INTERNAL GYPSUM PLASTER


Quality Control Checklist

Building : Floor :

Room : Contractor

Date
Sr.No. Activity Done Not Done Remarks
Checked

PRE PLASTER CHECKS

Check all the Reinforced concrete structures. The Concrete


surface should be dressed if required RCC members
1
dressing if required, honeycombed and improper surface
rectified.

Has the concrete surface been Hacked (small depressions to


2
create a rough surface for bonding)?

Have all the Bricks and Blocks received a minimum of 7 days


3
curing before Plastering?
Are all the Concrete and Wall surfaces cleaned of dust, dirt,
debris, grease, form release agent, laitance or any other
4
detrimental materials (biological growth) that may affect
bonding of plaster?
Have the Electrical and Plumbing Lines been laid (If they are
4 concealed inside Blockwork). Completion of concealed
electrical/plumbing lines/modular boxes fitting.

Check if PVC hexagonal chicken mesh (20G with opening


8 10X10mm & 150mm wide) or GI chichen mesh in installed at
(This will avoid cracks in the plaster later)
· Interface between brick/block and RCC element.
· Around door frame
· Around Window lintels
· Around opening of Electrical Services.
Has the window marble sill fixing completed? (Sill is the
9 granite installed on 4 surfaces of window. Plaster should be
done after Sill installation Only)
10 Covering of electrical boxes (to be in line & level)
What Brand of Gypsum plaster brand is being used? (Should
11
be specifed by Architect or Clinet)
Level pad given on wall.(Minimum 6mm & maximum 18 mm.
12 If thickness is above 18 mm thickness,cement dash coat to
be done & cured)
DURING PLASTER STATEMENTS

Has the contractor applied Bonding agent on the wall, if


1
specified?

2 Is the Plaster mix uniform and of optimum workability?

1 of 2
© www.happho.com

INTERNAL GYPSUM PLASTER


Quality Control Checklist

Building : Floor :

Room : Contractor

Date
Sr.No. Activity Done Not Done Remarks
Checked

Is the plaster mix quanitty regulated? (plaster mixed to be


3
consumed with in 15mins)

4 Is the Surface smoothly finished and Flat?


Is the paster work terminated at groove lines, corners,
5
openings & no visible line of termination is observed?
POST PLASTER CHECKS

Use Alumium straight edge or thread and place it on the


1 surface of the plaster to check if there are no undulations on
the plaster. Check the wall length wise and diagonally also

2 Check if the plaster is truly vertical (Check with a plumb)

TAP the wall at multiple places as see if you get any hollow
3 sound. If hollow sound is observed then the defective area
has to be removed.

Other defective plasters includes hairline cracks and blisters


4
are to be rectified.

Checked by Agreed By

Client Contractor

2 of 2

Potrebbero piacerti anche