Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DAY 5
22 May 2020
PART ONE
Quantification of Works during
various Stages of works
HIERARCHY OF ESTIMATES
COST PER SQ M OF
ELEMENTAL COST INDIVIDUAL ELEMENTS
DESIGN
DEVELOPMENT
COMPOSITE ITEMS &
APPROX. QTYS OR BUILDER’S RATES
QUANTITIES
+/- 20 – 100%
+/- 20 – +/- 10 – +/- 5 – 15%
50% 25%
COST ESTIMATING--
PRINCIPLE OF COSTING
Indirect Costs
• Main Contractor’s Overheads- Cost of maintaining the head office + Return on capital
investment
• Main Contractor’s Preliminary- Cost of maintaining the site establishment+ Cost not
Adaptation
attributable directly to work+ Program
insurance bondsin,Quantity Surveying
warranties etc.
(APQS)
What is a Cost Estimate??
A guess work - but an informed one !
Adaptation Program in Quantity Surveying (APQS)
An estimate is the anticipated or probable cost of a work and is usually prepared before
construction is taken up
The estimate is prepared by identifying the scope of work, computing / calculating the
quantities of items of work required and then calculating the cost at suitable rate –accuracy
depends on (the accuracy of Data and the Rate)
Needs substantiation of the figures used ( previous works, experience, database maintained
etc.)
Leads to a better understanding of the problem (Narrow Down the Unknown area and have
judicious approach),
Improves management insight into resource allocation ( remain cautious in problemetic
area)
Provides an objective baselineAdaptation
to measureProgram
progress.
in Quantity Surveying
(APQS)
Cost Estimate Cannot:
Adaptation Program in Quantity Surveying (APQS)
Be applied with
Substitute for sound
cookbook precision,
judgment, or
but must be tailored
management control
to a particular system
• Cost Information
• Source of cost data
• Supplier’s / Sub-contractor’s quotations
• Use of previous cost data
• Use of previous cost analysis
• Application of tender price indices
• Reasonable % allowances
• Inclusions & exclusions
• Market Information
• Market conditions (e.g. inflation / deflation etc.)
• Rapid change of material (e.g. huge variations in Cement)
• Change of labour costs (e.g. geography/ time)
• A. CLASSIFICATION OF AREAS
• NET FLOOR AREA (NFA)
In most countries, NFA is the area contained within
the external walls of the building measured at each
floor level (including any floor below the level of the
ground), together with the area of balconies and the
thickness of external walls (for submission to
Planning Authorities) Note : Carpark & plant room
areas are usually excluded, but this is NOT a fixed
rule. It depends on country specific regulations, bye
laws/Rules
• A. CLASSIFICATION OF AREAS
Total Constrn Costs = Constrn Floor Area (CFA) x Unit Rate (Rs/CFA)
CFA
• Land & development conditions (e.g. site area, plot ratio, site coverage, height limitation &
NFA)
• Maximum buildable area = site area x approved plot ratio
• Approx. CFA = site coverage area x no. of floor (for building with full site
coverage)
• Approx. CFA = NFA x conversion factor (1.15-1.30 for residential, 1.25-
1.35 for office) or as per Bye-Laws
Unit Rate
• Location factors
• Specification level
• Construction methods
• Cost analysis of previous similar projects
• Adjustment of price index
• 200 Room Hotel (3*)= 55m2 to 100m2 per room/key x Rs B/Key. @ 60L= Rs 120Cr
Elemental Quantity
• Design information (e.g. Architect’s first sketch design)
• Analysis of previous similar projects
Elemental Unit Rate
• Location factors
• Specification level
• Construction methods
• Cost analysis of previous similar projects
• Adjustment of price index
Allowance for
• Preliminaries
• Contingencies
Techni
cal
specifi Labor
cations
Plant
Client’s Qualit How to
y Estimat Materi Cost per
Requir do the unit
Requir e Inputs al- Estim
ement job
ement Calcul e
ate
Quanti
Site ty
Conditi Sub-
ons contrac
Degree of Approximation tors Accuracy
Cost ( Amount
Accuracy
of Effort)
Ease of Difficult to
Measurement measure
Risk Reduction- Risk is unacceptable but mitigating steps can be taken which would reduce risk
Risk Retention- Risk which is not controllable and hence resides with the owner
QUESTIONS?
• Consistency
• Same items in each element-avoid payment more than once due to overlap
exclusions in an item.
information, knowledge)
• Based on trades
• Divided into sections based on trades
• Identifies measurements rules for measuring various scenarios
• Specifies that Bills of Quantities - The bills of quantities shall
fully describe the materials and workmanship, and accurately
represent the work to be executed
• The item descriptions are elaborate
• Seldom linked to detailed specifications and drawings
• Does not fully cater to the requirements of modern construction
methods
• Does not give any guidance on preliminaries, cost planning
principles, presentation of bills of quantities
• Elaborate on MEP services and other non-building related works
underside)
• Where inclination to horizontal plane exceeds 30 (where shuttering may be provided both on the
0
underside and upper side if required ) (The only underside area to be measured).
• Up to 6 m span
• Above 6 m span
• Cylindrical Shells ( Area of Underside lo be Measured)
• Radius less than 3 m
• Radius above 3 m
• Waffle or ribbed slabs where shuttering is required for the bottom
inclined surface;
• Dormer vaults and shell roofs having curved surfaces in both
directions (Only the area of underside shall be measured)
• Sides and soffits of beams, beam haunchings, cantilevers, girders,
bressummers, and lintels; beams and girders 1 m deep and over
shall be measured separately;
• Sides of columns, piers, pillars, posts and stanchions and struts
(square/rectangular/polygonal/circular/curved to be measured
separately)
• Edges of slabs and breaks in floors and walls (To be measured in
running meters where under 203 mm width or thickness).
Adaptation Program in Quantity Surveying
(APQS)
PART 5-FORMWORK
• Cornices and moldings.
Adaptation Program in Quantity Surveying (APQS)
62
edition)
• intended to be used only for civil engineering works and
simple building works incidental to civil engineering works
• does not deal with the preparation of Bills of Quantities for
complex mechanical or electrical engineering work, or
complex building work or work which is seldom encountered
in civil engineering contracts
• This defines
• how work is to be divided into separate items in the Bill of
Quantities
• the information to be given in item descriptions
• the units in which the quantities against each item are to be
expressed
• how the work is to be measured for the purpose of calculating
quantities Adaptation Program in Quantity Surveying
(APQS)
CESMM4
• 26 Main Classes (A to Z) - 3 division each – upto 8
Adaptation Program in Quantity Surveying (APQS)
SMM7 CESMM4
• Document for • Defines procedure for
measurement BOQ preparation &
• Does not set out rules pricing, expressed and
for production of BoQ measured
• Requires more detailed • Many items deemed
items of BoQ included in one item
• Suitable for building • Suitable for Civil
projects (more items, Engineering works
less quantities) (Less items, more
quantities)
QUESTIONS?
DAY 5
POST LUNCH
DEVELOPMENT OF ESTIMATES-PRE
TENDER
PART 3
• Approximate Estimate: including Cost capacity
factors and cost Indices during Feasibility stage;
• Pre Tender Estimate including first principle
analysis during Planning stage
• Prime Cost Sum and Provisional Sum
Adaptation Program in Quantity Surveying
(APQS)
LEARNING OUTCOMES
Adaptation Program in Quantity Surveying (APQS)
Cost indices show the changes of a certain facility’s costs over time
Year 1913 = 100, …Year 2007 = 4432
If Facility A is similar to my ‘wish’ facility and I know the value of Facility A at 1913,
I can assume my ‘wish’ facility’s value at 2007.
Source: http://www.enr.com/features/conEco/
• PUBLISHED PERIODICALLY BY
ENGINEERING NEWS RECORD (ENR) AND
OTHER PUBLICATIONS. ENR’S BUILDING
COST INDEX (BCI): CHANGES OF
FACILITY’S COSTS OVER TIME
Source: http://www.enr.com/features/conEco/
Source: http://www.enr.com/features/conEco/
ANNUAL
JAN. FEB. MARCH APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
AVG.
1990 2664 2668 2673 2676 2691 2715 2716 2716 2730 2728 2730 2720 2702
1991 2720 2716 2715 2709 2723 2733 2757 2792 2785 2786 2791 2784 2751
1992 2784 2775 2799 2809 2828 2838 2845 2854 2857 2867 2873 2875 2834
1993 2886 2886 2915 2976 3071 3066 3038 3014 3009 3016 3029 3046 2996
1994 3071 3106 3116 3127 3125 3115 3107 3109 3116 3116 3109 3110 3111
1995 3112 3111 3103 3100 3096 3095 3114 3121 3109 3117 3131 3128 3111
1996 3127 3131 3135 3148 3161 3178 3190 3223 3246 3284 3304 3311 3203
1997 3332 3333 3323 3364 3377 3396 3392 3385 3378 3372 3350 3370 3364
1998 3363 3372 3368 3375 3374 3379 3382 3391 3414 3423 3424 3419 3391
1999 3425 3417 3411 3421 3422 3433 3460 3474 3504 3505 3498 3497 3456
ANNUAL
JAN. FEB. MARCH APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC.
AVG.
2000 3503 3523 3536 3534 3558 3553 3545 3546 3539 3547 3541 3548 3539
2001 3545 3536 3541 3541 3547 3572 3625 3605 3597 3602 3596 3577 3574
2002 3581 3581 3597 3583 3612 3624 3652 3648 3655 3651 3654 3640 3623
2003 3648 3655 3649 3652 3660 3677 3684 3712 3717 3745 3766 3758 3694
2004 3767 3802 3859 3908 3955 3996 4013 4027 4103 4129 4128 4123 3984
2005 4112 4116 4127 4167 4188 4194 4196 4209 4218 4265 4312 4329 4203
Source: http://www.enr.com/features/conEco/
• EXAMPLE:
• COST INDEX=4432/2996=1.479
• $X =1.479*$4,200,000 = $6,213,084
Adapted from: Barrie & Paulson, 1992
Source: http://www.enr.com/features/conEco/
costIndexes/constIndexHist.asp
ACTUAL COSTS
• WHERE
• C2 = ESTIMATED COST OF THE NEW FACILITY
W/CAPACITY Q2
• C1 = KNOWN COST OF FACILITY OF CAPACITY Q1
• X = THE COST-CAPACITY FACTOR FOR THIS TYPE
OF WORK Adaptation Program in Quantity Surveying
(APQS)
COST-CAPACITY FACTOR
Adaptation Program in Quantity Surveying (APQS)
EXAMPLE REVISIT:
EXAMPLE REVISIT:
• C2 = UNKNOWN COST;
• Q2 = CAPACITY REQUIRED
• Q1 = EARLIER CAPACITY
• CONSIDERATIONS
• LOCATION OF JOBSITE (LOCAL SKILL BASE,
JURISDICTION RULES – HIRING & FIRING)
• LEARNING CURVES
• WORK SCHEDULE (OVERTIME, SHIFT WORK)
• WEATHER
• ENVIRONMENT
• LOCATION ON JOBSITE, NOISE, PROXIMITY TO
MATERIALS
• MANAGEMENT STYLE (E.G., INCENTIVE)
• WORKSITE RULES
• Unit-price
• Professional CM
Adaptation Program in Quantity Surveying
• Design-Build (APQS)
Definitive Estimates: Types & Timing
Adaptation Program in Quantity Surveying (APQS)
• Lumpsum
• Unit Price
• Design-Build
• Based on B.Q.
• Priced in current unit rates
• Supplier’s / Sub-contractor’s quotations
• Recent returned tenders
• Cost analysis of previous similar projects
• Adjustment of price index
105
• Contractor’s estimate low enough to obtain the work, yet high enough to
make profit
• Who? – contractor
• More detail depending upon the contractor’s own procedures
• Overall unit prices (past) → detailed categories (present)
• Often relies on
OPTIONS
• CRANE BASES (LEVEL B3); LEVEL B3 BASES AND PITS; LEVEL B3 SLABS;
LEVEL B3 LINING WALLS; LEVEL B3 COLUMNS; LEVEL B3 STAIRS (STEPS
FOR CHANGE IN LEVELS); LEVEL B3 SERVICE TUNNEL
• LEVEL B2 SLABS; LEVEL B2 UPSTANDS;
• LEVEL B1 SLABS; LEVEL B1 UPSTANDS
• GROUND FLOOR SLABS; GROUND FLOOR UPSTANDS
• CORE A (LEVEL B3 TO ROOF)
• CORE B (GROUND TO LEVEL 4)
• CORE C (LEVEL B2 TO ROOF)
• CORE CAPPING SLABS
• BELOW SLAB DRAINAGE
• ANCILLARY ITEMS - EARTHING PITS, COLUMN STRENGTHENING, ETC.
PROVISIONAL SUM
PRIME COST SUM
• PROVISIONAL
NOT FULLY WORKED OUT, AGREED UPON OR FINAL AND
IS PROVIDED TO SERVE OR ACT AS SUFFICIENT FOR
THE TIME BEING-SUBJECT TO REVIEW, ADJUSTMENT
OR CHANGE.
• PROVISIONAL SUM
A REASONABLE ESTIMATE OF THE COST (OR PRICE) OF
CERTAIN WORKS, IF THE BUILDER, AFTER MAKING
REASONABLE INQUIRIES, CANNOT GIVE A DEFINITE
PRICE WHEN THE CONTRACT IS SIGNED
• HEATING,
• AIR CONDITIONING,
• LANDSCAPING,
• REPAIRS
• DAMP-PROOFING COURSES IN EXISTING
MASONRY WALLS WHERE THE EXTENT OF THE
PROBLEM IS YET TO BE UNCOVERED OR
DETERMINED.
• FUNCTIONS OF ESTIMATING
QUESTIONS?
References:
A project manager’s guide to cost estimating and cost planning by-
Karl Medak Frame’s General Manager Solution & Delivery
Introduction to Estimating for Construction by Brian Greenhalgh, Routledge, London (2013)