Sei sulla pagina 1di 1

OBRA:

LOCALIDAD:
EMPRESA:

No. Descripción Unidad cantidad pu total %


1 ESTRUCTURA
1.1 CUBIERTA
1.1.1 LAMINA GALVANIZADA CAL. 24 m2 2788.00 $ 160.00 $ 446,080.00 36.67%
1.1.2 PERFIL MONTEN (8MT12) Pza/6ml 358.00 $ 266.00 $ 95,228.00 7.83%
1.1.3 PERFIL ESTRUCTURAL (IR 254 x 44.8) Pza/6ml 91.00 $ 3,680.00 $ 334,880.00 27.53%
1.1.4 PERFIL ESTRUCTURAL (IR 203 x 15) Pza/6ml 56.00 $ 2,050.00 $ 114,800.00 9.44%
SUBTOTAL DE CUBIERTA : $ 990,988.00 81.46%

1.2 COLUMNAS DE CONCRETO REFORZADO DE 30X30cm


1.2.1 CONCRETO PREMEZCLADO f'c=250 kg/cm2 m3 15.42 $ 1,250.00 $ 19,278.00 1.58%
1.2.2 ACERO DE REFUERZO CORRUGADO DEL No. 3 Ton. 0.76 $ 12,000.00 $ 9,094.33 0.75%
1.2.3 ACERO DE REFUERZO CORRUGADO DEL No. 6 Ton. 4.71 $ 12,000.00 $ 56,578.18 4.65%
SUBTOTAL DE COLUMNAS : $ 84,950.51 6.98%

SUBTOTAL DE ESTRUCTURA: $ 1,075,938.51 88.45%

2 CIMENTACION
2.1 DADOS DE CONCRETO REFORZADO DE 40X40cm
2.1.1 CONCRETO PREMEZCLADO f'c=250 kg/cm2 m3 14.85 $ 1,250.00 $ 18,564.00 1.53%
2.1.2 ACERO DE REFUERZO CORRUGADO DEL No. 3 Ton. 0.31 $ 12,000.00 $ 3,744.72 0.31%
2.1.3 ACERO DE REFUERZO CORRUGADO DEL No. 6 Ton. 3.34 $ 12,000.00 $ 40,076.21 3.29%
SUBTOTAL DE DADOS : $ 62,384.93 5.13%

2.2 ZAPATAS AISLADAS


2.1.1 CONCRETO PREMEZCLADO f'c=250 kg/cm2 m3 40.16 $ 1,250.00 $ 50,203.13 4.13%
2.1.2 ACERO DE REFUERZO CORRUGADO DEL No. 3 Ton. 0.66 $ 12,000.00 $ 7,878.51 0.65%
2.1.3 ACERO DE REFUERZO CORRUGADO DEL No. 4 Ton. 1.67 $ 12,000.00 $ 20,088.40 1.65%
SUBTOTAL DE ZAPATAS AISLADAS : $ 78,170.04 6.43%

SUBTOTAL DE CIMENTACION: $ 140,554.97 11.55%

TOTAL DE PRESUPUESTO DE MATERIALES: $ 1,216,493.48