1
April 24, 2015 (Friday) @ 11:00 A.M.
Attendees :
MR. ROGER REGALA OWNER
ARCH. BRYAN TAN PRINCIPAL ARCHITECT
ENGR. JOSE T. TAYAMORA JT&G (PRESIDENT/STRUC. DESIGNER/CONTRACTOR)
ENGR. RENUEL DICHOSA JT&G (SITE ENGINEER)
MR. ARNEL STA. INEZ JT & G (FOREMAN)
MR. JERRI MATIENZO JT & G (LEADMAN / WAREHOUSEMAN)
MR. REGALA 2
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE JUNE 16, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 9:00 A.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT 51.66%
NO. OF DAYS ACTUAL
124 CALENDAR DAYS
ELAPSED ACCOMPLISHMENT 54.50%
PROJECT NO. OF DAYS PROJECT VARIANCE 2.84%
116 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
1.5 DAY (ADVANCE)
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 3
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE APRIL 24, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 9:00 A.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT 57.00%
NO. OF DAYS ACTUAL
137 CELENDAR DAYS
ELAPSED ACCOMPLISHMENT 45.00%
PROJECT NO. OF DAYS PROJECT VARIANCE
103 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 5
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE AUG. 17, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
187 CELENDAR DAYS
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
53 CALENDAR DAYS
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 6
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 7
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 14, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 8
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 21, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 9
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE SEPT. 28, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 10
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE OCT. 26, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 11
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 12
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE NOV. 16, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 13
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE NOV. 23, 2015
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 14
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE JAN. 11, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 2:00 P.M.
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 15
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 16
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE OCTOBER 12, 2015
MR. REGALA 17
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE FEB. 29, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.
CONTRACT PROJECT
240 DAYS 76%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
76%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE
MR. REGALA 18
CONTRACT PROJECT
240 DAYS 76%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
76%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE
MR. REGALA 19
PROJECT : PROPOSED 2-STOREY RESIDENTIAL WITH BASMENT DATE MARCH 28, 2016
JOBSITE : ST. ANTHONY ST. ST. CHARBEL EXEC VILL Q.C. TIME 1:00 P.M.
CONTRACT PROJECT
240 DAYS 80%
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
80%
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE
MR. REGALA
CONTRACT PROJECT
240 DAYS
DURATION ACCOMPLISHMENT
NO. OF DAYS ACTUAL
ELAPSED ACCOMPLISHMENT
PROJECT NO. OF DAYS PROJECT VARIANCE
CONTRACT REMAINED STATUS EQUIVALENT NO.
START OF OF DAYS
FEBRUARY 12, 2015
CONSTRUCTION
COMPLETION DATE