PROJECT NAME & LOGOS

CHECK LIST FOR: Form No:


INSTALLATION OF CHILLED WATER EXPANSION TANK & Rev. No: 0
PRESSURIZATION UNIT
Page : 1 of 1
SUBCONTRACTOR X CONTRACTOR

SECTION OF WORK: MECHANICAL LOCATION:


LEVEL: WIR No.:
STAGE ITEM Checked by Checked Date
by

S/C CONT CONS.

SETTING Check Layout & details of installation


OUT Check Level.
Ensure material is approved via MIR.
MEP/CIVIL Check for Services Clearances.
1. Check model no., type, electrical components & capacity of
the units as per the approved technical details.

2. Check any damages incurred during rigging & installations.

3. Check if all piping is correctly installed with the correct size.


4. Check for any visible damage to the units which occur during
the installation.
5. Ensure flow switches, pressure switches, isolation valves,
pressure gauges, flow balancing valves, vent cocks, drains &
Installation

thermometer wells are correctly & properly fixed.


6. Verify if water meter has been provided.
7. Check the proper clearances around the unit been
maintained as per the submittal or manufacturers’
recommendation.
8. Check all electrical connections if properly connected &
wired.
9. Check the unit if accessible & does not clash with other
services.
10. Check the foundation of the units meets the requirement of
the specification.
11. Verify all safety precautions have been complied before &
after the unit installation.

For S/C QA/QC: Date: FOR CONTRACTOR Date: For CONS. Date:
QA/QC: Rep.:

Name: Sign: Name: Sign: Name: Sign: