Ball mill inspection

Inspection during
operation

Key benefits FLSmidth uses its many years of


experience and the knowledge gained
-
-
Bearing lubrication system
Trunnion
- Root cause analysis from installing almost 4000 ball mills - Mill shell
around the world to carry out essential - Mill head bolts
- Performed during both normal ball mill inspections. - Mill internals
operation and standstill - Man hole
An inspection by FLSmidth service - Trunnion bearings/slide shoe
- Performed by highly experi- specialists with in-depth process bearings
enced FLSmidth specialists knowledge is your best guarantee for
ensuring optimal, trouble-free operation. Monitoring & diagnosing
- Optimal mill availability Periodic checks of wear and tear are an Process specialists evaluate:
absolute must for maintaining a high, - Material feed
- Uninterrupted production
reliable mill run factor. - Pressure, flow and temperature across
- More predictable maintenance the ball mill and separator circuit
costs We are experienced in inspecting both - Ball mill charge/level
FLSmidth and non-FLSmidth ball mills. - Crash stop and metre samples
- Knowledge-sharing with In order to evaluate the condition of your analysis
maintenance staff ball mill, it is necessary to collect data
during both operation and standstill. In addition, the mill trunnion and girth
- Recommendations for process This allows our specialists to get a clear gear temperature is measured using a
improvements picture of potential problem areas, as non-contact type thermometer to analyse
well as important information for post- the condition of these components.
inspection analysis and evaluation.
The inspection also includes electronic
Obtaining data data logging and an evaluation of the
Ball mill specialists check every process hydraulic system and lubrication units.
and mechanical aspect of the ball mill
system, including:

Ball mill inspection


approach

Training session
Process inspection Mechanical inspection
In addition to the mill
inspection, we also offer a
two-day training session for Analysis & Evaluation
hydraulic and lubrication
pump station operation and
troubleshooting. The session
consists of theoretical as well Recommendations
for action
as practical training.
3

Inspection Inspection Inspection


during of the of the
standstill separator gear

To get a detailed picture of the mill’s over- The separator is an essential part of the FLSmidth’s specialists use intricate
all condition, including parts that need to mill installation. It is important that it is vibration measurements to get an
be replaced, it is important to carry out checked regularly and that any necessary accurate overview of the ball mill’s gear.
an external and internal inspection during repairs are carried out immediately to The inspection also includes temperature
standstill. This allows specialists to detect maintain overall mill performance. and back lash measurement.
potential threats before they become a
problem, such as: The inspection includes an examination
- Hydraulic and lubrication problems of the overall condition of the separator,
- Cracks in ball mill internals including a check of wear on the rotor
and guide vanes.
Additionally, FLSmidth specialists check
the water injection system and measure
tolerances between the slide shoe and
slide ring with feeler gauges.

Final report
When inspections of mill components The report covers the condition
have been carried out, our specialists of all mill components:
Recommendations
provide a final comprehensive technical - Mill body for action
evaluation and analysis report, as well as - Bearings
recommendations for repairs, spare parts, - Mill internals and diaphragm
adjustments and optimisations. - Girth gear drive
- Hydraulic and lubrication units
The report is an essential document to - Mill internals Actions during scheduled
help production and maintenance maintenance stop
departments plan future maintenance In addition, the report includes evaluation Modification of the mill
activities, such as ensuring that the right of grinding efficiency, separator efficiency maintenance program
spare parts are available, and – most and feed analysis.
Spare parts management
importantly – avoid unscheduled, costly
shutdowns. If required, we’re available to
stay and carry out the recommended
adjustments and repairs.
C 10-13 300-23-ENG

Copyright © 2013 FLSmidth A/S. ALL RIGHTS RESERVED. FLSmidth is a trademark of FLSmidth A/S. This brochure makes no offers, representations or
warranties (express or implied), and information and data contained in this brochure are for general reference only and may change at any time. www.flsmidth.com

Contact information

Find your local supplier at www.flsmidth.com/onsiteservices

Potrebbero piacerti anche