MANNAR WIND POWER PROJECT

DAY AHEAD REQUEST FOR INSPECTIONS LIST - Rev -1


Inspection Request List for 6/5/2020 Submitted to : Vestas Wind Sri Lanka Submitted On: 6/5/2020

Involved Field Location Scheduled Date/Time


Contractor/ Responsible
Ref/ no Sub Field Inspection description
officer's name (contact)

06.00-
Civil/Elec/Mech Zone Element Date
18.00 Hrs

LABORATORY ACTIVITIES

ACC/MWPP/GR/CON/33(07 days)
ACC/MWPP/PC/TOP/26(7 days)
1 MWPP-ACC-CN-8729 Civil CN Project Laboratary ACC/MWPP/CON/MA/139(7 days) Concrete cube crushing test 6/5/2020 09.00 onwards Access Eng/Anjana(ME)

2 MWPP-ACC-CN-8730 Civil CN Project Laboratary cooling pipe Cementitious grout trial 6/5/2020 14.00 Access Eng/Anjana(ME)

3 MWPP-ACC-CN-8731 Civil CN Batching plant Aggregate stockpile Sample collection 6/5/2020 9.00 Access Eng/Anjana(ME)

HARDSTAND ACTIVITIES

4 MWPP-ACC-CN-8732 Civil CN WTG 15 CH 0+080-0+125 Access road Field density testing of embankment layer 6/5/2020 10.00 Access Eng/Thanusha(SE)

5 MWPP-ACC-CN-8733 Civil CN WTG 15 CH 0+080-0+125 Access road Field density testing of sub base 1st layer 6/5/2020 17.00 Access Eng/Thanusha(SE)