1 M2 BEKISITING MULTIPLEX 9 MM
Kaso 5/7 borneo sp (2x pakai) 50% 0,0170 m3 Rp 4.567.200,00 Rp 77.642,40
Multiplek 9 mm (2x pakai) 75% 0,3470 br Rp 123.500,00 Rp 42.854,50
Paku 0,4000 kg Rp 15.800,00 Rp 6.320,00
Pekerja 0,1200 oh Rp 90.000,00 Rp 10.800,00
Tukang kayu terampil 0,2700 oh Rp 113.000,00 Rp 30.510,00
Kepala tukang kayu 0,1500 oh Rp 136.000,00 Rp 20.400,00
Mandor 0,0500 oh Rp 159.000,00 Rp 7.950,00
TOTAL Rp 196.476,90
1 M3 KOLOM KP (15/15)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 181,3333 130.653,00 2.369.174,40
d
BEKISITING MULTIPLEX 9 MM m2 26,6667 196.476,90 5.239.384,0000
PASANGAN STOOT WERK m2 26,6667 405.871,00 10.823.226,6667
19.431.981,55
NO URAIAN SATUAN VOLUME HARGA JUMLAH
PEKERJAAN STRUKTUR LANTAI 2
1 M3 BALOK B1 (15/25)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 300,5681 130.653,00 3.927.012,61
a
BEKISITING MULTIPLEX 9 MM m2 10,9333 196.476,90 2.148.147,4400
PASANGAN STOOT WERK m2 4,0000 405.871,00 1.623.484,0000
TOTAL 8.698.840,53
1 M3 BALOK B2 (15/30)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 309,6116 130.653,00 4.045.168,36
b
BEKISITING MULTIPLEX 9 MM m2 13,6000 196.476,90 2.672.085,8400
PASANGAN STOOT WERK m2 4,0000 405.871,00 1.623.484,0000
TOTAL 9.340.934,68
BALOK B4 (20/45)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 501,0957 130.653,00 6.546.965,02
c
BEKISITING MULTIPLEX 9 MM m2 22,9333 196.476,90 4.505.870,2400
PASANGAN STOOT WERK m2 5,3333 405.871,00 2.164.645,3333
TOTAL 14.217.677,08
KOLOM KP (13/13)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 228,9550 130.653,00 2.991.365,67
d
BEKISITING MULTIPLEX 9 MM m2 30,7904 196.476,90 6.049.609,4160
PASANGAN STOOT WERK m2 30,7904 405.871,00 12.496.945,0520
TOTAL 22.538.116,62
KOLOM K2 (13/30)
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 248,1900 130.653,00 3.242.676,97
e
BEKISITING MULTIPLEX 9 MM m2 22,0499 196.476,90 4.332.303,6793
PASANGAN STOOT WERK m2 22,0499 405.871,00 8.949.430,8319
C.2
TOTAL 17.524.607,96
TALANG
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 57,0000 130.653,00 744.722,10
h
BEKISITING MULTIPLEX 9 MM m2 13,9286 196.476,90 2.736.642,5357
PASANGAN STOOT WERK m2 3,5714 405.871,00 1.449.539,2857
TOTAL 5.931.100,40
PELAT LANTAI
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,0000 1.000.196,48 1.000.196,48
BESI BETON TERPASANG POLOS/ULIR 10 Kg 153,1093 130.653,00 2.000.418,75
i
BEKISITING MULTIPLEX 9 MM m2 8,3333 196.476,90 1.637.307,5000
PASANGAN STOOT WERK m2 8,3333 405.871,00 3.382.258,3333
TOTAL 8.020.181,06
TANGGA
BETON MUTU fc=19,3 Mpa (K 225), slump (12+2) cm, w/c=0,58 m3 1,9375 1.000.196,48 1.937.900,69
BESI BETON TERPASANG POLOS/ULIR 10 Kg 85,9813 130.653,00 11.233.712,61
j
BEKISITING MULTIPLEX 9 MM m2 12,0937 196.476,90 2.376.132,6855
PASANGAN STOOT WERK m2 8,1837 405.871,00 3.321.526,5027
TOTAL 18.869.272,49
1 M2 MEJA DAPUR KERAMIK 20 X 40 VARIASI MOTIF
Keramik 10/20 53,0000 bh Rp 1.400,00 Rp 74.200,00
Semen PC 8,1900 kg Rp 1.416,00 Rp 11.597,04
Pasir pasang 0,0450 m3 Rp 161.600,00 Rp 7.272,00
Semen warna 2,7500 kg Rp 9.100,00 Rp 25.025,00
c
Pekerja 0,7000 oh Rp 90.000,00 Rp 63.000,00
tukang batu 0,3500 oh Rp 113.000,00 Rp 39.550,00
Kepala tukang batu 0,0350 oh Rp 136.000,00 Rp 4.760,00
Mandor 0,0350 oh Rp 159.000,00 Rp 5.565,00
TOTAL Rp 230.969,04
1 BH INSTALASI LAMPU SL
Lampu SL Philip 25 watt 1,0000 bh Rp 31.500,00 Rp 31.500,00
b Tukang 0,2200 oh Rp 90.000,00 Rp 19.800,00
Mandor 0,0200 oh Rp 159.000,00 Rp 3.180,00
TOTAL Rp 54.480,00
1 BH INSATALASI SAKLAR
Saklar Broko Tunggal Standard 1,0000 bh Rp 11.300,00 Rp 11.300,00
d Tukang 0,4000 oh Rp 90.000,00 Rp 36.000,00
Mandor 0,0400 oh Rp 159.000,00 Rp 6.360,00
TOTAL Rp 53.660,00
1 M2 PENGECATAN PLAFOND
Plamik tembok 0,1000 kg Rp 11.840,00 Rp 1.184,00
Cat dasar 0,1000 kg Rp 150.000,00 Rp 15.000,00
c Cat penutup 0,2600 kg Rp 150.000,00 Rp 39.000,00
Tukang 0,0600 oh Rp 90.000,00 Rp 5.400,00
Mandor 0,0025 oh Rp 159.000,00 Rp 397,50
TOTAL Rp 60.981,50
c. RANCANGAN ANGGARAN DAN BIAYA
NO ITEM PEKERJAAN SPESIFIKASI UNIT VOLUME HARGA SATUAN SUB JUMLAH Bobot (%)
A PEKERJAAN PERSIAPAN
a Pembersihan Site m2 96,0000 Rp 5.295,00 Rp 508.320,00 0,0815
b Pengukuran As dan Bouwplank m3 44,0000 Rp 14.950,00 Rp 657.800,00 0,1055
c Air Kerja PDAM ls 1 Rp 500.000,00 Rp 500.000,00 0,0802
d Listrik Kerja PLN ls 1 Rp 750.000,00 Rp 750.000,00 0,1203
Sub Jumlah A Rp 2.416.120,00
B PEKERJAAN TANAH DAN PONDASI
a Pondasi Strauss Pile K-225, Kedalaman 10 m titik 10 Rp 1.441.334,74 Rp 14.413.347,42 2,3122
b Pondasi Batu Kali
b.1 Galian Tanah Biasa Max. 2m m3 51,9025 Rp 88.155,00 Rp 4.575.464,89 0,7340
b.2 Urugan Tanah Kembali m3 46,6250 Rp 23.819,70 Rp 1.110.593,51 0,1782
b.3 Urugan Pasir Urug m3 10,8895 Rp 213.150,00 Rp 2.321.096,93 0,3723
b.4 Anstamping m3 6,2025 Rp 402.456,60 Rp 2.496.237,06 0,4004
b.5 Pas. Batu Belah 1PC:5PP m3 17,3370 Rp 732.601,40 Rp 12.701.110,47 2,0375
c Lantai Kerja m3 3,8400 Rp 1.704.007,89 Rp 6.543.390,28 1,0497
Sub Jumlah B Rp 44.161.240,56
C PEKERJAAN STRUKTUR
C.1 Pekerjaan Beton Struktur Lantai 1
a Sloof SL-1 (15/30) Beton K-225 m3 3,5170 Rp 6.179.441,88 Rp 21.733.097,10 3,4864
b Kolom K.1 (20/40) Beton K-225 m3 2,3424 Rp 12.178.124,18 Rp 28.526.038,08 4,5761
c Kolom K.2 (15/30) Beton K-225 m3 0,3294 Rp 15.904.100,08 Rp 5.238.810,57 0,8404
d Kolom KP (15/15) Beton K-225 m3 1,1529 Rp 19.431.981,55 Rp 22.403.131,53 3,5939
sub Jumlah C.1 Rp 77.901.077,28
C.2 Pekerjaan Beton Struktur Lantai 2
a Balok B1 (15/25) Beton K-225 m3 0,3206 Rp 8.698.840,53 Rp 2.788.848,27 0,4474
b Balok B2 (15/30) Beton K-225 m3 0,7227 Rp 9.340.934,68 Rp 6.750.693,50 1,0829
c Balok B4 (20/45) Beton K-225 m3 3,9357 Rp 14.217.677,08 Rp 55.956.511,68 8,9764
d Kolom KP (13/13) Beton K-225 m3 0,9249 Rp 22.538.116,62 Rp 20.845.504,06 3,3440
e Kolom K2 (13/30) Beton K-225 m3 1,3135 Rp 17.524.607,96 Rp 23.018.572,55 3,6926
f Ringbalok RB-1 (15/20) Beton K-225 m3 0,3158 Rp 7.938.157,98 Rp 2.506.870,29 0,4021
g Ringbalok RB-2 (15/25) Beton K-225 m3 1,3181 Rp 8.221.927,76 Rp 10.837.322,98 1,7385
h Talang Beton K-225 m3 0,2800 Rp 5.931.100,40 Rp 1.660.708,11 0,2664
i Pelat Lantai Beton K-225 m3 6,7217 Rp 8.020.181,06 Rp 53.909.251,06 8,6480
j Tangga Beton K-225 unit 1 Rp 18.869.272,49 Rp 18.869.272,49 3,0270
Sub Jumlah C.2 Rp 197.143.555,00
C.3 Pekerjaan Struktur Rangka Atap
a Pemasangan Rangka Atap Baja Ringan Main Truss C 75 m2 61,0800 Rp 181.981,00 Rp 11.115.399,48 1,7831
b Pemasangan Genting Genting Plentong m2 90,7038 Rp 54.200,00 Rp 4.916.145,96 0,7886
Sub Jumlah C.3 Rp 16.031.545,44
D PEKERJAAN FINISHING
D.1 Pekerjaan pasangan
a Pasangan 1/2 dinding bata bata merah 1 PC:5PP m2 376,0007 Rp 108.523,88 Rp 40.805.054,85 6,5459
b Pekerjaan Plesteran 1PC : 5PP m2 564,7894 Rp 50.122,14 Rp 28.308.455,64 4,5412
c Pekerjaan Acian m2 564,7894 Rp 34.092,00 Rp 19.254.800,22 3,0888
Sub Jumlah D.1 Rp 88.368.310,71
D.2 Pekerjaan Kusen, Pintu, Jendela
a Pintu type PJ1 Kusen Alumunium unit 1 Rp 2.161.728,00 Rp 2.161.728,00 0,3468
b Pintu Type P1 Kusen Alumunium unit 4 Rp 1.471.320,00 Rp 5.885.280,00 0,9441
c Pintu Type P2 Kusen Alumunium unit 3 Rp 1.206.840,00 Rp 3.620.520,00 0,5808
d Pintu Type P2' Kusen Alumunium unit 1 Rp 1.151.840,00 Rp 1.151.840,00 0,1848
e Pintu Type P3 Kusen Alumunium unit 1 Rp 1.038.584,00 Rp 1.038.584,00 0,1666
f Pintu Type P4 Kusen Alumunium unit 1 Rp 1.742.216,80 Rp 1.742.216,80 0,2795
g Jendela type J1 Kusen Alumunium unit 1 Rp 309.981,60 Rp 309.981,60 0,0497
h Jendela type J2 Kusen Alumunium unit 3 Rp 360.008,00 Rp 1.080.024,00 0,1733
i Jendela type BV Kusen Alumunium unit 1 Rp 200.019,20 Rp 200.019,20 0,0321
j Ventilasi Glass Block unit 1 Rp 388.000,00 Rp 388.000,00 0,0622
Sub Jumlah D.2 Rp 17.578.193,60
D.3 Pekerjaan Plafond
a Plafond Gypsum Board m2 98,0482 Rp 43.634,20 Rp 4.278.254,77 0,6863
Sub Jumlah D.3 Rp 4.278.254,77
D.4 Pekerjaan Penutup Lantai
a Lantai granite tile ( Ubin granit alam DN Uk 60x60 ) ex. Garuda motif * m2 76,4326 Rp 702.631,00 Rp 53.703.914,17 8,6151
b Lantai keramik (Ubin Keramik Uk 40x40 ) ex. Roman G447509 m2 1,5345 Rp 719.257,00 Rp 1.103.699,87 0,1771
c Meja dapur keramik variasi motif (Ubin Keramik 20x40 Variasi
) motif * m2 1,2750 Rp 230.969,04 Rp 294.485,53 0,0472
d Lantai kamar mandi (Ubin Keramik 25x25 ) ex. Roman G447509 m2 12,2130 Rp 370.933,40 Rp 4.530.209,61 0,7267
e Lantai kamar tidur pembantu (Ubin Keramik 40x40 ) ex. Roman G447509 m2 3,5613 Rp 333.482,00 Rp 1.187.612,77 0,1905
f Lantai kamar mandi pembantu (Ubin Keramik 20x20ex. ) Roman anti slip m2 1,5725 Rp 370.933,40 Rp 583.292,77 0,0936
g Lantai carport paving ukuran 30x30 cm ex. Cisangkan natural hitam
m2 28,0000 Rp 165.536,00 Rp 4.635.008,00 0,7435
Sub Jumlah D.4 Rp 66.038.222,72
D.5 Pekerjaan Sanitasi
a Instalasi Air Bersih
Pipa PVC 3/4 inch m' 55,0000 Rp 10.807,50 Rp 594.412,50 0,0954
Pipa PVC 1 inch m' 19,6000 Rp 7.920,00 Rp 155.232,00 0,0249
Perlengkapan m' 74,6000 Rp 29.737,50 Rp 2.218.417,50 0,3559
b Instalasi Air Kotor
Pipa PVC 4 inch m' 29,2000 Rp 81.015,00 Rp 2.365.638,00 0,3795
Pipa PVC 3 inch m' 23,9000 Rp 48.895,00 Rp 1.168.590,50 0,1875
Perlengkapan m' 53,1000 Rp 68.997,00 Rp 3.663.740,70 0,5877
c Instalasi Air Panas
pipa m' 41,8000 Rp 349.446,00 Rp 14.606.842,80 2,3432
Water Heater Merk Paloma ls 1 Rp 2.000.000,00 Rp 2.000.000,00 0,3208
d Pemasangan Keran bh 13 Rp 43.647,00 Rp 567.411,00 0,0910
e Pemasangan Kloset Jongkok bh 1 Rp 522.058,50 Rp 522.058,50 0,0837
f Pemasangan Kloset Duduk bh 3 Rp 2.244.440,00 Rp 6.733.320,00 1,0801
g Pemasangan Washtafel bh 4 Rp 1.342.676,00 Rp 5.370.704,00 0,8616
Sub Jumlah D.5 Rp 39.966.367,50
D.6 Pekerjaan Instalasi Listrik dan Armature
a Instalasi Lampu dan Stopkontak m' 42,0000 Rp 239.552,00 Rp 10.061.184,00 1,6140
b Pemasangan Lampu bh 18 Rp 54.480,00 Rp 980.640,00 0,1573
c Pemasangan Stopkontak bh 18 Rp 35.580,00 Rp 640.440,00 0,1027
d Pemasangan Saklar bh 15 Rp 53.660,00 Rp 804.900,00 0,1291
e Instalasi MCB bh 1 Rp 93.780,00 Rp 93.780,00 0,0150
f Instalasi Penangkal Petir bh 1 Rp 7.500.000,00 Rp 7.500.000,00 1,2031
Sub Jumlah D.6 Rp 20.080.944,00
D.7 Pekerjaan Laburan
a Pengecatan Dinding Interior m2 271,0989 Rp 60.981,50 Rp 16.532.018,30 2,6520
b Pengecatan Dinding exterior m2 293,6905 Rp 91.581,50 Rp 26.896.615,43 4,3147
c Pengecatan Plafond m2 98,0482 Rp 60.981,50 Rp 5.979.126,31 0,9592