ERECTION PROGRESS REPORT for Gulf Mall


Date :23-04-2012
Job No. QA-1044,QA -1299 Bldg. Size : 29 Sector Total Area of 76695.6m²
Project Name : gulf mall at gharrafa ROOF CLADDING :
Customer Name : Business trading company WALL CLADDING :
Project Info

Location : Gharafah SPECIAL MATERIALS:


No. of Buildings : 29 Sectors SUPPLIER : ATC
Erection by : ATC : Mabani Steel BSI
Cement. Paint By almouayad as sub. EBS LOCAL :
KIRBY OTHERS:
A.B. Shipment Date : RECEIVED NO
ANCHOR BOLT

A.B. Installation Date : YES NO


A.B. Setting / Checking Date : YES NO
Concrete casted /A.B. Final Checking Date: 5-8-2011 YES NO
PEB Date of 1st Delivery / Last Delivery Date : ١٠-‫ديسمبر‬-٠٧ -----
PPA Date of 1st Shipment / Last Shipment Date : ------ ------
PEB Date Erection Started / Expected Completion Date: ١٠-‫ديسمبر‬-١٠ ١٢-‫فبراير‬-٢٠
PEB Erection - ACTUAL Completion Date: ----
PPA Date Erection Started / Completion Date: ---- -----
DURATION

PPA Installation - ACTUAL Completion Date:


Erection Duration (as per the Contract) N/A
Time Elapsed N/A
No. of Weeks Remaining for Completion (as per the contract) N/A
Actual No. of Weeks Remaining for Completion N/A
Current Status ACTIVE ON HOLD
Erection Team Leader dolaram

MANPOWER
Foreman
Group Leader
Average No. of Erectors /day 12
No. of Crane/s on Site 65 ton crane
EQPTS.

No. of Boom loader on Site N/A


No. of Man lifts / Sissorlift 1 man lift 28 mtr
No. of Forklifts 1
From : Supplier ATC Office
PENDING ISSUES

From : Customer Consultant


From : Main Cont Others
From : erection team
Claims Issued to Date

PROJECT PROGRESS SUMMARY for the Period of -23 APRIL 2012


Bldg no. PEB STEEL Panel decking Cement. Paint
over all 89.00% 86.00% 83.00%

Date : Description of Work Progress REMARKS


23-Apr-12 sector 27-erection of rafters & purling along grid line 17 & 18 see below picture
23-Apr-12 sector 27-erection of joist @ grids line 15:16@ 13.7m level progress see below picture
23-Apr-12 sector 27-rafters assembly for grid line 19
23-Apr-12 sector 19-installation of steel frame tent metalex trading .co
23-Apr-12 sector 24- cement paint @7.7m level almoayyed company
23-Apr-12 sector 16- modification welding along grid lines 11&13 @ 13.7 m level see below picture
SITE COMMENTS
1 the erection progress are very slow To cause a shortage of labor, we need to increase more 10 labors to speed up our work
PHOTOS

sector 27 rafters assembly progress

sector 27 erection progress

sector 24 cement paint progress sector 24 cement paint progress


installation of three no of steel frame tent
S.NO NAME ID NO. JOB NO.
1 Shahdat Rfique 37 402
2 Sohel Mhd. Islam 71 402
3 Dolaram Meghwal 97 402
4 Sundramoorthy vengatachalm 457 402
5 Md.Younus Ali Sheikh 461 402
6 Kazimobassir Hasan 462 402
7 ramasamy babu 730 402
8 Durairj arunagiri 775 402
9 Veera pandi vaiyapuri 778 402
10 Thiru veshvaran 782 402
11 Chhoyfor Harjot Ali 867 402
12 Lakhvir singh gill 874 402
13 Mhd. Arief 375 402

Potrebbero piacerti anche