Sei sulla pagina 1di 14

C- 1

DEVELOPMENT OF TOYOTA ROUNDABOUT


AT NATIONAL HIGHWAY-KARACHI
COST ESTIMATE
Item Description BOQ ACTUAL ADDITIONAL
Unit RATE
No. Qty Amount Qty Amount Qty Amount
CIVIL WORKS
SITE CLEARANCE AND DEMOLITION WORK
1C Site clearance consisting removal of loose materials, excavation of unsuitable
materials, leveling, dressing, compaction of existing ground and disposal of
removed materials to designated places including loading, unloading, carting to
Job 25,000.0 1 25,000 1.0 25,000 - -
designated places outside Municipal limits complete in all respect.

2C Dismantling of existing footpath, pavers, kerbstone etc. including stacking of


useable materials, disposal of unused dismantled/ removed materials including
loading, unloading, carting to designated places outside Municipal limits complete
Job 50,000.0 1 50,000 1.0 50,000 - -
in all respect.

3C Relocation/ shifting of existing light poles with care without any damaging
including refixing with CC foundation and repainting of poles complete in all
respect as shown on the drawings or as directed by the Engineer. Job 50,000.0 2 100,000 2.0 100,000 - -

EARTH WORKS - - -
4C Excavation in all kinds of sub-surface materials upto required depth including
disposal of surplus/ rejected excavated material to designated places. Cft. 50.00 10,000.00 500,000 28,610.21 1,430,510 18,610.2 930,510

5C Back fill with selected material obtained from required excavation including
compaction. Cft. 40.00 4,300 172,000 - (4,300.0) (172,000)

6C Providing and filling approved selected earth including leveling, dressing and
compact in layers of 9" thick (compacted to 95% Modified Proctor's Relative Dry
Density) including the cost of laboratory and field density tests, spreading,
levelling, dressing and watering, all lead and lift etc.; complete in all respect as Cft. 40.00 13,400 536,000 21,620.18 864,807 8,220.2 328,807
shown on Drawings and as instructed by the Engineer.

PLAIN AND REINFORCED CONCRETE


7C Providing and laying of cement concrete 1:4:8 using sulphate resistant cement and
crushed stone as specified. Cft. 210.00 2,000 420,000 991.14 208,138 (1,008.9) (211,862)

8C Providing and placing 4000 PSI reinforced cement concrete in following structures
using crushed graded stone 3/4" and down gauge including machine mixing,
transporting, hoisting, placing in position in steel formwork, vibrating, curing,
removal of formwork etc; complete as per drawings, instructions of the Engineer - - -
(excluding the cost of reinforcement).

-
a) Foundation Cft. 360.00 2,300.00 828,000 2,709.88 975,555 409.9 147,555
b) Walls upto plinth Cft. 450.00 965 434,250 1,543.00 694,350 578.0 260,100
c) Underground water tank Cft. 450.00 310.00 139,500 281.36 126,614 (28.6) (12,886)
9C Providing and laying fairfaced 1:2:4 plain cement concrete situ wall using sulphate
resistant cement including steel form work as specified. Cft. 415.00 550 228,250 2,277.01 944,959 1,727.0 716,709

10C Providing and placing 4000 PSI fine fairfaced reinforced cement concrete walls in
superstructures/ above plinth as per design and elevation using crushed graded stone
3/4" and down gauge including machine mixing, transporting, hoisting, placing in
position in marine ply formwork, vibrating, curing, removal of formwork etc;
complete as per drawings, instructions of the Engineer (excluding the cost of Cft. 550.00 2,600.00 1,430,000 2,509.92 1,380,455 (90.1) (49,545)
reinforcement).

STEEL REINFORCEMENT - - - -
11C Providing and Fixing of mild steel bars round, using deformed bars grade 60
including cutting, bending, binding and placing reinforcement in position at any tonne 155,000.0 11 1,705,000 16.4 2,536,938 5.4 831,938
level and height.
C- 2

DEVELOPMENT OF TOYOTA ROUNDABOUT


AT NATIONAL HIGHWAY-KARACHI
COST ESTIMATE
Item Description BOQ ACTUAL ADDITIONAL
Unit RATE
No. Qty Amount Qty Amount Qty Amount
FLOORING AND WALL FINISHES - - - -
12C Providing and laying 6" thick compacted stone soling including spreading, levelling,
watering, compacting, filling with chips and spawls etc. complete in all respect. Sft. 40.00 600.00 24,000 676.00 27,040 76.0 3,040

13C Providing and laying Precast 80mm thick CC paving stone (Envicrete or approved
equivalent) in natural colour over footpath laid in approved pattern including 2"
thick sand cushion and 4" thick 1:4:8 cement concrete base complete in all respect
as shown on drawings and as directed by the Engineer. Sft. 220.00 3,000 660,000 1,756.37 386,400 (1,243.6) (273,600)

14C Providing and fixing 3/4" thick prepolished granite of approved quality, colour and
shade, as per design and elevation including fixing and fixing accessories complete
in all respect as shown on the drawings or as directed by the Engineer. Sft. 1,050.0 1,800 1,890,000 1,616.3 1,697,149 (183.7) (192,851)

15C Providing and applying 3/4" thick, 1:4 cement sand water proof plaster mixed with
Pudlo or other similar approved material mix with cement @ 3% by weight finished
as specified

a) Underground water tank Sft. 60.0 800 48,000 220.5 13,227 (579.5) (34,773)
b) Inside Planter walls Sft. 60.0 3,700 222,000 - (3,700.0) (222,000)
16C Providing and fixing full body porcelain tile textured finished to planter outer
surfaces of approved quality, colour and shade, as per design and elevation
including fixing and fixing accessories complete in all respect as shown on the
Sft. 350.0 1,700 595,000 - - (1,700.0) (595,000)
drawings or as directed by the Engineer.

LANDSCAPING - - - -
17C Selected/ approved sweet earth 12" depth (Garden soil) including levelling, dressing
and compaction complete in all respects as shown on the drawings, specifications or
as directed by the Engineer. Cft. 40.00 6,500 260,000 4,516.00 180,640 (1,984.0) (79,360)

18C Development of Dhaka lawn grass including 3" thick approved fertilizer and water
including mixing of fertilizer with topsoil, watering till maintenance period, rolling,
cutting, trimming and pesticides etc. complete in all respect as shown on
Drawings, specifications and as instructed by the Engineer. Sft. 84.00 5,000 420,000 3,435.74 288,602 (1,564.3) (131,398)

PRECAST EDGE & KERB STONE


19C Precast fairfaced cement concrete Kerbstone (1:1-1/2:3, 3750 PSI concrete)
(Envicrete or approved equivalent) of size 6"x12"x18" set in 1:4 cement sand mortar
including earthworks, concrete (1:3:6) base & side etc. complete in all respect as
Rft. 2,500 660 1,650,000 585 1,463,650 (74.5) (186,350)
shown on the drawings and/or as directed by the Engineer.

20C Precast fairfaced Cement concrete Edge Stone (1:1-1/2:3, 3750 PSI concrete ) of
approved size set in 1:4 cement sand mortar including earthworks, concrete (1:3:6)
base & side etc. complete in all respect as shown on the drawings and/or as directed
Rft. 1,500 300 450,000 - (300.0) (450,000)
by the Engineer.

PAINTING - - - -
21C Providing and applying Three or more coats of synthetic enamel paint to kerbstones
including primer coat and surface preparation complete in all respect as shown on
the drawings at any floor. Sft. 60.0 1,000 60,000 574.9 34,494 (425.1) (25,506)

22C Providing and applying two coats of Jotashield colour extreme textured finish
to exterior surfaces (manufactured by JOTUN PAINTS or approved equivalent)
comprising 100% acrylic emulsion coating including primer and surface preparation
complete in all respect as shown on the drawings, specifications and as per Sft. 70.0 2,600 182,000 - (2,600.0) (182,000)
manufacturer's specifications.
C- 3

DEVELOPMENT OF TOYOTA ROUNDABOUT


AT NATIONAL HIGHWAY-KARACHI
COST ESTIMATE
Item Description BOQ ACTUAL ADDITIONAL
Unit RATE
No. Qty Amount Qty Amount Qty Amount
BITUMEN COATING TO FOUNDATIONS - - - -
23C Two coat of Bitumen emulsion with primer to all exposed reinforced concrete
surfaces in contract with earth. Sft. 50.0 2,800 140,000 2,124.1 106,205 (675.9) (33,795)

M.S boundary Railing and Alphabet - - - -


24C Providing, fabricating and fixing m.s. painted boundary railing and alphabets
including fixing and fixing accessories complete in all respect as shown on the Job 1,449,000.0 1 1,449,000 1.0 1,449,000 - -
drawings.

ALUMINIUM POWDER COATED STRIPS - - - -


25C Providing, fabricating and fixing powder coated aluminium strips as per design and
elevation of approved quality and colur including fixing and fixing accessories
complete in all respect as shown on the drawings. Sft. 1,250.0 650 812,500 663.1 828,844 13.1 16,344

S.S. LOGO - - -
26C Providing and fixing stainless steel logo as per design and size as shown on
drawings including fixing and fixing accessories complete in all respect as shown on No. 200,000.0 3 600,000 - (3.0) (600,000)
the drawings.
Hard Barrication - - -
27C Providing and fixing of Hard Barication With GI or Corrogated Sheet with the help
of Scaffolding Pipe or Square pipe at required hieght 3m min also including
removing of Material after completion of job . No. 50,000.0 3 150,000 3.0 150,000 - -

TOTAL COST OF CIVIL WORKS 16,180,500 15,962,580 (217,920)

( A )= Total Cost After Rebate of 8% 14,886,060 14,685,573 (200,487)

NON BOQ ITEM


Item Description BOQ ACTUAL ADDITIONAL
Unit RATE
No. Qty Amount Qty Amount Qty Amount
Hard Barrication
28 Providing and fixing of Sign Board Job. 245,000 - - 1.0 245,000 1.0 245,000

Fair Face Plaster Sft 600.0 2,434.3 1,460,599 2,434.3 1,460,599

Walk Way Tiles Sft 290.0 340.0 98,600 340.0 98,600

Granite Tile Sft 490.0 1,616.3 792,003 1,616.3 792,003

Plantation Job 250000 1 250,000 1.0 250,000

Total Repair Works Job 375,000 1 375,000 1.0 375,000

Guard, Gardener and Water Job 606666 1 606,666.00


( B )= Total Cost For Addttional Work - 3,827,868 3,221,202
Total Cost For (A + B ) 14,886,060 18,513,442 3,020,716
NOTE :
1. IMC will not provide any kind of utility (Gas.Electric,Water etc) & also Material furhter.
2. Any approval of working from Govt. agencies will be IMC responsibility.
3. Contractor Must Be Used ready Mix Concrete.
FIVE STAR CONSTRUCTION COMPANY
MEASURMENT SHEET

Monument at Port Qasim

S.No Description Unit Nos Length Width Depth / Height Total

4C Excavation
1 Area 1 Cu.ct 1 43.58 4.50 26,853.02
2 Area2 Cu.ft 1 49.58 1.00 7,724.52
Deduction for area 2 Cu.ft 1 43.58 1.00 (5,967.34)
Total Excavation Total 28,610.21
6C Backfill
1 Total Excavated Cu.ft 1 28,610.21

Concrete Volume Backfill Deduct -


Raft Lean Cu.ft -1 25.00 25.00 0.50 (312.50)
Tank Lean Cu.ft -1 13.00 9.50 0.50 (61.75)
Lean Concrete for Walk Way Cu.ft -2 20.00 8.50 0.33 (112.20)
Raft Soling Cu.ft -1 26.00 26.00 0.50 (338.00)
Underground Water Tank Cu.ft -1 8.50 12.00 7.08 (722.16)
Raft 1:2:4 Concrete Cu.ft -1 24.00 24.00 2.50 (1,440.00)
Planter Wall Base Concrete Cu.ft -1 177.00 2.50 1.00 (442.50)
Tower 1 28' Cu.ft -1 7.00 12.00 3.50 (294.00)
Tower 1 28' Cu.ft -1 7.00 12.00 3.50 (294.00)
Tower 3 42' Cu.ft -1 7.00 12.00 3.50 (294.00)
Underground Water Tank Cu.ft -1 8.50 12.00 7.08 (722.16)
Planter Situ Wall Concrete +3 Cu.ft -1 12.00 6.50 0.50 (39.00)
Planter Wall Concrete +5 Cu.ft -1 90.00 6.00 0.50 (270.00)
Planter Wall Concrete +4 Cu.ft -1 30.00 6.00 0.50 (90.00)
Planter Wall Concrete +3 Cu.ft -1 12.00 6.00 0.50 (36.00)
Planter R.C.C Wall Concrete +5 Cu.ft -1 6.00 8.00 0.50 (24.00)
Planter R.C.C Wall Concrete +4 Cu.ft -1 35.00 6.00 0.50 (105.00)
Planter R.C.C Wall Concrete +3 Cu.ft -1 110.00 5.50 0.50 (302.50)
Planter R.C.C Wall Concrete +3 Cu.ft -1 24.00 5.00 0.50 (60.00)
Raft Walls Cu.ft -4 24.00 4.00 0.67 (257.28)
Inside Curb Retaining Wall RCC Cu.ft -1 256.59 0.67 3.25 (558.72)
Inside Curb Retaining Wall Base Cu.ft -1 256.59 0.50 1.67 (214.25)
Total (6,990.03)

Total Concrete Volume of area Total (6,990.03)


Total 21,620.18
PLAIN AND REINFORCED CONCRETE
3 Lean 1 : 4 : 8 Concrete
a Raft Cu.ft 1 25.00 25.00 0.50 312.50
b Tank Cu.ft 1 13.00 9.50 0.50 61.75
a Outer wall Cu.ft 1 185.00 3.50 0.50 323.75
b Inner wall Cu.ft 1 132.00 1.50 0.50 99.00
7c Lean Concrete for Floor +6 Ft Level Cu.ft 1 23.33 23.33 0.33 179.62
Deduction for towers Cu.ft 3 12.00 3.50 0.33 (41.58)
7c Lean Concrete for Walk Way Cu.ft 2 20.00 8.50 0.33 56.10
Total 991.14
LANDSCAPING
Grass Work
3 Total Area 1 40.83 40.83 3.14 5,237.99
Deduction -
Area of Monument Cu.ft -1 38.50 38.50 (1,482.25)
Area of Walk way Cu.ft -2 20.00 8.00 (320.00)
Total 3,435.74
2 Stone soling
a Raft Cu.ft 1 26.00 26.00 676.00
Total 676.00
5 Reinforced Cement Concrete
Underground Water Tank
Tank Bottom Slab Cu.ft 1 12.00 8.50 0.83 84.66
Deduction for Cover Cu.ft -1 2.00 2.00 0.50 (2.00)
Tank Top Slab Cu.ft 1 12.00 8.50 0.50 51.00
Tank Walls Longer side Cu.ft 2 12.00 5.75 0.67 92.46
Tank Walls Shorter side Cu.ft 2 7.17 5.75 0.67 55.24
Total 281.36
Base
Raft Cu.ft 1 24.00 24.00 2.50 1,440.00
Concrete Walkway Cu.ft 2 20.00 8.50 0.50 170.00
RCC Planter Wall Base Concrete Cu.ft 1 177.00 2.75 1.00 486.75
Inside Curb Retaining Wall Base Cu.ft 1 268.60 2.00 0.50 268.60
Outer Curb Retaining Wall Base Cu.ft 1 306.25 2.25 0.50 344.53
Total 2,709.88
Walls Upto Plinth & Above

Tower 1 20' Cu.ft 1 27.00 12.00 3.50 1,134.00


Tower 2 28' Cu.ft 1 35.00 12.00 3.50 1,470.00
Tower 3 36' Cu.ft 1 43.00 12.00 3.50 1,806.00
Deduction Punch portion
Base to el +6' Cu.ft 4 8.25 7.00 0.50 (115.50)
Base to El+6+ Cu.ft 2 2.00 7.00 0.75 (21.00)
El+6' to top of inclination Cu.ft 4 8.25 15.00 0.75 (371.25)

Deduction ellipse
Elipse Dimension 8'-0" x 5'-6" Cu.ft 3 4.00 2.75 3.50 (362.67)
Tower 28' -
Base to el +6' Cu.ft 2 8.25 7.00 0.75 (86.63)
Base to El+6+ Cu.ft 1 2.50 7.00 0.75 (13.13)
Inclination Cu.ft 2 8.25 8.75 0.75 (108.28)

Planter Walls
Planter Wall Concrete +5 Cu.ft 1 7.50 6.00 0.50 22.50
Planter Wall Concrete +4 Cu.ft 1 35.00 6.50 0.50 113.75
Planter Wall Concrete +3 Cu.ft 1 110.00 5.50 0.50 302.50
Planter Wall Concrete +2.5' Cu.ft 1 23.00 5.00 0.50 57.50
Raft Walls Longer side Cu.ft 2 24.00 7.00 0.67 225.12
Raft walls Cu.ft 2 22.67 7.00 0.67 212.64
Total 4,052.92
Situ
Planter Wall Concrete +5 Cu.ft 1 87.00 8.50 0.50 369.75
Planter Wall Concrete +4 Cu.ft 1 30.00 7.50 0.50 112.50
Planter Wall Concrete +3 Cu.ft 1 12.00 6.50 0.50 39.00
Planter Wall Base Concrete Cu.ft 1 165.60 2.50 1.00 414.00
Inside Curb Retaining Wall RCC Cu.ft 1 268.60 0.66 3.25 576.15
Outer Curb Retaining Wall Cu.ft 1 306.25 1.00 2.50 765.61
Total 2,277.01
Bitumen Coating
Planter Wall Base Concrete Cu.ft 1 165.00 2.00 330.00
Planter Wall base Sides Cu.ft 2 165.00 1.00 165.00
Planter Situ Wall Concrete +5 Cu.ft 1 87.00 6.00 522.00
Planter Situ Wall Concrete +4 Cu.ft 1 28.00 6.00 168.00
Planter Situ Wall Concrete +3 Cu.ft 1 10.00 5.00 50.00
Planter R.C.C Wall Concrete +5 Cu.ft 1 6.00 6.00 36.00
Planter R.C.C Wall Concrete +4 Cu.ft 1 36.00 4.00 144.00
Planter R.C.C Wall Concrete +3 Cu.ft 1 110.00 4.00 440.00
Planter R.C.C Wall Concrete +3 Cu.ft 1 24.00 3.00 72.00
Raft Walls Cu.ft 4 23.67 5.00 118.35
Half of Planter
Wall 1,2 & 3 D shaoe Cu.ft 3 3.75 7.00 26.25
Wall 1,2 & 3 Rectangke Cu.ft 3 7.50 7.00 52.50
Total 2,124.10
Walkway Tiles
Tiles Sq.ft 2 8.50 20.00 340.00
Total 340.00
Granite Tiles
1 Granite Tiles
Floor Sq.ft 1 24.00 24.00 576.00
Deduction Sq.ft 3 12.00 2.00 (72.00)
Side Sq.ft 2 24.00 2.41 115.68
Sides Sq.ft 2 24.00 2.00 96.00
Treads
Type1 Sq.ft 12 5.33 1.00 63.96
Type2 Sq.ft 2 7.00 1.00 14.00
Type3 Sq.ft 2 8.00 1.00 16.00
Risers -
Type1 Sq.ft 14 5.33 0.50 37.31
Type2 Sq.ft 2 7.00 0.50 7.00
Type3 Sq.ft 2 8.00 0.50 8.00
Planters (A,B Similar Sides) -
Planter el+2.5' -
Top Sq.ft 1 12.00 0.75 9.00
Side Sq.ft 1 12.00 0.83 9.96
Planter el+3' -
Top Sq.ft 2 32.00 0.75 48.00
Side Sq.ft 2 32.00 1.41 90.24
Planter el+4' -
Top Sq.ft 2 32.00 0.75 48.00
Side Sq.ft 2 6.00 2.41 28.92
Side Sq.ft 2 12.75 1.33 33.92
Side Sq.ft 2 14.66 1.25 36.65
Planter el+5' -
Top Sq.ft 2 29.00 0.75 43.50
Side Sq.ft 2 8.75 1.25 21.88
Side Sq.ft 2 14.83 1.25 37.08
Planters (C,D Similar)
Planter el+2.5' -
Top Sq.ft 1 12.00 0.75 9.00
Side Sq.ft 1 12.00 0.83 9.96
Planter el+3' -
Top Sq.ft 2 29.00 0.75 43.50
Side Sq.ft 2 29.00 1.41 81.78
Planter el+5' -
Top Sq.ft 2 29.00 0.75 43.50
Side Sq.ft 2 29.00 2.75 159.50
Total 1,616.33
Almunium Strip
Total Sq.ft 1 884.10 0.75 663.08
Total 663.08
Curb Stones
Outer Circle R.ft 1 306.25 311.58
Inner Circle R.ft 1 268.66 273.88
Total 585.46
Pavers
Area1 Sq.ft 1 49.58 7,724.52
Area2 Sq.ft 1 43.58 5,968.16
Total 1,756.37
Paint on curb Stones
Outer Circle Sq.ft 1 306.25 1.00 306.25
Inner Circle Sq.ft 1 268.66 1.00 268.66
Total 574.91
Plaster
Tank Walls Longer side Cu.ft 2 12.00 5.75 138.00
Tank Walls Shorter side Cu.ft 2 7.17 5.75 82.46
Total 220.46
15C Fairface Plaster
Wall 3 Sq.ft 1 31.00 20.00 620.00
Wall2 Sq.ft 1 31.00 28.00 868.00
Wall1 Sq.ft 1 31.00 36.00 1,116.00
Deduction for Ovals Sq.ft 6 3.00 (169.67)
Total 2,434.33
INDUS MOTOR COMPANY PORT QASIM

Project IMC
Estimated By
Structure Dwg No.
Item/Component Bar Mark Sheet No.

Member
No. in Cut Total
Total
S No

Description Dia each Length SHAPE Length


No.
Member (Feet) (Feet)

ROUND ABOUT

WALL-01

COLUMNS 5/8 2 10 20 32.84 656.85


0.5 Plus Lap 0.5
29.03 2.813
1.67 0.17
COLUMN 0.17
RING 3/8 2 54 108 5.00 540.00
0.66 0.66
1.67
WALL
a VERTICAL 1/2 2 17 34 12.00 408.00
upto 6'-0" plus Lap 0.5
11.50

WALL
VERTICAL
a 6'-0" to taper area 3'-6" 1/2 2 17 34 6.66 226.44
Average
6.66

WALL
a 1/2 2 31 62 11.17 692.54
DISTRUBTUION 0.5 0.5
10.17

b 1/2 1 22 22 12.00 264.00


WALL 0.5
VERTICAL 11.50
D-SHAPE
b
Full Length 1/2 1 22 22 20.38 448.36
0.5
19.88

WALL
VERTICAL
b D-SHAPE TAPER AREA 1/2 1 36 36 8.95 322.20
0.5
Average
8.45
3.17 0.17
0.17
b 3/8 1 15 15 8.00 120.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 1 15 15 8.68 130.20
UPTO 6'-0" 1 1
3.17
3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
3.17 0.17
0.17
b 3/8 2 13 26 8.00 208.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 13 52 8.68 451.36
6'-0" TO 8'-9" 1 1
3.17
7.75 0.17
D- 0.17
b Shap 3/8 1 13 13 23.68 307.84
e 3.92 3.92
7.75
3.17 0.17
0.17
b 3/8 2 9 18 8.00 144.00
0.66 0.66
3.17
D-SHAPE WALL
RING
8'-9" TO OVEL Page 8 of 14
Bar Mark

Member
No. in Total Cut Total
S No
Description Dia each Length SHAPE Length
Member No. (Feet) (Feet)

3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 9 36 8.68 312.48
8'-9" TO OVEL 1 1
3.17
12.33 0.17
D- 0.17
b Shap 3/8 1 9 9 32.50 292.50
e 3.75 3.75
12.33
3.17 0.17
0.17
b 3/8 2 15 30 8.68 260.40
1 1
D-SHAPE WALL 3.17
RING
OVEL to TOP 3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
1
EXTRA BAR TAPER AREA 3/4 1 6 6 18.92 16.92 113.52
1

EXTRA BAR OVEL AREA 1/2 2 5 10 14.50 145.00


14.5

EXTRA BAR AROUND OVEL 1/2 3 5 15 12.66 189.90


AREA 0.5 0.5
11.66
3.17 0.17
0.17
TOP RING 3/8 1 21 21 9.02 189.42
1.17 1.17
3.17

WALL-02

COLUMNS 3/4 4 10 40 41.41 1656.20


0.5 Plus Lap 0.5
37.03 3.375
1.67 0.17
COLUMN 0.17
3/8 4 70 280 5.00 1400.00
RING 0.66 0.66
1.67
WALL
a VERTICAL 1/2 4 17 68 12.00 816.00
upto 6'-0" plus Lap 0.5
11.50

WALL
VERTICAL
a 6'-0" to taper area 3'-6" 1/2 2 17 34 9.46 321.64
Average
9.46

a WALL 1/2 2 43 86 11.17 960.62


DISTRUBTUION 0.5 0.5
10.17

b 1/2 1 22 22 12.00 264.00


WALL 0.5
VERTICAL 11.50
D-SHAPE
b
Full Length 1/2 1 22 22 28.38 624.36
0.5
27.88

b 1/2 1 36 36 10.25 369.00


0.5
WALL
VERTICAL 9.75
D-SHAPE TAPER AREA
Average
b 1/2 1 36 36 7.96 286.56
0.5
7.46
3.17 0.17
0.17
b 3/8 1 15 15 8.00 120.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 1 15 15 8.68 130.20
UPTO 6'-0" 1 1

Page 9 of 14
Bar Mark

Member
No. in Total Cut Total
S No
Description Dia each Length SHAPE Length
Member No. (Feet) (Feet)
D-SHAPE WALL
b RING 3/8 1 15 15 8.68 130.20
UPTO 6'-0"
3.17
3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
3.17 0.17
0.17
b 3/8 2 21 42 8.00 336.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 21 84 8.68 729.12
6'-0" TO 15'-0" 1 1
3.17
7.75 0.17
D- 0.17
b Shap 3/8 1 21 21 23.68 497.28
e 3.92 3.92
7.75
3.17 0.17
0.17
b 3/8 2 13 26 8.00 208.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 13 52 8.68 451.36
15'-0" TO OVEL 1 1
3.17
12.33 0.17
D- 0.17
b Shap 3/8 1 13 13 32.50 422.50
e 3.75 3.75
12.33
3.17 0.17
0.17
b 3/8 2 15 30 8.68 260.40
1 1
D-SHAPE WALL 3.17
RING
OVEL to TOP 3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
1
EXTRA BAR TAPER AREA 3/4 1 6 6 25.50 23.5 153.00
1

EXTRA BAR OVEL AREA 1/2 2 5 10 14.50 14.5 145.00

EXTRA BAR AROUND OVEL 1/2 3 5 15 12.66 189.90


AREA 0.5 0.5
11.66
3.17 0.17
0.17
TOP RING 3/8 1 21 21 9.02 189.42
1.17 1.17
3.17

WALL-03

COLUMNS 5/8 2 10 20 49.41 988.10


0.5 Plus Lap 0.5
45.03 3.375
1.67 0.17
COLUMN 0.17
3/8 2 86 172 5.00 860.00
RING 0.66 0.66
1.67
WALL
a VERTICAL 1/2 2 17 34 12.00 408.00
upto 6'-0" plus Lap 0.5
11.50

WALL
VERTICAL
a 6'-0" to taper area 3'-6" 1/2 2 17 34 9.46 321.64
Average
9.46

WALL
a DISTRUBTUION 1/2 2 55 110 11.17 1228.70
0.5 0.5
10.17

b 1/2 1 22 22 12.00 264.00


WALL 0.5
VERTICAL 11.50
D-SHAPE
b
Full Length 1/2 1 22 22 38.63 849.86

Page 10 of 14
Bar Mark

Member
WALL No. in Total Cut Total
S No
Description
VERTICAL Dia each Length SHAPE Length
Member No. (Feet) (Feet)
D-SHAPE
b
Full Length 1/2 1 22 22 38.63 849.86
Plus Lap 0.5
35.88 2.250

b 1/2 1 36 36 10.25 369.00


0.5
WALL
VERTICAL 9.75
D-SHAPE TAPER AREA
Average
b 1/2 1 36 36 15.92 572.94
0.5
15.42
3.17 0.17
0.17
b 3/8 1 15 15 8.00 120.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 1 15 15 8.68 130.20
UPTO 6'-0" 1 1
3.17
3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
3.17 0.17
0.17
b 3/8 2 21 42 8.00 336.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 21 84 8.68 729.12
6'-0" TO 15'-0" 1 1
3.17
7.75 0.17
D- 0.17
b Shap 3/8 1 21 21 23.68 497.28
e 3.92 3.92
7.75
3.17 0.17
0.17
b 3/8 2 29 58 8.00 464.00
0.66 0.66
3.17
3.17 0.17
D-SHAPE WALL 0.17
b RING 3/8 4 29 116 8.68 1006.88
15'-0" TO OVEL 1 1
3.17
12.33 0.17
D- 0.17
b Shap 3/8 1 29 29 32.50 942.50
e 3.75 3.75
12.33
3.17 0.17
0.17
b 3/8 2 15 30 8.68 260.40
1 1
D-SHAPE WALL 3.17
RING
OVEL to TOP 3.17 0.17
D- 0.17
b Shap 3/8 1 15 15 14.85 222.75
e 3.92 3.92
3.5
1
EXTRA BAR TAPER AREA 3/4 1 6 6 25.50 23.5 153.00
1

EXTRA BAR OVEL AREA 1/2 2 5 10 14.50 14.5 145.00

EXTRA BAR AROUND OVEL 1/2 3 5 15 12.66 189.90


AREA 0.5 0.5
11.66
3.17 0.17
0.17
TOP RING 3/8 1 21 21 9.02 189.42
1.17 1.17
3.17

RAFT FOUNDATION
RAFT 5/8 2 48 96 27.50 2640.00
BOTTOM 2 2
23.50

RAFT 5/8 2 36 72 27.50 1980.00


TOP 2 2

Page 11 of 14
Bar Mark

Member
No. in Total Cut Total
S No
Description Dia each Length SHAPE Length
Member No. (Feet) (Feet)
RAFT
TOP 5/8 2 36 72 27.50 1980.00
23.50

WALL
VERTICAL 1/2 1 284 284 9.83 2791.72
0.25 0.5
9.08

WALL DISTRUBTION 1/2 2 32 64 24.25 1552.00


1
23.25

WALL DISTRUBTION
5/8 2 4 8 24.25 194.00
Extra on TOP 1
23.25

PLANTER WALL (177'-2")


PLANTER
BED 1/2 2 270 540 2.83 1528.20
0.33 0.33
2.17

PLANTER 0.25
3/8 2 270 540 7.08 3823.20
WALL 6.17 0.66

PLANTER
WALL 3/8 2 7 14 183.92 2574.88
Plus Lap
DISTRUBUTION
177.17 6.750
PLANTER
WALL 5/8 1 2 2 183.92 367.84
Plus Lap
DISTRUBUTION
177.17 6.750

ROUND ABOUT WALL (82'-0" DIA)

R.C.C BED 1/2 1 4 4 271.20 1084.80


Plus Lap
257.7 13.500
0.25
R.C.C WALL 3/8 2 391 782 4.83 3777.06
0.83 0.33
3.42

R.C.C WALL
3/8 2 5 10 271.20 2712.00
DISTRIBUTION Plus Lap
257.7 13.500

ROUND ABOUT WALL (99'-0" DIA)

R.C.C BED 3/8 1 4 4 324.56 1298.23


Plus Lap
311.058 13.500
0.25
R.C.C WALL 3/8 2 472 944 4.33 4087.52
1.33 0.33
2.42

R.C.C WALL
3/8 2 4 8 324.56 2596.46
DISTRIBUTION Plus Lap
311.058 13.500

U.G.W.TANK
2 2
1/2 1 18 18 13.16 236.88
0.5 0.5
TANK 8.16
BOTTOM
SLAB 2 2
1/2 1 13 13 16.65 216.45
0.5 0.5
11.65
2 2
1/2 1 21 21 13.16 276.36
0.5 0.5
TANK 8.16
TOP
SLAB 2 2
1/2 1 12 12 16.65 199.80
0.5 0.5
11.65

1/2 -1 4 -4 2.33 (9.32)

Less Manhole

Page 12 of 14
Bar Mark

Member
No. in Total Cut Total
S No
Description Dia each Length SHAPE Length
Member No. (Feet) (Feet)
1/2 -1 4 -4 2.33 (9.32)
2.33
Less Manhole

1/2 -1 4 -4 2.33 (9.32)


2.33

Extra Bar
1/2 2 2 4 3.00 12.00
at Manhole
3

Page 13 of 14
Bar Mark

Member
No. in Total Cut Total
S No
Description Dia each Length SHAPE Length
Member No. (Feet) (Feet)

Bar Size (inch) 3/8" 1/2" 5/8" 3/4" 1"


Weight (Kg/Feet) 0.170 0.302 0.472 0.680 1.209
16.367
Total Length (RF) 35442.136 18902.13 6826.79 2075.72 0
Total Weight (Tons) 6025.163 5708.443 3222.245 1411.490 0.000

Page 14 of 14

Potrebbero piacerti anche