1. Which of the following Schedule no. Of Galvanized Iron Pipes is the thinnest?
a. No.10
b. No.10S
c. No. 5
d. No. 160
2. At least how many days the contractor shall notify the engineer before they intend to start top soil
stripping operations?
a. 3 Days
b. 4 Days
c. 5 Days
d. Not Specified
3. This is the rate of dilution for each layer for item 206 (Sept 2019)
a. 1:5 to 1:9
b. 1:3 to 1:6
c. 1:5 to 1:7
d. 1:3 to 1:9
4. What is the minimum weight of gravity hammers used in pile driving?
a. 2000 kg
b. 2500 kg
c. 3000 kg
d. 3500 kg
5. What is Tensile strength of rubber waterstops?
a. 10 MPa
b. 9.6 MPa
c. 15 MPa
d. 17 MPa
6. What is the most fluid grade of medium curing cutback Asphalt?
a. MC-30
b. MC-70
c. MC-800
d. MC-3000
7. What is the ratio of mortar used for cobble stone or wet stone masonry, as to water:
Portland:Sand
a. 1:2:3
b. 1:2:4
c. 1:2:5
d. 1:2:6
8. What is the standard height of reflectorized thermoplastic rubble strips?
a. 4-13 mm
b. 5-13 mm
c. 3.2-4.8 mm
d. 2.2-4.8 mm
9. What is the maximum international roughness Index (IRI) for both asphalt and concrete
pavements?
a. 1.5 m/km
b. 2.0 m/km
c. 2.5 m/km
d. 3.0 m/km
10. What is the color code for grade 60 reinforcing Steel bars
a. White
b. Yellow
c. Green
d. None
11. What is the volume of the slump cone mold?
a. 0.0055m³
b. 0.055m³
c. 0.55m³
d. 0.00055m³
12. How much is the required lapped lenght of splices of reinforcing bars as per item 104 when the
splice type is compression and the reinforcement is grade 40
a. 20 bar diameter
b. 24 bar diameter
c. 12 bar diameter
d. 36 bar diameter
13. In the construction of bituminous road-mix surface course, what is the suggested rate of
application of bituminous material?
a. 0.5 L/m² - 10.00 L/m²
b. 0.51 L/m² - 10.00 L/m²
c. 0.4 L/m² - 10.00 L/m²
d. 0.2 L/m² - 10.00 L/m²
14. Given the safe heating temperature of 225°C for asphalt joint sealant, what is the pouring point
temperature requirement?
a. 212°C
b. 214°C
c. 215°C
d. 210°C
15. Determine the Recommended thickness of a preformed joint filler for item 601 - Side Walk
a. 10mm
b. 3mm
c. 5mm
d. 20mm
16. How much is the Recommended static load increment in pile testing?
a. 5 tonnes
b. 2 tonnes
c. 7 tonnes
d. 3 tonnes
17. The weight of a hot-poured type concrete joint sealant sample
a. 800±50 g
b. 800±10 g
c. 800±40 g
d. 800±30 g
18. How many measurements are required in the determination of thickness of an asphalt core using
a caliper?
a. 4
b. 8
c. 9
d. 10
19. What is the minimum offset of Chevron signs from the edge of pavement?
a. 1.8m
b. 1.5m
c. 1.0m
d. 2.0m
20. A sample of chemical for concrete obtained in a single Operation
a. Composite
b. Grab Sample
c. Pick Sample
d. Single Sample
21. What item consisting of furnishing and placing of aggregate in stockpiles?
a. item 208
b. item 207
c. item 209
d. item 204
22. What is the minimum uniform density of crushed slag when used for macadam pavement and
bituminous seal coat?
a. 1120 kg/m³
b. 960 kg/m³
c. 1210 kg/m³
d. 1400 kg/m³
23. Sampling of cement should be at least how many days prior to usage?
a. 14 days
b. 12 days
c. 10 days
d. 7 days
24. What is the minimum required lapped lenght of splices of rebars
a. 150mm
b. 200mm
c. 100mm
d. 300mm
25. What is the solvent is used in extraction of bitumen?
a. Diesel
b. Gasoline
c. Water
d. Kerosene