Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Zamboanga del Sur 1st Engineering District
Pagadian City

Accomplishment no. _________


Contrat ID :14JO0012
Name of Project:Construction of Permanent Bridge, Senote Bridge along Eastern Bobongan - Sominot - Midsalip - Dumingag Road
Location :Dumingag, Zamboanga del Sur
Contractor: :ESR Construction and Development Corporation
Contrat Amount:: 38,024,766.50
Status:
STATEMENT OF WORK ACCOMPLISHMENT (SWA)
AS OF :

% ACCOMPLISHM
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL RELATIVE QUANTITY ACCOMPLISHMENT % ACCOMPLISHM
Wt. PREV. THIS PERIOD TO DATE PREV. THIS PERIOD
PART A- FACILITIES FOR THE ENGINEERS
FE A1.3 Construction Safety and Health Program 1.00 LS 129,080.00 129,080.00 0.339%
PART B- OTHER GENERAL REQUIREMENTS
1 Maintain and Protect of Traffic 167.00 Days 601.92 100,520.64 0.264%
PART C- EARTHWORK
102(2)a Roadway Excavation (Surplus Common) 6,864.80 Cu.m. 134.92 926,198.82 2.436%
103(1)a Structure Excavation (Common Soil) 410.00 Cu.m. 134.15 55,001.50 0.145%
103(2)a Bridge Excavation (Common Soil) 319.73 Cu.m. 132.55 42,380.21 0.111%
103(5)b Shoring & other related works (assumed footing area = 25 sq.m.) 25.00 Sq.m. 12,899.01 322,475.25 0.848%
104(1) Embankment (from excavation) 3,431.84 Cu.m. 195.30 670,238.35 1.763%
105(2) Subgrade Preparation (Common Soil) 5,032.50 Sq.m. 23.17 116,603.03 0.307%
PART D-SUBBASE AND BASE COURSE
200 Aggregate Base Course 3,280.00 Cu.m. 901.02 2,955,329.91 7.772%
PART E-SURFACE COURSE
300(1) Gravel Surface Course (uncrushed) 426.00 Cu.m. 1,084.15 461,847.90 1.215%
311(1)a PCCP (Plain)-Conventional Method, 280mm thick 5,639.00 Sq.m. 1,637.67 9,234,821.13 24.286%
PART F- BRIDGE CONSTRUCTION
400(4)a Precast Concrete Pile, Furnished (400mm x 400mm- type B) 900.00 M. 4,720.89 4,248,801.00 11.174%
400(14)b Precast Concrete Sheet Piles, driven 864.00 M. 1,937.20 1,673,740.80 4.402%
400(16)a Test pile, Furnished and Driven (400mmx400mm) 50.00 M. 3,735.20 186,760.00 0.491%
401a Reinforced Concrete Railing (Double) 30.00 M. 4,123.82 123,714.60 0.325%
403(1) Structural steel (Furnished, Fabricated and Erected) 1,364.00 Kg. 99.10 135,172.40 0.355%
404a Reinforcing Steel Bar, Grade 40 (Bridge Structures & Other major Structures) 1,803.92 Kg. 71.78 129,485.38 0.341%
404b Reinforcing Steel Bar, Grade 60 (Bridge Structures & Other major Structures) 55,316.10 Kg. 73.59 4,070,711.80 10.705%
405(1) Strcutural Concrete, Class A (major structure)-Bridge Superstructure,20.70 Mpa 224.72 Cu.m. 6,766.40 1,520,544.40 3.999%
405(2) Strcutural Concrete, Class A (major structure)-Bridge Superstructure,27 Mpa 119.16 Cu.m. 7,425.87 884,866.67 2.327%
405(3) Strcutural Concrete, Class A (Lean Concrete-minor Structure) 7.73 Cu.m. 6,560.69 50,714.13 0.133%
406(1) Pre Stressed Concrete Girder, Type IV-B (30 meters) 4.00 Each 1,011,552.50 4,046,210.00 10.641%
412 Elastomeric Bearing Pad 8.00 Each 22,592.50 180,740.00 0.475%
PART G- DRAINAGE AND SLOPE
505(5) Grouted Riprap, Class A 705.00 Cu.m. 3,492.65 2,462,318.25 6.476%
505(a) Grouted Riprap, Class B (Line Canal) 170.00 Cu.m. 3,173.80 539,546.00 1.419%
507 Rubble Concrete 259.40 Cu.m. 3,594.34 932,371.80 2.452%
508 Hand Laid Rock Embankment 410.02 Cu.m. 2,000.50 820,245.01 2.157%
622(2) Bio-Engineered Coco Fiber Erosion Control 1,650.00 Sq.m. 292.15 482,047.50 1.268%
622(3) Bio-Engineered Erosion Control System (Vegetation) 1,650.00 Sq.m. 185.61 306,256.50 0.805%
OTHER ITEMS
605(2) Regulatory Signs (60cm Triangle) 2.00 Each 12,111.76 24,223.52 0.064%
SPL 1 Mobilization & Demobilization 1.00 LS 191,800.00 191,800.00 0.504%
TOTAL 38,024,766.50 100.00%

Prepared by: Checked & Verified by: Approved by


ENGR. JESUS A. MANIAGO JR.
Project Engineer Authorized Managing Officer
Date Started:
Target Completion Date:
% Proj. Accomp. To Date:
Slippage;

T OF WORK ACCOMPLISHMENT (SWA)


AS OF :

ACCOMPLISHMENT
% Wt. REMARKS
% ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT ACCOMP.
THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE

Approved by:
TESSIE J. YU
Proprietor