Sei sulla pagina 1di 1

18th June, 2020

Design Status (Rajasthan)


Official Activity Internal Activity Rev-0 Rev-1 Rev-2 Rev-3 Rev-4 Rev-5 Rev-6 Rev-7
Item Unit Qty
Qty Rev Date Days Status Date Days Person Remarks Date Ref Date Ref Date Ref Date Ref Date Ref Date Ref Date Ref Date Ref
Plan & Profile Km
Pavement Design Km
Box Culverts No
Package-1

SVUP No
LVUP No
VUP No
MNB No
ROB No
Boundary Wall Km
Embankment Design Km
Plan & Profile Km 30 30 6 17-Jun-20 1 Modified P&P Submitted (Rev-6) (Site-109) 17-Jun-20 1 TL GFC awaited 11-Jan-20 HO-04 NA 4-Feb-20 Mail 26-Feb-20 HO-08 6-Mar-20 HO-10 23-Mar-20 Mail 17-Jun-20 Site-109
Pavement Design Km 30 30 7 6-Jun-20 12 Rev-6 Approved (AE-127). Approved PDR (Rev-7) Site-95 11-Jan-20 HO-04 15-Feb-20 HO-07 16-Apr-20 Mail 21-May-20 Mail 26-May-20 Mail 27-May-20 Mail 4-Jun-20 Mail 6-Jun-20 Site-95
Box Culverts No 40 37 5 16-Jun-20 2 Reinforcement for 1-2m cushion modified but 0-1 still pending 18-Jun-20 0 Santosh Final Drawings awaited 20-Jan-20 HO-05 18-Mar-20 HO-13 31-Mar-20 Mail 21-Apr-20 Mail 28-Apr-20 HO-15 19-May-20 Mail
SVUP No 5 5 6 9-Jun-20 9 Final submission for all 5 SVUPs (Rev-6) (Site-100) 9-Jun-20 9 TL GFC awaited 14-Feb-20 HO-06 18-Mar-20 HO-13 4-May-20 Mail 15-May-20 Mail 23-May-20 Mail 5-Jun-20 Site-93 9-Jun-20 Site-100
Package-2

Observations on LVUP (33+250 & 39+450) Rev-1


LVUP No 8 8 1 6-Jun-20 12 6-Jun-20 12 Jain Sir Compliance from Jain Sir awaited 14-Feb-20 HO-06 6-May-20 Mail
Revised Geotech submitted (Site-96) 6-6-20
VUP No 5 2 3 5-Jun-20 13 Submission of VUP @ 38+630 (R3) & 50+050 (R2) vide Site-92 5-Jun-20 13 Namrata Review of 3 VUPs awaited 9-Mar-20 HO-11 9-May-20 Mail 1-Jun-20 Site-90 5-Jun-20 Site-92
InterChange No 1 1 0 10-Jun-20 8 Compliance & submission of R1 (Site-102) 10-Jun-20 8 TL Approval Awaited 9-Mar-20 HO-11 10-Jun-20 Site-102
Boundary Wall Km 30 30 3 16-Jun-20 2 Further comments received on Rev-4 16-Jun-20 2 Jain Sir Compliance / Reply awaited 14-Feb-20 HO-06 18-Mar-20 HO-13 19-May-20 Mail 22-May-20 Mail 16-Jun-20
WaySide Amenities No 1 1 0 10-Jun-20 8 Compliance to observations submitted (Site-103) 10-Jun-20 8 TL Approval Awaited 30-May-20 Site-86
Service Road No 5 2 0 12-Jun-20 6 SR & CR P&P for VUP @ 38+630 (Rev-0) submitted (Site-108) 12-Jun-20 6 TL Approval Awaited 12-Jun-20 Site-108
Embankment Design Km 30 30 1 11-Jun-20 7 Further observations received from AE (Rev-1) 18-Jun-20 0 Geotech Compliance awaited from STPL (Reminder sent) (Original 12-6-20) 14-Apr-20 Mail 1-Jun-20 Site-89
Plan & Profile Km 30 28.21 1 28-Apr-20 51 28.21 Km approved 28-Apr-20 51 Anuj Sir Get approval of remaining 2 Km 19-Mar-20 HO-07 25-Mar-20 Mail
Pavement Design Km 30 After approval of Pkg-2 (Same Design)
Box Culverts No 32 After approval of Pkg-2 (Same Design)
Package-3

SVUP No 10 12-Jun-20 6 Nitin Cross-Road P&P awaited


LVUP No 8 After approval of Pkg-2 (Same Design) 12-Jun-20 6 Prasanna Geotech Reports received
VUP No 4 After approval of Pkg-2 (Same Design) 12-Jun-20 6 Prasanna Geotech Reports to be prepared
Boundary Wall Km 30 After approval of Pkg-2 (Same Design)
WaySide Amenities No 1 1 0 5-Jun-20 13 WSA Concept Layout submitted 5-Jun-20 13 TL Approval Awaited 5-Jun-20 Site-02
Service Road Km 0.3 0.3 0 12-Jun-20 6 SR & CR P&P for VUP @ 68+592 (Rev-0) submitted (Site-61) 12-Jun-20 6 TL Approval Awaited 12-Jun-20 Site-61
Embankment Design Km 30 After approval of Pkg-2 (Same Design)
Plan & Profile Km 28 28 3 15-Jun-20 3 Final P&P requested by AE as per finalised box culverts 18-Jun-20 0 Nitin Data sent to Site. (P&P Rev-4 awaited) 12-Dec-19 HO-06 NA 27-Feb-20 HO-23 30-Apr-20 Mail
Pavement Design Km 28 28 4 15-Jun-20 3 Approved Pavement Composition received (AE-438) 15-Jun-20 3 Anuj Sir Soil Tests sent. Compliance awaited 12-Dec-19 HO-06 27-Feb-20 HO-23 7-May-20 Mail 15-May-20 Mail 26-May-20 Site-85
Box Culverts No 29 29 3 9-May-20 40 Rev-3 Approved (AE-282) 18-Jun-20 0 Santosh Revised Drawings to be prepared 26-Dec-19 HO-08 8-Jan-20 HO-11 12-Mar-20 HO-24 16-Mar-20 HO-26
Package-5

SVUP No 11 11 3 5-Jun-20 13 Compliance and submission of Rev-3 5-Jun-20 13 TL Approval Awaited 12-Dec-19 HO-06 13-Jan-20 HO-13 16-Mar-20 HO-28 13-May-20 Mail
LVUP No 7 7 2 26-May-20 23 Comments on LVUP (Rev-2) (Retaining Wall Approved) 26-May-20 23 Jain Sir Compliance awaited from Jain Sir 12-Dec-19 HO-06 13-Jan-20 HO-13 19-May-20 Mail
VUP No 5 1 1 26-May-20 23 Compliance & Revised submission of VUP 137+901 (R1) 6-Jun-20 12 TL Approval Awaited 9-Mar-20 HO-23 26-May-20 Site-86
MNB No 1 1 0 16-Jun-20 2 COS details requested by AE to issue COS Notice 18-Jun-20 0 Tushar Minor Bridge Drawings awaited. Geotech Reports awaited
ROB No 1 1 1 3-Jun-20 15 Compliance & MNIT drawings submitted (Site-95 & 96) 3-Jun-20 15 TL Further directions awaited 12-Feb-20 HO-19 3-Jun-20 Site-96
Boundary Wall Km 28 28 3 15-Jun-20 3 Compliance & submission of Rev-3 (Site-106) 15-Jun-20 3 TL Approval Awaited 5-Feb-20 Site-34 16-Mar-20 HO-27 19-May-20 Site-80 15-Jun-20 Site-106
Embankment Design Km 28 28 0 21-May-20 28 Rev-0 Submitted vide Site-84 5-Jun-20 13 TL Approval Awaited 21-May-20 Site-84
Plan & Profile Km 24 18-Jun-20 0 Nitin Revised FRL awaited
Pavement Design Km
Box Culverts No
SVUP No
Package-6

LVUP No
VUP No
MNB No
ROB No
WaySide Amenities No 1 1 0 5-Jun-20 13 Approval of Conceptual Layout Plan for WSA requested 5-Jun-20 13 TL Approval Awaited 5-Jun-20 Site-02
Boundary Wall Km
Embankment Design Km
Plan & Profile Km 24 24 0 17-Jun-20 1 Lalit (s) Unofficially submitted to TL for review 17-Jun-20 Mail
Pavement Design Km
Box Culverts No 18-Jun-20 0 Lalit (s) Designs & Drawings (Rev-0) sent to Site 18-Jun-20 Mail
Package-3/3

SVUP No
LVUP No
VUP No
MNB No
ROB No
WaySide Amenities No 1 1 0 5-Jun-20 13 Approval of Conceptual Layout Plan for WSA requested 5-Jun-20 13 TL Approval Awaited 5-Jun-20 Site-02
Boundary Wall Km
Embankment Design Km

NHAI NKC Projects Pvt. Ltd.