Sei sulla pagina 1di 1

`

MANNAR WIND POWER PROJECT

DAY AHEAD REQUEST FOR INSPECTIONS LIST - Rev -2


Inspection Request List for 6/6/2020 Submitted to : Vestas Wind Sri Lanka Submitted On: 6/6/2020

Involved Field Location Scheduled Date/Time


Contractor/ Responsible
Ref/ no Sub Field Inspection description
officer's name (contact)

06.00-
Civil/Elec/Mech Zone Element Date
18.00 Hrs

LABORATORY ACTIVITIES

ACC/MWPP/PL/GR/CON/18(07 days)
ACC/MWPP/PC/CON/25( 28days)
1 MWPP-ACC-CN-8771 Civil CN Project Laboratary ACC/MWPP/CON/MA/140(7 days) Concrete cube crushing test 6/6/2020 09.00 onwards Access Eng/Anjana(ME)

HARDSTAND ACTIVITIES

2 MWPP-ACC-CN-8772 Civil CN WTG 15 CH 0+080-0+125 Access road Field density testing of sub base 1st layer 6/6/2020 10.00 Access Eng/Thanusha(SE)

3 MWPP-ACC-CN-8773 Civil CN WTG 12 Crane pad Field density testing of ABC top layer 6/6/2020 10.00 Access Eng/Thanusha(SE)

Potrebbero piacerti anche