API new edition may be used beginning with the date of issuing but it be comes
immediately after six month from the date of issuance.
During the six months time, uses shall specify to which addition, agenda the equipment is
to be rerated & inspected.
For 31.3 the above requirement is applicable unless a specific agreement between
contracts parties to use another addition or agenda.
API-570 is applicable for repair, alteration and re rating of METALIC PIPING that are IN
INSERVIVE.
It is developed for petroleum refining & chemical process industries, may be used where
practical for other piping system.
It is intended for use by organizations that maintain Inspection department, repair
capabilities, qualified Piping Engineer, Inspector & Examiners.
It shall not be used as a substitute for the original construction requirements governing a
piping system before it is placed in service.
Fluid service like water (including fire protection system) steam, steam-condensate, Boiler
feed water & category ‘D’ fluid service are EXCLUDED from API 570.
Following class of piping system are excluded :
o Piping on Truck,barg, other mobile equipment (movable structure)
o Piping on pump, compressors, turbines, generators, Engine & Hydraulic or
Pneumatic cylinder (Integral part of component)
o Internal piping of fired heaters boilers, tubes, tube header.
o Internal piping & External connection of pressure vessels etc.
o Plumbing, sanitary sources, process work server, storm sources.
o Piping or tubing outside water that of NPS 1/2” (<1/2”).
o Non metallic piping, polymeric or glass line piping.
API-RP-579- Fitness for service (provide generate requirements and detailed assessment
procedure for specific types of degradation.
Publ 2201- Hot-tapping procedure.
API-RP-574- Inspection of piping system components.
API-RP-578- Material verification program.
Authorized Inspection Agencies :
o Owner or User
o Contractor to owner.
o Govt Jurisdiction.
o Govt approved agency
o Insurance.
Auxiliary piping- Instrument & machinery piping like small bore piping ex: Flush line, Seal
oil lines, analyzer line, drain 7 vents etc.
CUI- Corrosion under insulation.
Dead legs- no significant flow – spare pump piping, control valve by pass lines, level bridle,
relief valve inlet & outlet, height point vents, sample points, drains, bleeders, instrument
connections.
Hold point- work may not proceed until inspection done.
Injection point: Locations where two process stream joining are not considered as injection
point (Mixing Tees).
Example of Injection points: Chlorine in re-formers, Polysulfide in Catalytic cracking wet
gas, Antifoam injections, and Inhibitors neutralizers.
NPS; Nominal pipe size, specific size designation without an inch symbol.
Piping circuit: Section of piping that has all points exposed to an environment of similar
corrosivity, design condition & Construction material.
Piping system; Assembly of interconnected piping that is subjected to the same set of
design condition.
Primary process piping: In normal active service that can not be isolated greater than 2”
NPS.
Rerating: A change in design temp or MAWP of piping system may consists of an increase,
decrease or a combination of both Derating below original design condition is a means to
provide increased corrosion allowance.
Soil to air (S/A) Interface: Corrosion will vary depending on factors such as moisture,
oxygen content in the soil & operating temp. Zone in 6” above 12” below the soil 6/12.
Temperature embrittlement: Loss of ductility & notch toughness in low alloy steels (1¼
Cr 2¼ Cr) due to prolonged exposure to high temp service (370°-575°C).
Test point: Area defined by circle 2”dia upto 10” pipe line, 3” dia above 10’’ pipe line.
Material verification program: Procedure used to assess metallic alloy materials.
PMI Testing: physical evaluation or test of material.
Section A
Authorized Inspector Duties:
Determine that the requirements of API 570 on inspection, examination & testing are met.
Directly involved in the inspection activities.
All examination results shall be evaluated & accepted by the Authorized Inspection.
Appendix A
INSPECTOR CERTIFICATION:
Examination shall be based on the current API body of knowledge.
Education + Experience requirement in addition to exam.
o BS degree + One year experience = Inspection Exp.
o 2 years Diploma + 2 years experience = 1 year Inspection Exp.
o High school + 3 years experience = 1 year Inspection Exp.
o No Qualification + 5 years experience = 1 year Inspection Exp.
Certification is valid for 3 years.
Recertification every 3 years, by written test if inspector is not activity engaged as AI.
Activity engaged as an Ai shall be defined as a minimum 20% of time spent performing or
supervising inspection activities during 3 years certification period.
Section 5
Risk based Inspection: Combing the assessment like wood of failure and the
consequence of failure are the essential elements of RBI.
Assessment includes: Check material, design condition relative operating condition,
design codes & standard used, effectiveness of corrosion monitory, quality of maintenance
& QA/QC programs, equipment failure data & Information.
Consequences includes: Potential incident that may occur as a result failure like-
explosion, fire, toxic exposures, environment impact, health effects.
Preparation: Isolation, PTW, PPE, NDE equipment are safe to use, Review history of
individual piping system.
Injection points: Considered separate inspection circuits. Injection point circuit is
Upstream: 12” or 3 pipe diameter which ever is greater
Downstream: Second change in flow direction or 25 feet (7.6m) which ever is less.
TML Location
o On fittings
o Impingement location
o On longest straight pipe
o At up stream & down stream limit
Preferred method of inspection is RT or UT
During periodic inspection extensive inspection
Up stream 12”, Down stream 10 pipe diameter
Dead leg: Hot piping system high part area more corrosive due to convention current
set up in the dead leg.
CUI: sources of moisture rain, water leaks, condensation and deluge system
C.S – localized corrosion, SS chloride test corrosion crack
Warmer marine location requires extensive inspection program
C.S piping system insulated personal protection 25ºF to 250ºF cut is aggressive were
operative temperature causes frequent condensation and re-evaporation
C.S piping normally in-service > than 250ºF but intermitted
SS piping operating between 150ºF to 400ºF
C.S piping above 250ºF no problems of CUI
SS piping below 150ºF and above 400ºF no problem of CUI
Soil to air interface (S/A): if buried piping uncoated at the grade, consideration should be
given to excavating 6” to 12” (150 mm to 350mm) deep.
Erosion can be characterizes by grooves, rounded holes, waves and valleys in a directional
pattern. It usually occurs in areas of turbulent flow change of flow direction, control valve
down stream where vaporization occurs.
Due to high velocity flowing of solid or liquid will increase erosion danger.
Velocity sensitive system are hydro sulphide & Sulfuric Acid.
Environment cracking: polythionic acid SCC of sanitized austenitic alloy steel, caustic in
carbon steel amine SCC in piping not PWHT
Corrosion under lining coating: separation, breaks, holes and blisters and noted, than
lining should be remove
o Bulging or separation in refractory lining is an indication of corrosion.
Fatigue cracking: due to cyclic stress may be improved pressure, mechanical or thermal
means, low cycle fatigue – heat up or cold down, high cycle – vibration
Creep cracking: It is depended on time, temperature and stress brittle fracture: C.S., low
alloy and ferritic steel, are susceptable to brittle failure. It is not an concern with relatively
thin wall piping. Special attention to low alloy steel (2¼” CR – 1 MO material) there are
prone to temper embrittlement
Freeze damage
Thickness measurement method pipe larger than PMS 1” – UT is preferred less than 1
PMS preferred When UT is surface 150ºF should be careful