Mechanical Work Report and Planning (9/11/2019 to 06/12/019)

SL No. Description of Work Responsible person Work Status Date of Start Target Date of End Remarks.

Additional platform fabrication near R4001,R 4002 ,R 4003. Ideas Contractor is doing the work.
1 or All those Reactors need to elevate by 700 mm by making Anwar sadat Done 11/6/2019 11/15/2019 Asif Malik Sir had shown and told
template. okay.

2 Cooling Tower (Scope of work)


Hydro test of CWS CWR (ISBL + OSBL) Done 11/4/2019 11/12/2019
Extension of Pump suction line Done 11/5/2019 11/12/2019

Done 11/4/2019 11/12/2019


Fabrication of 8 inch two number of pump stainer Anwar sadat
Pipe support fabrication Done 11/6/2019 11/12/2019
Platform, Ladder making over pump house Done 11/3/2019 11/12/2019
Pump Alignment. Done 11/6/2019 11/12/2019
Civil Casting under rain shed column Mr. Haque Not Okay 11/12/2019
Colling water bypass line Done 11/8/2019 11/12/2019
Anwar sadat
Cleaning of Cooling water pond Done 11/3/2019 11/12/2019
Chemical for cooling water pond Mr. Aziz Not Okay 11/12/2019
Commissioning with Avenue Trade Anwar sadat Done 3/12/2019 3/12/2019

3 Steam Trap for Steam line Anwar sadat

ISBL Mr. Arif Spool fabrication done 11/12/2019

OSBL Anwar sadat Done 11/6/2019 11/12/2019

4 Nitrogen line for receiving Liquid Nitrogen. Anwar sadat Done 11/4/2019 11/12/2019
5 Fixing LPG pump stainer Anwar sadat Done 11/2/2019 11/10/2019
6 Emergency eye and body shower for NHT CRU Anwar sadat On going 11/15/2019 Khulna Mechanical doing work
7 CFP Sampling Point 6 Nos.

Flange Welding Anwar sadat Mr. Topu Done 11/12/2019

Tubing E&I Done

8 Flare BMS Skid bolt Tighten (For leak prevention) Anwar sadat Done 11/7/2019 11/8/2019

9 Hydrogen Booster Compressor


Suction Discharge piping Anwar sadat Done 10/21/2019 11/12/2019
CWS CWR piping Anwar sadat Done 10/28/2019 11/12/2019
Pipe support Anwar sadat Done 11/4/2019 11/12/2019
Rain shed Anwar sadat Done 10/31/2019 11/12/2019
Luboil Filling Anwar sadat Done 11/12/2019
Electrical Power E&I Done 11/12/2019
Grouting Mr. Haque Done 11/12/2019

10 Hydrogen storage Tank


Pipe fabrication Anwar sadat Done 10/22/2019 11/12/2019
PG setting E&I Done 11/12/2019
Vessel Inspection Anwar sadat Done 11/2/2019 11/12/2019

11 Hydrogen Generator
CWS, CWR, PW Line, Product line Anwar sadat Done 11/2/2019 11/12/2019
Table and Frame making for tubing Anwar sadat Done 11/3/2019 11/12/2019
Tubing E&I Done 11/12/2019
SS DM water line fabrication Anwar sadat Done 1/12/2019 3/12/20169

12 Sump oil Pit tank


Rain Shed fabrication Anwar sadat Done 10/31/2019 11/12/2019
Platform fabrication Anwar sadat Done 11/1/2019 11/12/2019
Pipin Modification Anwar sadat Done 11/7/2019 11/12/2019

13 CFP Air Cooler

Alignment, Belt tension, Pitch angle. Anwar Sadat, Mr. Shofi Done 10/28/2019 10/27/2019

Belt procurement Anwar Sadat, Mr. Shofi Not Okay 11/20/2019 Demand not raised

14 NHT CRU Air Cooler


ARL team doing Alignment, Belt
Alignment, Belt tension, Pitch angle. Anwar Sadat, Mr. Shofi On going 11/3/2019 11/15/2019
tension, Pitch angle.

Belt procurement Anwar Sadat, Mr. Shofi On going 11/3/2019 11/15/2019

15 Additional ISBL Pipng work


PID Received on 6-11-19 KHULNA
Excess Hydrogen line Anwar Sadat Done 11/7/2019 11/22/2019
is working
EDPS line Anwar Sadat Done 11/7/2019 11/22/2019 PID Received on 6-11-19 KHULNA
Start up line Anwar Sadat Done 11/7/2019 11/22/2019 PID Received on 6-11-19 KHULNA
Relief to flare line Anwar Sadat Done 11/7/2019 11/22/2019 PID Received on 6-11-19 KHULNA
K3001, K4001 suction and discharge line Anwar Sadat Done 11/7/2019 11/22/2019 Additional work,
CWS CWR line Anwar Sadat Done 11/7/2019 11/22/2019 Additional work

16 Compressor Filter Installation Anwar Sadat Done 11/9/2019 11/20/2019


Piping work Anwar Sadat Done 11/9/2019 11/21/2019
Civil Foundation Mr. Haque Done 11/9/2019 11/22/2019

17 Hydrotest of Utility line (ISBL)


PW Line Mr. Ali Hossain Done 11/1/2019 11/3/2019
DW Line Mr. Ali Hossain Done 11/1/2019 11/3/2019
DSW Line Mr. Ali Hossain Done 11/1/2019 11/3/2019
Insulation on going. Mr. Haque and
Steam Line LS Mr. Ali Hossain Done 11/5/2009 11/9/2019
Mr. Saiful
Insulation on going. Mr. Haque and
Condensate Line LC Mr. Ali Hossain Done 11/5/2009 11/9/2009
Mr. Saiful
CWS Line Mr. Ali Hossain Done 11/4/2009 11/12/2019
CWR Line Mr. Ali Hossain Done 11/4/2009 11/12/2019
PA Line Mr. Ali Hossain Done 11/8/2019 11/12/2019
Nitrogen Line Mr. Ali Hossain Done 11/8/2019 11/12/2019

IA Line Mr. Arif Done 11/14/2019

18 Automation and Final check of fire network Anwar Sadat Done 11/7/2019 11/9/2019 Not yet handed over.

19 Pressure vessel Platform making Mr. Arif and Mr. Saiful On going 11/25/2019 Material demand has been placed

New Material demand has been


20 Platform making SS 04 to C1001, MPR Anwar Sadat On going 11/25/2009
made

Process compressor K 4001 and K 3001 need to make


21 ready for online application by checking all punch list. IA and Anwar sadat Not started 11/20/2019
N2 Line need to check.

22 Piping and modification work Mr. Arif


23 Piping dia inch record keeping Mr. Arif On going

24 Instrument air line for control valve Done


Mr. Arif
Need portable tools ,vibration and
All rotary pump luboil level, Alignment, Dry rum current CFP Done, CRU On
25 Mr. Aziz and Anwar Sadat temperature measuring instrument
reading, Temperature, vibration need to check. going
(Vibrotip) (Received at site)

Stataic Vessle of NHT CRU Need to inspect and have to


26 Anwar sadat Done 11/12/2019
prepare a punch list.

27 Inspection and Preparing Punch list for NHT CRU. Mr. Ali Hossain On going

28 Need to Run Instrument air compressor 2nd unit, Cooling Mr. Aziz Done
tower. Also need to finish automation of fire pump.

29 Hydro testing, flashing, boxup of NHT CRU. Mr. Ali Hossain Done

30 Insulation work Mr. Haque, MR. Saiful On going


31 NDT and PWHT and Q.C Mr. Topu. On going
32 Inventory keeping in store Anwar sadat On going
Mr. Ali Hossain and Mr.
33 On going
Local material Procurement Shofi
34 Painting work of remaining pipe and structure Mr. Aziz On going

Additional Work (December, 2019)

35 Boxup of Tank Manhole Mr. Ali Hossain Done 30/11/2019 4/12/2019


36 CFP ( Requested by process) Mr. Ali Hossain Done 25/11/2019 7/12/2019
Clamping NFL Line Mr. Ali Hossain Done 25/11/2020 7/13/2019
Short bolting E1001 Mr. Ali Hossain Done 25/11/2021 7/14/2019
Ground floor pipe support Mr. Ali Hossain Done 25/11/2022 7/15/2019
Small insulation work Mr. Ali Hossain Done 25/11/2023 7/16/2019
Painting Mr. Aziz Done 25/11/2024 7/17/2019
Readiness Air cooler A1001 Anwar sadat Done 25/11/2025 7/18/2019
CFP Sampler fixing Anwar sadat Done 25/11/2026 7/19/2019
C1001 Manhole fixing, LG Valve fixing Anwar sadat Done 25/11/2027 7/20/2019
Fixing lock nut SS 01 Mr. Ali Hossain Done 25/11/2028 7/21/2019
Fixing Chain Guard Mr. Ali Hossain Done 25/11/2029 7/22/2019
V-1001 LG Extension Mr. Ali Hossain Done 25/11/2030 7/23/2019
Spool making for SS tank nozzle Mr. Ali Hossain Done 25/11/2031 7/24/2019
Valve fixing V-2001 Mr. Ali Hossain Done 25/11/2032 7/25/2019
PG Fixing for all heat exchanger Mr. Saiful Done 25/11/2033 7/26/2019
37 Fire line near truck loading Anwar sadat On going 4/12/2019 15/12/2019
38 LPG water sprinkler Anwar sadat On going 4/13/2019 15/12/2020
39 Nitrogen vessel fabrication Anwar sadat On going 4/14/2019 15/12/2021
40 Drain line from K3001 K4001 FILTER Anwar sadat On going 4/15/2019 15/12/2022
42 Small additional line for N2 / IA / PW Line Anwar sadat On going 4/16/2019 15/12/2023