L&T-Hydrocarbon Engineering Page: 1 of 4

Owner : HINDUSTHAN PETROLEUM CORPORATION LIMITED Technical Queries (TQ) No : HPCL/RUF/QA-QC/LTMMH/Vessels/001


Project Title : RESIDUE UP-GRADATION FACILITY (RUF) (EPCC-3 PACKAGE) FOR "VISAKHA REFINERY MODERNIZATION PROJECT (VRMP) Date : 07.03.2020
Equipment : Vessels Supplier : L&T MMH Kanchipuram
Requisition (MR) No. : RUFV‐MES‐QE‐D0‐001 INCLUDING ALL ADDENDUMS Offer reference : LTEW/MKTG/PROPOSAL/2019-20/064/A & LTEW/MKTG/PROPOSAL/2019-20/076
Offer Date : 4-3-2020 & 6-3-2020

Status SL No. Rev No. MR/Spec/Bidder offer reference LTHE Query Bidder's Reply LTHE Reply LTHE agreed Remark
(DD-MONTH-YYYY) (DD-MONTH-YYYY) (Y or N)

GENERAL QUALITY QUERIES

VENDOR to confirm compliance to Material Requisition & its attachments:


OPEN QA-1 0 Compliance to MR & its addendums Deviation if any, shall be listed only in deviation list and furnished separately as per format through proper ACCEPTED
channel. No deviation shall be accepted in the form of documents like ITP,Quality procedures,drawings etc .

In case of any conflict between Process package requirements / OWNER/Consultant’s specifications and code
General QA/QC requirements - requirements, the most stringent requirement of these shall govern and the decision of OWNER/Consultant in the
OPEN QA-2 0 specifications and code requirements resolution of the conflict shall be final. ACCEPTED
No deviation shall be entertained in any form of document approval.

OPEN QA-3 0 Comply to Vendor enlistment Vendor to ensure for availabilty of valid EIL enlistments for both supplier & sub-supplier items. ACCEPTED

Vendor to confirm compliance to the Shop QC & Inspection Procedure (Approved copy attached herewith)

Compliance to Shop QC inspection


OPEN QA-4 0 procedure ACCEPTED
Adobe Acrobat
Document

Vendor to ensure all the specification shall be fully complied though out the job. If vendor have clarity on the
OPEN QA-5 0 General QA/QC requirements specification , it shall be clarified with LTHE/EIL & licensor . Assumptions (or) consideration of previous job ACCEPTED
practices /PTRs are not acceptable.

OPEN QA-6 0 General QA/QC requirements In pre-order stage - Vendor shall check and ensure the availablity of all relevant specification/document specified ACCEPTED
in the MR/PR/ any additional specification refered in the specification provided.

Supplier shall submit all documents as per the agreed schedule. Supplier shall provide documents on keeping a
review time by LTHE/TPIA min 10 days & min. 21 working days for EIL to enable them to review and make
OPEN QA-7 0 General QA/QC requirements comments. Supplier shall respond to LTHE/PMC observations/comments within reasonable time not exceeding ACCEPTED
seven (7) working days.

LTHE informed that equipments under “ A&B" Category.


Based on the inspection Category of equipment, Vendor to prepare detailed ITP of the identified items in line with
the indicative ITP's. Vendor to specify in ITP, Pre-inspection meeting, review / approval of referance documents
and sequence of inspection and test activities related to the product along with the interventions of all the
concerned parties like sub supplier, supplier, LTHE, TPIA and PMC/Owner. For preparing ITP Vendor to consider the
requirements of Datasheet, Applicable EIL and licensor Specifications, Project Inspection test Plan, Applicable
OPEN QA-8 0 General QA/QC requirements - statutory requirements, codes and standard requirements and any other requirements as specified in MR . ACCEPTED
ITP /QAP approval Standard ITP / Indicative ITP provided in enquiry is for referance only. Supplier to note that interventions of LTHE,
TPIA and EIL/Owner for stage inspection (like hold, witness, random witness, spot witness, review point) shall be
decided by LTHE/EIL at the time of ITP approval (after close out of Engineering requirements).
Initial Comments on QAP & Procedures shall be provided by LTHE prior to EIL review. Vendor to plan a visit to LTHE
office for across the table discussion during document review/approval by EIL.

LTHE informed that for equipment are under Inspection Category is “A&B”. i.e. Stage wise and final inspection
General QA/QC requirements - including review of quality control documents by TPIA/EIL. Equipments being inspection Category “A & B” Items,
OPEN QA-9 0 ITP /QAP approval endorsement of EIL is required on TPIA’s IRN. Supplier to get IRN endorsed by EIL regional office. However, LTHE ACCEPTED
will provide support for earlier endorsement from EIL if felt necessary.

File Name:481588616.xlsx_x000D_ Sensitivity: LNT Construction Internal Use


#
L&T-Hydrocarbon Engineering Page: 2 of 4

Owner : HINDUSTHAN PETROLEUM CORPORATION LIMITED Technical Queries (TQ) No : HPCL/RUF/QA-QC/LTMMH/Vessels/001


Project Title : RESIDUE UP-GRADATION FACILITY (RUF) (EPCC-3 PACKAGE) FOR "VISAKHA REFINERY MODERNIZATION PROJECT (VRMP) Date : 07.03.2020
Equipment : Vessels Supplier : L&T MMH Kanchipuram
Requisition (MR) No. : RUFV‐MES‐QE‐D0‐001 INCLUDING ALL ADDENDUMS Offer reference : LTEW/MKTG/PROPOSAL/2019-20/064/A & LTEW/MKTG/PROPOSAL/2019-20/076
Offer Date : 4-3-2020 & 6-3-2020

Status SL No. Rev No. MR/Spec/Bidder offer reference LTHE Query Bidder's Reply LTHE Reply LTHE agreed Remark
(DD-MONTH-YYYY) (DD-MONTH-YYYY) (Y or N)

Any Technical comment as required by specification received from LTHE, TPIA and PMC / Owner shall be
incorporated by Vendor / Sub vendor on these documents without any delivery & price implication. QA-QC
General QA/QC requirements - Document documents including sub-vendor documents shall be reviewed, checked, approved and duly signed/stamped by
OPEN QA-10 0 review & approval main vendor before submission to LTHE, TPIA and PMC/ Owner. LTHE will co-ordinate with PMC for approval of ACCEPTED
Quality documents. Vendor to provide necessary supporting documents for the same

Vendor shall submit VDR / DCI for Quality document for LTHE, TPIA and PMCs approval before start of submission
of documents (during KOM) and shall submit documents for necessary approvals during execution. Vendor shall
follow Document Numbering procedure issued by LTHE. Vendor to ensure that Main / basic Engineering
OPEN QA-11 0 General QA/QC requirements -Document documents are approved in at least "Code-2" by LTHE, TPIA & PMC, before submission of QA/QC document to ACCEPTED
review & approval LTHE for approval. Review cycle for QA/QC documents will start only after approval of engineering documents in
code - 2. Vendor to ensure that Engineering & QA/QC documents / Procedures shall be approved in at least "Code
-2" by LTHE, TPIA & PMC, before start of the manufacturing activity. FInal Inspection shall be as per approved
Code-1 document..

OPEN QA-12 0 General QA/QC requirement -Document Vendor to ensure that all the requirements shall be captured on the documents and once document approved in ACCEPTED
approval Code-1, resubmission by vendor shall not be entertained by vendor due to vendor internal changes.

Vendor Audit will be conducted on selective basis by LTHE and PMC/Owner during manufacturing . Vendor to
OPEN QA-13 0 General QA/QC requirements - Audit note and provide support during such audits. ACCEPTED

Inspection Call Monitoring System (ICMS) shall be used for raising of all inspection calls for this Project. All
General QA/QC requirements - Inspection necessary access will be provided to vendor, post award of contract.Inspection notification shall be raised in
OPEN QA-14 0 calls & its notifications advance -PMC/owner as per agreed notice period as specifed in approeved Shop QC and Inspection methodology. ACCEPTED
Supplier shall submit a sperate monthly Inspection look ahead schedule to LTHE in advance .

General QA/QC requirements - After award of contract Vendor shall plan for Pre-inspection meeting at manufacturing location and raise
OPEN QA-15 0 ACCEPTED
Pre-inspection meeting notification for meeting through ICMS. LTHE, TPIA and Owner/Licensor may participate in the meeting.

Vendor shall be responsible for obtaining all statutory approvals and provide certificate as applicable. Vendor shall
General QA/QC requirements - Statutory check the IBR and ASME code stamping applicability for the items. If any statutory approval is applicable, all
OPEN QA-16 0 Approval & Certification requirements of applicable codes shall be complied. For all such items - LTHE / TPIA/ CLIENT may Carry out ACCEPTED
inspection (if envisaged) in addtion to the staturoy body inspection

Vendor shall ensure that the inspecting personnel (LTHE/TPIA/PMC) are given free access to all the required places
OPEN QA-17 0 General QA/QC requirements and information connected with their work, besides working facilities to carry out their functions. The said ACCEPTED
inspection, test and analysis shall be so conducted as not to interfere with the manufacturer’s normal production.

During inspections - Material certificates, routine & type test certificates, shop test data, certificates for Sub-
OPEN QA-18 0 General QA/QC requirements components and other relevant documents shall be furnished for review, as requested by inspectors, so as to ACCEPTED
confirm that all project quality requirements have been compiled.

Vendor Shall prepare & submit job specific procedures in line with project requirments for review and approvals.
OPEN QA-19 0 General QA/QC requirements ACCEPTED

File Name:481588616.xlsx_x000D_ Sensitivity: LNT Construction Internal Use


#
L&T-Hydrocarbon Engineering Page: 3 of 4

Owner : HINDUSTHAN PETROLEUM CORPORATION LIMITED Technical Queries (TQ) No : HPCL/RUF/QA-QC/LTMMH/Vessels/001


Project Title : RESIDUE UP-GRADATION FACILITY (RUF) (EPCC-3 PACKAGE) FOR "VISAKHA REFINERY MODERNIZATION PROJECT (VRMP) Date : 07.03.2020
Equipment : Vessels Supplier : L&T MMH Kanchipuram
Requisition (MR) No. : RUFV‐MES‐QE‐D0‐001 INCLUDING ALL ADDENDUMS Offer reference : LTEW/MKTG/PROPOSAL/2019-20/064/A & LTEW/MKTG/PROPOSAL/2019-20/076
Offer Date : 4-3-2020 & 6-3-2020

Status SL No. Rev No. MR/Spec/Bidder offer reference LTHE Query Bidder's Reply LTHE Reply LTHE agreed Remark
(DD-MONTH-YYYY) (DD-MONTH-YYYY) (Y or N)

All documents that require LTHE/EIL approval/review must be submitted in an orderly


OPEN QA-20 0 General QA/QC requirements and timely manner to ensure progress of WORKS as per contractual schedule. LTHE /EIL approval/ review shall not ACCEPTED
absolve supplier for full contractual responsibility and liabilities for all contents of such documents.

Verification or Inspection by the LTHE/OWNER/LICENSOR is not a substitute for verification or Inspection by the
Supplier and does not absolve the Supplier/vendor of its contractual obligations. Where the LTHE employs a Third
OPEN QA-21 0 General QA/QC requirements Party Inspection Agency, they shall have the same access to the Supplier’s Quality System documentation and ACCEPTED
reports to LTHE.

PMI shall be performed as per approved PMI procedure ( the procedure shall be in line with EIL specifiction 6-81-
OPEN QA-22 0 General QA/QC requirements - PMI / 0001)& applicable KBR specifications( if any as per datasheet) . Inspection interventions shall be specified in ACCEPTED
alloy verification of materials. detailed in ITP / QAP.

Third Party Inspection will be in LTHE Scope, & TPIA for Sub-supplier shall be supplier/Sub-supplier's scope. LTHE /
LTHE appinted TPIA interventions (if any) shall be specified during KOM /PIM and same shall be mentioned suitably
in ITP.
OPEN QA-23 0 General QA/QC requirements Statutory requirements (as applicable) shall be in supplier's scope. ACCEPTED
Supplier to note that non sufficient work load/rework/non-readeness of items/stage for TPIA shall be in Supplier's
account .

The materials shall be new, of first quality and of the type and grade specified on individual
equipment drawing / data sheets. All materials shall be accompanied by Mill test certificates, certified by reputed
Inspection Agency. Material certification:
1. Material used in pressure part, directly welded to pressure part, skrit plate directly welded to equipment &
contact with process fluid shall be certified as per EN 10204-3.2 certification minimum.
2. Non-Pressure Parts shall be EN 10204 Type 3.1 minimum certification.
OPEN QA-24 0 General Material requirements Supplier to consider & comply all the material specifications attached in the MR/ Project specifications. ACCEPTED

Material used for NACE & HIC etc. shall be categorically certified for NACE & HIC etc. respectively in MTC and if
Dual certificatification is required for material as per EIL & licencer specifications, shall comply both materials
specification requirement & reported in MTC.
All the material requirements of EIL & CLG specifications for plates,pipes,flanges, vessels,heat exchangers
attached , referred in the MR/PR shall be complied.

Unless specified separetly in contract Vendor to provide confirmation for following as a minimum,
1) WPS/PQR/WPQ shall be as per the ASME standard and shall be qualified under independent well known TPIA
like (CEIL, LR, BV, TUV, DNV) . Any other agency shall be subject to approval by LTHE/EIL
2)Welding consumable shall meet ASME Sect. II C and Specification requirement . Welding consumable shall be
OPEN QA-25 0 General QA/QC requirements - WPS/PQR EN10204-3.1 certified for mech, chemical properties etc. In addition batch testing shall be performed as per the ACCEPTED
and Welding consuamble requirements. applicable specification requirements.
3) For establishing New Welding Procedure / welder performance Qualifications, - TPIA , laboratory testing etc.
shall be in VENDOR's scope. TPIA shall be as per the approved list provided in the MR.
4)Welding consumable shall be procured from EIL approved manufacturere only.

1) NDT personnel & NDT Procedures shall be certified by NDE Level III in line with EIL & licensor requirements.
2) NDT personnel shall be qualified II Level ASNT-TC 1A and/or EN 473 with valid certificate as per the specification
requirement. LTHE at any stage has rights to demand for the certifications for verification. Vendor shall provide the
OPEN QA-26 0 General QA/QC requirements same. ACCEPTED
3) For U-Stamp equipments, AI approval on Welding and NDE procedures & its demostration/qualifications
required prior to submission to LTHE.

File Name:481588616.xlsx_x000D_ Sensitivity: LNT Construction Internal Use


#
L&T-Hydrocarbon Engineering Page: 4 of 4

Owner : HINDUSTHAN PETROLEUM CORPORATION LIMITED Technical Queries (TQ) No : HPCL/RUF/QA-QC/LTMMH/Vessels/001


Project Title : RESIDUE UP-GRADATION FACILITY (RUF) (EPCC-3 PACKAGE) FOR "VISAKHA REFINERY MODERNIZATION PROJECT (VRMP) Date : 07.03.2020
Equipment : Vessels Supplier : L&T MMH Kanchipuram
Requisition (MR) No. : RUFV‐MES‐QE‐D0‐001 INCLUDING ALL ADDENDUMS Offer reference : LTEW/MKTG/PROPOSAL/2019-20/064/A & LTEW/MKTG/PROPOSAL/2019-20/076
Offer Date : 4-3-2020 & 6-3-2020

Status SL No. Rev No. MR/Spec/Bidder offer reference LTHE Query Bidder's Reply LTHE Reply LTHE agreed Remark
(DD-MONTH-YYYY) (DD-MONTH-YYYY) (Y or N)

Supplier/Vendor shall provide proper clarification / explanation to LTHE/TPIA/EIL personnel during all phases upon
OPEN QA-27 0 General QA/QC requirements request by LTHE for monitoring the vendor's Work. ACCEPTED

General requirement- sub contracting All the fabrication work shall be in house & if it is subcontracted it shall be as per EIL approved list including dish
OPEN QA-28 0 works end forming . ACCEPTED

General QA/QC requirements - Scope of For any additional check testing /any new welding, mock up qualifications etc. – Inspection (including TPIA) ,
OPEN QA-29 0 check testing & Qualifications. testing shall be in Supplier scope. ACCEPTED

General QA/QC requirements - IRN of Vendor shall offer spares to TPIA for inspection and arrange for separate IRN from TPIA or separate Annexure to
OPEN QA-30 0 spares main IRN shall specify the Spare description, Size, Qty. etc. to be included in IRN from TPIA ACCEPTED

All the requirements of CLG specifications including BA-175858 CLG service requirements & reference
OPEN QA-31 0 CLG specification requirements specifications specified in MR/PR, datasheet requirements shall be complied. ACCEPTED

OPEN QA-32 0 EIL specifcation requirement All the requirements of EIL specification & EIL standard ITP requiremnts shall be fully complied. ACCEPTED

Specific WOL testing requirement (if Before bend and liquid penetrant testing (PT), the weld overlay procedure qualification test plate and weld overlay
OPEN QA-33 0 applicable) shall be subjected to the total thermal history planned for the completed vessel. ACCEPTED

Hardness testing shall be performed using Telebrineller™, Eitzen™, or Owner-accepted


OPEN QA-34 0 Hardness testing machine requirement equal. a. Use of Equotip® for hardness testing shall not be permitted. ACCEPTED
b. Other portable hardness test instruments shall be subject to Owner acceptance.

OPEN QA-35 0 General Requirement No paint or primer shall be applied to the vessel prior to hydrostatic testing. ACCEPTED

All the vessel/column dimension tolerance shall be as per EIL & CLG specification,datasheet. Whichever Stringent
OPEN QA-36 0 General Requirement requirement shall be considered. ACCEPTED

Vendor to provide the AI’s Role /intervention on all the equipment shall be captured in the ITP & NB registration
OPEN QA-37 0 General Requirement process details for the equipment if any with respect to client requirement. Vendor have valid U stamp certification ACCEPTED
& shall have the provision of ASME U stamp for carrying out inspection/fabrication at project sites.

The above technical queries raised by LTHE are only the minimum requirement & the same shall be applicable for other offers which was quoted by the vendor/bidder in HPCL RUF project. However, vendor to comply with all specification attachmnets & reference made on the specifications in PR/MR/ project
specifications . If any clarification/queries on the specifcations,attachments,reference mentioned on specifcations/datasheets shall be raised by vendor & get it clarified before the award of contract.