Sei sulla pagina 1di 3

Main Contractor: AL MAJAL INTERNATIONAL TRADING & CONTRACTING Project name : ANDAZ HAYAT 5 STARS HOTEL

ITP for AAC Block works

ARAB ENGINEERING
AL MIRQAB TOURIST COMPANY ANDAZ HAYAT 5 STARS HOTEL
BUREAU

Inspection and Test Plan for AAC Block Works

Rev: Date: Comments: Prepared By: Reviewed By: Approved By:

XInspection & Test Plan

Date: Page 1 of 3 Inspection and Test Plan Number:


Main Contractor: AL MAJAL INTERNATIONAL TRADING & CONTRACTING Project name : ANDAZ HAYAT 5 STARS HOTEL

ITP for AAC Block works

Title/Description AAC Block works ITP No. :

Unit Area: INTERNAL AREA Discipline: AAC Block work


 Rev. 00
Verifying Documents
/Demonstrated Evidence
Inspection Test Requirements Reference Documentation Inspections / Verification
Report Checklist
Activity (Reference Number)
Activity / Description
No.
Test or
Contract
Inspection Stage/Frequency Code/Spec/etc Acceptance Criteria Engr. Employer
o
Performed

1 Approval / Permits/Preliminaries
Preparation of
 ITP,
Prior to Start of Specification Section
1.1  Method Statement Approval  Code 1/ 2 E R H Approved Submittals
Work Number
 Material Submittals
 Drawings
2 Material Inspections (Delivery on Site)
Material Arrival on Specification Section Material Receiving
2.1 Materials Visual E W S
Site Number Inspection Report (MRIR)

Material Arrival on Specification Section  As per approved Material Material Receiving


2.2 Accessories Visual E W S
Site Number Submittals Code 1/2 Inspection Report (MRIR)

3 Work Process
3.1 Prior to Start Blockwork

 As per approved IRF


One Wall Panel Approved Drawings  As per approved shop IRF
 Mock up
3.1.1 Visual with all required Specification Section drawing E W H Method Statement Checklist:
accessories used Number  All required accessories Checklist number
included in the mock up

3.2 Blocks Laying/ Installation

Date: Page 2 of 3 Inspection and Test Plan Number:


Main Contractor: AL MAJAL INTERNATIONAL TRADING & CONTRACTING Project name : ANDAZ HAYAT 5 STARS HOTEL

ITP for AAC Block works

Approved Shop As per approved survey


Setting out & Surface Prior to laying of Checklist:
3.2.1 Visual Drawing for Block layout E W W
Preparation every first course Checklist number
work layout No unsatisfactory condition

All accessories required are


Approved shop installed and verified.
During block laying Checklist:
3.2.2 Block layer installation Visual drawings for block All MEP required E S S
works Checklist number
work layout embedment's and openings
are placed and verified
Construction Tolerances:

1. For Vertical lines. Plumb


shall not vary by more than
6mm in 6m height.
2. For vertical alignment of
exposed head joints, do not
vary from plumb by more
than 6mm by 3m, nor 12mm
Approved Shop max.
Every 18 bays for
Drawings block work 3. For horizontal line, do not
CFS Bldg. Checklist:
layout vary from level by more
3.2.3 Final Inspection Visual For other buildings E H W Checklist number
than 6mm in 6m, nor 12mm
every completed
Specification Section max.
First Course
Number 4. For exposed bed joints,
do not vary from thickness
by more than +/- 3mm &
adjacent course with a max.
thickness limited to 12mm.
5. For exposed head joints,
do not vary from thickness
by more than +/- 3mm.

4.0 As - built Drawings Approval Progressively Code 1 E R R Approved As-Built Drawings

Legend: I-Inspection, T-Test, W-Witness Point, H-Mandatory Hold Point for Inspection, R-Document Review, S-Surveillance, E-Execution, RE-Records

Date: Page 3 of 3 Inspection and Test Plan Number:

Potrebbero piacerti anche