Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
' I
SAMUELG . PAIKOWSKY
Department of Civil Engineering, University of Lowell, 1 University Avenue, Lo well, MA 01854, U.S. A .
AND
ROBERTV. WHITMAN
Department of Civil Engineering, Massachusetts Institute of Technology, 77 Massachusetts Avenue,
Cambridge, MA 02139, U.S.A .
Received May 24, 1989
Accepted April 5, 1990
D>uringinstallation of open-pipe piles, soil enters the pile until the inner-soil cylinder develops sufficient resistance
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
to prevent further soil intrusion and the pile becomes "plugged." In spite of its frequent occurrence, only limited attention
has thus far been given to this phenomenon and its consequences. The effects of plugging on pile performance and
design are examined in reference to the following aspects: ultimate static capacity, time-dependent pile capacity, and
dynamic behavior. Pile plugging is shown to have the following effects: marked contribution to the capacity of piles
driven in sand; delay in capacity gain with time for piles driven in clay; and change in behavior of piles during installation,
causing it to differ from that described by the models commonly used to predict and analyze pile driving.
Key words: pipe piles, pile plugging, open-ended piles, static capacity, time-dependent capacity, dynamic analysis,
pile driving, pile performance.
+
Durant l'installation de pieux cylindriques a paroi mince, le sol progresse A l'interieur du tube jusqu'ace qu'il developpe
la resistance necessaire pour s'opposer toute autre penetration de materiel, creant ainsi un ctbovchon>).Jusqu'a ce
jour et malgre la frequence du phknomkne, peu d'efforts ont ete consacres A son etude et a ses cons2quences. Les aspects
suivants de ce bouchon sont etudiis : capacite statique ultime, variation de la capacite en fonction du temps et
comportement dynamique du pieu. I1 est demontrC que le bouchon augmente considerablement la capacite du pieu
For personal use only.
lorsqu'il est enfoui dans du sable, et qu'il retarde l'augmentation de la capacitk du pieu lorsque 'celui-ci est enfoui dans
des argiles. Enfin, le bouchon affecte le comportement du pieu durant la phase d'installation; comportement qui diffkre
de ce que prkdisent les modkles communement utilises pour l'analyse de penetration de pieux.
Mots elks :pieux cylindriques a paroi mince, bouchon de pieu, pieux ouverts, capacite statique, capacite differee,
analyse dynarnique, installation de pieux, comportement de pieux.
1~c51s
I INCI: (OPEN / CLOSED) (%) however, towards the end of the ppnetraiion, a tendency to
o 20 40 60 80 100 120 full plugging was again observed.
The resistance to penetration (pushing at a rate of 25 mm/s
(open) and 0.75 mm/s (closed)) of the open- and the closed-
ended piles was used to prepare Fig. 3. The ratio of the static
load test results (performed about 1.5 months after installa-
tion) at the final penetration depth was added. The load test
results indicate an 11Yo increase in the capacity ratio in rela-
es~stanceforces tion to the ratio of the resistances to penetration at the final
depth. The range of resistance ratio from Fig. 2a was added
to Fig. 3 showing that (1) the ratio of open- and closed-ended
pile resistances and the plugging depth during quasi-static
penetration fits the simplified predicted behavior, and
(2) when plugged, the open-ended pile developed a resistance
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
LOAD (N)
FIG. 4. Installation and load tests on open and closed-ended model pipe piles pushed into loose sand: ( a )pile resistance vs. penetra-
tion depth, ( b ) load settlement relations at the final installation depth, (prepared using data from Kishida (19676)).
pile prior to plugging. At the final penetration depth, the ended piles, and under working loads both will have the
50-mm plugged pile exhibited a resistance approximately same response.
equal to that of the 100-mm unplugged pile, which has four 6 . The plugging of piles in sand is a complex phenome-
times its cross-sectional area. non even under quasi-static penetration (Paikowsky 1990).
4. Comparison of the load-settlement behavior of the As mentioned above, the plug resistance is controlled by the
three piles in Fig. 4b reveals the following. (i) The open- arching mechanism, and therefore the plugging depth was
and closed-ended 50-mm-diameter piles exhibit the same not correctly assessed through the simplified assumptions of
ultimate bearing capacity of about 400 N. (ii) Following Appendix I. However, both the simplified analysis and the
ultimate load, the open-ended pile exhibited larger settlements test results demonstrated the effect of the plugging on the
than the closed-ended pile. However, the entire load- static capacity of open-ended piles in sand.
settlement curves for the two piles are very similar. (iii) The
100-mm-diameterunplugged pile exhibited a load-settlement
behavior similar to that of the 50-mm-diameter closed-ended The influence of a soil plug on time-dependent pile
and plugged piles. Its ultimate bearing capacity of about capacity
500 N (analyzed by Kishida to be 400 N) is much smaller, The allowable load, and the stage and manner in which
however, than its potential when plugged (about 1750 N, the load can be applied, is determined by the rate of gain
based on the same bearing capacity). in pile capacity with time after driving. An estimate of the
5. The above leads to the conclusion that under static effect of the mode penetration (open vs. closed) on the rate
loading, plugged piles behave almost identically to closed- of capacity gain of piles in clay follows.
PAIKOWSKY AND WHITMAN
I \
4
Before Installation I, 1, , Before Installation
- ur, 1
-t
soil
After Installation ement After
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
Radial consolidation in which t is the elapsed time since pile driving, Ch is the
It is assumed that the piles are driven into insensitive clay coefficient of radial consolidation, Th is the time factor,
in which thixotropy (Skempton and Northey 1952) is not and R is the radius of the pile (closed-ended, R = B/2).
a factor. In such clay, the increase of skin resistance with Thus, the time needed to develop pile capacity is proportional
time is associated only with migration of pore water. This to the square of the pile size. By normalizing [3], one can
migration is caused by excess pore pressure initiated during use the dissipation time around a closed-ended pile of one
pile penetration. size (Rl,tl) io estimate that of another size (R2,t2), such
As the capacity of a pile in clay is controlled primarily that
by the skin friction, the increase in bearing capacity of such
piles is therefore determined by radial consolidation of the
clay (Soderberg 1962). For this reason, the gain in resistance
can be analyzed using radial diffusion theory. The time The use of [4] assumes no effect of pile diameter on the
associated with a specified degree of consolidation is given magitude of soil stresses or pore pressure. These assump-
by tions were confirmed by Baligh and Levadoux (1980), who
[3] t = T h * ~ 2 / ~ h compiled measurements of excess pore pressure due to
CAN. GEOTECH. J. VOL. 27, 1990 i
I
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
FIG.6 . Decay of excess pore pressure around piles driven in BBC (initial OCR = 2), after d r t e r et al. (1979).
For personal use only.
installation of closed-ended piles from various case histories. Soil displacements pnd pufe pressure dissipation around
The data were presented in the form of normalized excess open-ended vs. closed-ended piles
pore pressure (with respect to the original vertical effective Study of the soil displacement around open vs. closed-
stress a:,) versus the logarithm of the normalized radial ended piles may be utilized, therefore, to determine the ratio
distance (with respect to the pile radius). The different data of the gain in bearing capacity between the two types.
points fall within a narrow range (e.g., the excess pore The volume of the displaced soil during open-ended
pressure near the pile shaft was about 2.1(+0.2)~:,). This unplugged pile penetration depends on the pile diameter and
indicates that the magnitude of the soil stresses and the pore wall thickness. Simplified expressions that describe the radial
pressures is not a function of the pile diameter. Furthermore, soil displacements for open- and closed-ended piles were
Grosch and Reese (1980) reinterpreted data gathered by developed by Randolph et al. (1979). These expressions (see
Vesic (1977), which describe the increase in pile capacity with Fig. 5a) are based on radial volume conservation and assume
time after installation. They plotted the time required for the following: (i) no change in soil volume during penetra-
the piles to reach 50% of their maximum capacity vs. the tion; (ii) soil displacement is radial; and (iii) only outward
pile diameter. The obtained relations were those of [4], displacements occur during the penetration of open-ended
despite the fact that the data were gathered at various sites piles. The equations, along with the calculated soil
having different clays (mostly soft). displacements due to penetration of a 1220-mm-(48-in.)
The above findings can be summarized as follows. diameter pile in plugged (closed-ended) and unplugged
1. Equation [4] can be used to estimate the time required modes, are presented in Fig. 5. Figure 5b demonstrates the
for dissipation of excess pore pressure around one closed- large soil displacements caused by penetration of plugged
ended pile when given the dissipation measurements of piles as opposed to the much smaller soil displacements of
another pile of a different size in the same soil. open-ended pile penetration.
2. Since the magnitude of the stresses and excess pore pressure Bogard et al. (1985) presented data describing pore-
around the pile is not determined by the size of the pile, the pressure dissipation following the penetration of open-ended
dissipation time must therefore be controlled by the volume unplugged and closed-ended model piles. Both cases exhibit
of soil displaced during penetration. For closed-ended piles, the same normalized pattern of pore-pressure dissipation.
the volume of the displaced soil is proportional to the square Since the dissipation patterns were shown to be similar for
of the pile size, which is expressed by [4]. both types of piles, [3], which describes radial consolidation,
3. The bearing capacity of a pile in clay is primarily controlled can be applied in both cases. Equation [4] can, therefore,
by the skin friction. The skin friction is, in turn, controlled be used to assess the dissipation time around an open-ended
by the effective stresses near the pile shaft. These stresses unplugged pile based on the known dissipation time around
are a function of the pore pressure, which during consolida- a closed-ended pile. However, a value that represents the
tion following driving is determined by the volume of soil displaced soil volumes and corresponding soil behavior for
displaced by the pile penetration. Logic dictates that [4], the two types of piles must be substituted for the ratio of
which relates pile size to dissipation time of excess pore R, over R2 in [4].
pressure, can also be used to predict a gain of pile bearing One way to derive a value for this ratio is to follow the
capacity with time. logic of [4]. Calculation of the ratio of the displaced soil
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
FIG. 7. Predicted pore pressure dissipation decay around plugged and unplugged piles (Based on PLS measurements).
volumes of closed-ended vs. open-ended piles of the same pore-pressure measurement with time, being equal to ui at
outer diameter leads to time of installation and uo after dissipation (hydrostatic
pressure).
2. Curve no. 2 was constructed using [4] to adapt curve no. 1
to the diameter of the closed-ended 1220-mm pile.
For personal use only.
for which R, is the outer radius of the piles ( = B/2), and 3. Curve no. 3 represents a rough estimate of the pore-
Ri is the inner radius of the open-ended pile ( = R, - t). pressure dissipation around an open-ended pile, with a diarn-
A more comprehensive solution is presented by Carter eter of 1220 mm, that penetrates in an unplugged mode. The
et al. (1979). In their study, a soil model based on modified ratio between the decay of excess pore pressure around the
Cam clay was used, in which undrained conditions with sub- open-ended pile (curve no. 3) to that of the closed-ended
sequent consolidation could be simulated. Figure 6 shows pile (curve no. 2) is based on (i) the relations described by
the results obtained, presented as a set of curves that Fig. 6 (Carter et al. 1979) at 50% consolidation for relative
describe Ti, the excess pore-pressure ratio in the soil adjacent displacement of p = 1 (for the 1220-mm closed-ended pile)
to the pile (with respect to the maximum excess pore and p = 0.12 (for the 1220-mm open-ended pile); and (ii)
pressure) as a function of a nondimensional time factor for the relations of [5].
piles of different wall thicknesses penetrating into Boston The soil displacements associated with curve no. 3 (open-
Blue Clay (BBC) (see Fig. 5a for the definition of p). It ended, unplugged) and curve no. 2 (closed-ended, plugged)
should be noted that when predicting the maximum pore have been presented in Fig. 5. Using Fig. 6 , this difference
pressure (urnaxnormalized by the initial undrained shear is estimated to generate a pore pressure next to the plugged
strength C,(o)) for the open-ended piles, the pressure is pile about twice that of the unplugged pile. As a result of
dependent on the dimensions expressed by p; these relations the larger displaced soil volume and the greater pore pressure,
(presented as part of Fig. 6) predict a constant ratio of the time that is required for the pore pressure to dissipate
Aurnax/C,,(o) = 4.05 for the pore pressure around any around the 1220-mm closed-ended pile (of Fig. 7) is about
closed-ended piles (p = 1.0). an order of magnitude greater than the time required for
pore-pressure dissipation around the 1220-mm open-ended
Prediction of pore-pressure dissipation time around open- pile.
ended vs. closed-ended piles
The approach outlined above was used to prepare Fig. 7, Prediction of gain in capacity with time for open-ended vs.
which presents predictions of excess pore-pressure dissipa- closed-ended piles
tion for a 1220-mm (48-in.)-diameter pipe pile with a wall The relations of Fig. 7 can be further analyzed to evaluate
thickness of 38.1 mm (1.5 in.). The curves were constructed the gain in capacity with time. If no other measurements
in the following manner. exist, a simplified assumption of a direct relation between
1. Curve no. 1 shows the pore-pressure dissipation data gain in pile capacity to pore-pressure dissipation can be used.
measured by a P L S ~cell following penetration in BBC This assumption (supported by the previous discussion) leads
(from Morrison 1984). The excess pore-pressure ratio is
-
to the following relations:
u = Au/Aurnax= (u - uO)/(ui - u0) in which u is the
' I 2 i
LENGTH SOIL
TYPE DIA. it. TYPE -. LOCATION
steel H 14" :;: Silt Tappan Zee, N Y
A s t e e l pended
ipe 6" 22 S o f t Clay San F r a n c i s c o
A steel pipe 12" 60 SoftClay Michigan
r
-
I- @ 242 Soft to
U Q s t e e l pipe 24" Stiff Eugene I s l a n d
,Q o Clav
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
---
TIME, SINCE DRIVING I days Ir I' >
month 1 year :.
10. y e a r s
FIG. 8. Comparison of predicted set-up time for a 1220 mm (48 in.) pile, installed in BBC, to field data collected by Vesic (1977).
(1 in. = 2.54 cm).
For personal use only.
imply that the pile capacity at the penetration time ( t = 0, relations such as those of [7] need additional confirmation of
-
u = 1) is zero. Measured values of the horizontal effective the direct influenck of those values on the skin friction.
stresses (a;) during penetration (Morrison 1984), while 2. The accuracy of this process when applied to a sensitive
assuming that the skin friction and, therefore, the pile (st = 6) clay, such as the BBC, is questionable, taking its
capacity, are proportional to a; at any time during con- thixotropic behavior into consideration (O'Neill 1985). For
solidation, allow adjustment of [6] in the following manner: these reasons, the calculated curves in Fig. 8 should be
regarded as an approximation that serves the purpose of the
[71 Q(t) z
- - Ki + (1 - Ki)(l - a) present illustration.
Qfina~ 3. All analyses assumed that the plugged pile is analogous
where Ki is the ratio of the horizontal (radial) effective to a closed-ended pile. While this assumption is entirely cor-
stress at the time of penetration to the original vertical effec- rect for the end-bearing consideration, it is conditional for
tive stress (a:/u(,). the time-dependent pile capacity. If the pile penetrates in
Use of [7] and data provided by Morrison (1984) enable a plugged mode along a length that is significant in relation
estimation of the gain in capacity with time for the 1220-mm to its penetration depth in an unplugged mode, then these
pile. The estimations for the two modes of penetration approximations are valid. If, however, the pile penetrated
(plugged and unplugged) are presented in Fig. 8 along with in a plugged mode for only a short distance at the end of
measurements compiled by Vesic (1977). Figure 8 shows the its driving, then the effect on the gain in capacity with time
following. 1. The calculated gain in capacity with time fits will be less than that described above, despite the fact that
in with the general trend of actual measured data. 2. For the contribution of a given pile length to the total capacity
the considered 1220-mm friction piles driven in BBC, the of friction piles increases with depth.
time required for the closed-ended plugged pile to achieve
its maximal bearing capacity is an order of magnitude greater The influence of a soil plug on the dynamic behavior
than that required for the unplugged open-ended pile. 3. An and analysis of piles
unplugged pile with a diameter of 1220 mm in BBC requires Dynamic analysis of pile driving is performed for two
2.5 days to reach 50% and 25 days to reach 90% of its max- major reasons: (i) Prediction of the dynamic behavior of
imum capacity. A plugged pile of the same diameter will piles prior to construction. Such analysis enables the estab-
require a much longer time, such that 50% of its maximum lishment of relations between observed dynamic resistance
capacity is reached after 50 days and 90% after 500 days. (in the form of the hammer-blow count for a certain energy
The following should be emphasized in regard to the level) and anticipated static capacity. (ii) Prediction of the
above suggested relations. pile behavior under static loads, utilizing analysis of dynamic
1. The data compiled by Vesic (1977) were obtained by measurements obtained during driving. Both analyses are
direct pile load testing at different time stages (e.g., Seed typically based on a numerical solution of the one-
and Reese 1955, 1957). The calculated curves are based on dimensional wave equation (I-D WE). The solution utilizes
measurements of pore-water dissipation around a model mathematical models for the pile, the pile-soil interaction,
pile, and are subject to the assumptions made for [7]. and, in the case of the predriving analysis, for the driving
Morrison (1984) measured values of a, and u with time, but system also (Smith 1960).
PAIKOWSKY A,NDWHITMAN \ 437
I >
TON the friction forces does not violate any of the previous
PILE T-1/B
assumptions.
L. E.
PEN.
-- 85. E M
81. O M
DIAMETER-
HAMMER - 88
M-2500
IN.
- These underlying assumptions used for the theoretical
1500 description of the pile condition during driving are adequate
for most practical purposes.
The one-dimensional wave equation in light of pile plugging
To ensure the validity of the above analysis for open-
ended pile penetration, two possible'-inner-soil - pile interac-
tions must be examined. :.
F c a l . (a) Intrusion of soil into the p@epile during itspenetration
in an unplugged mode.
During unplugged penetrafion, the inside and outside fric-
For personal use only.
F c a l .
-1wow
top and the tip of the pile are shown in Figs. 96 and 9c,
respectively.
The pile capacity was estimated using a computer program
FIG.9. (a) Measurements of force and velocity vs. time for an called TEPWAP.' This program allows the input of the
unplugged pile; ( 6 )Plot of measured force at pile top compared measured velocity at the pile top as a function of time, solv-
to force obtained from TEPWAP analysis; (c) Comparison between ing [8] for a set of parameters describing the soil resistance
measured force near tip of pile and calculated force obtained from (dynamic and static) along the pile. Adjustments of the
TEPWAP analysis (referring to measurements at pile top) parameters are made until the calculated force at the top
(Paikowsky 1982). matches that measured, as shown in Fig. 9b. Figure 9c
In the case of open-ended pile penetration, the validity presents the comparison between calculated force at the tip
of the theory and the models used must be reviewed in light (obtained from the above procedure) to the measured force
of the various possible inner soil - pile interactions. at the tip. The match between these forces at the tip verifies
the validity of the analysis. From the calculated resistance
The one-dimensional wave equation and its underlying that led to the match in Fig. 9b, the static component acting
assumptions cumulatively on the inside and outside walls and tip of the
Stress propagation in a pile during driving can be pile was predicted to be 10.9 MN, compared with 12.0 MN
described by the following equation of movement: measured in a static load test. From this analysis it can be
concluded that when an open-ended pile penetrates in an
unplugged mode, a dynamic analysis can be conducted by
considering only the resultant of the inner- and outer-wall
in which u(x, t) is the longitudinal displacement of friction.
infinitesimal segment; A, and S, are the pile area and cir-
cumference, respectively; and E, and p, are the modulus of 'TEPWAP (Paikowsky 1982) utilizes a procedure somewhat
elasticity and density of the pile material. similar to the CAPWAP analysis described by Gravare et al. (1980).
438 CAN. GEOTECH. J. VOL. 27, 1990 ,
7 13N to longitudinal compressive'itress. An analysis of this system
PILE TEST #4 requires separate consideration ofhthei n h i a of the soil plug
2"em - L. E.
PEN.
-- GO. 3 9 M
Be. P W M
DIAMETER-
HAMMER-
5R IN.
M-ZSPm
itself, even though the pile and the plug undergo equal
1S*-9 - displacement. This complex pile-plug behavior is not con-
sistent with the simplified underlying assumptions of [8],
so that fully plugged piles cannot be analyzed utilizing the
1-D WE.
Analysis of the dynamic measurements obtained during
driving of an artificially plugged pile (concrete plug, inter-
nal annulus) was performed using TEPWAP. Figure 10
presents a comparison between calculated and measured
forces at the top of a 1422 mm (5641-1.) plugged pile driven
with a Menck 2500. The pile length was 69.35 m and the
penetration was 36.20 m with a plug length of about 30 m.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
inwa
L. E.
PEN.
-- as. 3 9 ~
35. Z w M
DIAMETER-
HAMMER-
5.5 IN.
M-25~70
I unacceptable as it could not explain the gain in capacity,
which was indicated by the blow count observed in the field
(similar results from WE analysis were reported by Stevens
et al. 1982).
Several attempts were made to resolve the problem of the
dynamic analysis of plugged piles.,.Heerma and DeJong
(1980) modeled the inner soil plug as"an independent lumped
mass-spring system subjected to 1,imited friction induced by
the inner pile wall. This system does not correctly model the
actual mechanism as described above and is therefore ade-
quate only as long as the pile remains unplugged.
For personal use only.
Conclusions
The plugging of a pile alters its mode of penetration,
The acceleration during driving is in the order of a few thereby affecting its static capacity and dynamic behavior.
hundred g's (say a,, = 200 g), and therefore the friction is 1. A fully plugged open-ended pile acquires the tip resis-
about 1B M N / ~(B~is the pile diameter in metres). tance of a closed-ended pile, resulting in a substantial
Calculations of friction stresses using [9] for large-diameter increase in bearing capacity of piles driven in sand.
pipe piles would indicate that such piles can never plug, espe- 2. The plugged pile penetration mode is accompanied by
cially when considering soil softening during pile driving. large soil displacements typical of closed-ended piles. The
However, since such piles do plug, the assumption of full increased volume of displaced soil results in a more extensive
compatibility is unlikely. The soil plug, being incompatible, region of pore-pressure increase around a pile driven in clay.
is subjected to radial shear-stress propagation in addition Therefore, the time required for the pile capacity gain
PAIKOWSKY AN13 WHITMAN 439
i
I
increases in accordance with the longer time needed f o r the open piles installed in sand. (in Japanese). winistry of Construc-
pore pressure dissipation. This time factor is o f great tion, Institution of Building Research, Japan.
significance, a n d must be taken into account in pile design. -1967b. The ultimate bearing capacity of pipe piles in sand.
3. T h e inner soil in a fully plugged pile exhibits a complex Proceedings of the 3rd Asian Regional Conference on Soil
Mechanics and Foundation Engineering, Haifa, Israel, 1967,
behavior under the dynamic loads o f driving. Analyses using Vol. 1, pp. 601-604.
t h e 1-D WE fail t o model correctly the actual plug-pile KISHIDA,H., and ISEMOTO,M. 1977. Behavior of sand plugs in
interaction, a n d s o d o not accurately predict field behavior open-end steel pipe piles. Proceedings of the 9th International
o r explain dynamic measurements. Conference of Soil Mechanics and Foundation Engineering,
T h e importance o f pile plugging in affecting the behavior, Tokyo, Japan, pp. 601-604.
design, a n d analysis o f pipe piles has been reviewed i n this KISHIDA,H., UESUGI,M., and MORITA,S. 1985. Behavior of dry
paper. A s plugging was found t o have a great influence o n sands in steel pipe piles. 8th Southeast Asian Geotechnical Con-
pile performance, further interest in the phenomenon should ference, Kuala Lumpur, Malaysia.
be focused on (a) detection o f plugging o f piles driven in KLOS, J., and TEJCHMAN, A. 1977. Analysis of behaviour of
tubular piles in subsoil. Proceedings of the 9th International Con-
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
BEGEMANN, H.K.S. 1969. Negative skin friction of a single pile. clay. Ph.D. Thesis, Repartkment of Civil Engineering,
Special Session on Negative Skin Friction and Settlement of Pile Massachusetts I n s ~ t h t eof Technology, Cambridge, MA.
Foundations, 7th International Conference of Soil Mechanics O'NEILL,D.A. 1985. Undrained strength anisotropy of an over-
and Foundation Engineering, Mexico City, Mexico, 1969. Paper consolidated thixotropic clay. M.Sc. Thesis, Department of
No. I. Civil Engineering, Massachusetts Institute of Technology,
BOGARD, J.D., MATLOCK, H., AUDIBERT, J.M.E., and BAMFORD, Cambridge, MA.
S.R. 1985. Three years experience with model pile segment tool PAIKOWSKY, S.G. 1982. Use of dynamic measurements to predict
tests. Proceedings of the 7th Offshore Technology Conference, pile capacity under local conditions. M.Sc. Thesis, Department
Houston, TX, OTC 4848, pp. 65-72. of Civil Engineering, Technion-Israel Institute of Technology,
CARTER,J.P., RANDOLPH, M.F., and WROTH,C.P. 1979. Some Haifa, Israel.
aspects of the performance of open and closed-ended piles. Pro- -1989. A static evaluation of soil plug behavior with applica-
ceedings of a Conference on Numerical Methods in Offshore tion to the pile plugging problem. Sc.D. Thesis, Department of
Piling, Institution of Civil Engineering, London, U.K., Civil Engineering, Massachusetts Institute of Technology,
pp. 165-170. Cambridge, MA.
GRAFF,K.F. 1975. Wave motion in elastic solids. Ohio State Uni- -1990. The Mechanism of pile plugging in sand. Proceedings
versity Press, Columbus, OH. of the 22nd Offshore Technology Conference, Houston, TX,
GRAVARE, C.J., GOBLE,G.G., RAUCHE,F., and LIKINS,G. 1980. OTC 6490, Val. 4, pp. 593-604.
Pile driving construction and control by the CASE method. PAIKOWSKY, S.G., WHITMAN,R.V., and BALIGH,M.M. 1989.
Ground Engineering, 13(2): 20-25. A new look at the phenomenon of offshore pile plugging. Marine
GROSCH,J.J., and REESE,S.C. 1980. Field tests of small-scale pile Geotechnology, 8(3): 213-230.
segments in a soft clay deposit under repeated axial loading. Pro- RANDOLPH, M.F. 1987. Modeling of the soil plug response during
ceedings of the 12th Offshore Technology Conference, Houston, pile driving. Proceedings of the 9th Southeast Asian Geotechnical
TX, pp. 143-151. Conference, Bangkok, Thailand. pp. 6-1 to 6-14.
HEERMA, E.P., and DEJONG,A. 1980. An advanced wave equa- RANDOLPH, M.F., STEINFELT, J.S., and WROTH,C.P. 1979. The
tion computer program which simulates dynamic pile plugging effect of pile type on design parameters for driven piles. Pro-
through a coupled mass-spring system. In Numerical methods ceedings of the 7th European Conference on Soil Mechanics,
in offshore piling, Institution of Civil Engineers, London, U.K. Brighton, U.K. British Geotechnical Society, London, U.K.,
1980, pp. 37-42. V O ~2,. pp. 107-114.
JAMIOLKOWSKI, M., LANCELLOTTA, R., TORDELLA,L., and SEED,H.B., and REESE,L.L. 1955. The action of soft clay along
BATTAGLIO, M. 1982. Undrained strength from CPT. Proceed- friction piles. Proceedings of American Society of Civil Engineers
ings of the 2nd European Symposium on Penetration Testing (81), Paper 842.
(ESOPT) 11, Amsterdam, The Netherlands, pp. 599-608. -1957. The action of soft clay along friction sites. Transac-
KARLSRUD, K., and HAUGEN, T. 1981. Cyclic loading of piles and tions of the American Society of Civil Engineers, Paper
pile anchors, field model tests at HAGA. Static reference tests NO. 2882, pp. 731-764.
on piles A1 and A2. Data Report 40010-4, Norwegian SIMONS,H.A. 1985. A theoretical study of pile driving. Ph.D.
Geotechnical Institute, Thesis, Cambridge University, Cambridge, U.K.
KINDEL, C.E. 1971. Mechanism of soil resistance for driven pipe SKEMPTON, A.W. 1951. The bearing capacity of clays. Building
piles. 4th Annual Symposium of the Waterway, Port, Coastal Research Congress, London. The Institution of Civil Engineer-
and Ocean Division of American Society of Civil Engineers, ing, Division I, pp. 180-189.
Long Beach, CA. SKEMPTON, A.W., and NORTHEY,R.D. 1952. The sensitivity of
KISHIDA,H. 1967a. Model tests on ultimate bearing capacity of clays. Geotechnique, 3: 30-53.
440 C A N . GEOTECH. J. VOL. 27, 1990 \
1.
I
SMITH,E.A.L. 1960. Pile driving analysis by the wave equation. same. With the development of the full pluggingxate, greater
ASCE Journal of Soil Mechanics and Foundation Division, friction stresses are developed at the lower part of the soil
86(4): 35-61. plug. These, however, will not affect the above assumption,
SMITH, I.M., and CHOW,Y .K. 1982. Three-dimensional analysis as at this stage the analysis considers the pile as a closed-
of pile driveability. Proceedings of the 2nd International Con- ended one.
ference on Numerical Methods in Offshore Piling, pp. 1-19. 5. Groundwater is assumed to be at the surface elevation
SODERBERG, L.O. 1962. Consolidation theory applied to founda-
tion pile time effects. Geotechnique, 7: 217-225. and the ratio between the total and the effective soil unit
STEVENS,R.F., WILTSIE, E.A., and TURTON,T.H. 1982. weight is y, = 2.47'.
Evaluating pile drivability for hard clay, very dense sand, and 6. Pile diameter to wall thickness B/t = 40 is used. This
rock. 14th Annual Offshore Technology Conference, Houston ratio is within the range commonly found in offshore pile
TX. 1982. design (Paikowsky et al. 1989).
SZECHY, C.H. 1959. Tests with tubular piles. Acta Technica of 7. Piles in clay.
the Hungarian Academy of Science, 24: 181-219. ( a ) end resistance.
SZECHY, C.H. 1961. The effects of vibration and driving upon the
=
qp qc = Nc Cu + avo
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
relations in Fig. 2 Jamiolkowski et al, 1982), lye adopted the following value
The aim of Fig. 2 is to provide general normalized rela- of N, for soft tostiff clays (nonfissured):
tions describing the ratio (in percent) of tip and total resis- Nc = 14.5 ( + 30%)
tance of open-ended over closed-ended piles, both in sand and
and clay. These ratios are presented as a function of the pile
Cu z 0.22 a:, (Mesri 1975)
penetration (D), normalized by its diameter (B). The rela-
tions of Fig. 2 were obtained using the following general, ( b ) Skin resistance
simplified assumptions.
1. The analysis does not consider dynamic effects during f,, = ---
1 q, (Begemann
17.5
1969)
driving; e.g., the effect of strain rate on the shear strength
and the inner-soil mass - pile relations during transient f,, z C,, (Vesic 1977)
loading. The analysis is therefore applicable to quasi-static Substituting Cu, q,, and y, = 2.47' leads to an average
penetration only. skin friction along the pile of fso = 0.135y1D
2. Pile diameter is assumed not to influence pile capacity. where D is the depth of penetration.
This assumption is correct for the ultimate skin friction of 8. Piles in sand.
driven and bored piles in sand or clay, but it is limited to ( a ) End resistance
pile diameters smaller than 0.5 m ( B I0.5 m) when con-
sidering the end bearing capacity of the piles (Meyerhof where Nq is the bearing capacity factor, and q,,, is the
1983); e.g., when increasing pile diameter from 0.5 to 1.O m, limiting value of q, at the critical depth D,.
Meyerhof suggests a reduction of the end bearing of 44%
in medium dense sand and 33% in stiff fissured clay. Loose sand: Dc z 7B - -
4' = 30" Nq = 35
3. The different load-settlement relations of the open and
closed piles are not considered when referring to the pile
medium dense sand: D, z 15B - 4' z 35' -
capacity.
4. The shaft friction is affected by various factors, such densesand: Dcz18B-4' z40°-Nq=70
as soil density, surface roughness, and construction method
D, uses values from Meyerhof (1976), 4' uses typical
(McClelland 1974). These factors are assumed to be identical
values, and Nq use values from Zeitlen and Paikowsky
for the analysis of the open-ended and closed-ended pile
(1982).
capacity. For simplification, the effect of pile penetration
( b ) Skin resistance
on soil compaction, and therefore on the shaft resistance,
Using McClelland's (1974) simplification (which was sug-
is not considered, and hi is assumed to be equal to fso
gested for D > 6B), we obtain
regardless of the pile diameter. This assumption is supported
by the aforementioned fact that pile-diameter effect on shaft .
f s z 7 ' ' D tg4 ' 5 fsrnax
friction can be neglected (Meyerhof 1983). Furthermore, as where f,,,, is the limiting value off, at the critical depth
long as the piles are penetrating in an unplugged mode, the Dc-
inside and outside shaft friction can be assumed to be the