ID Task Name Duration Start Finish % Complete August 2019 September 2019 October 2019 November 2019

14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14
1 Kerja-Kerja Pengantian Sistem Gas Perubatan MA4 Serta 81 days Mon 22/7/19 Mon 11/11/19 0%
Kerja-kerja lain berkaitan di Hospital Seberang Jaya

2 Letter of Award 1 day Mon 22/7/19 Mon 22/7/19 0%


3 LA receive 1 day Mon 22/7/19 Mon 22/7/19 0%
4 Prelimanaries 14 days Tue 23/7/19 Fri 9/8/19 0%
5 Insurance 7 days Tue 23/7/19 Wed 31/7/19 0%
6 CPM 7 days Tue 23/7/19 Wed 31/7/19 0%
7 Site Preparation 7 days Thu 1/8/19 Fri 9/8/19 0%
8 Procument & Delivery 52 days Tue 23/7/19 Wed 2/10/19 0%
9 Compressor 30 days Tue 30/7/19 Mon 9/9/19 0%
10 Dryer 47 days Tue 30/7/19 Wed 2/10/19 0%
11 Dryer Control 47 days Tue 30/7/19 Wed 2/10/19 0%
12 Exhaust Fan 10 days Tue 23/7/19 Mon 5/8/19 0%
13 Installation 40 days Tue 20/8/19 Mon 14/10/19 0%
14 Medical Gas MA4 system 32 days Fri 30/8/19 Mon 14/10/19 0%
15 Demolition work of existing system 10 days Fri 30/8/19 Thu 12/9/19 0%
16 Install Oil-Injected screw Compressor 10 days Tue 10/9/19 Mon 23/9/19 0%
17 Dryer System 14 days Tue 24/9/19 Fri 11/10/19 0%
18 Dryer Control 14 days Tue 24/9/19 Fri 11/10/19 0%
19 Testing and Commissioning of New system 4 days Wed 9/10/19 Mon 14/10/19 0%
20 Mechanical Ventilation System 15 days Tue 20/8/19 Mon 9/9/19 0%
21 Inline fan Installation 5 days Tue 20/8/19 Mon 26/8/19 0%
22 Wall mounted Direct Driven Propeller Fan 5 days Tue 27/8/19 Mon 2/9/19 0%
23 MCC c/w new wiring 5 days Tue 3/9/19 Mon 9/9/19 0%
24 Testing and Commissioning 10 days Tue 29/10/19 Mon 11/11/19 0%
25 Testing of whole system 5 days Tue 29/10/19 Mon 4/11/19 0%
26 Certificate of Completion 5 days Tue 5/11/19 Mon 11/11/19 0%
27 Handover 1 day Tue 15/10/19 Tue 15/10/19 0%
28 Project handover 1 day Tue 15/10/19 Tue 15/10/19 0%

Task Project Summary Manual Task Start-only Deadline

Project: Compressor For Hospit Split Inactive Task Duration-only Finish-only Progress
Date: Mon 29/7/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone