Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Chapter 3
by
° WATERTIGHTNESS
3.1 General
3.2 Steel Shell Tunnels
3.3 Concrete Tunnels
3.4 The Expansion Joint Concept for Concrete Tunnels
3.5 The Waterproofing Membrane Concept
3.6 Protection of Concrete Against Chemical Attack
3.7 Longitudinal Prestressing
o L O N G I T U D I N A L A R T I C U L A T I O N AND J O I N T S
5.1 Steel Shell Tunnels
5.2 Concrete Tunnels
5.3 Shear Transfer in Intermediate Joints
5.4 Intermediate Flexible Rubber Joint Design
5.5 Expansion Joint Design
5.6 Final Joint of Concrete Tunnels
o LOADINGS
8.1 Loading Combinations and Allowable Stress Increments
8.2 Accidental Loads
DOUBLESlIE3~ SHELL
SECOND HAMPTON ROADS 11JNNEL Ig76,
) I
71111O i
BAU.ASTCONCRE'~ 12400 '-I
I- 25200 _!3050~
I--
= 111120
I
Unless proper measures are taken, vertical full-depth The vertical joint between two segments is basically an
cracks can occur at about 5-m intervals. Satisfactory unreinforced cold joint provided with a cast-in flexible
processes have been developed to avoid these construction waterstop. In this way, the tunnel element can be subjected
cracks, namely by reducing heat of hydration by using to flexural deformations without developing longitudinal
concrete with relatively low cement content and forced tensile strain between the expansion joints, which .can
cooling in the lower part of the walls (see Fig. 3-3). Sometimes cause cracking of the concrete. It is common practice to
this is done in combination with insulation and heating of provide an external sealant or waterproofing membrane
the base slabs. If cracks nevertheless are found, remedial across the immediate vicinity of the joint (see Fig. 3-9).
grouting appears to be effective. Great care must be taken to assure that shrinkage of
Effective control of differential heat development largely thermal cracking does not occur in the segments and that
depends on the heat of hydration of the concrete. This any cracks which do occur are sealed prior to floating the
process, in turn, is a direct function of the amount of cement element out of the casting basin.
in the mix. Therefore, the use of typical concrete mixes with During transportation and installation, the segments of
high cement factors (taken from highway structures codes) such a tunnel element must be structurally coupled in the
can be counterproductive in this respect. longitudinal direction. This can be done by temporary
There are two basic concepts regarding control of leakage coupling rods, with or without prestress; or by temporary
for concrete tunnels: longitudinal prestressing tendons over the full length of the
1. The expansion joint concept involves avoiding longitu- tunnel element. The temporary prestressing tendons are
dinal stresses that can cause cracks, thereby relying on the usually cut after installation. However, they are sometimes
watertightness of the uncracked concrete. maintained permanently--for example, when flexural bend-
2. The waterproofing membrane concept involves en- ing of the tunnel is not expected, as may be the case with a
veloping the concrete tunnel element in a waterproofing piled foundation.
membrane.
Each of these concepts is discussed in more detail below. 3.5 Waterproofing Membrane Concept
For a number of reasons, such as seismic loading or control
3.4 Expansion Joint Concept for Concrete Tunnel of displacements, it may be desirable to make tunnel elements
Waterproofing monolithic in, say, 100-m lengths. Full-depth transverse
cOncrete cracks can develop, especially in the vertical
The expansion joint concept involves achieving water- construction joints, unless action is taken to reduce that
tightness by avoiding transverse cracking of the concrete. A possibility. With such a concept, the membrane waterproofing
tunnel element 100 m long or more is designed with expan- that envelopes the element is a prerequisite and plays an
sion joints. The length between the expansion joints is important part. There may be other reasons for using a
determined by the practical length of a complete concrete waterproofing membrane, such as to protect the concrete
pour, which is in the range of 20 m. against aggressive qualities of the surrounding environment,
j t,
I~ 108(~D
26180 5O0
I_ 12680 _ I
30000
39700
~
.= 10300
j
.,= 241 O0 _ I
exhau~ , ~ plate
air duc'li
i i i ili i i i !!ii i 1i l
l:i;i!iiiiiiiii!ill lil;i!ii!ili!i!iii!iiili?iiiiii!ilililil
Figure 3-6. Typical tremie concrete joint for a double-shell Figure 3-7. Intermediate joint with sliding arrangement
steel tunnel. for a double-steel-shell tunnel .
5.2 Concrete Tunnels ment under expected long-term decompression and relax-
ation of the gasket. Nevertheless, a second flexible rubber
Concrete tunnels are usually provided with permanent
water barrier is installed at the dewatered joint by bolting
flexible joints to reduce restraint to temperature contrac-
tion and to reduce flexural bending. However, there is an it to the inside faces of the two tunnel elements. The shape
of this curved, slab-type rubber seal or gasket, often re-
example of a concrete tunnel made monolithic over 400 m,
ferred to as the "Omega" seal because of its shape, is
but with flexible terminal joints.
sometimes considered to be the main seal. The space
The type of solid rubber gaskets generally used between
between the Gina gasket and the Omega seal is usually
concrete immersion units normally can provide enough
drained off to the inside of the tunnel, providing a direct
flexibility for this purpose without losing their sealing
capacity. These rubber gaskets only transfer compression indication of the performance of the outer gasket. An
effectively. To prevent shear deformation in an intermedi- example of an intermediate flexible joint design for concrete
tunnels is shown in Figure 3-8. This type of joint can also
ate joint, which is desirable for the alignment and for
be used for steel tunnels, when flexible joints are required.
sealing performance, shear keys are required. An example
of an intermediate joint for a double steel-shell tunnel is The Gina-type gasket acts as a flexible joint under
compression, and can practically be considered as a hinge in
shown in Figure 3-7.
longitudinal moment transfer. Shear resistance can be
ignored, because it has a tendency to slip along its base
5.3 Shear Transfer in Intermediate Joints under shear deformation. For this reason, shear deformation
Transfer of large shear forces in intermediate joints can across a joint is not limited by properties of the Gina g~isket,
best be achieved by shear keys in the walls that are made in but rather by the allowable shear strain of the Omega
situ in front of the inner face of the permanent watertight gasket, especially with regard to its corner sections.
gasket. They can also be installed prior to placement with The exterior rubber gasket should be placed as much as
provisions for in-situ adjustment. Shear transfer for small possible to the outside of the structure, in order to keep the
shear forces can be accomplished using shear keys or longi- recess between the side and the outside of the gasket
tudinally movable dowels in the base slab area of the joint. shallow. This arrangement prevents backfill material from
Settlement discontinuities often occur at the terminal accumulating gradually and obstructing the proper move-
joint, Shear fixity is desirable, but the shear force and ment of the joint.
resulting bending moment can become very large. To reduce
the shear, the following solutions, or a combination thereof, 5.5 Expansion Joints
can be applied:
These joints are used in some concrete tunnel elements at
• Ground improvement, in the case of soft upper layers.
the location of the vertical construction joints. They are
• Delaying the shear connection until a part of the basically cold joints without steel reinforcement, provided
settlement has taken place. with steel-rubber flexible waterstops. Special provisions are
• Readjustment of the tunnel elevation with reinjection made to enable pressure grouting access around the waterstop
of bedding sand. after the main structural concrete is hardened. A typical
• Preloading by internal flooding. Dutch expansion joint is shown in Figure 3-9. Sealant is
provided at the external face to prevent entry of backfill.
5.4 Intermediate Flexible Rubber Joint Design When the tunnel in its permanent condition is subjected
to longitudinal curvature, these joints will open at the
A type of solid rubber gasket, sometimes referred to as a
"tension" side. However, tension cannot be transferred
"Gina" gasket, is used for practically all concrete tunnels. It
through these joints. This relieves the concrete between the
is used as a temporary seal at the installation stage and
expansion joints of longitudinal tension transfer.
remains as a flexible compression seal for the permanent
stage. The facing tunnel element ends are lined with steel
plates that are matched as parallel planes within +5 mm 5.6 Final Joint of Concrete Tunnels
tolerance. The gasket is clamped at its backside. The final joint cannot be made with the intermediate
The specifications for material characteristics and geom- rubber compression joint that is used in the regular
etry are usually based on the permanent sealing require- intermediate joints. Wedges or spacers are placed by diver
1 I
N T ~IT ~
Figure 3-8. Intermediate flexible joint for concrete tunnels Figure 3-9. Typical Dutch expansion joint.
( D u t c h solution).
1
the structure can be assumed to be the same temperature as
the surrounding water.
The temperature changes of the concrete are usually
specified in two parts:
1. An overall increase or decrease, relative to the ambi-
ent ground water, with a range from _+ 15°C to + 10°C.
2. A temperature "gradient" over the thickness of a wall
or slab (e.g., a linear temperature variation from 0°C on the
outside to + 10°C on the inside: this gradient can then be
split into an overall increase or decrease of 5°C, to be added
Figure 3-10. Example of the final joint for concrete to (1), above, and a linear variation over the thickness from
tunnels. -5°C to +5°C, or vice-versa).
The overall increase or decrease of the temperature of
concrete area is equal to the ratio of the densities of concrete the structure will lead to longitudinal deformation. For
and water, a simple expression for the average concrete tunnels with monolithic intermediate joints between the
stress is: terminals, this could lead to concrete stresses in the range
f (avg.) = D e * 0,024 MPa, ( D in m) of the tensile strength or yielding of the vertical joints.
Tunnels with intermediate flexible compression joints are
The longitudinal hydrostatic compression force will fol- not restrained to longitudinal deformation of the concrete,
low the changes in water depth (e.g., by the tide), as long as but the flexible joints will react with a minor increase or
the immersed part of the tunnel has a free end and friction decrease of compression.
between the free end and the section under consideration The linear temperature variation over the thickness of a
can be ignored. wall or slab of +5°C to -5°C will cause bending stresses
The hydrostatic compression will be fixed as soon as the varying from -1.0 MPa to +1.0 MPa over the thickness of a
tunnel is closed between the terminal structures. The concrete wall or slab. Although small, these stresses are a
compression is assumed to act at the centroide of the magnitude larger than the hydrostatic precompression. On
structure when flexible intermediate compression joints the outside, there will be tension in the summer and com-
are used. pression in the winter. The stress diagrams of Figure 3-12
Losses of the fixed hydrostatic compression. Losses of clearly show that the temperature variations will not cause
the fixed hydrostatic compression are caused by time- transverse cracks.
dependent relaxation of rubber compression joints and
shortening of concrete, causing decompression of the joint.
The degree of relaxation of the rubber compression joints
6.2.3 Longitudinal bending
varies with the characteristics of the selected type and the Discontinuity of surcharge and discontinuity of settle-
range of compression. Generally the loss will be about 50% ment have the same effect. They cause longitudinal bend-
of the initial compression. Typical performance rates for ing of the tunnel, which can be analysed as a beam on elastic
flexible rubber compression gaskets used as intermediate foundation. The large beam stiffness of the tunnel leads to
joints are shown in Figure 3-11. high shear force and bending moment response to longitu-
Shortening of the concrete can be caused by shrinkage dinal bending.
and temperature deformation. Creep of the concrete can be This is illustrated by the following theoretical example
practically ignored. The concrete codes do not provide for a monolithic tunnel element (not segmented) that
proper parameters to determine the shrinkage strain for wants to settle 50 mm, but has shear restraint at one end
thick-walled concrete members of immersed concrete tun- (which could be the terminal joint). The joint is flexible for
nels. If calculated according to the FIP-CEB model code, a rotation. The main variable is the spring constant of the
very small strain is found. The shrinkage strain is not subgrade reaction. For this example, K° = 2 MN/m 3 is used,
restrained when flexible intermediate joints are utilised, corresponding to a deflection of 0.05 m under a pressure of
but the resulting decompression of these joints will cause a 0.1 MPa (or 10 t/m 2, as could be caused by heavy sur-
minor loss of the locked-in compression force. In the charge).
Netherlands, the shrinkage strain is ignored for tunnels in Figure 3-13 shows an example of longitudinal analysis
which the concrete is directly exposed at the outside. for the response of concrete tunnels to unequal settlement.
i I
~ ~, ~ ~0 ~ '" ~
v rnctM -
'1
i
/ ' - M ma -
0u~J~ 7t0"c F t o ~ , ~ -I.0 ~ -0..o6
,,
¢a,/PJICmlON
Figure 3-12. Diagrams of concrete temperature and Figure 3:13. Examples of longitudinal analysis of the
stresses for summer and winter, valid for tunnels with response of concrete tunnels to unequal settlement.
flexible intermediate joints.
7. Structural Analysis for Composite Steel Shell In some cases, interior "spiders" may be required to main-
Tunnels tain the roundness of the shell plate. Accurate roundness
must be maintained to assure a uniform thickness of the
The design of steel shell immersed tunnels differs from
interior ring concrete. This is critical to the eventual
that of concrete tunnels because of the manner of their
structural integrity of the elements when it is backfilled.
construction. Concrete tunnels are cast in a basin, floated,
A portion of the exterior concrete about 1.5 m thick and
and then placed and backfilled without much change in the
called the "keel," is usually placed in the bottom of the
basic structural section. In contrast, the fabrication of steel
formplate prior to launch. This provides protection for the
shell elements involves a structure that undergoes a series
bottom of the element during launch, as well as stability
of stages, each involving a basically different structure.
during towing. After this concrete is placed, the loads of
The description below applies to double steel-shell struc-
the element are transferred to launching sleds or, in the
tures. The structural concept is simpler for the single-shell
case of end-launching, fore and aft poppets prior to launch-
type because there is no exterior concrete, other than ballast
ing. The shell and diaphragms may require additional
concrete on the roof. In fact, the single steel-shell tunnel has
reinforcements in either case. The keel concrete is consid-
the same stages as basically different structures. Because
ered to act as a longitudinal beam acting compositely with
this type of shell has no external diaphagms, temporary
the stiffened shell plate and diaphragms. Both static and
internal spider frames are utilised. In the case of double-
d y n a m i c water pressures that will occur during launch
tube shells, temporary longitudinal trusses also are utilised
must also be determined and allowed for in the design.
in the middle.
While the basic design of the elements takes into ac-
The structural stages are:
count some of the expected launching loads, the contractor
Stage 1: Fabrication and launching. must be made responsible for checking the details for his
Stage 2: Internal outfitting with concrete. proposed method of supporting and launching, and must
Stage 3: Final condition after backfilling in place. provide whatever additional reinforcement that may be
Each of these stages is described in detail below. r eq u i r ed .
Towing may impose longitudinal stresses on the steel
7.1 Stage I: Fabrication and Launching element. Often the practice has been to tow the element
under its own flotation, because the draft of an element that
During Stage 1, the loads on the structure are largely a has not been outfitted with interior concrete and the re-
function of the method of support and launching, if the mainder of the exterior concrete is only about 2 to 3 m. If the
element is to be constructed on shipways. It may be elements are to be towed in ocean waters, the height of long
launched sideways or end-launched, in either a controlled or periodic swells becomes important, because the swells im-
an uncontrolled launching. pose significant longitudinal bending moments. Unless
As an example of a different process, the elements of the they are accounted for, these bending moments could cause
(I-664) Monitor-Merrimac Tunnel in Hampton Roads, Vir- buckling of the top shell. More recent practice, when ocean
ginia (U.S.A.) were constructed in a drydock and floated out, towing is required, has been to tow elements on large
with all of the interior concrete installed prior to installation offshore construction barges in order to reduce this effect.
of the end bulkheads. However, for this tunnel the design Chapter 7 of this edition discusses the impact of tunnel
had been based on being a launched element because the element transportation on immersed tunnel design for
expectation had been that the elements would be con- both steel and concrete options.
structed in the conventional way with fitting out being done
while afloat. Boston's Ted Williams Tunnel was constructed
in the same drydock, although very little of the interior
7.2 Stage 2: Internal Outfitting with Concrete
concrete was placed prior to floating out because of the long During outfitting, the loading conditions on the shell
distance of travel to Boston. change constantly during concrete placement, At the begin-
During fabrication, each steel binocular or monocular ning of outfitting, the element is supported uniformly as it
module (with about eight modules per element) must be floats with a constant draft. The end bulkheads are quite
supported adequately to avoid distortion or local buckling. heavy and impose a hogging moment on the element. As
Type of Structure
Ill (F):
I (S): Steel II (S): Reinforced Reinforced
shell traffic concrete tunnel concrete
tunnel with waterproofing traffic tunnel
Stress Increments (S) or Load Factor (F) (U.S.A.) membrane (Japan) (Netherlands)
NOTE: A dash indicates that this aspect is known not to be reviewed, or is not critical.
* Refers to Dutch practice: the load factor used for the ultimate limit state is 1.7, reduced for the material factor incorporated.
** The factor 1.30 also includes extremely high water.
*** 1.4" A + 1.15 * B1.
108 TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY Volume 12, Number 2, 1997
8.2.1 Sunken ship loads 9. Typical Material Specifications
For immersed tunnels in soft ground, the tunnel may 9. I Structural Concrete for Concrete Tunnels
respond more rigidly than the adjacent backfill. This can be
Although specifications vary considerably worldwide, a
accounted for in the load to be specified, usually as a uniform
distinction can be made between two main groups of speci-
load over a minimum area. For the design of an immersed
fications. One group of contractors tends to use highway
tunnel across the Great Belt in Denmark, which is an
structure codes, which usually specify high-grade concretes,
international waterway used by very large vessels, the
with characteristic strength in the range of 40 Mpa, and
specification was 100 kN/m 2 over 250 m 2.
with durability requirements associated with sulphate at-
tack. The latter requirements generally lead to the use of
8.2.2 Dropping and dragging anchors sulphate-resisting cement or Portland cement to which
Immersed tunnels are generally covered with a protec- pulverised fly ash (p.f.a.) has been added.
tive concrete layer on the roof. For navigation conditions, The use of silica fumes with p.f.a, and Portland cement
protective stone cover is also applied. concrete is being considered in some countries.
The energy of an object free falling in water has to be The other group, of which the Netherlands is typically
absorbed by the stone cover and partly by the crushing of the representative, uses lower-grade concrete, with the empha-
concrete cover layer. The structural roof load is related to sis on construction crack avoidance, low permeability, and
the impact pattern. This factor can usually be accommo- chloride penetration resistance. Watertight membranes
dated without additional reinforcement. are not used.
The lateral load of a dragging anchor hooking behind the A typical concrete specification for Dutch immersed
edge of the tunnel roof can be derived from the effective .tunnels is:
anchor-rope-breaking loads. For large vessels, the load can Characteristic strength: 22.5 Mpa
be in the range of 3,0130 kN, acting as low as 4 m below the Cement types: Dutch blast furnace cement
rooftop, depending on the type of bottom material and (more than 65% slag)
anchor. The upper part. of the walls may need to be provided Max. cement content: 275 kg/m 3
with cover concrete to avoid mechanical damage to the
Max. water/cement ratio: 0.5
structural concrete. Dragging anchor loads of this magni-
tude normally can be resisted by the available friction of the Permeability: Less than 20 mm in
foundation and passive pressure behind the tunnel. penetration test, according
to DIN 1048
8.2.3 Flooding of tunnels
9.2 Materials for Steel Shell Tunnels
The probability of internal flooding is very small during
the operational life of a tunnel, although several such Typical material specifications for structural concrete
incidents have already occurred. It makes sense to investi- and structural steel, as presently used in the U.S.A., are:
gate this type of incident in the light of possible undesirable Structural concrete:
settlements. In many cases, it is only one tube that has
flooded, and then usually not higher than roof level at the Strength: 4,000 psi (also for tremie concrete)
lowest point. Cement: Portland Cement: AASHTO M85,
Type I or II
8.2.4 Internal explosion loads Cement content: 565-610 lb/yd 3
The probability and extent of internal explosion loads
Water/cement
depends very much on how the tunnel is to be used. An ratio: 0.48-0.50, depending on size of ag-
example is the rectangular Liefkenshoek Belgium, located gregate
near an industrial area, which has been designed for an Slump: 2 in.-5 in.
internal explosion pressure of 4 bar. This requirement Permeability: 2,000 coulombs per 6 hours, where
substantially increased the amount of transverse reinforce- tested per AASHTO T-277
ment needed. El)' ash: will be substituted for 5% of the
cement for all concrete.
Structural steel: ASTM Grade A36 (mild steel with
36,000 psi yp)
Reinforcing AASHTO M31 Grade 60 (60,000 psi
steel: YP)