Sei sulla pagina 1di 37

MINUTES OF THE PREVIOUS MEETING NO.

1
April 24, 2015 (Friday) @ 11:00 A.M.

Attendees :
MR. ROGER REGALA OWNER
ARCH. BRYAN TAN PRINCIPAL ARCHITECT
ENGR. JOSE T. TAYAMORA JT&G (PRESIDENT/STRUC. DESIGNER/CONTRACTOR)
ENGR. RENUEL DICHOSA JT&G (SITE ENGINEER)
MR. ARNEL STA. INEZ JT & G (FOREMAN)
MR. JERRI MATIENZO JT & G (LEADMAN / WAREHOUSEMAN)

REVIEW AND CONFIRMATION OF PREVIOUS RESOLUTION


ITEM
MEETING AGENDA & DECISION MADE REMARKS IN-CHARGE DUTE DATE

1. BLDG. PERMIT STILL ON PROCESS


2. ELECTRIC SUPPLY STILL ON PROCESS
3. ADJUSTMENT OF CISTERN TANK WILL ISSUE A FINAL LOCATION
4. POURING OF GROUND FLOOR SLAB - SUSPENDED REVIEW THE DROP FLR FOR CR /
PLUMBING (UNDER SLAB) /
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 2

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE JUNE 16, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 9:00 A.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT 51.66%
NO. OF DAYS ACTUAL
124 CALENDAR DAYS
ELAPSED ACCOMPLISHMENT 54.50%
PROJECT NO. OF DAYS PROJECT VARIANCE 2.84%
116 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
1.5 DAY (ADVANCE)
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. LOCATION OF SEPTIC TANK TO EXCAVATE ARCH. BRYAN


2. LOCATION OF CISTERN TANK TO EXCAVATE ARCH. BRYAN
3. LOCATION OF SUMP PIT TO EXCAVATE ARCH. BRYAN
4. LAYOUT OF SWIMMING POOL TO EXCAVATE ARCH. BRYAN
5. CHANGES OF GLASS WALL TO CONCRETE WALL FOR MR. REGALA / ENGR. JOE
GYM AT BASEMENT / ARCH. BRYAN
6. ELECTRICAL APPLICATION ( ON PROCESS) ENGR. JOE
7. BUILDING PERMIT (FOR RELEASE) ENGR. JOE
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 3

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE APRIL 24, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 9:00 A.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT 57.00%
NO. OF DAYS ACTUAL
137 CELENDAR DAYS
ELAPSED ACCOMPLISHMENT 45.00%
PROJECT NO. OF DAYS PROJECT VARIANCE
103 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. TRUSSES FABRICATION OF TRUSSES JULY 6, 2015


2. ELECTRIC SUPPLY METER BASE FOR INSTALLATION
3. PLASTERING & CHB LAYING ON-GOING
4. LAYOUT OF STAIR ON-GOING
5. OTHER CONCERN
SUPPLIER OF ROOF TILES MR. REGALA
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 5

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE AUG. 17, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
187 CELENDAR DAYS
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
53 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. TRUSSES ALREADY FABRICATED & FOR DELIVERY


2. ELECTRIC SUPPLY WAITING FOR MERALCO METER
3. BLDG. PERMIT ACCOMPLISHED
4. PLASTERING & CHB LAYING ON-GOING
5. LAYOUT OF STAIR ON-GOING
6. CONCRETING OF CISTERN TANK ON GOING
7. REBARS OF CISTERN & SEPTIC ON GOING
8. ELECTRICAL WIRING ON GOING
9. SWIMMING POOL EXCAVATION FOR SCHEDULE
10. REPLACEMENT OF CHB WALLS FOR DOORS & WINDOWS ACCOMPLISHED
11. DRAWING OF REVISION OF STAIRS ARCH. BRYAN
12. DRAWING OF CEILING DESIGN ARCH. BRYAN
13. SCHEDULE OF DELIVERY OF DOOR JAMBS MR. REGALA
14. RESPOSE OF BTIC (PVC UNDERSHEETING) BTIC
15. OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 6

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 7, 2015


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. TRUSSES ALREADY AT THE ROOF AREA


2 INSTALLATION OF C-PURLINS FOR SCHEDULE AFTER ELEC CONNECTION
3 ELECTRIC SUPPLY WAITING FOR MERALCO METER
4 BLDG. PERMIT ACCOMPLISHED
5 PLASTERING & CHB LAYING FENCE ON-GOING
6 LAYOUT OF MAIN STAIR WAITING FOR DRAWING
7 CONCRETING OF CISTERN TANK FOR SCHEDULE
8 REBARS OF CISTERN ON GOING
9 REBARS & CONCRETING OF SMALL SEPTIC TANK ACCOMPLISHED
10 CONCRETE FACIA, CONCRETE LEDGE ON GOING
11 ELECTRICAL WIRING (CO & OUTLET) ON GOING
12 SWIMMING POOL EXCAVATION HOLD
13 DRAWING OF CEILING DESIGN WAITING FOR DRAWING
14 DOOR JAMBS INSTALLATION ALREADY STARTED
15 PAINTING (SKIMCOAT) ALREADY STARTED
16 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 7

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 14, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. INSTALLATION OF C-PURLINS ALREADY STARTED


2 PLASTERING & CHB LAYING FENCE ON-GOING
3 ELECTRIC SUPPLY ALREADY INSTALLED
4 STAIR ELEVATION @ ENTRANCE ACTUAL ELEVATION - FOR APPROVAL
5 PAINTING (SKIMCOAT) ALREADY STARTED
6 DOOR JAMBS INSTALLATION ON-HOLD
7 CONCRETING OF CISTERN TANK FOR SCHEDULE
8 REBARS OF CISTERN ON GOING
9 REBARS & CONCRETING OF SMALL SEPTIC TANK ACCOMPLISHED
10 CONCRETE FACIA, CONCRETE LEDGE ON GOING
11 ELECTRICAL WIRING (CO & OUTLET) ON GOING
12 SWIMMING POOL EXCAVATION SUBJECT FOR FINAL ELEVATION
13 DRAWING OF CEILING DESIGN WAITING FOR DRAWING
14 LAYOUT OF MAIN STAIR WAITING FOR DRAWING
15 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 8

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 21, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1. INSTALLATION OF C-PURLINS 90% ACCOMPLISHED


2 PLASTERING & CHB LAYING FENCE 75% ACCOMPLISHED
4 STAIR ELEVATION @ ENTRANCE ALREADY INSTALLED
5 PAINTING (SKIMCOAT) ALREADY STARTED
6 DOOR JAMBS INSTALLATION ON-HOLD
7 CONCRETING OF CISTERN TANK FOR POURING SCHEDULE
8 REBARS OF CISTERN ON GOING
9 REBARS & CONCRETING OF SMALL SEPTIC TANK ACCOMPLISHED
10 CONCRETE FACIA, CONCRETE LEDGE ON GOING
11 ELECTRICAL WIRING (CO & OUTLET) ON GOING
12 SWIMMING POOL EXCAVATION SUBJECT FOR FINAL ELEVATION
13 DRAWING OF CEILING DESIGN OWNER' VERIFICATION - CHANGES
14 LAYOUT OF MAIN STAIR ALREADY STARTED
15 OTHER CONCERN
REQUEST FOR MATERIALS SUCH AS : SUBJECT FOR CONTRACTORS ESTIMATE
HARDI SENEPA, TILES, DOOR JAMB,
ROOF TILES,
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 9

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 28, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 INSTALLATION OF C-PURLINS 100% ACCOMPLISHED


2 INSTALLATION OF UNDERSHEETING FOR SCHEDULE
4 PLASTERING & CHB LAYING FENCE 75% ACCOMPLISHED
5 STAIR ELEVATION @ ENTRANCE ALREADY INSTALLED
6 PAINTING (SKIMCOAT) ALREADY STARTED
7 DOOR JAMBS INSTALLATION ON-HOLD
8 CONCRETING OF CISTERN TANK FOR POURING SCHEDULE
9 REBARS OF CISTERN ON GOING
10 CONCRETE FACIA, CONCRETE LEDGE ON GOING
11 ELECTRICAL WIRING (CO & OUTLET) ON GOING
12 SWIMMING POOL EXCAVATION FOR EXCAVATION
13 DRAWING OF CEILING DESIGN METAL FURRING INSTALLATION FOR SCHEDULE
14 LAYOUT OF MAIN STAIR ALREADY STARTED
15 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 10

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE OCT. 26, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 INSTALLATION OF UNDERSHEETING ON GOING


2 PLASTERING & CHB LAYING FENCE 80% ACCOMPLISHED
3 MAIN STAIR 100% ACCOMPLISHED
4 PAINTING (SKIMCOAT) ALREADY STARTED
5 DOOR JAMBS 80% INSTALLED
6 BIG SEPTIC TANK & SWIMMING POOL FOR REBARS
7 BASEMENT FLOORING 50% ACCOMPLISHED
8 POURING OF RAMP FOR POURING SCHEDULE W/IN THE WEEK
9 ELECTRICAL WIRING (CO & OUTLET) ON GOING
10 CEILING MATERIALS FOR PICK UP
11 INSTALLATION OF HARDI SENEPA FOR SCHEDULE W/IN THE WEEK
12 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 11

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE NOV. 2, 2015


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 INSTALLATION OF UNDERSHEETING ON GOING


2 PLASTERING & CHB LAYING FENCE 80% ACCOMPLISHED
3 MAIN STAIR 100% ACCOMPLISHED
4 PAINTING (SKIMCOAT) ALREADY STARTED
5 DOOR JAMBS 80% INSTALLED
6 BIG SEPTIC TANK & SWIMMING POOL FOR REBARS
7 BASEMENT FLOORING 50% ACCOMPLISHED
8 POURING OF RAMP FOR POURING SCHEDULE W/IN THE WEEK
9 ELECTRICAL WIRING (CO & OUTLET) ON GOING
PLUMBING ON GOING
10 CEILING MATERIALS FOR PICK UP
11 INSTALLATION OF HARDI SENEPA FOR SCHEDULE W/IN THE WEEK
12 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 12

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE NOV. 16, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 INSTALLATION OF UNDERSHEETING 100% INSTALLED


2 PLASTERING & CHB LAYING FENCE 80% ACCOMPLISHED
3 DOOR JAMBS 100% INSTALLED
4 PAINTING (SKIMCOAT) ALREADY STARTED
5 DOOR JAMBS 80% INSTALLED
6 BIG SEPTIC TANK & SWIMMING POOL FOR REBARS
7 BASEMENT FLOORING ON GOING
8 METAL FURRING INSTALLATION ON GOING
9 ELECTRICAL WIRING (CO & OUTLET) ON GOING
10 PLUMBING ON GOING
11 ROOF TILES INSTALLATION ON GOING
12 INSTALLATION OF HARDI SENEPA - NEW LAYOUT WAITING
13 CEILLING NEW DESIGN WAITING
14 WATER & ELEC CONSUMPTION
15 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 13

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE NOV. 23, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 PLASTERING & CHB LAYING FENCE 80% ACCOMPLISHED


2 PAINTING (SKIMCOAT) ALREADY STARTED
3 BIG SEPTIC TANK & SWIMMING POOL FOR REBARS
4 BASEMENT FLOORING ON GOING
5 METAL FURRING INSTALLATION ON GOING
6 ELECTRICAL WIRING (CO & OUTLET) ON GOING
7 PLUMBING ON GOING
8 ROOF TILES INSTALLATION ON GOING
9 INSTALLATION OF HARDI SENEPA - NEW LAYOUT FOR INSTALLATION
10 INSTALLATION OF CEILING ON GOING
11 TILES FOR CR WAITING FOR TILES
12 TOPPING OF FLOORING @ 3RD FLR. FOR APPROVAL
13 STAIR 100% FINISHED
14 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 14

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE JAN. 11, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 SWIMMING POOL ON GOING


2 PARKING RAMP SCHEDULE FOR POURING
3 PAINTING ON GOING
4 METAL FURRING INSTALLATION ON GOING
5 ELECTRICAL WIRING (CO & OUTLET) ON GOING
6 PLUMBING ON GOING
7 TILES SETTING WAITING FOR OWNER SUPPLY
8 WOOD WORKS OWNER SUPPLY & INSTALLATION
9 PERIMETER FENCE PAINTING - ON GOING
10 SOLID SURFACE GRANITE SAMPLE SUBMITTED TO OWNER
11 NATURAL STONE FOR CLADDING READY FOR INSTALLATION
12 PVC SPANDREL OWNER SUPPLY & INSTALLATION
13 DOORS WAITING FOR OWNER SUPPLY
14 INTERIOR & EXTERIOR PAINTING - FINAL COLOR READY FOR 1ST COATING
15 ADJUSTMENT OF WINDOW OPENING ALONG ALREADY ACCOMPLISHED
LIVING AREA
16 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 15

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE FEB. 2, 2016


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 11:00 A.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 SWIMMING POOL WAITING FOR PIPING LAYOUT OF SUBCON


2 PARKING RAMP DRAWING ALREADING SUBMITTED
3 PAINTING ON GOING
4 METAL FURRING INSTALLATION ON GOING
5 ELECTRICAL WIRING (CO & OUTLET) ON GOING
6 PLUMBING ON GOING
7 TILES SETTING WAITING FOR OWNER SUPPLY
8 WOOD WORKS OWNER SUPPLY & INSTALLATION
9 PERIMETER FENCE PAINTING - ON GOING
10 SOLID SURFACE GRANITE SAMPLE SUBMITTED TO OWNER
11 NATURAL STONE FOR CLADDING READY FOR INSTALLATION
12 PVC SPANDREL OWNER SUPPLY & INSTALLATION
13 DOORS WAITING FOR OWNER SUPPLY
14 INTERIOR & EXTERIOR PAINTING - FINAL COLOR READY FOR 1ST COATING
16 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 16

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE FEB. 9, 2016


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

SWIMMING POOL WAITING FOR PIPING LAYOUT OF SUBCON


PARKING RAMP DRAWING ALREADY SUBMITTED
TILES SETTING WAITING FOR OWNER SUPPLY
FLOOR TOPPING @ 3RD FLR. ON GOING
CEILLING INSTALLATION ON GOING
ELECTRICAL WIRING (CO & OUTLET) ON GOING
PLUMBING ON GOING
PVC SPANDREL OWNER SUPPLY & INSTALLATION
DOORS WAITING FOR OWNER SUPPLY
SOLID SURFACE GRANITE SAMPLE SUBMITTED TO OWNER
NATURAL STONE FOR CLADDING READY FOR INSTALLATION
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 17

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE FEB. 29, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.

CONTRACT PROJECT
240 DAYS 76%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
76%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 SWIMMING POOL WAITING FOR PIPING LAYOUT OF SUBCON


2 PARKING RAMP 100% COMPLETED
3 TILES SETTING READY FOR INSTALLATION
4 FLOOR TOPPING @ 3RD FLR. 80% ACCOMPLISHED
5 CEILLING INSTALLATION 70% ACCOMPLISHED
6 ELECTRICAL WIRING (CO & OUTLET) 65% ACCOMPLISHED
7 PLUMBING 70% ACCOMPLISHED
8 DOORS WAITING FOR OWNER SUPPLY
9 PAINTING ON GOING
10 PVC SPANDREL ON GOING BY SUB-CON
11 SWITCH AND OUTLET MAPPING ON GOING
12 WATER LINE INSTALLATION ON GOING
13 TILE LAYOUT WAITING FOR SUPPLIER FOR INSPECTION
14 WATER PROOFING ON GOING
15 COVELIGHT LAYOUT ON GOING
16 CEILING FOR 3RD FLR. NEAR ALTAR ON GOING
17 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 18

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE MARCH 7, 2016


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.

CONTRACT PROJECT
240 DAYS 76%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
76%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 SWIMMING POOL WAITING FOR PIPING LAYOUT OF SUBCON


2 PARKING RAMP 100% COMPLETED
3 TILES SETTING READY FOR INSTALLATION
4 FLOOR TOPPING @ 3RD FLR. 80% ACCOMPLISHED
5 CEILLING INSTALLATION 70% ACCOMPLISHED
6 ELECTRICAL WIRING (CO & OUTLET) 65% ACCOMPLISHED
7 PLUMBING 70% ACCOMPLISHED
8 DOORS WAITING FOR OWNER SUPPLY
9 PAINTING ON GOING
10 PVC SPANDREL ON GOING BY SUB-CON
11 SWITCH AND OUTLET MAPPING ON GOING
12 WATER LINE INSTALLATION ON GOING
13 TILE LAYOUT WAITING FOR SUPPLIER FOR INSPECTION
14 WATER PROOFING ON GOING
15 COVELIGHT LAYOUT ON GOING
16 CEILING FOR 3RD FLR. NEAR ALTAR ON GOING
17 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA 19

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE MARCH 28, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.

CONTRACT PROJECT
240 DAYS 80%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
80%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

1 SWIMMING POOL - INSTALLATION OF REBARS ON GOING


2 PARKING RAMP 100% COMPLETED
3 TILES SETTING ON GOING
4 FLOOR TOPPING @ 3RD FLR. 100% COMPLETED
5 CEILLING INSTALLATION 90% ACCOMPLISHED
6 ELECTRICAL WIRING (CO & OUTLET) 80% ACCOMPLISHED
7 PLUMBING 70% ACCOMPLISHED
8 DOORS WAITING FOR OWNER SUPPLY
9 PAINTING ON GOING
10 PVC SPANDREL ON GOING BY SUB-CON
11 SWITCH AND OUTLET MAPPING ON GOING
12 WATER LINE INSTALLATION ON GOING
13 TILE LAYOUT ON GOING
14 WATER PROOFING ON GOING
15 COVELIGHT LAYOUT ON GOING
16 CEILING FOR 3RD FLR. NEAR ALTAR 100% COMPLETED
17 OTHER CONCERN
FIELD COORDINATION MEETING
PROJECT CODE MEETING NO.

MR. REGALA

PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE


JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.

CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE

ITEM ISSUSES FOR DISCUSSION FEEDBACK


FOR DECISION & FOLLOW-UP REMARKS IN-CHARGE DUE DATE

Potrebbero piacerti anche