Bill of Quantities
Division 15: Mechanical Works
Quantit
S.No Description of Work Unit Price Amount
y
Plumbing Works

SEWER & DRAINAGE SYSTEM

Pipes

Supply, install, test and commission sewer and


drain piping system, complete with piping,
fittings, sleeves, tees, bends, reducers and all
connections, warning tape and all other required
accessories. Pipes and fittings shall be PVC Sch.
40. Except for pressurized line Work to include
excavation of trenches, sand bedding,
compaction test, piping installation, warning
tape, backfilling, hydrostatic testing, and
commissioning complete as approved by the
Engineer.

15.01 6" dia. PVC, Sch. 40 sewer/drain pipe 85 M


underground

15.02 4" dia. PVC, Sch. 40 sewer/drain pipe 170 M


underground

15.03 3" dia. PVC, Sch. 40 sewer/drain pipe 65 M


underground

Supply, install, connect and test the Pipes


including all necessary fittings, fixing and
accessories complete as shown on the Drawings.
Pipes and Fittings shall be PVC Schedule 40.
And the slope shall not be less than 2%. The
drainage system shall be adequately vented. All
the sections of drainage and vent system shall be
subjected to water test.

15.04 4" diameter for sewer /vent pipe 10 M

15.05 3" diameter for sewer lines/vent pipe 5 M

15.06 2" diameter for sewer /vent pipe 75 M

Page Total

Page 15 - 1
Villa (D)
Bill of Quantities
Division 15: Mechanical Works
Quantit
S.No Description of Work Unit Price Amount
y

Miscellaneous

Supply, Install and Test the Following Fittings


and as Shown on Drawings. Floor Drains &
Cleanouts shall be of the UPVC construction
with 50 mm water seal. Drain shall have heavy
duty stainless steel (chrome plated brass)
removable square tile with circular grid strainer.
The open area of the strainer shall be at least
two-thirds of the cross-section area of the drain
line to which it connects.

Floor cleanouts shall have cast iron body and


frame with square adjustable scoriated secured
nickel bronze top. Unit shall be vertically
adjustable for a minimum of 50 mm. When a
waterproof membrane is used in the floor
system, provide clamping collars on the
cleanouts. Cleanouts shall consist of "Y" fittings
and 3 mm bends with brass or bronze screw
plugs.

15.07 Floor Cleanouts 24 No.

15.08 Floor Drains, coated cast iron body with bottom 18 No.
outlet, combination invertible membrane clamp
and adjustable collar with seepage slots. Outlet
size to suit connected pipe work.

15.09 Drain grill dia 4” 6 m

15.10 Gully trap 10 No.

Page Total

Page 15 - 2
Villa (D)
Bill of Quantities
Division 15: Mechanical Works
Quantit
S.No Description of Work Unit Price Amount
y
WATER SUPPLY SYSTEM
Pipes
Supply, install, connect and test the Pipes
including all necessary fittings, fixing and
accessories complete as shown on the Drawings.
All the Pipes and Fittings shall be PVC Schedule
80 for cold water supply and use CPVC/Copper
pipes for hot water supply.

Cold Water Pipes

15.14 50 mm diameter pipes 50 M

15.15 25 mm diameter pipes 3 M

15.16 20 mm diameter pipes 30 M

15.17 15 mm diameter pipes 140 M

Hot water pipes


15.18 20 mm diameter pipes 35 M

15.19 15 mm diameter pipes 40 M

Water Pump

Supply, installation of Water pump from a


approved manufacturer to suit the requirement,
including all accessories, all related concrete
work, fittings and fixings to complete the job as
shown on the drawings.

15.20 Water Pumps capacity 25 GPM and @ 70 FT 2 No.

UNDER GROUND TANKS

15.21 Supply, install, connecting and testing all under


ground concrete Domestic Water tank for water
supply tank & irrigation tank . the item include
sleeves, valves, flanges, unions and all fittings
including fillings, over flow, fire pump suction,
low and high level alarms, fire test line, drain,
all accessories as specified and as shown on
drawings 1 No.

Total Division 15 - Mechanical Works

Page 15 - 3
Villa (D)
Bill of Quantities
Division 15: Mechanical Works
Quantit
S.No Description of Work Unit Price Amount
y