi- distribution, instrument cabinets, monitoring
neering (CAE) systems with different software rooms
requirements: 5. Preparation of installation documents such as
cable run plans, cable lists, hookups, and list
of installation materials
1. Preparation of basic documents such as
coding system, power supply and distribu- The pareparation of as-built documents
tion, materials of construction, P & I dia- once the plant has been commissioned and the
grams, control strategy, functional dia- maintenance of important documents thereafter
Vol. 8 Chemical Plant Design and Construction 315

facilitate plant maintenance and the remedying puter programs is indispensable (to keep the
of malfunctions. consumer list, perform short- circuit/load –
Information on reliability, maintenance cost, flow calculations, determine the run up behavior
spare parts management, experience, availability of motors, and carry out the sizing of cables).
over an extended time, and service are important The results of these steps are entered in the block
factors in the selection of instruments and sys- diagram.
tems. Ease of access to instruments and systems The list of electrical consumers gives a de-
greatly reduces the number of plant malfunctions tailed description of energy consumption and
and thus increases profits. provides the basis for the energy balance, in
which the installed power and net power demand
are calculated.
5.4.6. Electrical Design
Planning of Electric Utilities. Once the
The objective of electrical design is to supply results of the above activities are available,
electric power reliably and economically to all documents needed for specifying the electrical
consumers. The designer does not create isolat- utilities are prepared. These include technical
ed solutions component by component but must specifications, engineering data sheets, circuit
find the optimal solution for the system as a diagrams, cable lists, terminal diagrams, and
whole. mimic diagrams. These technical procurement
Design begins where high-voltage power en- documents form the basis for bid comparisons
ters the plant, and may include medium- and low- and order specifications. The plans are prepared
voltage switchgear, transformers, generators, by CAD methods.
emergency backup systems,lighting,grounding,
and communications. It covers three areas: Installation Planning. Electrical installa-
tion accounts for a significant fraction of invest-
1. Planning of power generation and distribution ment costs, so detailed planning is a prerequisite
2. Planning of electric utilities for economic execution. At this stage access to a
3. Installation planning plant model is extremely helpful.
The installation plans are drawn up by CAD
Planning of Power Generation and Distri- methods on the basis of layout plans and
bution. The operator wants to optimize use of comprise:
the electric power and to insure that the system
can handle short- circuit loads, that the power 1. Position plan for electrical consumers
grid can handle short- circuit loads, that the pow- 2. Cable run plan
er grid offers the necessary reliability, that in- 3. Cable run sections
vestment costs are minimized, and that operating 4. Grounding position plan
costs are held down. 5. Lighting layout plan
The following points therefore have to be 6. Hazardous area classification
examined carefully in the design of the distribu- 7. Layout plan for communication systems
tion grid:
On the basis of the designs and documents
1. Selection of voltage levels prepared, the quantities needed are determined
2. Determination of transformer ratings and bid invitations are prepared for bulk materi-
3. Location of load centers als and installation. The ordered equipment is
4. Location of distribution stations (with allow- inspected at the workshops to check for compli-
ance for danger zones) ance with the specifications.
5. Reliability of supply from electric utilities The cost of electrical equipment and materi-
and/or in-plant generating capacity als makes up 6 – 10 % of the total chemical
6. Materials of construction plant costs. The high end of the range applies
to grass-roots plants where a new infrastructure
The elements of the electrical grid must be must be created. For further information, see
selected and sized. The use of powerful com- [134], [135].
316 Chemical Plant Design and Construction Vol. 8

5.5. Procurement 7. Negotiations with the assistance of the spe-


cialist engineer and possibly the project
Procurement activities consist of three main manager
tasks: 8. Preparation of order documents
9. Checking order confirmation
1. The purchase of plant components and 10. Approval of bill payments after confirmation
services from the specialist engineer
2. Expediting during the fabrication of plant 11. Compilation of lists of bid invitations, bid
components (i.e., supervising the fabrication comparisons, and orders
sequence of plant components according to an
agreed time schedule) Bid Invitations and Comparisons. The en-
3. The shipping of plant components to the gineer responsible for a particular discipline
construction site prepares specifications for the components he
needs in the form of data sheets, guide drawings,
In U.S. oriented regions, workshop inspection descriptions, and information on when each item
of plant components also comes under this will be needed. These documents are sent to the
heading. purchasing department, which adds relevant
Depending on the terms of the contract, the business conditions and sends the packages to
engineering firm procures plant equipment in its selected bidders. The potential bidders are cho-
own name or in the name and on behalf of the sen by the responsible engineers and purchasing
investor. The procurement department of an agents when the vendor list is drawn up. If goods
engineering firm is acquainted with the world are purchased in the name and on behalf of the
market and carefully observes trends. The pro- investor, the investor commonly has a say in the
curement and engineering activities are closely process. Good definition of equipment items
linked together. The purchasing and shipping covered by the bid invitations is important so
agents as well as the expediters are also members that bids from competing vendors are compara-
of the project team, and thus subordinate to the ble as to content and thus price.
project manager. Procurement man-hours make The above procedure is also followed in the
up 8 –12 % of total engineering hours spent on procurement of services. The technical docu-
project execution. mentation (e.g., for installation of piping) is
prepared by the specialist engineers responsible
for piping, in close cooperation with the erection
5.5.1. Purchase of Equipment and Services planning department. This documentation in-
cludes the piping material takeoff, plant layout,
The main steps in purchasing are: specifications for piping installation, information
on material storage capabilities, and schedules.
1. Preparation of a vendor list, possibly in The received bids for plant components and
collaboration with the investor services are examined by the responsible engi-
2. Preparation and dispatch of bid invitations neers to insure that they are comparable and
based on requisitions written by the special- conform to the requirements stated in the bid
ist engineers invitations. Bidders may often be asked to correct
3. Handling queries from bidders, checking on- their scope of delivery and services. The bid price
time receipt of bids, checking received bids may be adjusted as a result.
for completeness Technical bid comparison is followed by com-
4. Checking bids for comparability by the mercial bid comparison and an order recommen-
engineer dation. Often, the final decision is only made after
5. Preparation of bid comparison and order verbal negotiations with two or three bidders.
recommendation by the purchasing depart- Decision criteria include not only lowest price but
ment also the technical reliability of the plant component
6. Checking the order recommendation (by covered by the bid, the experience and reliability of
cost engineers, specialist engineers, and pos- the manufacturer, and the vendor’s solvency and
sibly the project manager) workshop capacity utilization.
Vol. 8 Chemical Plant Design and Construction 317

Orders. Especially in the case of complicat- 1. Checking the specifications for packaging,
ed plant components and large service packages, shipping, payments, and duties (these are
the order often goes out in abbreviated form by usually part of the contract with the investor)
Telex, to make the best possible use of the 2. Drawing up plans for the delivery of
agreed-on lead time. The detailed order docu- equipment
ment follows immediately. The order is prepared 3. Issuing standard invoices for import licenses
by computer-aided techniques so that, for exam- 4. Obtaining packaging bids and issuing
ple, the value of the order is transferred directly orders
into the computer-aided cost control system. 5. Checking container lists and obtaining
If the plant components are clearly defined, transport approval for large and heavy
the specification used for the bid invitation can containers
also be employed for ordering. For larger and
more complicated items, the scope of delivery or Further activities include booking freight
service must be unambiguously described with a space, procuring insurance, and supervising
statement of exclusions. Imprecision at this point loading and transport. Shipping, customs, and
can result in unpleasant confrontations with the bank documents (including invoices) must also
vendor. Receipt of the order is confirmed in be prepared. Finally, damage and faults must be
writing by the vendor. taken care of.

5.5.2. Expediting 5.6. Planning and Execution of Civil


Work and Erection
The engineering firm has an obligation to the
investor to erect the plant within a certain time. The main execution phases of a project up to
The time schedule agreed between the engineering mechanical completion (engineering, procure-
firm and the vendor must therefore also be com- ment, civil work, erection) overlap one another
plied with. The engineering firm establish a pro- in time. The sequence of engineering work
duction schedule monitoring system for this pur- should guarantee that
pose. Supervision begins as soon as stocks of
material are ordered, it covers the manufacturer’s 1. Plant equipment with long delivery times
design work (workshop drawings) and other pro- (e.g., compressors, complicated apparatus)
duction steps. Expediters from the engineering can be ordered as early as possible
firm carry out their checks by telephone calls and 2. Civil work (e.g., foundations, cable ducts,
regular visits to material vendors and the manu- buildings) is begun early so that equipment
facturers of plant equipment. They report regularly erection is not delayed
to the expediting engineer and the project manager.
When delays are expected, corrective mea- Civil work should be begun as soon as the
sures must be instituted in collaboration with the engineering work is 25 – 30 % complete.
manufacturer (e.g., changing material vendors, By way of example, Figure 33 shows the
weekend work, night shifts). project master schedule for the design and
construction of the expansion of a refinery
complex including the progress curves for
5.5.3. Shipping engineering and construction. The time to
mechanical completion is 30 months if basic
The packaging and shipping of plant components engineering (which must be performed by the
to the construction site may be included in the licenser) is complete at the outset. Usually the
order given to the vendor, or may be the respon- time required for basic engineering is four to
sibility of the engineering firm. In larger projects, six months. Figure 33 also shows that engi-
the engineering firm should take responsibility neering office work is only complete by the
for coordinating and supervising packaging and time of ‘‘mechanical completion.’’ The re-
shipping. The principal activities of the shipping maining work includes the preparation of final
department are: documentation.
318 Chemical Plant Design and Construction Vol. 8

Figure 33. Project master schedule (refinery expansion project)

5.6.1. Planning of Civil Work and Erection 1. Soil evaluation report that contains, data on
the subsurface soil conditions at the plant site,
The planning of civil work and erection is part of water table, water analysis, and soil bearing
detail engineering. capacity. It should also give settlement cal-
culations so that plant components subjected
5.6.1.1. Planning of Civil Work (Including to severe dynamic loads can be calculated and
Structural Steel Work) designed.
2. Data on the proposed wastewater system.
As a rule, engineering for civil work and struc- 3. An approved layout.
tural steel is done by engineers in the civil 4. Geological and climatic figures such as earth-
engineering department assigned to the project quake factor, prevailing wind direction, and
team. Often, however, their activity is limited to severe snow conditions.
basic civil design, while detailed civil design is 5. Static and dynamic load data for the founda-
assigned to engineering firms in the country tions of machinery, equipment, furnaces, and
where the plant will be built. These firms are steel structures.
familiar with local conditions, know the local 6. Footprint dimensions of machinery and
regulations, and have short lines of communica- equipment: piping and cable cutouts in floors,
tion to the construction site and the firm perform- platforms, and walls.
ing the civil work.
Important information required at the start of On the basis of this information, preliminary
basic civil design includes: plans are drawn for foundations, buildings, steel
Vol. 8 Chemical Plant Design and Construction 319

frames, traffic routes, underground piping, se- installation of piping, electricals, and control
wers, wastewater systems, and heating/ventila- systems. Subcontracting takes place in the detail
tion/air conditioning systems. They are the basis engineering stage as soon as sufficiently exact
for detailed planning by the civil engineering information is available on the plant components
subcontractor or in the office. Together with the and bulk materials. This is especially important
estimated quantities determined for steel and when installation is covered by a fixed-price
concrete, these documents are used in inviting contract.
bids. The detail engineering for structural steel is
usually carried out by the structural steel
supplier. 5.6.2. Execution of Construction
After the submitted bids have been evaluated,
the contractors for civil work and structural steel The construction work performed by specialist
are selected on the basis of qualitative and price subcontractors is generally directed by the engi-
aspects. neering firm. If the contract provides for the
investor or a third party to do the construction,
5.6.1.2. Erection Planning the engineering firm only supplies technical ad-
visory services.
Planning the installation of plant equipment
starts at a relatively early stage in the engineering 5.6.2.1. Construction-Site Organization and
process. The sequence of installation activities Management
can strongly influence the detailed scheduling of
engineering and procurement. The schedule for The construction manager and his team super-
overall project execution should be developed vise, coordinate, and direct construction. Re-
backward from the agreed mechanical comple- sponsibility for all site activities belongs to the
tion date and specifically for equipment with long construction manager, as specified in the con-
delivery times. In large plants, separate schedules tract, relevant codes, and regulations. The con-
are worked out for each plant section. Erection struction manager is answerable to the project
schedules are revised at intervals throughout manager and is the engineering firm’s principal
detail engineering and procurement as the agreed representative to the investor on the site. The
equipment delivery times are incorporated into organization of the construction team must take
the schedules. account of the size and complexity of the project,
Drawing up the plot plan calls for the cooper- time schedule, local conditions, and contractual
ation of an experienced erection engineer, who obligations.
must consider in particular the erection require- Figure 34 shows a typical site organization for
ments for heavy components (space requirement, a large project. Commonly the investor maintains
accessibility). a similar, but smaller organization so that dis-
The land on which the plant will later be cussions can be carried on at all technical levels.
built must be prepared prior to construction The main tasks of the construction site team
work. The planning of temporary facilities is are:
generally the responsibility of the engineering
firm. Besides surveying and leveling, it is nec-
essary to plan for the delivery of utilities and 1. To plan, coordinate, and manage all site
the removal of runoff and sewage. Other facili- activities
ties include construction offices, stores, open- 2. To arrange for site offices and establish site
air storage areas, site roads, site fencing, piping security systems
prefabrication shops, communication facilities, 3. To organize and oversee materials manage-
toilets, first-aid station, guardroom, changing ment
rooms, and accommodation for subcontractor 4. To perform scheduling and progress control
personnel. 5. To define working methods
The engineering firm subcontracts installation 6. To prepare and carry out quality control
work to qualified firms specializing in the erec- 7. To establish and supervise work safety
tion of structural steel, apparatus, machinery, and procedures
320 Chemical Plant Design and Construction Vol. 8

Figure 34. Organization of a construction team

8. To coordinate and oversee the work of con- This plan is continually refined as new informa-
struction subcontractors tion becomes available.
9. To manage and clarify the construction Construction work calls for more detailed,
documentation individual schedules for on-site activities, which
10. To implement a cost control system and allow better monitoring of individual jobs and
arrange payments fast response to schedule changes.
11. To prepare construction-site orders Experience shows that detailed construction
12. To prepare deficiency reports and control network diagrams are unwieldy because of the
insurance cases large quantity of data. Individual schedules for
13. To prepare as-built drawings use at the construction site are therefore usually
14. To implement a change order management prepared as bar charts that also show the inter-
system dependencies between the various activities.
15. To submit reports to the investor and the Two types of bar charts are usually used:
project manager
16. To direct and oversee functional tests 1. Detail schedules for plant sections, subdi-
17. To initiate and direct the final plant inspec- vided according to functional disciplines.
tion and, when the plant is mechanically These charts form the basis for assessing
complete, to pass it on to the commissioning progress of work.
manager or turn it over to the custody of the 2. Detailed schedules for each functional disci-
future plant operator pline that include all plant sections. These
charts are used for capacity planning for
5.6.2.2. Time Scheduling and Progress construction personnel and their tools, equip-
Control ment, materials, and consumables.

Time Schedules. An overall construction Progress of Work. Regular evaluation of


schedule is created during detail engineering. progress in construction provides reliable
Vol. 8 Chemical Plant Design and Construction 321

information about the current status of the proj- The progress report contains the above infor-
ect. Schedule changes show up and measures can mation and is an essential part of the regularly
be planned and carried out early enough to insure updated construction-site report.
on-time completion of the plant.
Progress planning is based on a detailed 5.6.2.3. Construction Work [123]
schedule, list of plant components, material take-
offs, and specific rating factors. A specific rating Work at the construction site begins with prepa-
factor is an empirical number of hours required ration of the terrain. The plot must be surveyed,
for a specified activity (e.g., hours per tonne, m3, graded, and terraced if necessary. Access roads
or piece). If there are no rating factors, the hours must be laid out and old structures demolished.
required for stated activities are estimated in Utilities for construction must be brought in.
advance. Construction-site offices, storage areas, and
The total number of hours thus found for each workshops must be built. Accomodation (con-
activity is allotted to the planned execution time tainers) for construction personnel must be
for individual activities. Expressing such allot- provided.
ments in percent allows a target progress curve to The construction work begins with excavation
be determined for each functional discipline in and foundation work. If the soil quality necessi-
each plant section; this curve serves as a refer- tates driving piles, this must be done first. The
ence for monitoring construction progress. sequence of pouring foundations depends on the
Progress in each special discipline is evaluat- order in which equipment is to be delivered and
ed every two to four weeks. Activities not com- installed.
pleted at the time of progress assessment must be The first step in erection is the erection of
included. The activities of the special disciplines heavy equipment (reactors, towers) and steel
are therefore divided into steps and evaluated. A structures (pipe bridges and equipment support-
breakdown for above-ground piping installation ing frames). Very large process equipment often
serves as an example: cannot be shipped in one piece. Tall towers are
divided into sections, while large tanks are de-
livered in the form of prefabricated pieces. The
Prefabrication: tools needed for assembly (e.g., welding and
Pick up material 2%
Prepare and tack parts 16 %
cutting machines) and facilities for stress-relief
Weld 16 % annealing of the welds must be provided at the
Fit up and weld small parts 6% site. If possible, the delivery of heavy units
Installation: should be scheduled so that they can be placed
Transport 5%
Install, tack 20 %
on their foundations or supported in their frames
immediately. Specialists provided by the manu-
Weld 11 % facturer usually assist in the installation of
Attach clamps, supports 9% pumps, compressors, and turbines, as well as
Inspection:
Do preliminary tests, remedy deficiencies 6%
‘‘package units’’ such as refrigeration systems
Pressure test, flush 7% and complicated conveyors; these experts later
Do final test and prepare report 2% commission the components installed.
Total 100 % Piping installation at a chemical plant is often
the most labor intensive and longest phase of
installation. It starts with the placement of un-
Assessments of individual operations result derground pipelines,the mounting of straight
from years of experience. The progress values piping on bridges, and the prefabrication of
found for each discipline are then summarized piping. When the number of connection points
for each plant section, yielding the progress for to apparatus and machinery is great enough (i.e.,
each plant section or the plant as a whole. These when the devices have been delivered and put in
values are compared with the planned target place), the prefabricated piping sections are con-
progress values. If there are deviations, the nected. Satisfactory progress in prefabrication
causes are analyzed and appropriate measures and smooth installation of piping depends on
taken. skillful scheduling of the preparation of isometric
322 Chemical Plant Design and Construction Vol. 8

drawings and the observance of this schedule. cally completed when subsequent commission-
Furthermore, the procurement of piping material ing will not be delayed or disrupted by installa-
should be scheduled so that the material for tion work and that the safety of the plant is fully
prefabrication arrives at the site on time. Com- guaranteed.
puter-aided integrated material management sys- The certificate of mechanical completion is
tems are a great help in the handling of bulk usually accompanied by a ‘‘punch list’’ that
material. defines all installation work that is still outstand-
Weld inspection is carried out by X-ray meth- ing and to be done in the commissioning phase.
ods. Which piping is to be inspected depends on The certificate is generally granted when the
the quality assurance specifications. following activities have been performed:
After a pipe run has been installed, it is
pressurized with water to reveal any leaks. The
pressure test is documented in a report and the 1. Pressure testing of equipment and vessels
piping is approved for painting or insulation. with air, water, or nitrogen
Insulation work starts at vessels, towers, and 2. Purging and, if necessary, chemical cleaning
reactors and often requires the construction of and pressure testing of piping
complex scaffolds. Pipes should not be insulated 3. Testing of stress-free piping connections to
until a given plant section has a sufficiently large machinery and checking of rotation direction
number of pipe runs that have been approved for and coupling seating
insulation. 4. Brief trial run of pumps (with water) and of
The installation of electronic devices and machinery and motors (as possible without
control systems takes place after a section of product)
piping has been completed. Devices in control 5. Calibration of measuring instruments, alarms,
rooms and substations can, however, be installed interlocks, and cutoff points
independent of other work as soon as the build- 6. Functional checking of electrical equipment
ings have been completed. Underground electri- and control systems
cal cables are layed after piping. Electrical and
pneumatic cables for measurement and control Figure 35 shows a three-train reformer plant
are installed in cable ducts after the completion of under construction.
underground work. The laying of cables on cable
trays is put off until as late as possible to prevent
damage during simultaneous piping installation. 5.7. Commissioning
The same applies to the installation and junctions
of field instruments. 5.7.1. Plant Design and Commissioning
Furnaces are lined with refractories before
shipping to the site or on site. Trays are installed Commissioning must be considered even during
in towers after access to the towers has been basic and detail engineering in the design of
provided by platforms and ladders. Lightning equipment, piping, and control systems. Faulty
protection and grounding wires are installed at process design can have serious effects on the
an early stage, during the fill work of foundation time required for commissioning and the amount
excavations. of corrective work needed. The start of produc-
Functional tests of the installed equipment tion may be significantly delayed and the owner
mark the end of erection work. These tests are may suffer a substantial loss of production and
done with the plant in the cold condition and with revenue.
no product. Difficulties in commissioning and causes of
The contract must precisely define ‘‘mechan- delays have been identified as [136]:
ical completion,’’ since the contractual obliga-
tions of the engineering contractor to the inves-
tor often end at this point. Responsibility for the
26 – 29 % faulty design
commissioning of the plant may lie with the 56 – 61 % failure of plant components
investor, the licenser, or the engineering con- 13 – 15 % errors by operating personnel
tractor. Generally speaking, a plant is mechani-
Vol. 8 Chemical Plant Design and Construction 323

Figure 35. Reformer plant during construction, courtesy of Lurgi AG

Commissioning costs as a percentage of total 5.7.2. Operating Manual


plant investment are:
The operating manual is a condensed ‘‘reference
5 – 10 % for established processes
book’’ for the entire plant. It should contain all
10 – 15 % for relatively new processes important details about the design and opera-
15 – 20 % for novel processes tion. The typical contents of an operating man-
ual for a chemical plant follow [123], [136],
[137]:
Commissioning should be a special consider-
ation when the piping and instrumentation dia-
gram is designed. A commissioning engineer Part I. Operating Instructions
with relevant experience should be brought in 1. Design Principles
during the planning work. This engineer should Statement of the type, purpose, and capacity of
prepare the complete operating manual which the plant; specification of quality and quanti-
should be available before the final version of the ties of feedstocks and products (including
piping and instrumentation diagram. waste streams); utilities and consumables.
The experienced commissioning engineer 2. Description of the Process and the Plant
along with specialists (and maintenance engi- 2.1. Description of the process with its princi-
neers) working for the future plant operator ples (e.g., chemical and physical principles of
should also be involved in checking the piping the process stages). The process itself is dem-
model. Errors in pipe routing and poor access for onstrated by process flow diagrams showing
the servicing, installation, and removal of equip- equipment, machinery, and instruments and
ment can thus be remedied at an early stage. important process conditions.
324 Chemical Plant Design and Construction Vol. 8

Auxiliary systems such as refrigeration, steam, or plant sections in operation while problems
slop (wastewater) systems are similarly are being remedied; and how to perform
shown. The delivery and disposal of utilities restart afterward.
and consumables is also discussed.
6. Plant Shutdown
2.2. The plant description covers the designs of
This chapter describes procedures for planned
the individual plant sections, the functions of
and unplanned shutdown of the plant. It is
their components, and the control of the in-
subdivided as follows:
stalled unit operations.
a. Partial shutdown for periodic catalyst re-
2.3. Material balances.
generation or removal of cracking deposits
2.4. Process principles and guidelines for plant
from furnace tubes
operation explain the theoretical basis of the
b. Procedure for brief shutdown
process, as well as the process variables and
c. Procedure for extended shutdown
their effects on product quality or composi-
d. Shutdown on utilities outage
tion. Diagrams, formulas, nomographs, and
e. Emergency shutdown and special
tables allow estimation of these variables
precautions
(e.g., raw-materials composition, cooling wa-
ter temperatures). 7. Analysis Specifications
3. Special Equipment Analysis specifications: required or recom-
This chapter contains an in-depth description of mended number of analyses during commis-
special-purpose or critical equipment (e.g., sioning under steady-state operating condi-
reactors, compressors, turbines). A subchap- tions and exceptional operating conditions.
ter deals with particularly important or com- 8. Operating Report
plex control loops or interlockings and emer- This chapter describes which data are to be
gency shutdown systems. recorded during plant operation. A standard
4. Preparation of the Plant for Commissioning form for reporting during steady-state opera-
This chapter lists the preparatory steps required tion or commissioning is recommended.
for commissioning (e.g., flushing, cleaning, 9. Safety Practices
and neutralizing of piping, equipment, and The safety regulations are summarized. Potential
plant sections; inspections; pressure and leak hazards are discussed, and the behavior of the
tests; inspection of safety devices; mechanical operating personnel is recommended or pre-
tests of machinery; drying of furnace refrac- scribed. Information about safety facilities
tory or reactor linings; and specifications for and the locations of first-aid stations is given.
charging catalysts and consumables). 10. Miscellaneous
5. Plant Startup List of blinds, setpoints for alarm and switching
An outline of the overall plan for starting up the functions.
plant is first given. All startup operations are Part II. Drawings and Equipment
then described in detail step-by-step. Special Specifications
precautions and unusual design conditions are 1. Drawings
highlighted. This chapter contains drawings that relate to the
The startup instructions are broken down as process or to the plant as a whole:
follows: a. Process flow diagrams and P & I diagram
a. Initial startup after installation is complete. b. Plant layout plan
b. Startup after a prolonged shutdown. c. Underground plan
c. Restart after a brief shutdown when the d. Selected overall drawings of important
plant is still warm. equipment (e.g., reactors)
d. Procedures for catalyst regeneration or
replacement. 2. Specifications
e. Measures to be taken after abnormal oc- Equipment design specifications are compiled.
currences. Possible disturbances are listed Relevant drawing numbers, technical pro-
together with their effects and countermea- curement specifications, and other documents
sures. This section discusses how to reme- containing supplementary information are
dy problems during operation; how to keep also noted.
Vol. 8 Chemical Plant Design and Construction 325

3. Equipment Manufacturers Operating Instruc- portant input to process control. Sampling and
tions analysis programs must be prepared and dis-
Part III. Technical Documentation and cussed with the laboratory.
Drawings The commissioning team should be present on
Manuals are prepared for each engineering dis- site during the final installation phase. While the
cipline. These manuals show all specifications installation team performs function tests, the
and drawings relating to plant components commissioning engineers perform a detailed
and their operation and maintenance. check of the plant, focusing on process design
and operation (e.g., inspection of towers, inter-
5.7.3. Responsibility and Organization nals, and control systems). Changes requested by
the commissioning team can then be carried out
Responsibility for commissioning generally lies by the installation team.
with the party granting the process license: the When the commissioning manager is con-
investor/owner, licenser, or the engineering firm. vinced that the plant is ready for operation, he
The commissioning team is led by the commis- takes over responsibility for further activities
sioning manager. The key positions are occupied from the erection management.
by experienced startup engineers. Startup opera-
tion goes on around the clock, so that an adequate
number of startup engineers must be available for 5.7.5. Plant Startup
shift work.
In large plants involving two or more process The measures described in Sections 5.7.3 and
steps, it is desirable to break the plant down into 5.7.4 apply to chemical plants in general, where-
sections and assign responsibility for each to a as activities during the initial startup of a plant
smaller startup team. depend on the type of process.
On mechanical completion of the plant most Commissioning takes place step by step as
of the installation personnel leave. Some special- specified in the operating manual. The first units
ist engineers remain on site, however, especially to be started are utilities and off-sites (e.g., cool-
those involved with piping, electricals, control ing water loop, steam generation). At the same
systems, and machinery, who solve problems time, lined furnaces are dried and heated in
that arise during commissioning. accordance with the vendor’s specifications. The
The actual manual commissioning activities catalyst is charged, reduced when necessary, and
are generally performed by personnel of the brought up to reaction temperature. Plants in
operator who have already gone through class- which combustible media circulate must be
room training. The operating personnel can often purged with inert gas so that they are oxygen-
be trained in similar plants operated by associa- free before charging. Steam lines must be care-
ted firms. fully dewatered.
All measurements are recorded and balances
are run so that incorrect behavior of the plant can
5.7.4. Preparation for Commissioning be quickly detected and corrective measures
instituted.
The commissioning manager must ensure that Initial disorders are almost always encoun-
the plant is supplied with the necessary quantities tered: these result, for example, from utilities
and qualities of feedstocks, utilities, consum- outages, mechanical damage, and hot running of
ables, and energy in time for the planned start bearings or stuffing boxes. An attempt should be
of commissioning. Spare parts and a fully made, however, to get the plant running first and
equipped repair shop must also be available. The start up all systems, provided the safety of per-
cooperation of specialists provided by the man- sonnel and equipment is not endangered. The
ufacturers is essential for the commissioning of defects can then be remedied during the first
complicated equipment (e.g., compressors, re- scheduled shutdown of the plant.
frigeration plants). After operation has stabilized, conditions are
The plant laboratory has a vital function dur- optimized. When the planned values of product
ing commissioning. Analytical data are an im- quantity and quality, utilities consumption etc.,
326 Chemical Plant Design and Construction Vol. 8

have been attained, the guarantee test is carried on computer-aided design (CAD), computer-
out. Guarantee values and conditions for per- aided engineering (CAE), design calculations,
forming the guarantee test are stipulated in the data-base management,and office communica-
contract. tion sys-tems [138]. Decisions on the use of such
If the test results are satisfactory, a report for systems, in particular CAD and CAE, are driven
handover of the plant to the owner is signed. by benefits, chiefly reductions in costs and turn-
Responsibility for the plant and its operation now around times, gains in the transparency of meth-
shifts to the owner. Any defects still to be re- ods used, and systematic support for project
medied are entered in a punch list and a deadline procedures.
for corrective action is established. Generally the
service life of plant equipment is guaranteed for a
further, contractually agreed period (parts sub- 6.1. Role of Computers in Project
ject to wear are usually exempt from this guar- Execution
antee). Whether this guarantee is the responsi-
bility of the manufacturers or the engineering A variety of systems based on discrete and closed
firm depends on the contract. Figure 36 shows mathematical models are employed in process
part of a plant complex for olefin production. engineering for the simulation and design of
processes. They can be accessed from mainframe
computers, workstations, or personal computers
6. Computer Support (PCs).
For special processes, firms use internally
Most engineering contractors have invested developed programs and modules based on stan-
heavily in computerization, with the emphasis dard PC software. Internationally recognized

Figure 36. Section of an olefin complex, courtesy of Lurgi AG


Vol. 8 Chemical Plant Design and Construction 327

simulation programs are employed to prepare ical staff work with PC support connected to laser
mass and energy balances and to optimize printers.
heat-exchanger systems. Powerful systems are
also available for computer-aided process analy-
sis in large plants, dynamic simulation, and plant
6.2. EDP Infrastructure and Systems
optimization.
Progressive engineering companies strive for
Project management uses computer software
complete system integration so that engineering,
with a high degree of integration for scheduling,
commercial, and management data can be uti-
cost planning, and project control. These systems
lized in interlinked modules. In addition to main-
are generally accessible on both mainframes and
frame computers, PCs are increasingly used for
PCs.
individual support at engineering workstations.
The specific applications of computer systems
The growing demand for ‘‘distributed intelli-
vary. Graphical documents (e.g., process flow
gence’’ and advances in computer capabilities
diagrams, P & I diagrams, loop diagrams) are
are now leading to the use of interconnected,
prepared with CAD systems which are being
decentralized workstations with alphanumeric
increasingly linked to engineering data bases.
applications (data bases, calculations) and graph-
Two-dimensional design instruments are in
ical ones (CAD). Extensive standardization of
widespread use for site layout planning and plant
the data-processing infrastructure is desirable.
de-sign; three-dimensional design systems are
The variety of software systems used in proj-
occasionally used in special piping-intensive
ect execution are illustrated by the following
projects [139].
examples:
The advantages of graphics in plant design are
Design Calculations. Many software systems
the consistent and systematic use of models and
are developed in-house for the process design and
overlays and the reuse and evaluation of graphi-
engineering of plant equipment. The following
cal elements with variable intelligence [140].
general-purpose programs are also commercially
CAD use improves collaboration between
available:
individual disciplines. For example, if plant and
civil engineering both use the same CAD system,
plant design can be optimized ‘‘at the source.’’ PROCESS, ASPEN PLUS simulation programs, flow sheeting
Engineering calculations can be performed SDC material data compiler
HTRI design of heat exchangers
with PC programs developed in-house or with ROHR2 strength calculations for piping
internationally recognized standard software PROBAD/FEZEN strength calculations for apparatus
products. ANSYS, STRUDL finite-element method (FEM)
Standard systems are predominant in direct programs for structural analysis and
material and heat flow
daily use by engineers. In subfields, such as
finite-elements design, tasks are delegated to
specialists who can perform optimizations with Data-Base Management Systems. The fol-
special computer tools. lowing list includes systems developed by Lurgi
Every step in the procurement of equipment is from relational data-base systems:
computer-aided. All data and functions are inte-
grated into a system that performs bid invitation,
ANSY mechanical equipment
bid comparison, ordering, expediting, and ship- LUPREA electrical equipment
ping. Relevant data are available not only to the MASY control systems
cost control system but also to accounting. As a MVS/LUROMAK piping
rule, the entire accounting process is also DISPO disposition of bulk materials
MOSY management of materials on-site
computer-aided. BISAM bid invitation and ordering
Specialized relational data-base systems are VERONA shipping
widely used in the procurement of plant compo- ATERM expediting
nents and bulk materials. These systems are KAPAZ capacity planning
KOKO cost control
linked by interfaces. DOSY documentation and archiving
Administrative functions are supported by REPRÜ accounting
integrated office communications systems. Cler-
328 Chemical Plant Design and Construction Vol. 8

Graphics. Standard systems for graphics ap- documented in production and service compa-
plications include: nies. Certification of these quality assurance sys-
tems by neutral organizations is in development.
CADAM/AEC two- and three-dimensional
The idea behind the creation of quality assur-
plant layout and design ance systems is that the quality of a product
INTERGRAPH/IGDS, CADEX preparation of P & I diagrams should not only be established after its produc-
AUTOCAD preparation of P & I diagrams tion, but rather that the entire production process
in special fields
should be subjected to appropriate quality assur-
ance practices on a phase-by-phase basis. Quality
assurance practices must be defined and imple-
6.3. Coordination and Interfaces mented for all services performed by the engi-
neering firm itself (e.g., project management,
Growing importance is now attached to the fast, engineering, procurement, supervision of con-
error-free transfer of information generated in struction, commissioning).
computer-aided operations of the engineering The company quality assurance system is usu-
firm during project execution, to the owner and ally documented in a ‘‘quality assurance manual’’
to engineering partners (and vice versa). Accord- which contains information on organizational
ingly, the partners must arrive at a good under- structure and processes, as well as the procedures,
standing as to the content of documents and data means, and methods used to assure quality. It may
files to be transmitted; standards and codes (data also include references to internal procedures and
structures, nomenclature, symbols); and data work instructions which are not part of the manual.
formats and EDP procedures. The manual gives the owner and third parties a
The definition of interfaces between two dif- summary of the company’s quality policy and
ferent EDP systems is an important factor in data quality system. It is also an instrument for com-
transfer. Standardization of interfaces to a reli- municating the company’s quality policy to man-
able extent does not yet exist for plant design and agement and employees.
construction. Various engineering companies A typical table of contents follows:
have devised interfaces for two-dimensional
plant layout and design so that drawing data can 1. Quality policy of the company
be flexibly transmitted to any computer system. 2. Brief description of the company
3. Elements of quality assurance:
Management tasks
7. Quality Assurance Company quality assurance system
Marketing
The primary goal in the design and construction Research and development, engineering,
of chemical plants is to satisfy quality require- project management
ments. These are defined by agreement between Documentation
the investor and the engineering contractor, by Procurement
legal regulations, and by objectives set by the Fabrication, civil work, erection, commissioning
engineering firm. The quality requirements are Measuring and test equipment, inspection
generally specified in the contract between the status, corrective action
investor and the engineering firm. Quality records
Quality assurance is ensured by installation of Internal quality audits
relevant systems. These quality assurance sys- Education and training
tems cover all technical and organizational prac-
tices needed to achieve the desired quality. The quality assurance system must not be
Requirements for quality assurance systems regarded as a fixture that schematizes all proce-
are defined in standards. The international stan- dures – it needs to be continuously improved in
dards ISO 9000 – 9004 have already been incor- the light of practical knowledge.
porated into most national standards systems An engineering firm does not usually have its
[141]. Increasing numbers of quality assurance own fabrication capacity or perform construc-
systems have been developed, introduced, and tion services. Equipment as well as construction
Vol. 8 Chemical Plant Design and Construction 329

and installation services must therefore be pro- company can convince himself of the
cured. Suppliers of equipment and firms perform- company’s ability to achieve the agreed-on
ing construction work must demonstrate their quality of the product or service
own quality assurance systems to the engineering 2. A company’s quality assurance systems, ex-
firm and allow them to be verified. In addition to amined and certified by a competent neutral
this, employees of the engineering firm monitor organization, can mean a competitive
the fabrication of equipment and the construction advantage
work in accordance with established rues to 3. If a quality assurance system is organized in a
ensure that delivery and performance are in meaningful and expedient manner, agreed-on
accordance with quality requirements and quality of a product can be obtained at low
planned schedules. Such supervision does not, cost and with little expenditure of time
however, release a manufacturer or a construc-
tion contractor from its contract obligations. Quality assurance practices must already be
In the normal case, a project can be executed applied, for example, during the design stage for
and meet the quality requirements if the provi- a piece of plant equipment. Expensive post-
sions of the quality system are satisfied. In com- fabrication corrections on a wrongly specified
plicated projects or those involving a high degree device are then avoided.
of risk or innovation, a quality assurance plan
must be drawn up [142]. This sets forth in detail
the quality practices to be followed during exe- 8. Training of Plant Personnel
cution of the project. A quality assurance man-
ager is designated for the project who, after Preliminary Planning. The people who are
consultations with the project manager and the to operate and maintain a chemical plant must
heads of the functional divisions, directs the have the necessary theoretical background, prac-
quality assurance activities. He is independent tical training, and know-how.
of the project team, reports directly to company This applies in particular to personnel in
management, and confers with the investor on all developing countries, who should participate in
questions of quality assurance. specially developed know-how transfer
Many quality assurance practices are involved programs.
in the execution of a project, a few examples Many owners and operators of chemical
follow: plants write into their contracts with engineering
firms the transfer of operating and maintenance
knowledge to their specialists, supervisors, en-
1. Checking contracts against checklists gineers, and technicians. Training covers techni-
2. Defining the degree of checking of technical cal and commercial jobs as well as middle and
specifications and drawings for equipment upper management.
3. Implementing design change control The following questions should be explored at
4. Instituting design reviews to check, for exam- the feasibility study stage:
ple, process flow diagrams, layout plans, pip-
ing and instrumentation diagrams, and piping
models 1. What level of education exists in the
5. Selecting competent manufacturers for criti- region?
cal equipment 2. Will skilled labor be available in the region?
6. Identifying ‘‘hold points’’ and intensity of 3. Is the project a newly-built plant or an expan-
inspection for equipment during fabrication sion of an existing facility?
4. If it is an expansion, can skilled operating
Quality obtained on the basis of an assurance personnel be found?
system ‘‘tailored’’ to the company results in 5. Is the plant a labor-intensive production fa-
several important benefits: cility or one that can run automatically?
6. Can the plant operate autonomously (e.g., in a
1. After consultation of quality assurance docu- virgin forest area or on an island) or does it
ments, the customer of a production or service require an industrial infrastructure?
330 Chemical Plant Design and Construction Vol. 8

Training Plan. The training plan must be Training Costs. Training costs comprise
adapted to the needs of the plant and its surround- personnel, nonpersonnel, and incidental costs.
ings and should be workable regardless of the
initial qualifications of the workers being trained. Personnel Costs are incurred for the people
It should also convey state-of-the-art knowledge. who prepare, execute, and coordinate training, as
The training plan comprises organizational well as the trainees salaries. Nonpersonnel costs
charts, job descriptions, definition of minimum include payments to the operators of facilities
qualifications of future jobholders, training sche- where training takes place and the outfitting of
dules, and identification of facilities for practical training rooms on the construction site. Inciden-
training. It may also include administrative to- tal costs comprise costs for accomodation, travel,
pics (e.g., how to obtain a visa and residence and work clothing, insurance, and utilities. These
work permits, assistance in finding accomoda- may make up a significant fraction of total costs
tion, where to get work and safety clothing, if the trainees are sent abroad.
personal insurance and medical care during the
training period).
The planning documents provide a basis for References
hiring tests and results are compared with the
profile of requirements in the job descriptions. 1 H. Popper: Modern Cost Engineering Techniques,
The tests should pose and evaluate technical and McGraw-Hill, New York 1970.
management skills questions. If necessary, an 2 H. K€olbel, J. Schulze: Der Absatz in der chemischen
institute or an industrial psychologist can be Industrie, Springer-Verlag, Berlin 1982.
brought in. 3 J. T. Thorngren: ‘‘Probability Technique Improves In-
vestment Analysis,’’ Chem. Eng. Cost File, vol. 9,
McGraw-Hill, New York 1967.
Execution of Training. Every participant 4 D. J. Massey, I. H. Black: ‘‘Predicting Chemical Prices,’’
should receive a training schedule in which the Chem. Eng. Cost File, vol. 11, McGraw-Hill, New York
subject, day/time, and discussion partner or in- 1969.
structor are listed. 5 J. Jung: ‘‘Globale Vorausberechnung von Investitions-
Training should take place as late as possible kosten,’’ in GVT-Hochschulkurs: Angewandte Kosten-
so that there is no lag between training and job und Wirtschaftlichkeitsberechnungen bei der Projek-
assignment (fluctuation danger). However, train- tierung verfahrenstechnischer Anlagen, University of
Dortmund 1984, 90 – 114.
ing activities should be started early enough so
6 V. D. Herbert, A. Bisio: ‘‘The Risk and the Benefit,’’
that the future operator’s personnel can see their part 2, CHEMTECH 6 (1976) no. 7, 422 – 429.
own plant demonstrated in the final installation 7 H. K€olbel, J. Schulze: Projektierung und Vorkalkulation
phase and can perform some functions them- in der Chemischen Industrie, Springer-Verlag, Berlin
selves. This improves their sense of 1982.
responsibility. 8 J. E. Haselbarth: ‘‘Updated Investment Cost for 60 Types
The training program is usually broken down of Chemical Plants,’’ Chem. Eng. (N. Y.) 74 (1967)
as follows: Dec. 4, 214.
9 K. M. Guthrie: ‘‘Capital and Operating Cost for 54
Chemical Processes,’’ Chem. Eng. (N. Y.) 77 (1970)
June 15, 140 – 156.
Phase I. Presentation of basic information about the plant. 10 J. Jung: ‘‘Detaillierte Vorausberechnung von Investi-
Phase II. Presentation of generally important instructions on tionskosten,’’ in GVT-Hochschulkurs: Angewandte Kos-
plant operation, maintenance of machinery, safety ten- und Wirtschaftlichkeitsberechnungen bei der Pro-
practices, and organization. jektierung verfahrenstechnischer Anlagen, University of
Phase III. The trainees are divided into operating personnel, Dortmund 1984, pp. 115 – 137.
maintenance personnel, and administrative and 11 F. Strailk: ‘‘Das Verfahrensschema als Grundlage bei der
management personnel. When possible, these Planung in der chemischen Technik,’’ Chem. Appar. 92
groups are trained on the same or similar facilities
(1968) 419 – 434.
for the jobs they will later perform.
Phase IV. During the final phase of installation, the plant
12 H. C. Lang, Cost Engineering in the Process Industries,
personnel familiarize themselves in depth with their McGraw-Hill, New York, 1960, pp. 7 – 14.
own plant. The training period ends with active 13 C. H. Chilton, Chem. Eng. (N. Y.) 73 (1966) 184 – 190;
participation in plant commissioning. C. H. Chilton: Cost Engineering in the Process Indus-
tries, McGraw-Hill, New York 1960.
Vol. 8 Chemical Plant Design and Construction 331

14 W. E. Hand, ‘‘From Flowsheet to Cost Estimate,’’ Pet. 35 H. M€uller-Merbach: ‘‘Operations Research/Rev. 1,’’
Refin. 37 (1958) 331. Methoden und Modelle der Optimalplanung, 3rd ed.,
15 W. Burgert ‘‘Kostensch€atzung mit Hilfe von Kosten- M€unchen 1973.
strukturanalysen,’’ Chem-Ing.-Techn. 51 (1979) 484 – 36 H. F. Rase, M. H. Barrow: Project Engineering of
487. Process Plants, J. Wiley, New York 1957.
16 C. A. Miller: ‘‘Factor Estimating Refined for the Appro- 37 B. Aggteleky: Fabrikplanung, Hanser Verlag, M€unchen
priation of Funds,’’ Chem. Eng. Cost File, vol. 7, 1987, 1990.
McGraw-Hill, New York 1965. 38 E. Mach: Planung und Errichtung chemischer Fabriken,
17 K. M. Guthrie: ‘‘Date Techniques for Preliminary Cap- Sauerl€ander, Frankfurt 1971.
ital Cost Estimating,’’ Chem. Eng. (N. Y.) 76 (1969) 39 A. Franke: ‘‘Risk Analysis in Project Management,’’ Int.
Jan. 13, 138;76 (1969) March 24, 114 –142;76 (1969) J. Project Management 5 (1987) no. 1, 29 – 34.
April 14, 201 – 216. Chem. Eng. Cost File, vol. 11, 40 A. Jaafari: ‘‘Management Know-how for Project Feasi-
McGraw-Hill, New York 1969. bility Studies,’’ Int. J. Project Management 8 (1990)
18 Chemical Engineering, McGraw-Hill, New York – no. 3, 167 – 172.
D€usseldorf, published monthly. 41 W. T. Nichols, Ind. Eng. Chem. 43 (1951) no. 19, 2295.
19 Chemische Industrie, Verlag Handelsblatt, Frankfurt am 42 American Association of Cost Engineers: A Guide to
Main (published monthly). Capital Estimating (1988) 14.
20 P. M. Kohn: ‘‘CE Cost Indexes Maintain 13-Year As- 43 R. J. Loring: ‘‘Cost of Preparing Proposals,’’ Chem. Eng.
cent,’’ in: Modern Cost Engineering: Methods and Data, (N. Y.) 77 (1970) Nov. 16, 126.
McGraw-Hill, New York 1979. 44 P. Grassmann: Physikalische Grundlagen der Chemie-
21 J. Schulze: ‘‘Modernisierter Preisindex f€ur Chemieanla- Ingenieur-Technik, Sauerl€ander, Frankfurt 1983.
gen,’’ Chem. Ind. (D€
usseldorf) 32 (1980) no. 10, 657 – 663. 45 E. U. Schl€under: Heat Exchanger Design Handbook,
22 J. Jung: ‘‘Globale Vorausberechnung von Betriebskos- Hemisphere Publ. Corp., Washington 1983.
ten,’’ in GVT-Hochschulkurs: Angewandte Kosten- und 46 J. H. Perry: Chemical Engineers Handbook, McGraw-
Wirtschaftlichkeitsberechnungen bei der Projektierung Hill, New York 1984.
verfahrenstechnischer Anlagen, University of Dort- 47 McGraw-Hill, New York: L. Clarke, R. L. Davidson:
mund 1984, pp. 90 – 114. Manual for Process Engineering Calculations, 1962; E.
23 J. T. Sommerfeld, C. T. Lenk, Chem. Eng. 77 (1970) W. Comings: High Pressure Technology, 1956; D. L.
May 4, 136 – 138. Katz: Handbook of Natural Gas Engineering, 1959; A.
24 H. Gaensslen, Chem. Ing. Tech. 48 (1976) no. 12, L. Kohl, F. C. Riesenfeld: Gas Purification, 1960; W. L.
1193 – 1195. Nelson: Petroleum Refinery Engineering, 1958; M. van
25 F. C. Vilbrandt, C. E. Dryden: Chemical Engineering Winkle: Distillation, 1967. H. Harnisch, R. Steiner, K.
Plant Design, McGraw-Hill, New York 1959. Winnacker: Chemische Technologie, C. Hanser Verlag,
26 ICI ‘‘Factest,’’ Eur. Chem. News 21 (1972) March 17, M€unchen 1984.
32. 48 Gulf Publ. Co., Houston: R. N. Watkins: Petroleum
27 ASPEN: TECHNOLOGY ASPEN plus Costing Manu- Refinery Destillation, 1979; E. E. Ludwig: Applied
al, Cambridge 1984. Process Design for Chemical and Petrochemical Plants,
28 M. S. Peters, K. D. Timmenhaus: Plant Design and 1964.
Economics for Chemical Engineers, McGraw-Hill, New 49 R. H. Perry: Perry’s Chemical Engineers’ Handbook,
York 1980. McGraw-Hill, New York 1984.
29 Verband der chemischen Industrie: Kostenrechnung in 50 K. Weissermel, H.-J. Arpe: Industrial Organic Chemistry,
der Chemischen Industrie, Gabler, Wiesbaden 1962. VCH Verlagsgesellschaft, Weinheim, Germany 1993.
30 R. I. Reul: ‘‘Which Investment Appraisal Technique 51 L. B. Evans: Foundations of Computer-Aided Chemical
Should You Use’’? Chem. Eng. Cost File, vol. 10, Process Design, vol. 1, Engineering Foundation, New
McGraw-Hill, New York 1968. W. R. Park: ‘‘The York 1981, 425 – 469.
Investment Profit-Prophet,’’ Chem. Eng. Cost File, 52 R. Raman: Chemical Process Computations, Elsevier
vol. 10, McGraw-Hill, New York 1968. Appl. Sci. Publ., London 1985.
31 D. Spethmann: ‘‘Flexibilit€ats€uberlegungen bei Investi- 53 DECHEMA, DETHERM-SDC (Stoffdaten-Compiler),
tionsprogrammen,’’ Vortrag auf dem 22. Deutschen Frankfurt, updated regularly. Design Institute of Physi-
Betriebswirtschaftler Tag, Deutsche Gesellschaft f€ur cal Property Data (DIPR), American Institute of Chemi-
Betriebswirtschaft, Berlin 1971. cal Engineers (AIChE), DIPPR Data Compilation, up-
32 H. Jonas: Investitionsrechnung, De Gruyter, Berlin 1964. tated regularly. Thermodynamics Research Center
33 J. Leibson, C. A. Trischmann: ‘‘When and How to Apply (TRC), Vapor Pressure Datafile, updated regularly.
Discounted Cash Flow and Present Worth,’’ Chem. Eng. 54 Landolt-B€ornstein: Zahlenwerte und Funktionen aus
(N. Y.) 78 (1971) Dec. 13, 97 – 106. Naturwissenschaft und Technik, Springer-Verlag, Berlin
34 A. Fletscher, G. Clarke: Mathematische Hilfsmittel der 1985.
Unternehmensf€ uhrung, Verlag W. Dummer & Co., 55 D’Ans-Lax: Taschenbuch f€ ur Chemiker und Physiker,
M€ unchen 1966. Springer-Verlag, Berlin 1970.
332 Chemical Plant Design and Construction Vol. 8

56 D. Behrens, R. Eckermann: Chemistry Data Series, 77 DIN 52 900, Feb. 1983, DIN Safety Data Sheet for
DECHEMA, Frankfurt 1977 ff. Chemical Substances and Preparations, Beuth Verlag,
57 M. Munsch, T. Mohr, E. Futterer, Chem. Ing. Tech. 62 Berlin 1983.
(1990) 995 – 1002. 78 T. Redeker, W. M€oller: ‘‘Chemsafe-Datenbank f€ur si-
58 D. W. Townsend, B. Linnhoff, AIChE J. 29 (1983) cherheitstechnische Kenngr€oßen,’’ TU 29 (1988) no. 5,
742 – 771. 174, VDI Verlag, D€usseldorf.
59 M. A. Duran, I. E. Grossmann, AIChE J. 32 (1986) 79 V. Pilz: ‘‘Sicherheitsanalysen zur systematischen
123 – 138. Überpr€ufung von Verfahren und Anlagen – Methoden,
60 B. Linnhoff: ‘‘New Concepts in Thermodynamics for Nutzen und Grenzen,’’ Chem. Ing. Tech. 57 (1985) no. 4,
Better Chemical Process Design,’’ Chem. Eng. Res. Des. 289 – 307.
61 (1983) 207 – 223. 80 A Guide to Hazard and Operability Studies, Chemical
61 B. Linnhoff: ‘‘W€arme-Integration und Pro- Industry Safety and Health Council of the Chemical
zeßoptimierung,’’ Chem. Ing. Tech. 59 (1987) no. 11, Industries Association, Alensbie House, 93 Albert Em-
851 –857. bankment, London SE 1 7TU. Reprinted 1985.
62 A. W. Westerberg, Comput. Chem. Eng. 13 (1989) 81 Risikobegrenzung in der Chemie, PAAG-Verfahren
365 – 376. (HAZOP), ISSA Prevention Series No. 2002, May
63 V. Hlavacek, Comput. Chem. Eng. 2 (1978) 67 – 75. 1990. Published by: IVSS Internationale Vereinigung
64 N. Nishida, G. Stephanopoulos, A. W. Westerberg, f€ur soziale Sicherheit, Berufsgenossenschaft der
ALChE J. 27 (1981) 321 – 351. chemischen Industrie, Geisbergstraße 11, D-6900
65 A. W. Westerberg, Comput. Chem. Eng. 9 (1985) Heidelberg.
421. 82 Wasserhaushaltsgesetz Sept. 23, 1986 (BGBl. I, 1986,
66 G. Hosemann: ‘‘Methodisches Grundkonzept tech- 1529)
nischer Sicherheit,’’ DIN-Mitteilung 70, no. 3, Beuth 83 Allgemeine Rahmen-Verwaltungsvorschrift €uber Mind-
Verlag, Berlin 1991. estanforderungen an das Einleiten von Abwasser in
67 E. Tr€oster: ‘‘Sicherheitsbetrachtungen bei der Planung Gew€asser (Rahmen Abwasser VwV) vom Sept. 8,
von Chemieanlagen,’’ Chem. Ing. Tech. 57 (1985) no. 1, 1989 (GMBI, 1989, 518).
15 – 19. 84 H.-O. Braubach, E. Sommer, K. Zellmann: ‘‘Anforder-
68 Bundes-Immissionsschutzgesetz vom May 14, 1990 ungen an verfahrenstechnische Anlagen durch die Wei-
(BGBl I, 880) terentwicklung der Gew€asserschutz-Vorschriften,’’
69 Zw€olfte Verordnung zur Durchf€uhrung des Bundes- Chem. Ing. Tech. 57 (1985) no. 3, 113 –118.
Immissionsschutzgesetzes (St€orfallverordnung) vom 85 Allgemeine Verwaltungsvorschrift €uber die n€ahere Bes-
September 20, 1991 (BGBl I 1991, 1891) timmung wassergef€ahrdender Stoffe und ihre Einstu-
70 Gewerbeordnung, Jan. 1, 1987 (BGBl. I, 1987, 925). fung entsprechend ihrer Gef€ahrlichkeit (VwV wasser-

Amended by Gesetz zur Anderung der Gewerbeord- gef€ahrdende Stoffe), Mar. 9, 1990 (GMBI, 1990, 114).
nung, April 5, 1990 (BGBl. I, 1990, 706) and Gesetz 86 Gesetz €uber die Vermeidung und Entsorgung von Abfl€a-

zur Anderung der Gewerbeordnung Nov. 9, 1990 len (Abfallgesetz – AbfG), Aug. 27, 1986 (BGBl I,
(BGBl. I, 1990, 2442) 1986, 1410).
71 Bundesnaturschutzgesetz (Mar. 12, 1987) Bundesge- 87 Verordnung zur Bestimmung von Abf€allen nach x 2
setzblatt (BGBl) I (1987), 889. Abs. 2 des Abfallgesetzes (Abfallsbestimmung-Ver-
72 G. Hohe: ‘‘Sicherheitsabst€ande – Definition und ordnung – AbfBestV) April 3, 1990 (BGBl. I, 1990,
Bedeutung in Rechtsvorschriften und Technischen Re- 614).
gelwerken,’’ Berichtsband zum BPU-Seminar: ‘‘Sicher- 88 Allgemeine Abfallverwaltungsvorschrift €uber Anfor-
heitsabst€ande bei Planung und Betrieb industrieller derungen zum Schutz des Grundwassers bei der Lager-
Anlagen,’’ BPU GmbH, Berlin 1990. ung und Ablagerung von Abf€allen, Jan. 31, 1990
73 Gesetz zur Umsetzung der Richtlinie des Rates, June 27, (GMBI, 1990, 74).
1985 Concerning environmental compatibility testing in 89 MAGS-L€armschutz beim Raffineriebau, Minister f€ur
public and private projects (85/337/EWG). (BGBl. I, Arbeit, Gesundheit und Soziales des Landes Nordr-
1990, 205). hein-Westfalen, 1977.
74 Gesetz € uber die Umwelthaftung, Bundesgesetzblatt 90 Forschungsbericht 79–105–03–302, Stand der Technik
(BGBl) F (1990), 2634. bei der L€armminderung in der Petrochemie, commis-
75 Abst€ande zwischen Industrie- bzw. Gewerbegebieten sioned by the Bundesumweltamtes, Dec. 1979.
und Wohngebieten im Rahmen der Bauleitplanung 91 H. M. Bohuy: L€ armschutz in der Praxis, R. Oldenbourg
(Abstandserlaß), Minister f€ur Umwelt, Raumordnung Verlag, M€unchen 1986.
und Landwirtschaft, March 21 1980 (MBl.NW, 504 / 92 M. Heckl, H. A. M€uller: Taschenbuch der Technischen
SM Bl. NW, 283). Akustik, Springer-Verlag, Berlin 1975.
76 Erste Allgemeine Verwaltungsvorschrift zum Bundes- 93 Allgemeine Verwaltungsvorschrift €uber genehmigungs-
Immissionsschutzgesetz (Technische Anleitung zur Re- bed€urftige Anlagen nach x 16 der Gewerbeordnung
inhaltung der Luft – TA Luft), Feb. 27, 1986. GewO, Technische Anleitung zum Schutz gegen L€arm
Vol. 8 Chemical Plant Design and Construction 333

(TA L€arm), July 16, 1968 (Beilage zum BAnz Nr. 137, 111 R. E. Meissner, D. C. Shelton, Chem. Eng. (N.Y.), April
July 26, 1968) 1992, 81 – 85, 89 – 94.
94 Verordnung €uber Arbeitsst€atten, March 20, 1975 112 R. S. Aries, R. D. Newton: Chem. Eng. Cost Estimation,
(BGBl. I, 729). Modified by decrees passed on Jan. 2, New York (1955) 2, 77.
1982 (BGBl. I, 1) and Aug. 1, 1983 (BGBl. I, 1057) 113 J. T. Gallagher: ‘‘A Fresh Look at Engineering Con-
95 Unfallverh€ utungsvorschrift L€arm (UVV-L€arm) Oct. 10, struction Contracts,’’ Chem. Eng. Cost File, vol. 9,
1990, Hauptverband der gewerblichen Berufsgenossens- McGraw-Hill, New York 1967, p. 23.
chaft. 114 J. in ’t Veld, W. A. Peters: ‘‘Keeping large Projects under
96 Gesetz € uber Betriebs€arzte, Sicherheitsingenieure und Control: The Importance of Control Type Selections,’’
andere Fachkr€afte f€ur Arbeitssicherheit, Dec. 12, 1973 Int. J. Project Management 7 (1989) no. 3.
(BGBl. I, 965). Modified by law passed on April 12, 115 A. Morna, N. J. Smith: ‘‘Project Managers and the Use of
1976 (BGBl. I, 965) Turnkey Contracts,’’ Int. J. Project Management 8
97 Verordnung €uber Druckbeh€alter, Druckgasbeh€alter und (1990) no. 3, 183 – 189.
F€ullanlagen (Druckbeh€alterverordnung), Feb. 27, 1980 116 J. Madauss: Projektmanagement, 3rd ed., C. E. Poeschel
(BGBl. I, 173). Modified by decree passed on April 21, Verlag, Stuttgart 1989.
1989 (BGBl. I, 830) 117 E. Mosberger: ‘‘Projektmanagement im Anlagenbau,’’
98 M. P€ utz: Die Genehmigungsverfahren nach dem Chem. Ing. Tech. 63 (1991) no. 9, 921 – 925.
Bundes-Immissionsschutzgesetz. Handbuch f€ ur Antrag- 118 D. Arnold: ‘‘Projektmanagment im internationalen
steller und Genehmigungsbeh€ orden, Erich Schmidt, Großanlagenbau und Konsequenzen f€ur die Aus- und
Berlin 1986. Weiterbildung von F€uhrungskr€aften,’’ Zfbf Sonderheft
99 Neunte Verordnung zur Durchf€uhrung des Bundes-Im- 24 (1989) 55 – 77 (Verlagsgruppe Handelsblatt,
missionsschutzgesetzes (Grunds€atze des Genehmi- D€usseldorf-Frankfurt).
gungsverfahrens – 9. BImSchV), Feb. 18, 1977 (BGBl. 119 D. Kumar: ‘‘Developing Strategies and Philosophies
I, 274) and May 19, 1988 (BGBl. I, 608, 623) Early for Successful Project Implementations,’’ Int. J.
100 Ber€ucksichtigung von Emissionen und Immissionen bei Projekt Management 7 (1989) no. 3.
der Bauleitplanung sowie bei der Genehmigung von 120 L. F. Rolstad: ‘‘Project Start-Up in Tough Practice,’’ Int.
Vorhaben (Planungserlaß), Minister f€ur Landes- und J. Project Management 9 (1991) no. 1, 10 – 14.
Stadtentwicklung, Minister f€ur Arbeit, Gesundheit 121 H. Reschke, H. Schelle, R. Schnoop: Handbuch Pro-
und Soziales und Minister f€ur Wirtschaft, Mittelstand jektmanagement, vol. 1, Verlag TÜV Rheinland, K€oln
und Verkehr, July 8, 1982 (MBl. NW, 1366 /SM Bl. 1989.
NW, 2311). 122 N. Thumb: Grundlagen und Praxis der Netzplantechnik,
101 Die Beteiligung an der Bauleitplanung Verlag Moderne Industrie, M€unchen 1969.
(Beteiligungserlaß), Minister f€ur Landes- und Stadtent- 123 G. Bernecker: Planung und Bau verfahrenstechnischer
wicklung, July 16, 1982 (MBl. NW, 1375 / SM Bl. NW, Anlagen, 3rd ed., VDI Verlag, D€usseldorf 1984.
2311). 124 H. Groh, R. Gutsch: Netzplantechnik, 3rd ed., VDI
102 A. Rahmel, W. Schenk: Korrosion und Korro- Verlag, D€usseldorf 1982.
sionsschutz von St€ ahlen, Verlag Chemie, Weinheim, 125 A. Franke: ‘‘Risikobewußtes Projektcontrolling, Ri-
Germany 1977. sikomanagement als Element eines integrierten Pro-
103 U. Heubner et al.: Nickellegierungen und hochlegierte jectcontrollings,’’ Dissertation, Universit€at Bremen
Sonderst€ ahle; Kontakt und Studium, vol. 153, Expert- 1991.
Verlag, Sindelfingen 1985. 126 S. C. Ward, C. B. Chapman, B. Curtis: ‘‘On the Alloca-
104 H. Gr€afen et al.: Die Praxis des Korrosionsschutzes; tion of Risk in Construction Projects,’’ Int. J. Project
Kontakt und Studium, vol. 64, Expert-Verlag, Grafenau Management 9 (1991) no. 3, 140 – 147.
1981. 127 E. Diegelmann, H. Benesch: ‘‘Industriemodelle –
105 U. R. Evans: Einf€ uhrung in die Korrosion der Metalle, Methodik, Abwicklung,’’ 3 R International (1983)
Verlag Chemie, Weinheim, Germany 1965. no. 11, 535 – 541.
106 DIN Taschenbuch 219: Korrosion und Korro- 128 E. Diegelmann: ‘‘Erfassung, Beschaffung und Montage
sionsschutz, Beuth-Verlag, Berlin 1987. von Rohrleitungsteilen,’’ Chem. Ing. Tech. 54 (1982)
107 H. Gr€afen et al.: Kleine Stahlkunde f€
ur den Chemieap- no. 4, 303 – 313.
paratebau, VDI Verlag, D€usseldorf 1978. 129 J. Hengstenberg, B. Sturm, O. Winkler: Messen, Steuern,
108 VDI-Berichte 385: Schadensverh€utung durch Qualit€ats- Regeln in der Chemischen Technik, 3rd ed., vol. V,
sicherung von Werkstoffen und Bauteile-Optimierung Springer-Verlag, Berlin 1985.
des Bauteilhaltbarkeit. Tagung, M€unchen 1980, VDI- 130 VDI 3546 – Konstruktive Gestaltung von Pro-
Verlag, D€ usseldorf. zeßleitwarten, Beuth-Verlag, Berlin 1987 – 90.
109 D. Behrens: DECHEMA Corrosion Handbook, VCH 131 VDI 3683 – Beschreibung von Steuerungsaufgaben,
Verlagsgesellschaft mbH, Weinheim, Germany 1988 ff. Pflichtenheft, Beuth-Verlag, Berlin 1986.
110 J. R. Brauweiler: ‘‘Economics of Longlife – Shortlife 132 VDI 3693 – Verteilte Prozeßleitsysteme, Pr€ufliste f€ur
Material,’’ Chem. Eng. (N. Y.) 70 (1963) no. 2, 128. den Einsatz, Beuth-Verlag, Berlin 1985.
334 Chemical Plant Design and Construction Vol. 8

133 VDI 2180 – Sicherung von Anlagen in der Verfah- 141 R. Gareis: Projektmanagement im Maschinen- und An-
renstechnik, Bl. 1 bis 5, Beuth-Verlag, Berlin 1984 – lagenbau, Manz-Verlag, Wien 1991.
88. 142 S. J. Heisler: ‘‘Project Quality and the Project Manager,’’
134 ABB (ed.): Schaltanlagen, 8th ed., Cornelsen-Verlag, Int. J. Project Management 8 (1990) no. 3, 133 – 137.
D€usseldorf 1988.
135 Siemens (ed.): Handbuch der Elektrotechnik, 3rd ed.,
Verlag Girardet, Essen 1971.
136 J. Matley: ‘‘Keys to Successful Plant Start-Ups,’’ Chem.
Further Reading
Eng. (N.Y.) 76 (1969) Sept. 8, 110 – 130.
137 W. Langhoff: ‘‘Inbetriebnahme,’’ Beitrag im Kursush- F. P. Helmus, C. Ahner: Process Plant Design, Wiley-VCH,
andbuch ‘‘Planung und Bau von Großanlagen der Che- Weinheim 2008.
mischen Industrie,’’ DECHEMA, Erfahrungsaustausch, R. E. Meissner: Plant Layout, ‘‘Kirk Othmer Encyclopedia of
D. Behrens, K. Fischbeck, Frankfurt 1969. Chemical Technology’’, 5th edition, John Wiley & Sons,
138 VDI-Richtlinien, Datenverarbeitung in der Konstruk- Hoboken, NJ, online DOI: 10.1002/0471238961.
tion, Einf€
uhrungsstrategien und Wirtschaftlichkeit von 1612011413050919.a01.pub2.
CAD-Systemen, VDI 2216 (October 1990, draft). R. E. Meissner: Plant Location, ‘‘Kirk Othmer Encyclopedia
139 W. Hilkert, R. Pfohl: Anlagenkonstruktion mit CAD/ of Chemical Technology’’, 5th edition, John Wiley &
CAE-Werkzeugen – ein Erfahrungsbericht – VDI-Ber- Sons, Hoboken, NJ, online DOI: 10.1002/0471238961.
ichte Nr. 861.5, 1990. 1612011413050919.a02.pub2.
140 H. Schmidt-Traub: ‘‘Integrierte Informationsverarbei- G. Towler, R. K. Sinnott: Chemical Engineering Design -
tung im Anlagenbau,’’ Chem. Ing. Tech. 62 (1990) Principles, Practice and Economics of Plant and Process
no. 5, 373 – 380. Design, Butterworth-Heinemann, Oxford 2007.

Potrebbero piacerti anche