Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
This document
Number of Allowable Tensile was partially produced to prevent construction accidents
Loading Cycles
a
Stress (psi) associated with column base plates. For example, OSHA
20,000 to 100,000 40,000 requires that all column based have four anchor rods.
100,000 to 500,000 25,000 The following discussion presents methods of designing
500,000 to 2,000,000 15,000 and detailing column bases.
Over 2,000,000 10,000
a
– These categories correspond to the loading 9.1 Resisting Tension Forces with Anchor Rods
conditions indicated in Appendix K of the AISC
Specification. The design of anchor rods for tension consists of four steps:
1. Determine the maximum net uplift for the column.
Building columns must be anchored to the foundation sys- 3. Determine the appropriate base plate size, thickness
tem to transfer tension forces, shear forces, and overturning and welding to transfer the uplift forces. Refer to
moments. This discussion will be limited to the design of AISC Design Guide 1 (AISC, 1990).
column anchorages for shear and tension forces. The prin-
ciples discussed here can be applied to the design of anchor- 4. Determine the method for developing the anchor rod
ages for overturning moments. in the concrete (i.e. transferring the tension force from
Tension forces are typically transferred to the foundation the anchor rod to the concrete foundation).
system with anchor rods. Shear forces can be transferred to
the foundation system through bearing, friction, or shear Step 1
friction. The principal means of shear transfer considered in The maximum net uplift for the column is obtained from the
this section is through bearing of the anchor rods and structural analysis of the building for the prescribed build-
through bearing of embedded components of the column. ing loads. The use of light metal roofs on industrial build-
Friction should not be considered if seismic conditions ings is very popular. As a result of this, the uplift due to
exist. Design for these various anchorage methods is wind often exceeds the dead load; thus the supporting
addressed in the following text. columns are subjected to net uplift forces. In addition,
Improper design, detailing and installation of anchor rods columns in rigid bents or braced bays may be subjected to
have caused numerous structural problems in industrial net uplift forces due to overturning.
buildings. These problems include:
Step 2
1. Inadequate sizing of the anchor rods,
Anchor rods should be specified to conform to ASTM
2. Inadequate development of the anchor rods for ten- F1554. Grades 36, 55 and 105 are available in this specifi-
sion, cation where the grade number represents the yield stress of
the anchor. Unless otherwise specified, the end of anchor
3. Inadequate design or detailing of the foundation for will be color coded to identify its grade. Welding is permit-
forces from the anchor rods, ted to the Grade 36 and also to the Grade 55 if it conforms
to the S1 supplement.
4. Inadequate base plate thickness, Anchor rods should no longer be specified to A307 even
if the intent is to use the A307 Grade C anchor that con-
5. Inadequate design and/or detailing of the anchor rod -
forms to A36 properties. Anchor rods conforming to the
base plate interface,
ASTM specifications listing of Anchor Rods and Threaded
6. Misalignment or misplacement of the anchor rods dur- Bolts in the 1999 AISC LRFD Specification can be used as
ing installation, and well as 304 and 316 stainless steels.
The number of anchor rods required is a function of the
7. Fatigue. maximum net uplift on the column and the allowable tensile
load per rod for the anchor rod material chosen. Prying
The reader should be familiar with the OSHA require- forces in anchor rods are typically neglected. This is usually
ments contained in Safety and Health Standards for the justified when the base plate thickness is calculated assum-
Construction Industry, 29 CFR 1926 Part R Safety Stan- ing cantilever bending about the web and/or flange of the
Step 3
Base plate thickness may be governed by bending associ-
ated with compressive loads or tensile loads. For compres-
sive loads, the design procedure illustrated in the “Column
Base Plates” section of Part 3 of the AISC 9th Edition Man-
3hef
ual of Steel Construction, and Part 14 of the Third Edition
of the LRFD Manual of Steel Construction, may be fol-
lowed. However, for lightly loaded base plates where the
dimensions “m” and “n” (as defined in this procedure) are
small, thinner base plate thickness can be obtained using
yield line theory.
For tensile loads, a simple approach is to assume the
anchor rod loads generate bending moments in the base
Fig. 9.1.1 Full Breakout Cone in Tension per ACI 318-02
Tu
c1
Tu
A A
1 1/2"
hef
Edge of 1
Concrete 1.5
Reinforcing steel to be
View A - A Potential sized and developed
Failure Plane for the recommended
tensile capacity of the
anchor rods on both
g sides of the potential
failure plane.
c1 1.5hef
Fig. 9.1.4 The Use of Steel Reinforcement for Developing Anchor Rods
N sb
1.5hef
c1
H = Lateral ft
Bursting Force
1.5hef
ft
170
160
1 1/4"
Dia.
S2 S1
150
S1xS2= 8x16
130
1 1/8"
Dia.
120
S1xS2= 8x8 and 6x10
S1xS2= 8x8
Ultimate Uplift Force, kips
90
S1xS2= 6x6 and 4x8
80
7/8"
Dia.
70
S1xS2= 4x4
60
3/4"
Dia.
50
40
5/8"
Dia.
Steel: 1.25 φA seFy
30
with φ=0.9
Concrete: φNcbg as given in Example 9.4.1
Concrete Uncracked ( ψ3 = 1.25)
20 Concrete Strength f'c= 4000 psi
Concrete Breakout
70 % Concrete Breakout
10 Anchor Rods Fy = 36ksi
0 2 4 6 8 10 12 14 16 18 20 22 24
1.5C1 1.5C1
Top Of
Concrete
1.5C1
View A-A
PDL= 22k
PUPLIFT= 56k
(Due To WL)
Fy = 36 ksi
4"
M y (4)
treq ' d . =
beff φ Fy( )
Fig. 9.4.2 Rod Load Distribution
Use a 11/8 in. thick plate (Fy = 36 ksi). To achieve a concrete breakout strength, φNcbg, that
For welding of the column to the base plate: exceeds the desired 4(18.7) = 74.8 kip steel capacity,
T / Bolt 17.5 the embedment depth must be at least 13 in. deter-
Maximum weld load = = = 4.78k/in. mined by trial and error or from Figure 9.1.6.
beff 3.65
Minimum weld for a 11/8 in. thick base plate = 5/16 in. Per ACI 318-02 Appendix D, the concrete breakout
(Table J2.4 of LRFD Specification). strength
Design weld load per in. for a 5/16 in. fillet weld with AN
E70 electrode: φ N cbg = φψ 3 24 fc′ hef 1.5 for hef ≤ 11 in.
ANo
= (5/16)(0.707)(0.75)(70) = 11.6 k/in. and
4.78 < 11.60 AN
φ N cbg = φψ 316 fc′ hef 5/ 3 for hef > 11 in.
Check web: ANo
φPn = φbeff(2)Fytw
= (0.9)(3.65)(2)(36)(0.35) where
= 82.8 kips φ = 0.70
ψ3 = 1.25 considering the concrete to be uncracked
82.8 > (4)(17.5) o.k. hef = 13 in.
4. As noted earlier, this column is anchored in the middle AN = concrete breakout cone area for group
of a large spread footing. Consequently, there are no = (3(13) + 4)(3(13) + 4) = 1849
edge constraints on the concrete tensile cones and ANo = concrete breakout cone area for single anchor
there is no concern regarding edge distance to prevent = 9(13)2 = 1521
lateral breakout of the concrete. ⎛ 1849 ⎞
φ N cbg = 0.70(1.25)(16) 0.004(13) 5/ 3 ⎜
To ensure a ductile failure in the case of overload, ⎝ 1521 ⎟⎠
design the embedment of the anchor rods to yield = 77.4 kips
some prior to concrete breakout. For 7/8 in. diameter
F1554 Grade 36 rods, this is equal to
(1.25)(0.9)(0.462)(36) = 18.7 kips/rod.
20"
V = 23k
(Due To WL)
2 Inch V
Grout 5" 20"
20 Inch Square
Bed
Concrete Pier
(f'c = 4000 psi)
5"
Fig. 9.4.4 Column pier support Fig. 9.4.5 Pier for Ex. 9.4.2 Showing Shear Breakout Cone
Solution: (
0.85 2 0.004 )(20 × 17.5) = 18.82 kips
< 1.6(23)
2
1. As determined in Example 9.4.1, the net uplift on the
From this calculation it is obvious that the applied
column = 69.8 kips, and as determined from the last
shear of 23 kips must be transferred to tie reinforce-
part of Example 9.4.1, it is necessary to transfer the
ment at the top of the pier and then transferred down
tensile loading to the pier vertical reinforcement. The
the pier with the aid of tie reinforcement, since the
vertical reinforcement in the pier will be larger in this
shear is greater than that which can be taken by con-
case due to the moment introduced into the pier from
crete alone.
the applied shear.
ACI 318-02 in section 7.10.5.6 requires the use of
2. A total of four anchor rods are to be used. The same
either 2-#4 or 3-#3 ties as lateral reinforcement within
four 7/8 in. diameter rods used in Example 9.4.1 could
the top 5 in. of the pier.
be used here as well, provided the
Per Section 12.13.2.1 of ACI 318-02, the #4 bar can be
ft ≤ φFt = φ 452 − 6.25 fv2 .
developed by hooking around a vertical bar. There-
fore 4-#4 hooks can develop 4(0.20)(60)(0.9) = 43.2
However, 11/8 in. diameter F1554 Grade 36 anchors are
kips. Since Vu = 1.6 (23 kips) = 36.8 kips is less than
required in this case.
the 43.2 kips the 2-#4 ties at the top of the pier can
fv =
(1.6 )(23) = 9.26 ksi; ft =
69.8
= 17.56 ksi
transfer the shear into the pier. With #4 ties at the min-
4(0.994) 4(0.994) imum required spacing in shear (use 8 in.), the φVn for
the pier is φ ⎡ 2 f c′bw d + Av f y d / s ⎤ , which equals
⎣ ⎦
φFt = 0.75 45 2 − 6.25 (9.26 )
2
(
0.85 2 0.004(20)(17.5) + 0.2(2)(60)(17.5) / 8 )
= 28.94 ksi o.k.
= 82.2 kips > 36.8 kips.
3. Position the rods within the profile of the column with
a 5 in. square pattern. Conservatively assume the ten- The vertical reinforcement in the pier at 1 percent
sile loads in the anchor rods generate one-way bend- would require the use of 4-#9 bars. If the provisions
ing in the base plate about the web of the column or of ACI-318-02 Section 10.8.4 and 15.8.2.1 are appli-
assume that two way bending occurs by considering cable, 0.5 percent reinforcement ratio could be used
bending of the base plate between flanges.
Solution:
20"
1. Two criteria are used to determine the appropriate 20
"a" "
embedment for the lug. These criteria are the bearing 9" 9.5
"a" "
strength of the concrete and the shear strength of the 1
concrete in front of the lug. As discussed in Section 1
Shear Lug
1 1/2" b
G = Grout
Thickness
1
d
1
Fig. 9.4.7 Shear Lug Depth Fig. 9.4.8 Lug Failure Plane